About this file

This Scope of Work document is issued by the Virginia Department of Health (VDH) for a well installation and spring abandonment project located at 358 Lauck Lane, Luray, VA 22835, under permit number WIIN24-01_W&WA. The project requires the contractor to construct a private water well meeting Virginia Private Well Regulations (12VAC5-630-10 et seq.) and Page County Department Well Construction Permit #139-WW-20658, including tree removal and site clearing, installation of a minimum 50 feet of casing and grout, provision of well pump and plumbing by licensed professionals, well disinfection, and abandonment of the existing spring according to regulatory specifications. The contractor must obtain all necessary permits, inspections, and comply with erosion and sediment control requirements. Initial bids must be submitted for an estimated depth of 150 feet with itemized costs for mobilization and setup; actual payment will be based on verified actual depth drilled. A pre-bid site visit is recommended, and bidders should contact Angelica Cipara at angelica.cipara@vdh.virginia.gov to arrange visitation. Selected bidders must provide a signed Notice to Proceed within three business days of notification and submit project start and end dates within two weeks prior to work initiation or within four weeks after issuance of the Purchase Order.

Bidders must submit detailed cost breakdowns for the base 150-foot installation and separate cost schedules for additional services, with per-foot pricing for depths exceeding 150 feet. Bidders who submit bids for over or under the 150-foot estimate will not be accepted. The contractor must be certified as a Water Well System Provider by the Department of Professional and Occupational Regulations and provide proof of insurance; failure to submit required documentation within 24 business hours of VDH's request will result in non-responsive bid status. All change orders, contract extensions, and additional services beyond the scope require prior written approval from VDH. Final invoicing occurs only after the Local Health Department issues a Record of Inspection and the contractor submits all required documentation including the GW-2 completion report, water quality test results (GW-5), and lab results to VDH_SWAP_Grant@vdh.virginia.gov.

View the file

Other files

File Type Posted
Construction Terms and Conditions-.docx DOCX document
General_Terms_and_Conditions PIM 45 July 2025.docx DOCX document
REDACTED_UPDATED WIIN24-01_W&WA Well Permit.pdf PDF
ARPA FUNDING-.docx DOCX document
SPECIAL TERMS AND CONDITIONS.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Well Installation and Well Abandonment (WIIN24-01_W&WA)

Address: 358 Lauck Lane Luray, VA 22835

Scope of work:

The contractor shall furnish all labor, supervision, equipment, tools, parts, supplies and materials, as necessary, to perform the services as described herein:

Cost for Line Item #1 (include total cost for items A-H). These are known factors. Vendors must invoice for actual cost incurred as described herein. The initial bid should be an average cost/foot of depth for 150 feet (add other itemized costs such as mobilization/setup, etc.). Please note: 150 feet is an estimate, vendor will bill based on actual service performed, actual depth drilled (as verified on the GW-2 and VDH’s Record of Inspection). Vendor will only be paid for actual well depth drilled, casing depth, grout depth, depth of drop pipe, pump, etc. Vendor must provide a detailed bid for 150 ft.; any additional footage must be listed as additional services at a per foot rate. Vendors who submit bids for over or under 150 feet will not be accepted.

A) Construct a private water well that meets the location, construction specifications, water quantity, and water quality requirements of the Virginia Private Well Regulations (12VAC5-630-

10 et seq., the Regulations).

B) Tree Removal and Site Clearing: A pre-bid site visit is recommended to determine what if any tree removal or site clearing that may need to occur. Per the above referenced

Permit, remove any trees and wood debris as described in the permit and haul away wood and debris unless notified otherwise. Costs of tree removal and site clearing should be included in initial bids. Any additional site clearing or tree removal required during installation must be submitted in writing to and approved by VDH in writing including an additional cost estimate.

Any personal property items that will prohibit the contractor from accessing the site or installation of the new system is the responsibility of the homeowner to remove and should not be included in the bid.

C) Construct the above class III(B) well with a minimum of 50' of casing and grout and in compliance with the Page County Department Well Construction Permit #139-WW-20658 /

HDID #139-26-03 and spring abandonment instructions at the location shown on the permit.

The permit may contain additional conditions, notes, and information needed to construct the well.

D) Provide, or subcontract with a licensed plumber and electrician to provide, the well pump, plumbing, and electrical required to convey the water under sanitary conditions from the well to the home plumbing system in the quantity required by the Regulations and the Virginia Uniform

Statewide Building Code. This includes obtaining or assuring that the owner obtains all permits and inspections necessary by the local building authority in compliance with the Virginia

Uniform Statewide Building Code.

E) Disinfect the well and plumbing as required by the Regulations and provide the required

Uniform Water Well Completion Report (GW2). Obtain a final compliance inspection from the health department and a Record of Inspection and assure that the well is tested and complies with the water quality requirements of the Regulations.

F) Appropriately abandon existing private drinking water supply/well. Abandon the spring as specified by the Regulations and by the Page County Department Well Construction Permit

#139-WW-20658 / HDID #139-26-03.

G) Follow all regulations and permitting pertaining to erosion and sediment control including stabilizing, seeding and grading the site after construction to return to the original state. Control construction runoff with proper practices so as not to become a nuisance to the owner or to neighboring properties or cause sediment to be discharged into state waters and drainage ditches.

Any construction debris must also be removed from the site and disposed of properly.

H) Bidders shall comply with all requirements of the Department of Professional and

Occupational Regulations (DPOR) for contracting and executing the contract with the Virginia

Department of Health. Operate within the requirements of the DPOR Water Well System

Provider Certification and proof of insurance. Bidders contacted by VDH to provide any missing required documents must provide the document within 24 business hours or their bid will be considered non-responsive.

I) Provide to VDH_SWAP_GRANT@vdh.virginia the following information by the listed deadline:

• Project Start and End Dates: Estimated project start and completion dates to be provided two (2) weeks prior to the start of the installation/work or within four (4) weeks after issuance of PO (issuance of Notice to Proceed); whichever is earlier.

• Name and licensure of subcontractor(s): The contractor shall within four (4) weeks after the signing of the contract (or within two weeks of the work starting or within 1 week after changing subcontractor; whichever is earlier), notify VDH in writing of the names of subcontractors proposed for the principal parts of the work.

• Request for Change Orders: All request for changes must be provided in writing per the contract terms and conditions and are not authorized until a response in writing is sent by the SWAP team.

• Request for Extensions: If it is determined that the work will not be able to be completed by the contract expiration date listed in the Notice to Proceed and the PO, a request for an extension must be provided, in writing, a minimum of two weeks prior to contract mailto:VDH_SWAP_GRANT@vdh.virginia

• expiration date. Justification for why work could not be performed within original contract term must be provided. Extensions requested on or after the expiration date will not be able to be accommodated.

J) Provide all required documentation (completion report, water tests GW-2 and/or GW-5, etc.) to the Page County Department following completion of construction in order to obtain a

Record of Inspection for both the well installation and well abandonment.

K) Submit invoice to VDH_SWAP_Grant@vdh.virginia.gov once and the Local Health

Department has inspected the work and has issued the Record of Inspection (ROI) along with a copy of the ROI, GW-2, GW-05, lab results and completion statement.

Additional Services (If Needed) Bidder must contact VDH Project Manager listed on the

Notice to Proceed for approval prior to any additional services performed. VDH will issue a change order for actual additional services rendered.

The contractor shall furnish all labor, supervision, equipment, tools, parts, supplies and materials, as necessary, to perform the services as described herein:

A. Additional depth (beyond 150 ft.): provide a per foot rate for additional depth. If bidder has an estimate of how deep the well may be at this location, please provide. Examples:

a. Additional Depth (beyond 150 feet): $xx/ft, estimated additional depth 250 feet, estimated total well depth 400 feet.

b. Additional cost for installation of a pump below 150 ft., including per foot cost for drop pipe.

B. Additional Services beyond what was quoted in A-K above (please list/enumerate and detail).

Breakdown of Total Cost

When responding to solicitation, Bidders must attach a document listing breakdown of total cost for line item 1. Bidders must attach a separate breakdown of cost for additional services.

Additional cost should not be included in line item 1 bid submission.

Optional site visit: If a site visit is needed, please contact Angelica Cipara to arrange a day/time for a site visit.

Additional questions:

Contact Angelica Cipara via email: angelica.cipara@vdh.virginia.gov

Notice to Proceed

If Bidder is selected for award, the Bidder shall be required to provide a signed Notice to proceed form within 3 business days of notification. VDH will provide a form for signature.