This file consists of demolition specifications and construction waste management requirements for the Wimbee Creek Fishing Pier Demolition Project located at the end of Wimbee Creek Landing Road in Dale, South Carolina, under Beaufort County's jurisdiction. The project encompasses the complete demolition and removal of seven timber pile bents, one reinforced concrete and steel pile bent, the plate girder superstructure, concrete and timber deck, and pedestrian stairs, followed by installation of new chain link fencing. Work is conducted under a single prime contract based on a stipulated sum and must be completed during normal business hours of 7:30 a.m. to 5:00 p.m., Monday through Friday, unless advance written permission is obtained from the Owner for weekend, holiday, or extended-hour work. The contractor shall coordinate facility closure with Beaufort County Public Works and provide pre- and post-demolition side scan sonar surveys extending 50 feet outside the pier perimeter, with all sonar information georeferenced and submitted prior to demobilization.
The specifications require strict adherence to federal safety regulations, including OSHA standards (29 CFR Part 1926) and U.S. Army Corps of Engineers EM 385-1-1 demolition requirements, with notification to the local fire department at least 24 hours prior to any work that may affect fire protection systems. The contractor is responsible for developing and implementing a comprehensive waste management plan within 15 days of the Notice to Proceed, which must address salvage, recycling, and disposal of all demolition waste in accordance with federal, state, and local environmental regulations. All hazardous materials must comply with OSHA hazardous communication programs and Material Safety Data Sheet requirements, with secondary containment capabilities for liquid hazardous materials. The contractor must provide daily site cleanup, prevent dust and debris spread, and avoid discharging wastewater to sewers or waterways. Materials designated for demolition become contractor property, while the existing abutment is designated for salvage and must be moved to an Owner-designated location. All waste disposal documentation, including weight tickets and facility manifests, must be submitted to the Engineer, and the contractor shall submit a final waste management report detailing actual quantities of salvaged, recycled, and disposed materials upon project completion.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 011000 - SUMMARY OF WORK
PART 1 - GENERAL
1.0 SUMMARY
Section Includes:
1. Project information
2. Work covered by Contract Documents
3. Access to site
4. Safety Precautions
5. Site Maintenance
1.1 PROJECT INFORMATION
Project Name: Wimbee Creek Fishing Pier Demolition
Project Location: Wimbee Creek Fishing Pier - End of Wimbee Creek Landing Road in Dale, SC
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. The work of the Project is defined by the Contract Documents and primarily includes, but is not limited to:
1. Demolition and disposal of 7 timber pile bents
2. Demolition and disposal of 1 reinforced concrete and steel pile bent
3. Demolition of plate girder superstructure
4. Demolition of concrete and timber deck
5. Demolition of pedestrian stairs
6. Installation of new chain link fence
B. Type of Contract:
1. Project will be constructed under a single prime contract based on a stipulated sum and time required to complete the project.
1.3 ACCESS TO SITE
A. General: During the demolition period the Contractor shall have use of project site for demolition operations as indicated on the drawings, as indicated by requirements of this Section, and as specified by the Engineer or Owner.
1. Material storage and work areas shall be as designated by the Owner
B. Use of Site: Limit use of Project site to demolition area indicated. Do not disturb portions of project site beyond areas in which the work is indicated.
1. Limits: Confine demolition operations to the area affected by construction.
2. The Contractor will be able to park in the general vicinity of the work site. The Contractor will be assigned an area in general vicinity of the site for storage of material, if required.
1.4 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on demolition operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work to normal business working hours of 7:30 a.m. to 5:00 p.m., Monday through Friday, unless otherwise indicated.
1. Submit request to the Owner at least 72 hours in advance for permission to work outside the normal working hours or on Saturdays, Sundays, or federal holidays.
C. Existing Utility Interruptions:
1. Submit request to the Owner at least 72 hours in advance of any utility interruptions.
2. Obtain Owner's written permission before proceeding with any utility interruptions.
D. Take action to prevent the spread of construction dust, debris, and fumes at all times. Submit a demolition waste control plan prior to work.
E. Sanitation Facilities: The Contractor shall provide temporary toilet, wash facilities, and drinking water for use by Contractor's personnel. Comply with requirements of authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.
1.5 SAFETY PRECAUTIONS
A. These construction documents and the construction work hereby contemplated shall be governed at all times by applicable provisions of federal regulations, including, but not limited to, the current edition, with the latest amendments of the following:
1. William-Steiger Occupational Safety and Health Act of 1970, Public Law 91-596; Part 1926 - Occupational Safety and Health Standards, Chapter XVII of Title 29, Code of Federal Regulations (29 CFR Part 1926).
B. The Contractor shall notify the local fire department at least 24 hours prior to the start of any demolition practices which may affect or impair any fire protection system or which may present a fire hazard (i.e., sanding, welding, grinding, applying hot tar, burning and utilizing of any flame producing device).
1. The Contractor shall have and maintain an appropriate functioning fire extinguisher in the work area, for the type of work being done and the materials present. The Contractor shall comply with OSHA, NFPA, and other local safety regulations.
C. The Contractor shall determine and employ all necessary safety precautions to protect the general public and Contractor or Subcontractor personnel during construction operations.
D. The Contractor shall coordinate closure of the facility with the Beaufort County Public Works.
1.6 SITE MAINTENANCE
A. The Contractor shall perform daily clean-up of work site, dumpsters and storage area. All dumpsters shall be covered and watertight.
B. The Contractor shall also protect existing plants, shrubs, fences, and structures within the demolition area.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
SECTION 017419
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL PART 1 - GENERAL
1.0 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Salvaging nonhazardous demolition and construction waste.
2. Recycling nonhazardous and regulated, demolition and construction waste.
3. Disposing of nonhazardous and regulated, demolition and construction waste.
B. The Contractor is responsible for complying with all Federal, State, and local environmental laws and requirements in the execution of this contract.
1.1 DEFINITIONS
A. Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.
B. Demolition Waste: Building and site improvement materials resulting from demolition or selective demolition operations.
C. Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction.
D. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.
E. Salvage: Recovery of demolition or construction materials and deliver them to the Owner ready for reuse.
F. Salvage and Reuse: Recovery of demolition or construction materials, prepare them for reuse, and subsequent incorporation into the work.
1.2 HAZARDOUS WASTE OPERATIONS
A. Contractors whose employees are exposed to hazardous waste, respond to emergencies involving hazardous materials, or participate in any cleanup or investigation of a government identified uncontrolled waste site, must follow all the requirements of 29 CFR 1910.120 which includes Site Safety and Health Plans, Emergency Contingency Plans and proper employee training. The Contractor, if required by 29 CFR 1910.120, shall submit to the Owner prior to performing the work, the Site Safety and Health Plans, Emergency Contingency Plans and proof of adequate worker training.
1.3 HAZARDOUS MATERIALS
A. The Contractor shall submit to the Engineer a copy of the Contractor's OSHA-approved hazardous communication program as required by 29 CFR 1910.1200.
B. The Contractor shall submit to the Engineer a copy of all Material Safety Data Sheets (MSDS) for each chemical or hazardous material to be used in the execution of this contract.
C. The Owner, upon review of the Contractor's MSDS, has the right to deny the Contractor the use of chemicals or products which, in the Owner's judgment, pose an undue health risk, cause the generation or potential generation of hazardous waste, or result in the generation of other regulated wastes including wastewaters and air emissions.
D. The Contractor shall have proper secondary containment for storage of all liquid hazardous materials at the work site. This secondary containment shall be capable of containing 10% of the volume of all containers or 100% of the volume of the largest container whichever volume is the greater.
1.4 PERFORMANCE REQUIREMENTS
A. General: Practice efficient waste management in the use of materials in the course of the Work.
Use all reasonable means to divert construction and demolition waste from landfills and incinerators. Facilitate recycling and salvage of materials.
1.5 WASTE GENERATION
A. The Contractor shall be responsible for the proper management and collection of all wastes generated·. ·
B. The Contractor shall provide waste collection containers for all wastes generated that include unregulated trash, regulated wastes (construction debris, unusable excavated materials; and recyclable used oil), hazardous wastes, and wastewaters that cannot be discharged. The Contractor shall submit to the Engineer copies of all weight tickets from the disposal of waste. All waste shall be disposed of in permitted landfills, recycling, or treatment facilities.
C. All regulated waste generated by the Contractor shall be managed in accordance with all State, Federal and local agencies having jurisdiction. '
D. All hazardous waste or potentially hazardous waste generated by the Contractor shall be managed in accordance with all Resource Conservation and Recovery Act (RCRA 40 CFR 260 - 266, 268 and 270), and other State and local agencies having jurisdiction. The Contractor shall be responsible for the proper collection and management of all hazardous waste.
E. The Contractor shall not discharge wastewater to any sewer, sanitary or storm, or into waterways.
1.6 SPILLS AND RELEASES
A. The Contractor shall be responsible for, and shall pay all costs for the cleanup and the disposal of wastes from any spills or releases of any hazardous materials (including all wastes) to the environment.
B. If the Contractor is performing a spill cleanup, the Contractor shall perform the cleanup in a manner that complies with applicable federal, state, and local laws and requirements.
1.7 ABATEMENT OF AIR POLLUTION
A. The Contractor shall comply with all federal, state, and local air pollution regulations.
B. The Contractor shall not release any chlorofluorocarbons (CFCs) to the environment when executing this contract.
1.8 SUBMITTALS
A Waste Management Plan: Submit plan within (15) fifteen days of date established for the Notice to Proceed.
B. Recycling and Processing Facility Records if applicable: Indicate weight, receipt and acceptance of recyclable waste by recycling and processing facilities licensed to accept them.
C. Landfill and Incinerator Disposal Records: Indicate weight, receipt and acceptance of waste by landfills and incinerator facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
D. OSHA-Approved hazardous communication program, site safety plan, emergency plans.
1. Indicate receipt and acceptance of hazardous wastes by a landfill facility licensed to accept hazardous wastes.
1.9 QUALITY ASSURANCE
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
1.10 WASTE MANAGEMENT PLAN
A. General: Develop a waste management plan according to ASTM E 1609 and requirements in this Section. Plan shall consist of waste identification and waste reduction work plan.
B. Waste Identification: Indicate anticipated types and quantities of salvage, recycling, and construction waste generated by the work.
C. Waste Reduction Work Plan: List each type of waste and whether it will be salvaged, recycled, or disposed of in landfill or incinerator. Include points of waste generation, quantity for each means of recovery, and handling and transportation procedures.
1. Salvaged Materials for Reuse: For materials that will be salvaged and reused in this Project, describe methods for preparing salvaged materials before incorporation into the Work.
2. Recycled Materials: Include list of local receivers and processors and type of recycled materials each will accept.
3. Disposed Materials: Indicate how and where materials will be disposed of. Include name, address, and telephone number of each landfill and incinerator facility.
4. Handling and Transportation Procedures: Include method that will be used for separating recyclable waste including sizes of containers, container labeling, and designated location where materials separation will be performed.
D. Waste Management Report: Provide a final report at the end of the project. Report shall consist of actual quantities by weight of waste salvaged, recycled, disposed of in landfill or incinerator.
PART 2- PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 PLAN IMPLEMENTATION
A. General: Provide handling, containers, storage, signage, transportation, and other items as required to implement waste management plan during the entire duration of the Contract.
B. Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Designate and label specific areas on Project site necessary for separating materials that are to be salvaged, recycled, and disposal.
3.2 RECYCLING DEMOLITION AND CONSTRUCTION WASTE, GENERAL
A. General: Recycle paper and beverage containers used by on-site workers.
B. Preparation of Waste: Prepare and maintain recyclable waste materials according to recycling or reuse facility requirements.
C. Procedures: Separate recyclable waste from other waste materials, trash, and debris. Separate recyclable waste by type at Project site to the maximum extent practical according to approved construction waste management plan.
1. Provide appropriately marked containers or bins for controlling recyclable waste until removed from Project site.
2. Remove recyclable waste from Owner's property and transport to recycling receiver or processor.
3.3 DISPOSAL OF WASTE
A. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.
1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. Burning: Do not burn waste materials.
C. Disposal: Remove waste materials from Owner's property and legally dispose of or recycle them.
D. Do not discard trash or construction debris into waterways.
END OF SECTION 017419
SECTION 024100 DEMOLITION
PART 1 GENERAL
This section details the requirements for removal of the Wimbee Creek Fishing Pier.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
A. U.S. ARMY CORPS OF ENGINEERS (USACE)
B. EM 385-1-1 (2008; Change 1-2010; Change 3-2010; Errata 1-2010) Safety and Health Requirements Manual
1.2 GENERAL REQUIREMENTS
Do not begin demolition until authorization is received from the Engineer. Remove rubbish and debris from the project site; do not allow accumulations. The work includes demolition and removal of resulting rubbish and debris. Remove rubbish and debris from Owner's property daily, unless otherwise directed.
Materials that cannot be removed daily shall be stored in areas specified by the Owner. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1, Section 23, Demolition, and other applicable Sections.
1.3 SUBMITTALS
Waste Certificates, Demolition Plan
1.4 REGULATORY AND SAFETY REQUIREMENTS
Comply with Federal, State, and local hauling and disposal regulations.
1.5 DUST AND DEBRIS CONTROL
Prevent the spread of dust and debris and avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution.
1.6 PROTECTION
A. Traffic Control Signs
Where pedestrian and driver safety is endangered in the area of removal work, use traffic barricades with flashing lights. Anchor barricades in a manner to prevent displacement by wind. Notify the Engineer prior to beginning such work.
B. Boat Landing
Contractor shall not impede boating operations or damage existing boat landing.
C. Existing Work
Before beginning any demolition work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing work showing the condition of structures and other facilities adjacent to areas of alteration or removal. Digital photographs with a photo log submitted on a CD will be acceptable as a record of existing conditions. Include in the description the location and extent of cracks and other damage and description of surface conditions that exist prior to starting work.
D. Items to Remain in Place
Take necessary precautions to avoid damage to existing items to remain in place. Repair or replace damaged items as approved by the Engineer. Coordinate the work of this section with all other work indicated. Ensure that structural elements are not overloaded.
E. Existing Construction
Do not disturb existing construction beyond the extent .indicated or necessary for installation of new construction. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove dust, dirt, and debris from work areas daily.
F. Utility Service
Maintain existing utilities to stay in service and protect against damage during demolition operations.
G. Protection of Personnel
Before, during and after the demolition work the Contractor shall continuously evaluate the condition of the structure being demolished and take immediate action to protect all personnel working in and around the demolition site.
1.7 BURNING
The use of burning at the project site for the disposal of refuse and debris will not be permitted.
1.8 REQUIRED DATA
The Demolition plan shall include procedures for careful removal and disposition of materials coordination with other work in progress, a detailed description of methods and equipment to be used for each operation and of the sequence of operations. The demolition plan shall clearly identify the disposal facility receiving all waste.
1.9 ENVIRONMENTAL PROTECTION
Comply with the Environmental Protection Agency requirements specified.
1.10 USE OF EXPLOSIVES
Use of explosives will not be permitted.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED OR/AND SALVAGED
A. Structures to be Removed Existing structures contain treated timber that require disposal. All structures indicated for removal shall be removed as indicated in the drawings, taking care not to leave any debris on the river bed or concrete boat landing.
1. Seven Timber Pile Bents
2. One Steel Pile and Reinforced Concrete Bent
3. Plate Girder Superstructure
4. Pedestrian Stairs
5. Deck and Railing
B. Structures to be Salvaged
1. Existing Abutment
3.2 DISPOSITION OF MATERIAL
3.2.1 Title to Materials
All materials and equipment designated for demolition shall become the property of the Contractor and shall be removed from Owner's property. All materials and equipment designated as salvage shall be moved to a location designated by the Owner.
3.3 CLEANUP
A. Cleanup of Site
Debris shall be removed and transported in a manner that prevents spillage on streets or adjacent areas.
Contractor shall verify that the boat ramp is free from debris and obstructions from demolition and salvage work. Contractor shall follow all local regulations regarding hauling and disposal.
3.4 DISPOSAL OF REMOVED MATERIALS
A. Regulation of Removed Materials
Dispose of debris, rubbish, scrap, and other non-salvageable materials resulting from removal operations shall comply with all applicable federal, state and local regulations as contractually specified off site.
Removed materials shall not be stored on the project site. Comply with Section 017419 -
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL.
B. Removal from Owner's Property
Transport waste materials removed from demolished structures from Owner's property for legal disposal.
3.5 REUSE OF SALVAGED ITEMS
Replace items damaged during removal and salvage operations or restore them as directed by the Engineer prior to reuse.
3.6 DEMOLITION VERIFICATION
A. Contractor shall conduct pre and post demolition side scan sonar surveys of the site. Side scan sonar information shall extend 50 ft outside of the perimeter of the existing pier. Sonar information shall be georeferenced. Sonar information shall identify any materials that extend more than 1 ft off of the existing channel bottom. Submit side scan sonar information to engineer prior to demobilizing from project site.
END OF SECTION 024100