PROJECT MANUAL

FOR

ROOF REPLACEMENT

AT

VILLAGE OF SCHAUMBURG

WELL #15

325 W. WISE ROAD

Schaumburg, Illinois 60173

OWNER:

Village of Schaumburg

DOCUMENTS DATED:

ISSUED FOR

PERMIT AND BID:

MARCH 26, 2021

845 DESIGN GROUP, PC.

106 CALENDAR COURT, NO. 131

LA GRANGE, IL. 60525

845 JOB NO. 20.01.04

2021 845 DESIGN GROUP

Professional Design Firm #184‐006583

VILLAGE OF SCHAUMBURG

WELL #15 ROOF REPLACEMENT Construction Specifications

TABLE OF CONTENTS Page: 011000-1

SECTION 01 10 00 – TABLE OF CONTENTS1

DIVISION 1 _ GENERAL REQUIREMENTS3

SECTION 01 15 00 SCHEDULE OF DRAWINGS4

SECTION 01 11 00 _ SUMMARY6

SECTION 01 25 00 _ SUBSTITUTION PROCEDURES7

SECTION 01 25 00A _ DATA FOR EVALUATION OF MATERIALS PRODUCTS8

SYSTEM9

SECTION 01 26 00 _ RFI FORM10

SECTION 01 33 00 _ SUBMITTAL PROCEDURES11

SECTION 01 40 00 _ QUALITY REQUIREMENTS12

SECTION 01 73 00 _ EXECUTION13

SECTION 01 77 00 _ CLOSEOUT PROCEDURES14

SECTION 01 78 23 _ OPERATION AND MAINTENANCE DATA15

SECTION 01 78 39 _ PROJECT RECORD DOCUMENTS16

SECTION 01 70 00 _ DEMONSTRATION AND TRAINING17

DIVISON 2 EXISTING CONDITIONS19

SECTION 02 41 19 SELECTIVE DEMOLITION20

DIVISON 4 MASONRY22

SECTION 04 10 00 MORTAR AND MASONRY GROUT23

SECTION 04 22 13 CONCRETE UNIT MASONRY24

DIVISION 5 METALS26

SECTION 05 12 00 STRUCTURAL STEEL FRAMING27

SECTION 05 40 00 COLD FORMED METAL FRAMING28

SECTION 05 50 00 METAL FABRICATIONS29

***SEE STRUCTURAL DRAWINGS FOR ADDITIONAL STEEL SPECS*30

DIVISION 6 CARPENTRY32

SECTION 06 10 00 ROUGH CARPENTRY33

SECTION 06 13 23 HEAVY TIMBER34

SECTION 06 15 16 WOOD ROOF DECKING35

SECTION 06 16 00 SHEATHING36

SECTION 06 20 23 INTERIOR FINISH CARPENTRY37

DIVISION 7 THERMAL AND MOISTURE PROTECTION39

SECTION 07 01 50 PREPARATION FOR RE-ROOFING40

SECTION 07 21 00 THERMAL INSULATION41

SECTION 07 25 00 WEATHER BARRIERS42

SECTION 07 42 13 INSULATED METAL PANELS43

SECTION 07 53 23 ETHYLENE-PROPYLENE-DIENE MONOMER (EPDM)44

ROOFING45

SECTION 07 71 00 ROOF SPECIALTIES46

SECTION 07 72 00 ROOF ACCESSORIES47

SECTION 07 84 13 PENETRATION FIRESTOPPING48

SECTION 07 92 00 JOINT SEALANTS49

DIVISION 8 DOORS AND WINDOWS51

SECTION 08 11 13 HOLLOW METAL DOORS AND FRAMES52

DIVISION 9 FINISHES54

SECTION 09 22 16 NON-STRUCTURAL METAL FRAMING55

SECTION 09 77 00 FRP PANELS56

TABLE OF CONTENTS Page: 011000-2

SECTION 09 91 23 PAINTING1

END OF SECTION 01 10 003

LIST OF DRAWING SHEETS 01 15 00-1

The construction site is located at:

Village of Schaumburg Well #15 South of Wise Road and East of Leonard Drive Schaumburg, IL. 60173

The Specification comprises the following Divisions:

Division Title

1 General Requirements 2-12 Architectural

The Drawings are comprised of the following:

No. Title

A100 COVERSHEET

S1.0 STRUCTURAL DRAWINGS

A101 DEMOLITION PLANS, ELEVATIONS, & SECTION

A102 PLANS, ELEVATIONS, AND SECTION

A300 WALL SECTIONS AND DETAILS

A400 ENLARGED PLAN DETAILS

VILLAGE OF SCHAUMBURG Construction Specifications

WELL #15 ROOF REPLACEMENT

SUMMARY 011000 ‐ 1

SECTION 011000 ‐ SUMMARY

PART 1 ‐ GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Access to site.

4. Coordination with occupants.

5. Work restrictions.

6. Specification and drawing conventions.

7. Miscellaneous provisions.

1.3 PROJECT INFORMATION

A. Project Identification: Roof Replacement for Well #15

1. Project Location: East of Leonard Drive and South of Wise Road, Schaumburg, IL. 60173

B. Owner: The Village of Schaumburg

C. Architect: 845 Design Group, P.C. Jamie Zaura (708)872‐4146

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of the Project is defined by the Contract Documents and consists of the following:

1. Remove the existing roof (including the mansard roof), gutters, downspouts, roof scuttle and prepare for new roof, new roof structure, new access doors, and new roof hatch.

Access vertically and horizontally is required of the new structure.

B. Type of Contract:

1. Project will be constructed under a single prime contract.

SUMMARY 011000 ‐ 2

1.5 ACCESS TO SITE

A. Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. The building will be in operation during working hours.

1.6 COORDINATION WITH OCCUPANTS

A. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Maintain existing exits unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.

2. Notify Owner not less than 24 hours in advance of activities that will affect Owner's operations.

1.7 WORK RESTRICTIONS

A. Work Restrictions, General: Have been provided in the Village of Schaumburg Contract Requirements.

B. Existing Utility Interruptions: Due to the nature of the work the existing utilities will need to be interrupted, please alert the Owner within 72 hours of equipment shut off.

C. Nonsmoking Building: All Contractors, their subcontractors, employees and agents are required to abide by the smoking policies in effect in all municipal buildings owner, leased, or operated by the Village of Schaumburg. Failure to abide by these regulations is a violation of this contract; and in addition, may subject the violator to civil penalties as prescribed State law.

1.8 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

SUMMARY 011000 ‐ 3

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

END OF SECTION 011000

SUBSTITUTION PROCEDURES 012500 ‐ 1

SECTION 012500 ‐ SUBSTITUTION PROCEDURES

PART 1 ‐ GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

1.3 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.

2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner.

1.4 ACTION SUBMITTALS

A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: Use data for evaluation of materials, products and systems form in the specification manual.

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.

b. Coordination information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors, that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable Specification Section.

Significant qualities may include attributes such as performance, weight, size, SUBSTITUTION PROCEDURES 012500 ‐ 2 durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested.

f. Certificates and qualification data, where applicable or requested.

g. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners.

h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

i. Research reports evidencing compliance with building code in effect for Project, from ICC‐ES.

j. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.

k. Cost information, including a proposal of change, if any, in the Contract Sum.

l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution.

Architect will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the Work.

b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.

1.5 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.

SUBSTITUTION PROCEDURES 012500 ‐ 3

1.6 PROCEDURES

A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.

PART 2 ‐ PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Substitution request is fully documented and properly submitted.

c. Requested substitution will not adversely affect Contractor's construction schedule.

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: Architect will consider requests for substitution if received within 15 days after the Notice of Award. Requests received after that time may be considered or rejected at discretion of Architect.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.

SUBSTITUTION PROCEDURES 012500 ‐ 4

b. Requested substitution does not require extensive revisions to the Contract Documents.

c. Requested substitution is consistent with the Contract Documents and will produce indicated results.

d. Substitution request is fully documented and properly submitted.

e. Requested substitution will not adversely affect Contractor's construction schedule.

f. Requested substitution has received necessary approvals of authorities having jurisdiction.

g. Requested substitution is compatible with other portions of the Work.

h. Requested substitution has been coordinated with other portions of the Work.

i. Requested substitution provides specified warranty.

j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

END OF SECTION 012500

DATA FOR EVALUATION OF MATERIALS, PRODUCTS AND SYSTEMS 012500A‐1

SECTION 012500A – DATA FOR EVALUATION OF MATERIALS, PRODUCTS AND SYSTEMS

1.1 GENERAL:

A. In order for the proposed substitution to be given proper consideration, please complete the following:

1. Product Name:_____________________________________

2. Manufacturer:______________________________________

3. Product Description:_________________________________

3.1 Basic Use:_________________________________________

3.4 Composition and Materials:___________________________

3.5 Location of place where the material or product has been extracted, harvested or recovered as well as manufactured: ____________________________________

1.2 PRODUCT EXPERIENCE AND MANUFACTURER QUALIFICATIONS:

A. List projects where this product was used in the same way as proposed for this project. Include names, addresses and telephone number of Contractors, Owners and Architects who can be contacted to report experience with this product. Submit information on project location, year installed and approximate square footage.

1. Describe in detail successful results:______________________________

2. Describe in detail unsuccessful results:_____________________________

3. Having reviewed the Contract Documents and being aware of the manner in which the product is to be used, furnish us with complete technical data as it pertains to the intended application in addition to your promotional catalogue.

4. Describe in detail the product’s limitations:__________________________

5. State your delivery parameters:____________________________________

6. To what extent do you warrant the product:__________________________

7. What has been your warranty history?______________________________

8. What previous experience have you had in this product line?

9. What are the qualifications of your field representative?

DATA FOR EVALUATION OF MATERIALS, PRODUCTS AND SYSTEMS 012500A‐2

10. (For new or small manufacturer)

10a. Do you have the financial resources to execute this project?_____________________________

10b. Do you have the production capacity to execute this project?____________________________

11. Submit a tailor specification as it pertains to the proposed application.

12. (For major items of significance)

Will you provide a field rep to observe or supervise installation?______________________________

Is your installer/applicator certified by the manufacturer?___________________________________

Will you certify, upon completion that the product has been installed according to the manufacturer’s recommendation?: ______________________________________

13. What union has jurisdiction:__________________________________________________________

14. Costs:

Material cost:______________________________________

Installed cost:______________________________________

1.3 PERFORMANCE DATA:

A. In order to evaluate the material, product, or system, please complete applicable portions of the following form. Add pertinent information, and indicate “not applicable” for items that are not appropriate. If you refer to product literature, please identify specifically, the portions that apply. List the following properties and characteristics for our information in evaluating its potential for use in our projects. Whenever applicable, responses should be quantitative, and in terms of the same recognized testing procedures of comparable or competitive products.

B. For each applicable property or characteristic below, identify testing procedure and results.

1. Strength and Stability

1.1 Loads:________________________________________

1.1.1 Wind:_____________________________________

1.1.2 Seismic:___________________________________

1.1.3 Compressive:_______________________________

DATA FOR EVALUATION OF MATERIALS, PRODUCTS AND SYSTEMS 012500A‐3

1.1.4 Tensile:____________________________________

1.1.5 Impact:____________________________________

1.1.6 Modulus of Rupture:_________________________

1.1.7 Impact:____________________________________

1.1.8 Weight:____________________________________

2. Fire Safety

2.1 Fire Resistance:_________________________________________

2.2 Flame Spread:__________________________________________

2.3 Smoke Development:____________________________________

2.4 Toxicity:______________________________________________

2.5 Fuel Contribution:_______________________________________

2.6 Combustibility:__________________________________________

2.7 Testing Lab Label:________________________________________

3. Habitability

3.1 Thermal Properties:_______________________________________

3.1.1 Thermal Conductivity:__________________________________

3.1.2 Thermal Expansion:____________________________________

3.1.3 Thermal Shock:________________________________________

3.2 Acoustic Properties:________________________________________

3.2.1 Sound Transmission:____________________________________

3.2.2 Sound Absorption:______________________________________

3.2.3 Sound Reverberation:____________________________________

3.3 Water Permeability:_________________________________________

3.3.1 Water Absorption:_______________________________________

3.3.2 Permeability:___________________________________________

3.3.3 Water Vapor Transmission:________________________________

DATA FOR EVALUATION OF MATERIALS, PRODUCTS AND SYSTEMS 012500A‐4

3.3.4 Moisture Expansion and Drying Shrinkage:____________________

4. Durability

4.1 Resistance to Wear:___________________________________________

4.1.1 Abrasion Resistance:_______________________________________

4.1.2 Scratch Resistance:_________________________________________

4.2 Weathering:__________________________________________________

4.2.1 Freeze‐Thaw:______________________________________________

4.2.2 Ozone:____________________________________________________

4.2.3 Fading:____________________________________________________

4.2.4 Chemical Fumes:____________________________________________

4.2.5 Bactericidal:________________________________________________

4.3 Adhesion of Coatings:_____________________________________________

4.3.1 Delamination:_______________________________________________

4.3.2 Blistering:__________________________________________________

4.4 Dimensional Stability:____________________________________________

4.4.1 Shrinkage:__________________________________________________

4.4.2 Expansion:__________________________________________________

4.4.3 Volume Change:_____________________________________________

5. Practicability

5.1 Transport:_________________________________________________________

5.1.1 Limitations with Respect to Size, Weight, Handling:_______________________

5.2 Storage on

Site:________________________________________________________

5.2.1 Protection Against

Element:___________________________________________

DATA FOR EVALUATION OF MATERIALS, PRODUCTS AND SYSTEMS 012500A‐5

5.3 Handling on Site & During

Installation:_____________________________________

5.3.1 Abrasion:______________________________________________________

5.3.2 Breakage:______________________________________________________

5.3.3 Patching:_______________________________________________________

5.4 Field

Tolerances:_______________________________________________________

5.4.1 Corrective

Measures:_________________________________________________

5.5 Connections:_______________________________________________________

5.5.1 Inserts:________________________________________________________

5.6 Availability:________________________________________________________

6. Compatibility

6.1 Jointing

Materials:______________________________________________________

6.1.1 Adherence of

Sealants:____________________________________________________

6.1.2 Ability to Receive & Retain

Coatings:_____________________________________________________

6.2.2 Interaction:_____________________________________________________

6.3 Galvanic Interaction or Corrosion

Resistance:_____________________________________

6.3.1 Steel:____________________________________________________________________

6.3.2 Aluminum:_______________________________________________________________

6.3.3 Wood:___________________________________________________________________

6.3.4 Others:__________________________________________________________________

7. Maintenance

7.1 Indentation &

Puncture:_________________________________________________________

7.1.1 Patching:______________________________________________________

DATA FOR EVALUATION OF MATERIALS, PRODUCTS AND SYSTEMS 012500A‐6

7.2 Chemical or Graffiti Attack:__________________________________________

7.2.1 Cleanability:____________________________________________________

7.2.2 Resistance to

Attack:_______________________________________________

7.3 Protection:_________________________________________________________

7.4 Delamination:______________________________________________________

7.5 Blistering:________________________________________________________

8. Code Acceptance

8.1 Review of

Codes:_____________________________________________________

8.1.1 Fire:__________________________________________________________

8.1.2 Health &

Safety:__________________________________________________

8.1.3 National:______________________________________________________

8.1.4 Local:_________________________________________________________

8.1.5 Energy:________________________________________________________

9. Economics

9.1 Installed

Costs:_______________________________________________________

9.2 Maintenance

Costs:____________________________________________________

9.3 Life Cycle

Costs:______________________________________________________

10. Installation

10.1 General:___________________________________________________________

10.2 Preparatory

Work:____________________________________________________

10.3 Placement/Application:_______________________________________________

DATA FOR EVALUATION OF MATERIALS, PRODUCTS AND SYSTEMS 012500A‐7

10.4 Precautions:________________________________________________________

10.5 Jurisdiction:________________________________________________________

10.6 Clean‐

Up/Cleaners:___________________________________________________

10.7 Tools/Equipment:___________________________________________________

11. Additional Items of Importance and/or Limitations that might affect the Performance of the

Product.

(Manufacturer & Address) Signature & Position Title (Date)

END OF SECTION 012500A

106 W. Calendar Court #131 La Grange, Illinois 60526 | www.845designgroup.com

R e q u e s t f o r I n f o r m a t i o n ( R F I )

To: From: Jamie Zaura

Project: Issue Date: RFI #

Project #

Copies to:

RFI Description:

Response:

Receiver’s Reply:

By: Date:

Note: This reply is not an authorization to proceed with work involving additional cost, time or both. If any reply requires a change to the Contract Documents, a Change order, Construction Change Directive must be executed in accordance with the Contract Documents.

106 W. Calendar Court #131 La Grange, IL. 60525 | www.845designgroup.com

R E Q U E S T F O R P R O P O S A L

Date: Request No.: Initiated by:

Owner

To: Project: Architect

Consultant

Field

Fax: Contractor

Attention: Project No.: Other

Please prepare and submit an itemized quotation for changes in the Contract Sum and or Time resulting from modifications to the Contract Documents described herein.

This is not a change order or direction to proceed with the work described herein. However, when signed by the Owner, this constitutes authorization to proceed with the work until such change order is issued.

Description of Change:

Documents Attached:

Reviewed With

845 DG:

Distribution:

Representative:

Owner’s Authorized

Authorized Date to Proceed:

SUBMITTAL PROCEDURES 013300 ‐ 1

SECTION 013300 ‐ SUBMITTAL PROCEDURES

1.1 DEFINITIONS

A. Action Submittals: Information that requires Architect's responsive action.

B. Informational Submittals: Information that does not require Architect's approval. Submittals may be rejected for not complying with requirements.

1.2 PROCEDURES

A. Electronic copies of the floor plan will be provided by Architect for Contractor's use.

B. Processing Time:

1. Initial Review: 15 days.

2. Concurrent Consultant Review: 15 days.

C. Transmittal Form: AIA Document G810 or equal

D. Submittal Procedures:

1. Files can be emailed to Architect or posted on General Contractor’s cloud based submittal site. No paper copies are required.

2. Tangible samples are required to be submitted.

E. Contractor's Review:

1. Submittals: Marked with approval stamp before submitting to Architect.

F. Architect's and General Contractor’s Action:

1. Action Submittals: Stamped with an action stamp and returned.

a.

SUBMITTAL PROCEDURES 013300 ‐ 2

2. Informational Submittals: Reviewed but not returned, or rejected if they do not comply with requirements.

3. Incomplete submittals will be returned without review.

4. Submittals Not Required: May not be reviewed and may be discarded.

END OF SECTION 013300

QUALITY REQUIREMENTS 014000 ‐ 1

SECTION 014000 ‐ QUALITY REQUIREMENTS

PART 1 ‐ GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for quality assurance and quality control.

1.3 DEFINITIONS

A. Quality‐Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.

B. Source Quality‐Control Testing: Tests and inspections that are performed at the source, e.g., plant, mill, factory, or shop.

C. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency. Verify that roof and hatch is water tight.

D. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub‐subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.

1. Use of trade‐specific terminology in referring to a trade or entity does not require that certain construction activities be performed by accredited or unionized individuals, or that requirements specified apply exclusively to specific trade(s).

E. Experienced: When used with an entity or individual, "experienced" means having successfully completed a minimum of five previous projects similar in nature, size, and extent to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.

1.4 CONFLICTING REQUIREMENTS

A. Referenced Standards: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality

QUALITY REQUIREMENTS 014000 ‐ 2

levels, comply with the most stringent requirement. Refer conflicting requirements that are different, but apparently equal, to Architect for a decision before proceeding.

B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits.

To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Architect for a decision before proceeding.

1.5 INFORMATIONAL SUBMITTALS

A. Contractor's Quality‐Control Plan: For quality‐assurance and quality‐control activities and responsibilities.

B. Qualification Data: For Contractor's quality‐control personnel.

C. Testing Agency Qualifications: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.

D. Schedule of Tests and Inspections: Prepare in tabular form and include the following:

1. Specification Section number and title.

2. Entity responsible for performing tests and inspections.

3. Description of test and inspection.

4. Identification of applicable standards.

5. Identification of test and inspection methods.

6. Number of tests and inspections required.

7. Time schedule or time span for tests and inspections.

8. Requirements for obtaining samples.

9. Unique characteristics of each quality‐control service.

1.6 CONTRACTOR'S QUALITY‐CONTROL PLAN

A. Quality‐Control Plan, General: Submit quality‐control plan within 10 days of Notice of Award, and not less than five days prior to preconstruction conference. Submit in format acceptable to Architect. Identify personnel, procedures, controls, instructions, tests, records, and forms to be used to carry out Contractor's quality‐assurance and quality‐control responsibilities.

Coordinate with Contractor's construction schedule.

B. Submittal Procedure: Describe procedures for ensuring compliance with requirements through review and management of submittal process. Indicate qualifications of personnel responsible for submittal review.

C. Testing and Inspection: In quality‐control plan, include a comprehensive schedule of Work requiring testing or inspection, including the following:

QUALITY REQUIREMENTS 014000 ‐ 3

1. Contractor‐performed tests and inspections including subcontractor‐performed tests and inspections. Include required tests and inspections and Contractor‐elected tests and inspections.

2. Special inspections required by authorities having jurisdiction and indicated on the "Statement of Special Inspections."

D. Continuous Inspection of Workmanship: Describe process for continuous inspection during construction to identify and correct deficiencies in workmanship in addition to testing and inspection specified. Indicate types of corrective actions to be required to bring work into compliance with standards of workmanship established by Contract requirements and approved mockups.

E. Monitoring and Documentation: Maintain testing and inspection reports including log of approved and rejected results. Include work Architect has indicated as nonconforming or defective. Indicate corrective actions taken to bring nonconforming work into compliance with requirements. Comply with requirements of authorities having jurisdiction.

1.7 REPORTS AND DOCUMENTS

A. Test and Inspection Reports: Prepare and submit certified written reports specified in other Sections. Include the following:

1. Date of issue.

2. Project title and number.

3. Name, address, and telephone number of testing agency.

4. Dates and locations of samples and tests or inspections.

5. Names of individuals making tests and inspections.

6. Description of the Work and test and inspection method.

7. Identification of product and Specification Section.

8. Complete test or inspection data.

9. Test and inspection results and an interpretation of test results.

10. Record of temperature and weather conditions at time of sample taking and testing and inspecting.

11. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements.

12. Name and signature of laboratory inspector.

13. Recommendations on retesting and reinspection.

B. Manufacturer's Technical Representative's Field Reports: Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections. Include the following:

1. Name, address, and telephone number of technical representative(s) making report.

2. Statement on condition of substrates and their acceptability for installation of product.

3. Statement that products at Project site comply with requirements.

4. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken.

QUALITY REQUIREMENTS 014000 ‐ 4

5. Results of operational and other tests and a statement of whether observed performance complies with requirements.

6. Statement whether conditions, products, and installation will affect warranty.

7. Other required items indicated in individual Specification Sections.

C. Factory‐Authorized Service Representative's Reports: Prepare written information documenting manufacturer's factory‐authorized service representative's tests and inspections specified in other Sections. Include the following:

1. Name, address, and telephone number of factory‐authorized service representative making report.

2. Statement that equipment complies with requirements.

3. Results of operational and other tests and a statement of whether observed performance complies with requirements.

4. Statement whether conditions, products, and installation will affect warranty.

5. Other required items indicated in individual Specification Sections.

D. Permits, Licenses, and Certificates: For Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.

1.8 QUALITY ASSURANCE

A. General: Qualifications paragraphs in this article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.

B. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in‐service performance, as well as sufficient production capacity to produce required units.

C. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in‐service performance, as well as sufficient production capacity to produce required units.

D. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in‐service performance.

E. Manufacturer's Technical Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to observe and inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.

F. Factory‐Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.

QUALITY REQUIREMENTS 014000 ‐ 5

1.9 QUALITY CONTROL

A. Contractor Responsibilities: Tests and inspections not explicitly assigned to Owner are Contractor's responsibility. Perform additional quality‐control activities required to verify that the Work complies with requirements, whether specified or not.

1. Unless otherwise indicated, provide quality‐control services specified and those required by authorities having jurisdiction. Perform quality‐control services required of Contractor by authorities having jurisdiction, whether specified or not.

2. Where services are indicated as Contractor's responsibility, engage a qualified testing agency to perform these quality‐control services.

a. Contractor shall not employ same entity engaged by Owner, unless agreed to in writing by Owner.

3. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspecting will be performed.

4. Where quality‐control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality‐control service.

5. Testing and inspecting requested by Contractor and not required by the Contract Documents are Contractor's responsibility.

6. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.

B. Manufacturer's Field Services: Where indicated, engage a factory‐authorized service representative to inspect field‐assembled components and equipment installation, including service connections. Report results in writing as specified in Section 013300 "Submittal Procedures."

C. Manufacturer's Technical Services: Where indicated, engage a manufacturer's technical representative to observe and inspect the Work. Manufacturer's technical representative's services include participation in preinstallation conferences, examination of substrates and conditions, verification of materials, observation of Installer activities, inspection of completed portions of the Work, and submittal of written reports.

D. Retesting/Reinspection: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality‐control services, including retesting and reinspection, for construction that replaced Work that failed to comply with the Contract Documents.

E. Coordination: Coordinate sequence of activities to accommodate required quality‐assurance and control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.

1. Schedule times for tests, inspections, obtaining samples, and similar activities.

F. Schedule of Tests and Inspections: Prepare a schedule of tests, inspections, and similar quality‐ control services required by the Contract Documents as a component of Contractor's quality‐ control plan. Coordinate and submit concurrently with Contractor's construction schedule.

Update as the Work progresses.

QUALITY REQUIREMENTS 014000 ‐ 6

1. Distribution: Distribute schedule to Owner, Architect, and each party involved in performance of portions of the Work where tests and inspections are required.

1.10 TEST AND INSPECTION LOG

A. Test and Inspection Log: Prepare a record of tests and inspections. Include the following:

1. Date test or inspection was conducted.

2. Description of the Work tested or inspected.

3. Date test or inspection results were transmitted to Architect.

4. Identification of testing agency or special inspector conducting test or inspection.

B. Maintain log at Project site. Post changes and revisions as they occur. Provide access to test and inspection log for Architect's and Contractor's reference during normal working hours.

1.11 REPAIR AND PROTECTION

A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.

1. Provide materials and comply with installation requirements specified in other Specification Sections or matching existing substrates and finishes. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible. Comply with the Contract Document requirements for cutting and patching in Section 017300 "Execution."

B. Protect construction exposed by or for quality‐control service activities.

C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality‐control services.

END OF SECTION 014000

EXECUTION 017300 ‐ 1

SECTION 017300 ‐ EXECUTION

PART 1 ‐ GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes general administrative and procedural requirements governing execution of the Work including, but not limited to, the following:

1. Construction layout.

2. Installation of the Work.

3. Cutting and patching.

4. Progress cleaning.

5. Starting and adjusting.

6. Protection of installed construction.

B. Related Requirements:

1. Section 011000 "Summary" for limits on use of Project site.

2. Section 017700 "Closeout Procedures" for submitting final property survey with Project

Record Documents, recording of Owner‐accepted deviations from indicated lines and levels, and final cleaning.

3. Section 024119 "Selective Demolition" for demolition and removal of selected portions of the building.

1.3 DEFINITIONS

A. Cutting: Removal of in‐place construction necessary to permit installation or performance of other work.

B. Patching: Fitting and repair work required to restore construction to original conditions after installation of other work.

1.4 INFORMATIONAL SUBMITTALS

A. Cutting and Patching Plan (IF REQUIRED): Submit plan describing procedures at least 10 days prior to the time cutting and patching will be performed. Include the following information:

1. Extent: Describe reason for and extent of each occurrence of cutting and patching.

EXECUTION 017300 ‐ 2

2. Changes to In‐Place Construction: Describe anticipated results. Include changes to structural elements and operating components as well as changes in building appearance and other significant visual elements.

3. Products: List products to be used for patching and firms or entities that will perform patching work.

4. Dates: Indicate when cutting and patching will be performed.

5. Utilities and Mechanical and Electrical Systems: List services and systems that cutting and patching procedures will disturb or affect. List services and systems that will be relocated and those that will be temporarily out of service. Indicate length of time permanent services and systems will be disrupted.

a. Include description of provisions for temporary services and systems during interruption of permanent services and systems.

B. Landfill Receipts: Submit copy of receipts issued by a landfill facility, licensed to accept hazardous materials, for hazardous waste disposal.

1.5 QUALITY ASSURANCE

A. Cutting and Patching (IF REQUIRED): Comply with requirements for and limitations on cutting and patching of construction elements.

1. Structural Elements: When cutting and patching structural elements Not provided in the drawings notify Architect of locations and details of cutting and await directions from Architect before proceeding. Shore, brace, and support structural elements during cutting and patching. Do not cut and patch structural elements in a manner that could change their load‐carrying capacity or increase deflection.

2. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as intended or that results in increased maintenance or decreased operational life or safety (this should not occur during this project). Operational elements include the following:

a. Primary operational systems and equipment.

b. Fire separation assemblies.

c. Air or smoke barriers.

d. Fire‐suppression systems.

e. Mechanical systems piping and ducts.

f. Control systems.

g. Communication systems.

h. Fire‐detection and ‐alarm systems.

i. Electrical wiring systems.

j. Operating systems of special construction.

3. Other Construction Elements: Do not cut and patch other construction elements or components in a manner that could change their load‐carrying capacity, that results in reducing their capacity to perform as intended, or that results in increased maintenance

EXECUTION 017300 ‐ 3

or decreased operational life or safety. Other construction elements include but are not limited to the following:

a. Water, moisture, or vapor barriers.

b. Membranes and flashings.

c. Exterior curtain‐wall construction.

d. Sprayed fire‐resistive material.

e. Equipment supports.

f. Piping, ductwork, vessels, and equipment.

g. Noise‐ and vibration‐control elements and systems.

4. Visual Elements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch exposed construction in a manner that would, in Architect's opinion, reduce the building's aesthetic qualities.

Remove and replace construction that has been cut and patched in a visually unsatisfactory manner.

B. Manufacturer's Installation Instructions: Obtain and maintain on‐site manufacturer's written recommendations and instructions for installation of products and equipment.

PART 2 ‐ PRODUCTS

2.1 MATERIALS

A. In‐Place Materials: Use materials for patching identical to in‐place materials. For exposed surfaces, use materials that visually match in‐place adjacent surfaces to the fullest extent possible.

1. If identical materials are unavailable or cannot be used, use materials that, when installed, will provide a match acceptable to Architect for the visual and functional performance of in‐place materials.

PART 3 ‐ EXECUTION

3.1 EXAMINATION

A. Examination and Acceptance of Conditions: Before proceeding with each component of the Work, examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations.

1. Examine walls, floors, and roofs for suitable conditions where products and systems are to be installed.

2. Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers.

EXECUTION 017300 ‐ 4

B. Written Report: Where a written report listing conditions detrimental to performance of the Work is required by other Sections, include the following:

1. Description of the Work.

2. List of detrimental conditions, including substrates.

3. List of unacceptable installation tolerances.

4. Recommended corrections.

C. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.

3.2 PREPARATION

A. Field Measurements: Take field measurements as required to fit the Work properly. Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work.

B. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.

3.3 CONSTRUCTION LAYOUT

A. Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify Architect and Contractor promptly.

B. Record Log: Maintain a log of layout control work. Record deviations from required lines and levels. Include beginning and ending dates and times of surveys, weather conditions, name and duty of each survey party member, and types of instruments and tapes used. Make the log available for reference by Architect and Contractor.

3.4 INSTALLATION

A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

1. Make vertical work plumb and make horizontal work level.

2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.

3. Conceal pipes, ducts, and wiring in finished areas unless otherwise indicated.

B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.

EXECUTION 017300 ‐ 5

C. Install products at…

This is the start of the file's text. The full file is on GovTribe.