This is a Performance Work Statement (PWS) for tank cleaning and inspection services on the USCGC William Hart (WPC-1134) and USCGC Joseph Gerczak (WPC-154) during FY2026 dockside availability.
The contractor must clean and inspect twelve fuel and waste tanks plus one void space, removing and disposing of specified quantities of diesel fuel and contaminated fluids in compliance with Federal, state, and local regulations. Key requirements include: furnishing protective coverings to prevent contamination of non-affected vessel components; removing tank covers and cleaning interior surfaces free of foreign materials (residual fuel, water, sediment, sludge, rust, biological growth) without damaging existing coating systems; performing comprehensive visual inspections of tank structural condition, coating integrity with pit measurements, fasteners, gasket seating surfaces, tank level indicators, sounding/vent tubes, suction/discharge piping, and zinc anode condition; maintaining written plug logs for tank vents; documenting complete chain of custody records for all removed fluids; and closing tanks with new gaskets conforming to AMS-C6183 and renewed fasteners per MIL-DTL-1222 specifications. The contractor must coordinate with ship's force regarding SSDG service tank draining schedules, witness initial and post-repair operational tests of tank level indicators, keep tanks open for at least 24 hours following authorized repairs, and notify the Contracting Officer at least 24 hours before closing. All work requires Coast Guard inspector approval, with CFRs (Contractor's Form Reports) submitted upon completion of major task phases. The government furnishes no property and will operate all shipboard machinery and equipment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF1449.pdf | ||
| dockside SOW.docx | DOCX document | |
| 154-WPC_601_302_1_-_D.pdf | ||
| SFLC-ESD-25_Tank_and_Void_Assessment_Form.pdf | ||
| 154B-WPC_601_302_1_-_A.pdf | ||
| 154-WPC_506_201_1_-_A.pdf | ||
| Wage Determination Honolulu.txt | TXT text file | |
| Fixed_Price_Service_FAR_HSAR_Clauses.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC WILLIAM HART (WPC-1134) DOCKSIDE AVAILABILITY FY2026
15 (Rev-0)
12305_JLW_0523_154WPC
WORK ITEM 1: Tanks, Clean and Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
TABLE 1 FUEL TANKS AND VOIDS
TANK LOCATION CAPACITY -
95%
(GALLONS)
FUEL OR
WASTE WATER
TO BE
REMOVED AND
DISPOSED OF
(GALLONS)
Fuel Oil Service 1S 3-17-1-F 1750 175
Fuel Oil Service 1P 3-17-2-F 1750 175
Fuel Oil Service 2S 3-41-1-F 840 84
Fuel Oil Service 2P 3-41-2-F 840 84
Emer Gen Fuel Tank 1-10-1-F 93 10
Fuel Oil Storage 1 3-11-0-F 5040 504
Fuel Oil Storage 2 3-23-0-F 5350 535
Fuel Oil Overflow 1 3-10-0-F 606 60
Fuel Oil Overflow 2 3-40-0-F 1159 115
Oily Water 3-34-1-W 336 34
Dirty Oil 3-34-2-F 336 34
Aft Void 3-43-0-V 924 N/A
1.2 Government-furnished property.
None.
USCGC JOSEPH GERCZAK (WPC-154) DOCKSIDE AVAILABILITY FY2026
16 (Rev-0)
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 154 WPC 601-302, Rev D, General Arrangement
Coast Guard Drawing 154B WPC 601-302, Rev -, General Arrangement
Coast Guard Drawing 154 WPC 506-301, Rev -, Fills, Vents, Sounds and Overflows Diagram
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
OTHER REFERENCES
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets
MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of Reliability Is Required
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor must remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
Fuel
Piping
Tank access cover
3.1.4.1 Fuel. The Contractor must remove and dispose of diesel fuel in the quantities listed in Table 1.
Dispose of removed fluids in accordance with all applicable Federal, state, and local regulations (see 4.2 (Tank content restoration)). Document a complete chain of custody record of the removed tank contents from the vessel to the point of final destination or delivery. Submit CFR to the COR upon completion of work.
17 (Rev-0)
3.1.4.2 SSDG service tank draining/cleaning. In the event that generators must be operated aboard the vessel during execution of this item, an adequate amount of fuel must remain in at least one generator service tank for the duration while others are being cleaned. The Contractor must coordinate with ships force to determine a plan for filling this requirement (e.g. drain/clean one SSDG service tank then ship force refill prior to working subsequent service tanks, etc.). Submit a CFR documenting the mutually agreed upon plan for SSDG service tank cleaning.
NOTE
Vessel may come in with less tank fluid contents than specified above.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard demonstrate existing operational condition. Submit a CFR.
3.3 Plug log. The Contractor must keep a written record of all plugs put in any tanks vents. A separate list must be kept for each tank being entered.
3.3.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.
3.3.2 Ensure the plug log is available to the Coast Guard inspector when the inspector is performing his close-out inspection on each tank.
NOTE
Initial and post repair operational tests apply only to tanks that possess TLIs.
3.4 Cleaning requirements. The Contractor must remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as residual fuel or water, sediment, sludge, rust, or biological growth, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.
3.5 Tank content and waste disposal. The Contractor must dispose of residual tank contents and any cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.
3.6 Inspection. The Contractor must accomplish the following tasks:
3.6.1 Visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces.
Submit a CFR including the following, as applicable:
Tank structural condition.
Inaccessible areas.
18 (Rev-0)
Condition of tank coating, including measurements taken, percentage, location, and type of coating failure (if tank interior surfaces are coated).
Tank level indicator (TLI) and/or float switch condition, as applicable.
Sounding/vent tube and striker plate condition.
Suction and discharge piping condition.
Fastener material and condition (correct fastener material is stainless steel).
Determine condition of zinc anodes in oily water & dirty oil tanks (zincs with 50% wastage or more should be renewed).
3.6.2 Include pit measurement results in CFR specified above, showing where pit measurements were taken and the depth of the pit.
3.7 Tank closing. The Contractor must ensure that the tank(s) remain open for at least 24 hours after completion of any KO-authorized repair and preservation procedures. Notify the COR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to AMS-C- 6183. Chase threads on studs to ensure even installation of the access covers. Renew any damaged or missing fasteners. Use MIL-DTL-1222 as guidance. Existing undamaged fasteners may be reused. For purpose of bid, assume 10% of existing fasteners will require renewal. Renew all Nylock hex nuts.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.8 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all operating condition. Submit a CFR.
4. NOTES
4.1 Tank content removal.
with the installed pumping system.
4.2 Tank content restoration.
appropriate time.