This is a project manual and bidding document for Wayne Community College's Master Meter and Booster Pump Addition project (Project No. 70141), prepared by engineer Timmons Group and issued in October 2025. The project includes installation of a master meter, master backflow preventer, packaged domestic and fire booster pump system with shelter, approximately 250 linear feet of water main extension off Wayne Community College Entrance Drive, nine 10-inch isolation valves, a bypass check valve and vault, booster system power connections, site and pavement repairs, erosion and sediment control measures, and traffic control. A pre-bid conference is scheduled for November 19, 2025, at 10:00 AM on campus, with bids due December 8, 2025, at 1:30 PM. The project duration is 180 days for substantial completion. Contractors must submit qualifications statements, bid bonds (5 percent of bid amount), performance bonds, and payment bonds. The contract documents establish comprehensive requirements for work execution including MBE/WBE compliance with EPA goals of 10.9 percent MBE and 10.4 percent WBE utilization and state goals of 10 percent combined utilization.

Liquidated damages are set at $250 per day for delays beyond the substantial completion deadline of 150 days and the final completion deadline of 180 days. Contract payment will be made monthly based on progress, with 95 percent of completed work value paid during construction and remaining balance at substantial completion, less retainage for punch list items valued at 200 percent of estimated completion costs. The contract requires contractors to obtain all necessary permits at their expense, comply with North Carolina Department of Transportation requirements for work in their rights-of-way, provide erosion and sediment control measures, and coordinate with existing utility owners. Funding source and project cost are not specified in the bidding documents. All work must conform to AWWA standards for water utilities, ASME standards for pressure vessels, NEC standards for electrical work, and current North Carolina regulations. The packaged pumping system must be manufactured by SyncroFlo, Inc., model 5P1800CCES28/50PM, or an approved alternate meeting specified ISO9001-2015 certification and performance criteria, with factory flow testing required before shipment.

View the file

Other files

File Type Posted
WCC Booster Pump and Master Meter Plans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Manual

November 6, 2025

Engineer:

Timmons Group

5410 Trinity Rd., Suite 102

Raleigh, NC 27607

MASTER METER AND BOOSTER

PUMP ADDITION

WAYNE COMMUNITY COLLEGE

Project Number 70141

11/07/2025

Issued: 10/2025

SECTION 00 00 00 – TABLE OF CONTENTS

Master Meter and Booster Pump Addition

TABLE OF CONTENTS 00 00 00 - 1

MBE/WBE REQUIRED DOCUMENTS

MBE/WBE Instructions

MBE/WBE Good Faith Effort Form

MBE/WBE Table A (Summary of Firms on Job)

MBE/WBE Table B MBE/WBE Change/Add Subcontractor Form

DIVISION 00 – PROCURMENT & CONTRACTING REQUIREMENTS

00 03 00 Bid Proposal

C-111 Advertisement for Bids C-200 Instructions to Bidders

C-435 Bid Bond

C-451 Qualifications Statement

C-520 Agreement C-550 Notice to Proceed

C-610 Performance Bond

C-615 Payment Bond C-625 Certificate of Substantial Completion

C-626 Notice of Acceptability of Work (Final Completion)

C-700 Standard Conditions C-800 Supplementary Conditions

C-940 Work Change Directive Form

C-941 Change Order Form

C-942 Field Order

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work

01 20 00 Measurement and Payment

01 25 00 Substitutions

01 31 00 Coordination 01 31 19 Project Meetings

01 33 00 Submittals

01 50 00 Temporary Facilities and Controls 01 70 00 Closeout Procedures

DIVISION 02 – SITE CONDITIONS

02 01 00 Site Conditions

DIVISION 03 – CONCRETE

03 30 00 Cast-In-Place Concrete

DIVISION 31 – EARTHWORK

31 23 33 Trenching and Backfilling 31 25 00 Erosion Control

Issued: 10/2025

SECTION 00 00 00 – TABLE OF CONTENTS

Master Meter and Booster Pump Addition

TABLE OF CONTENTS 00 00 00 - 2

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 12 16 Asphalt Paving

DIVISION 33 – UTILITIES

33 10 00 Water Utilities 33 14 43 Packaged Pumping Systems for Water Utility Service

END OF TABLE OF CONTENTS

Instructions Page 1 of 2

NC Division of Water Infrastructure MBE/WBE (DBE) Compliance Supplement

Instructions (This package combines the various aspects of State of NC HUB program requirements and Federal DBE requirements into a single compliance supplement in order to eliminate redundancy and ambiguity)

Item What to do with it Good Faith Efforts Form Provided by all bidders to be responsive Only low bidder’s form is submitted to the State

Table A (Summary of firms on job) Provided by all bidders to be responsive Only low bidder’s form is submitted to the State

Table B (per item being subbed) Provided by low bidder if SRF project or SRP/SEL* that obtains less than 10% M/WBE utilization (see page 2)

Provide documentation of anything you did - Proof of trade paper advertisement that is mentioned later in this supplement - Printouts of DBE sources used

- Solicitation emails and/or letters Additional Forms for SRF Projects (these forms are currently not applicable)

6100-3 (per M/WBE firm) Provided by low bidder if SRF project 6100-2 Distributed to M/WBE firms if SRF project Subs submit concerns on 6100-2 forms to: Michael Pigram

Region 4, Atlanta Federal Center 61 Forsyth Street Atlanta, GA 30303-8960

NOTES on this Compliance Supplement

Verifiable Goals

EPA MBE/WBE participation goals: MBE 10.9%

WBE 10.4%

These are goals that the State reports against and are not quotas. The good faith efforts must be adhered to and all forms provided regardless of what percentage utilization is achieved.

State of NC MBE/WBE participation goal: 10% (combined)

Table B is not required for SRP and SEL projects if you achieve 10% utilization.

DBE (MBE or WBE) Certification

In order for a firm to count towards the goals, a firm must be properly certified. Table A and Table B both provide spaces to note who certified the firm. The North Carolina Department of Administration and North Carolina Department of Transportation are the most common certifications we see listed. Division of Water Infrastructure staff verify all certifications listed.

Instructions Page 2 of 2

For SRF projects, please note the EPA’s six Good Faith Efforts found in 40 CFR 33 Filling out the Good Faith Efforts Form and providing Table B (if subcontracting is achieved) constitutes compliance with EPA’s six good faith efforts.

(1) Ensure MBE/WBEs are made aware of contracting opportunities to the fullest extent practicable through outreach and recruitment activities. For Indian Tribal, State and local Government recipients, this will include placing MBE/WBEs on solicitation lists and soliciting them whenever they are potential sources.

(2) Make information of forthcoming opportunities available to MBE/WBEs and arrange time for contracts and establish delivery schedules, where requirements permit, in a way that encourages and facilitates participation by DBEs in the competitive process. This includes, whenever possible, posting solicitations for bids or proposals for a minimum of 30 calendar days before the bid or proposal closing date.

(3) Consider in the contracting process whether firms competing for large contracts could subcontract with MBE/WBEs. For Indian Tribal, State and local Government recipients, this will include dividing total requirements when economically feasible into smaller tasks or quantities in order to increase opportunities for participation by MBE/WBEs in the competitive process.

(4) Encourage contracting with a consortium of MBE/WBEs when a contract is too large for one of these firms to handle individually.

(5) Use the services and assistance of the SBA and the MBDA.

(6) If the prime contractor awards subcontracts, require the prime contractor to take the steps in subparagraphs (1)-(5) of this section.

Pertinent State of North Carolina Administrative Code Regarding M/WBE Compliance. The provisions in this Compliance Supplement constitute compliance with the Rules below.

Owner Requirements 01 NCAC 30I .0306 Contractor Requirements 01 NCAC 30I .0308

Resources Some sources for identifying MBE/WBE (DBE) firms https://www.ips.state.nc.us/vendor/SearchVendor.aspx (NCDOA) https://www.ebs.nc.gov/VendorDirectory/default.html (NCDOT) http://dsbs.sba.gov/dsbs/search/dsp_dsbs.cfm (US SBA)

Some sources for finding minority trade papers for potential solicitation advertisements and Federal advertising options http://web.sba.gov/subnet/ (US SBA Subnet advertising website) https://www.mbda.gov/ (US Dept. of Commerce) https://ncadmin.nc.gov/businesses/hub (NC HUB Office) https://www.ips.state.nc.us/vendor/SearchVendor.aspx https://www.ebs.nc.gov/VendorDirectory/default.html http://dsbs.sba.gov/dsbs/search/dsp_dsbs.cfm http://web.sba.gov/subnet/ https://www.mbda.gov/ https://ncadmin.nc.gov/businesses/hub

Good Faith Efforts Form, Page 1 of 2

Good Faith Efforts Form Attempts to provide subcontracting opportunities for MBE/WBE firms.

Per 01 NCAC 30I .0101, 50 points must be claimed below by the bidder.

(This is identical to State of NC Affidavit A)

☐ 1 – (10 pts) Contacted minority businesses that reasonably could have been expected to submit a quote and that were known to the contractor, or available on State or local government maintained lists, at least 10 days before the bid date and notified them of the nature and scope of the work to be performed.

☐ 2 --(10 pts) Made the construction plans, specifications and requirements available for review by prospective minority businesses, or providing these documents to them at least 10 days before the bids are due.

☐ 3 – (15 pts) Broken down or combined elements of work into economically feasible units to facilitate minority participation.

☐ 4 – (10 pts) Worked with minority trade, community, or contractor organizations identified by the Office of

Historically Underutilized Businesses and included in the bid documents that provide assistance in recruitment of minority businesses.

☐ 5 – (10 pts) Attended prebid meetings scheduled by the public owner.

☐ 6 – (20 pts) Provided assistance in getting required bonding or insurance or provided alternatives to bonding or insurance for subcontractors.

☐ 7 – (15 pts) Negotiated in good faith with interested minority businesses and did not reject them as unqualified without sound reasons based on their capabilities. Any rejection of a minority business based on lack of qualification should have the reasons documented in writing.

☐ 8 – (25 pts) Provided assistance to an otherwise qualified minority business in need of equipment, loan capital, lines of credit, or joint pay agreements to secure loans, supplies, or letters of credit, including waiving credit that is ordinarily required. Assisted minority businesses in obtaining the same unit pricing with the bidder's suppliers in order to help minority businesses in establishing credit.

☐ 9 – (20 pts) Negotiated joint venture and partnership arrangements with minority businesses in order to increase opportunities for minority business participation on a public construction or repair project when possible.

☐ 10 - (20 pts) Provided quick pay agreements and policies to enable minority contractors and suppliers to meet cash-flow demands.

Good Faith Efforts Form, Page 2 of 2

Results of Good Faith Efforts Undertaken (you must check one box below)

☐ No subcontractors are being used for this contracted work. Fill out Table A listing only the Prime Contractor. (This statement takes the place of State of NC Affidavit B)

☐ Subcontractors are being used. Fill out Table A and B for each trade. Each Table B lists 3.

☐ Subcontractors are being used. If any Table B has fewer than 3 solicitations you must also advertise in an M/WBE trade paper and indicate what source of M/WBE firms you used (must list at least one). Some possible papers and sources of M/WBE firms are listed in the Instructions of this Supplement.

Name of the Trade Paper: __________________________________________________

Submit proof of advertisement with package

M/WBE Sources: Source:__________________ Source:_____________________

Submit printouts from M/WBE source(s)

Certification Statement and Affidavit of Contractor.

The below affidavit constitutes compliance with 01NCAC 30I .0308(7)(a) and (b) and takes the place of State of North Carolina Affidavits C and D.

I have read the information in this compliance supplement and all information provided to the State in this package is accurate and true to the extent of my knowledge including the calculated percentages and the good faith efforts presented herein.

Prime Contractor Company Name (Print) Prime Contractor Representative (Sign & Date)

State of_________________________, County of ________________________

Subscribed and sworn to before me this ______day of ______________ 20____

Notary Public _____________________________________________________

My Commission Expires_____________________________________________

Certification of Project Owner/Funding Applicant

Funding Applicant (City, Town etc) Applicant Authorized Representative (Sign & Date)

Division of Water Infrastructure Project Number

SEAL

N o te : T ab le

A s u b st it u te s fo r b o th t h e St at e o f

N C

Id en ti fi ca ti o n o f M in o ri ty

P ar ti ci p at io n fo rm a n d

E P

A F o rm

-4

Ta b le A

P ri m e C o n tr ac to r a n d li st o f se le ct e d s u b co n tr ac to rs

Li st

P ri m e an d

A

LL

o f th e se le ct ed s u b co n tr ac to rs b o th D

B E’ s an d n o n

-D B

E’ s) b ei n g u se d o n t h e p ro je ct

. E ac h T ra d e lis te d n th is s h ee t sh o u ld h av e a co m p le te d

T ab le B

Su b co n tr ac t

So lic it at io n

L is t sh o w in g th e

D B

E fi rm s co n ta ct ed a n d g iv en p p o rt u n it ie s to b id

C m p an y

N am e lis t p ri m e fi rs t th en s u s) m p an y

A d d re ss a d

P h o e

Tr ad e

A b o ve an ri ce

B el o w

M

B E o r

W B

E an d c e rt if yi n g ag en cy if ap lic ab le

(S ta te u se ly

Li st ed in

EP

LS

a s D eb ar re al cu la te M

/W B

E u ti liz at io n a s a p er ce n t (0

.0 o f th e p ri m e co n tr ac t.

L im it ed t o e ve n if t h e P ri m e is a D

B E.

M

E an d W

B E su b s to ta l m e C o n tr ac t P ce

Ta le B

Su b co n tr ac t

So lic it at io n

L is t Ta b le

B is r eq u ir ed if

P ro je ct is

F ed er al ly f u n d ed

SR

F) O

R

P ro je ct is a

S ta te R es er ve P ro je ct o r St at e

Em e rg en cy L o an

SR

P o r

SE

L) a n d

U ti liz at io n o n T ab le

A is le ss t h an

Tr ad e e n te r th e tr ad e b e in g so lic it e d , p av in g, h au lin g e tc

Li st t h e f ir m b e in g u se d o n t h e p ro je ct f ir st

. I f th re e M

B E o r

W B

E fi rm s ar e n o t lis te d

, a d d it io n al in fo rm at io m st b e p ro vi d ed s h o w in g ad ve rt is e m e n ts a n d

/o r so u rc es u se d t o id e n ti fy

M B

E/ W

B E su s.

U se a s m an y o f th es e s h e et s as a re n e ce ss ar y to c o ve r e ve ry t ra d e b e in g su b b e d o t.

m p an y N am m p an y A d d re ss a o

M

E o r W

B E an ce rt if yi n g ag en cy if ap lic ab le

H o w w as t h is f ir m c o n ta ct ed

(e m ai l, le tt er , p h o n e) a n d w at w as t h e re su lt o f th e so lic it at io

*M st s u b m it c o p ie s o f em ai ls o r le tt e rs

. I f p h o n e ca lls w er e m ad e th is s h ee t ca n s er ve a s d o cu m en ta ti o n o f ca lls

MBE/WBE (DBE) – Change or Add a Subcontractor Form

According to EPA guidance on 40 CFR 33.302

If a DBE subcontractor fails to complete work under the subcontract for any reason, the recipient must require the prime contractor to employ the six good faith efforts described in §33.301 if soliciting a replacement subcontractor.

Please provide the information below if the subcontracted work in question was included in previously submitted good faith efforts documentation:

Prime Contractor:

Subcontracted work:

Previous Subcontractor:

Reason this firm did not complete the work:

New subcontractor and DBE status: MBE WBE N/A

If this is a new trade being subcontracted, or was not documented in the original Project Bid Information submittal to the State then good faith efforts to solicit a DBE firm must be documented. As the original DBE instructions indicate, please provide a Table B from those original instructions, showing all the DBE firms contacted to perform this work. If three (3) firms are not listed on Table B, then additionally you must submit proof of an advertisement in a minority trade paper and evidence that there were not three reasonably available firms in the work area. The EPA provides in 33.301(a) that good faith efforts are to be carried out “…to the fullest extent practicable…”. If solicitations were not carried out due to being impracticable, please attach this explanation to this form.

Please follow the steps below for new subcontracted work:

Indicate the new trade being subcontracted:

Indicate the firm being used and DBE status: MBE WBE N/A

Attach Table B

(For State Use) Is this sub debarred? Yes No

Project Owner/Applicant: Project Number:

Signature of Prime Contractor’s Representative

EJCDC® C-111, Advertisement for Bids for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (6/16/2020).

ADVERTISEMENT FOR BIDS

Wayne Community College

WAYNE COUNTY, NORTH CAROLINA

Master Meter and Booster Pump Addition

General Notice

Wayne Community College (Owner) is requesting Bids for the construction of the following Project:

Master Meter and Booster Pump Addition 70141

Bids for the construction of the Project will be received at Wayne Community College, Dogwood Building – Cashiers Office, 3000 Wayne Memorial Drive Goldsboro, NC 27534 until 1:30 PM (local time) on December 8, 2025. Please note that any bids hand delivered between 1:30 PM – 2 PM on the bid opening date (12/08/25) should be delivered to the Walnut Building, room #104. At 2 PM (local time), the Bids received will be publicly opened and read.

The Project includes the following Work:

This project includes the addition of a master meter, master back flow preventer, and packaged domestic and fire booster pump system and shelter. This addition also includes an extension of approximately 250 LF of water main off of Wayne Community College Entrance Drive, an addition of nine, 10-inch isolation valves, installation of a bypass check valve and vault, connection of the packaged booster system to existing power, site/pavement repairs, implementation of required erosion and sediment control measures, installation and maintenance of traffic control, and the connection to existing private water main.

Bids are requested for the following Contract: Master Meter and Booster Pump Addition/70141

The Project has an expected duration of 180 days.

Obtaining the Bidding Documents

The Issuing Office for the Bidding Documents is:

Timmons Group 5410 Trinity Road, Suite 102 Raleigh, NC 27607

Prospective Bidders may obtain or examine the Bidding Documents at the Issuing Office on Monday through Friday between the hours of 9:00 AM and 5:00 PM and may obtain copies of the Bidding Documents from the Issuing Office as described below. Partial sets of Bidding Documents will not be available from the Issuing Office. Neither Owner nor Engineer will be responsible for full or partial sets of Bidding Documents, including addenda, if any, obtained from sources other than the Issuing Office.

EJCDC® C-111, Advertisement for Bids for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (6/16/2020).

Bidding Documents may be purchased from the Issuing Office during the hours indicated above. Cost does not include shipping charges. Upon Issuing Office’s receipt of payment, printed Bidding Documents or electronic documents on compact disk will be sent via the prospective Bidder’s delivery service. The shipping charge amount will depend on the shipping method chosen. Bidding Documents are available for purchase in the following formats:

Format Cost

Bidding Documents (including Full-Size Drawings) – CASH OR CHECK ONLY $30

Bidding Documents (including Half-Size Drawings) – CASH OR CHECK ONLY $20

Thumb Drive containing Bidding Documents in portable document format (PDF) $0 Instructions to download Bidding Documents in portable document format (PDF) $0

Pre-bid Conference

A pre-bid conference for the Project will be held on November 19, 2025 at 10 AM at Wayne Community College, 3000 Wayne Memorial Drive Goldsboro, NC 27534 in the Walnut Building, Room #104.

Attendance at the pre-bid conference is highly encouraged but not required.

Instructions to Bidders.

For all further requirements regarding bid submittal, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents.

This Advertisement is issued by:

Owner: Wayne Community College By: Derek Hunter Title: Vice President, Operations Date: 11/10/2025

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (6/16/2020).

TOC Page1 of 1

INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT

TABLE OF CONTENTS

Page

Article 1— Defined Terms

Article 2— Bidding Documents

Article 3— Qualifications of Bidders

Article 4— Pre-Bid Conference

Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site

Article 6— Bidder’s Representations and Certifications

Article 7— Interpretations and Addenda

Article 8— Bid Security

Article 9— Contract Times

Article 10— Substitute and “Or Equal” Items

Article 11— Subcontractors, Suppliers, and Others

Article 12— Preparation of Bid

Article 13— Basis of Bid

Article 14— Submittal of Bid

Article 15— Modification and Withdrawal of Bid

Article 16— Opening of Bids

Article 17— Bids to Remain Subject to Acceptance

Article 18— Evaluation of Bids and Award of Contract

Article 19— Bonds and Insurance

Article 20— Signing of Agreement

Article 21— Sales and Use Taxes................................................................. Error! Bookmark not defined.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (6/16/2020).

ARTICLE 1—DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office—The office from which the Bidding Documents are to be issued, and which registers plan holders.

ARTICLE 2—BIDDING DOCUMENTS

2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.

2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.

2.03 Bidder may register as a plan holder and obtain complete sets of Bidding Documents, in the number and format stated in the Advertisement or invitation to bid, from the Issuing Office.

Bidders may rely that sets of Bidding Documents obtained from the Issuing Office are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by Owner.

2.04 Plan rooms (including construction information subscription services, and electronic and virtual plan rooms) may distribute the Bidding Documents or make them available for examination.

Those prospective bidders that obtain an electronic (digital) copy of the Bidding Documents from a plan room are encouraged to register as plan holders from the Bidding Documents Website or Issuing Office. Owner is not responsible for omissions in Bidding Documents or other documents obtained from plan rooms, or for a Bidder’s failure to obtain Addenda from a plan room.

2.05 Electronic Documents

A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.

1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by Adobe Acrobat Reader Version compatible with Bluebeam Revu Version 20.0.20 or later. It is the intent of the Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents.

However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner and Engineer cannot and do not guarantee that Electronic

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (6/16/2020).

Documents and reproductions prepared from those versions are identical in every manner to the paper copies.

B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in Paragraph 2.06.A above. However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.

ARTICLE 3—QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder’s qualifications to perform the Work, after submitting its Bid and within 29 days of Owner’s request, Bidder must submit the following information:

A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.

B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the Effective Date of the Contract.

C. Subcontractor and Supplier qualification information.

D. Other required information regarding qualifications.

3.02 Bidder is to submit the following information with its Bid to demonstrate Bidder’s qualifications to perform the Work:

A. Bidder’s state or other contractor license number, if applicable.

3.03 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.04 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

ARTICLE 4—PRE-BID CONFERENCE

4.01 A non-mandatory pre-bid conference will be held at the time and location indicated in the Advertisement or invitation to bid. Representatives of Owner and Engineer will be present to discuss the Project. Bidders are encouraged to attend and participate in the conference;

however, attendance at this conference is not required to submit a Bid.

4.02 Information presented at the pre-Bid conference does not alter the Contract Documents. Owner will issue Addenda to make any changes to the Contract Documents that result from discussions

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (6/16/2020).

at the pre-Bid conference. Information presented, and statements made at the pre-bid conference will not be binding or legally effective unless incorporated in an Addendum.

ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S

SAFETY PROGRAM; OTHER WORK AT THE SITE

5.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

5.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:

a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.

b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.

c. Reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (6/16/2020).

5.03 Other Site-related Documents

A. In addition to the documents regarding existing Site conditions referred to in Paragraph 5.02.A, the following other documents relating to conditions at or adjacent to the Site are known to Owner and made available to Bidders for reference:

N/A - None

B. Owner has not verified the contents of these other Site-related documents, and Bidder may not rely on the accuracy of any data or information in such documents. Bidder is responsible for any interpretation or conclusion Bidder draws from the other Site-related documents.

C. The other Site-related documents are not part of the Contract Documents.

D. Bidders are encouraged to review the other Site-related documents, but Bidders will not be held accountable for any data or information in such documents. The requirement to review and take responsibility for documentary Site information is limited to information in (1) the Contract Documents and (2) the Technical Data.

E. No other Site-related documents are available.

5.04 Site Visit and Testing by Bidders

A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the Site.

B. A Site visit is scheduled following the pre-bid conference. Maps to the Site will be available at the pre-Bid conference.

C. A Site visit is scheduled for November 19, 2025 at 10:00 AM at Wayne Community College 3000 Wayne Memorial Drive Goldsboro, NC 27534. Maps to the Site will be made available upon request.

D. Bidders visiting the Site are required to arrange their own transportation to the Site.

E. All access to the Site other than during a regularly scheduled Site visit must be coordinated through the following Owner or Engineer contact for visiting the Site: Derek Hunter, mdhunter@waynecc.edu, 919-739-7020. Bidder must conduct the required Site visit during normal working hours.

F. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.

G. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.

H. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to mailto:mdhunter@waynecc.edu

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (6/16/2020).

schedule, access, existing operations, security, liability insurance, and applicable safety programs.

I. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

5.05 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions.

5.06 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Express Representations and Certifications in Bid Form, Agreement

A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.

B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.

ARTICLE 7—INTERPRETATIONS AND ADDENDA

7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.

7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents to the Engineer in writing by 5pm on December 1, 2025. Contact information and submittal procedures for such questions are as follows:

A. Chris Petree, PE, chris.petree@timmons.com

7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven days prior to the date for opening of Bids may not be answered.

7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (6/16/2020).

Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.

ARTICLE 8—BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of five (5) percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid bond will be issued in the form included in the Bidding Documents.

Bid security must be at least 5% of the Bidder’s maximum Bid price.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.

ARTICLE 9—CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.

9.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.

ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS

10.01 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (6/16/2020).

supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS

11.01 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for the following portions of the Work within five days after Bid opening:

A. N/A

11.02 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder will submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.

11.03 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers.

Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.07 of the General Conditions.

11.05 – The Contractor shall not award work to Subcontractor(s) in excess of the limits stated in SC 7.07A.

ARTICLE 12—PREPARATION OF BID

12.01 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form must be completed in ink and the Bid Form signed in ink. Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”

12.02 If Bidder has obtained the Bidding Documents as Electronic Documents, then Bidder shall prepare its Bid on a paper copy of the Bid Form printed from the Electronic Documents version of the Bidding Documents. The printed copy of the Bid Form must be clearly legible, printed on 8½ inch by 11-inch paper and as closely identical in appearance to the Electronic Document version of the Bid Form as may be practical. The Owner reserves the right to accept Bid Forms which nominally vary in appearance from the original paper version of the Bid Form, providing that all required information and submittals are included with the Bid.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (6/16/2020).

12.03 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown. The corporate seal must be affixed and attested by the corporate secretary or an assistant corporate secretary.

12.04 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.

12.05 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.

12.06 A Bid by an individual must show the Bidder’s name and official address.

12.07 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.

12.08 All names must be printed in ink below the signatures.

12.09 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.

12.10 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.

12.11 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.

12.12 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the Project is located, the Bid must contain evidence of Bidder’s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder’s state contractor license number, if any, must also be shown on the Bid Form.

ARTICLE 13—BASIS OF BID

13.01 Unit Price

A. Bidders must submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.

B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity”, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (6/16/2020).

13.02 Allowances

A. For cash allowances the Bid price must include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.

ARTICLE 14—SUBMITTAL OF BID

14.01 The Bidding Documents include one separate unbound copy of the Bid Form, and, if required, the Bid Bond Form. The unbound copy of the Bid Form is to be completed and submitted with the Bid security and the other documents required to be submitted under the terms of Article 2 of the Bid Form.

14.02 A Bid must be received no later than the date and time prescribed and at the place indicated in the Advertisement or invitation to bid and must be enclosed in a plainly marked package with the Project title, and, if applicable, the designated portion of the Project for which the Bid is submitted, the name and address of Bidder, and must be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid must be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.” A mailed Bid must be addressed to the location designated in the Advertisement.

14.03 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.

ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID

15.01 An unopened Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.

15.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 15.01 and submit a new Bid prior to the date and time for the opening of Bids.

15.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, the Bidder may withdraw its Bid, Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Modified to include RD edits from RUS Bulletin 1780-26 (6/16/2020).

and the Bid security will be returned. Thereafter, if the Work is rebid, the Bidder will be disqualified from further bidding on the Work.

ARTICLE 16—OPENING OF BIDS

16.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE

17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT

18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work.

18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.

18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then Owner will reject the Bid as nonresponsive.

18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.

18.05 Evaluation of Bids

A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

B. In the comparison of Bids, alternates will be applied in the same order of priority as listed in the Bid Form. To determine the Bid prices for purposes of comparison, Owner will announce to all bidders a “Base Bid plus alternates” budget after receiving all Bids, but prior to opening them. For comparison purposes alternates will be accepted, following the order of priority established in the Bid Form, until doing so would cause the budget to be exceeded.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .