This document is a Statement of Work for the Waterways Commerce Cutter (WCC) Cutter Boats - Aids to Navigation - Small (CB-ATON-S) Program. The Coast Guard intends to procure up to 66 cutter boats, including trailers, delivery, spares, and training. The contract will be a Firm Fixed Price (FFP), Indefinite Delivery Indefinite Quantity (IDIQ) with a 5-year base ordering period and a 2-year option period. The contractor will be responsible for the production and outfitting of the boats, as well as providing maintenance parts, technical manuals, acceptance testing, and delivery. The contractor will also design and produce prototype boats, which will undergo First Article Testing and Special Testing. The CB-ATON-S boats will be used for aids to navigation operations, search and rescue, and personnel transfers in inland waterways and western rivers. The Request for Proposal (RFP) is expected to be released in early December 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| WCC CB-ATON-S Technical Specification V2.0_DRAFT.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Waterways Commerce Cutter (WCC) Cutter Boats – Aids to Navigation – Small
(CB-ATON-S)
Statement of Work
Version 2.0
Prepared by:
Commandant (CG-9327)
United States Coast Guard MSN 7800 2703 Martin Luther King Junior Ave SE
Washington, DC 20593-7800
Distribution Statement A: Approved for public release; distribution is unlimited. DRAFT
Waterways Commerce Cutter (WCC) Statement of Work Cutter Boats ATON Small (CB-ATON-S) v2.0
This page intentionally left blank.
DRAFT
1 Table of Contents
2 Background
3 Scope
4 Period of Performance
5 Ordering Procedures
6 Intellectual Property Rights
7 Inspection / Acceptance
8 Contract Type
9 Electronic Submission of Payment Requests
2 Background
2.1 The Coast Guard established the Waterways Commerce Cutter (WCC) Program to replace the capability provided by the Inland Tender Fleet. The fleet provides the Coast Guard with the capability necessary to execute and support statutory and federally mandated missions in Inland Waterways and Western Rivers (IW&WR) of the United States which fall into three main categories: (1) construction and maintenance of fixed aids; (2) positioning and maintenance of floating Federal Aids to Navigation; and (3) repositioning, replacement, or removal of river buoys based on changes in water level and river conditions.
2.2 The River Buoy Tender (WLR), Inland Construction Tender (WLIC), and Inland Buoy Tender (WLI) cutter variants will require cutter boats to enhance the cutters’ ability to conduct aids to navigation (ATON) operations, search and rescue (SAR)/self-rescue operations, and personnel transfers. The boats will be deployed from the cutters to provide for autonomous operations and mission execution in areas where it is either physically impossible or dangerous for the cutter to navigate.
3 Scope
The Coast Guard intends to procure cutter boats, including trailers, delivery, spares and training.
3.0 Program Management
3.0.1 The Contractor shall be responsible for submitting the deliverables identified within the Spec “List of Deliverables.” For those deliverables that require Government acceptance, the Government will provide a written response within 30 calendars days of receipt, unless otherwise noted.
3.0.2 The Contractor shall construct the cutter boats according to the requirements of the Cutter Boat – Aids to Navigation – Small (CB-ATON-S) Technical Specification & Statement of Work that are otherwise not explicitly listed in other CLIN/SLINs on this contract.
3.0.3 The Contractor shall be responsible for the production of the cutter boats and integration of associated equipment and parts.
3.0.4 The Contractor shall be responsible for overall project management, subcontractor management, technical direction, coordination, and administrative work to ensure that contractual requirements are properly accomplished.
3.0.5 The Contractor shall produce and maintain an up-to-date Integrated Master Schedule and provide to the Government at the Logistics Conference and Routine Status Meetings. The Integrated Master Schedule may be combined with the Production Schedule following the Production Readiness Review.
3.0.6 The Contractor is required to possess and maintain an adequate property management system. The system must track all materials associated with this contract. Upon completion of the contract period of performance, all material associated with the contract that is purchased by the Contractor and not depleted or previously delivered to the Government during the performance of the contract shall become the property of the Government.
3.1 CLIN -001 CB-ATON-S Production
3.1.1 SLIN -001AA CB-ATON-S Production
3.1.1.1 The Contractor shall be responsible for the production of the cutter boats and integration of associated equipment and parts as required by the Technical Specification.
3.1.1.2 The Contractor shall be responsible for procurement, installation, integration, and testing of all Contractor Furnished Equipment (CFE) including software.
3.1.1.3 Outfitting
3.1.1.3.1 The Contractor shall outfit each cutter boat in accordance with Spec 600.1.
3.1.1.3.2 The Contractor shall place onboard the material specified by the authorized allowance documents, including ordering, funding, expediting, following-up, receipting, inspecting, and stowage of material.
3.1.1.4 Initial Maintenance Parts
3.1.1.4.1 The Contractor shall provide initial maintenance parts for each cutter boat in accordance with Spec 083.1.2.
3.1.1.5 Warranty
3.1.1.5.1 The Contractor shall provide a warranty for each cutter boat in accordance with Spec 041.2.
3.1.1.5.2 The rights and remedies of the Government provided in this clause are in addition to and do not limit any rights otherwise afforded to the Government under this contract.
3.1.1.6 Technical Manuals
3.1.1.6.1 The Contractor shall deliver a copy of the technical publications and manuals, in compliance with Spec 086, for each cutter boat.
3.1.1.7 Boat Information Book
3.1.1.7.1 The Contractor shall deliver the Boat Information Book, in compliance with Spec 086.3, for each cutter boat.
3.1.1.8 Serial Number Report
3.1.1.8.1 The Contractor shall deliver Serial Number Report, in accordance with Spec 083.3, for each cutter boat.
3.1.1.9 Acceptance Testing
3.1.1.9.1 The Contractor shall conduct Acceptance Testing, in accordance with Spec 092.1, for each cutter boat.
3.1.1.10 Delivery
3.1.1.10.1 The Contractor shall prepare each cutter boat for delivery in accordance with Spec 084.
3.1.1.11 Acceptance of Boat
3.1.1.11.1 Acceptance shall follow confirmation that individual boats meet the requirements of the Technical Specification and Statement of Work and consist of execution and signature of the DD-250 form, per boat.
3.1.2 SLIN -001AB Trailer
3.1.2.1 The Contractor shall provide boat trailers appropriate to the size and weight requirements of the cutter boats in accordance with Spec 910.
3.1.2.2 The Contractor shall provide a warranty for each trailer in accordance with Spec 041.2.
3.1.2.2.1 The rights and remedies of the Government provided in this clause are in addition to and do not limit any rights otherwise afforded to the Government under this contract.
3.2 CLIN -002 Delivery
3.2.1 The Contractor shall deliver the boats and trailers (if ordered) in accordance with Spec 084.3.
3.2.2 The Contractor may be required to deliver boats and any ancillary items ordered to other Coast Guard locations, as specified by the Contracting Officer.
3.2.3 Alternative delivery schedules may be established through bilateral agreement.
3.2.4 SLIN -002AA Shipyard Delivery
3.2.4.1 The Contractor shall deliver the cutter boats and any ancillary items ordered, no later than 90 days from the date of placement of each hulls associated delivery order or as agreed upon by the Government and the Contractor, to the below Shipyard address.
Birdon America, Inc.
13980 Shell Belt Rd, Bayou La Batre, Al, 36509
3.2.5 SLIN -002AB Continental U.S. (CONUS) Delivery
3.2.5.1 The Contractor may be required to deliver to other Coast Guard locations within the CONUS, billed at a per mile rate from the Contractor location to the destination.
3.3 CLIN -003 Spares
3.3.1 The Contractor shall provide spares to replace major equipment that becomes damaged beyond repair.
3.3.1.1 SLIN -003AA Outboard Engine
3.3.1.2 SLIN -003AB Lower Unit
3.3.1.3 SLIN -003AC Fendering
3.3.2 The Contractor shall provide a warranty for spares in accordance with Spec 041.2.
3.3.2.1 The rights and remedies of the Government provided in this clause are in addition to and do not limit any rights otherwise afforded to the Government under this contract.
3.3.3 The Contractor shall package and deliver the spares in accordance with Spec 083.5 and Spec 084.
3.4 CLIN -004 Training
3.4.1 The Contractor shall develop basic operational and maintenance training in accordance with Spec 089.
3.4.2 SLIN -004AA Familiarization Training
3.4.2.1 The Contractor shall travel to a designated location, within 50 miles of the Shipyard Delivery Location and provide familiarization training, for both operator and maintainer, in accordance with Spec 089.
3.4.3 SLIN -004AB Training Development
3.4.3.1 The Contractor shall develop the materials required to deliver the SLIN -004AA Familiarization Training in accordance with Spec 089.
3.5 CLIN -005 Materials/Subcontracts, Engineering Change Development/Studies and Travel
3.5.1 SLIN -005AA Materials and Subcontracts
3.5.1.1 During the performance of this contract, the Government may request the contractor to issue subcontracts and/or procure materials to respond to mission requirements.
3.5.1.2 The term “material” includes supplies, parts, equipment, hardware, and Information Technology (IT) resources including hardware, services, and software.
3.5.1.3 Subcontracts shall be classified as a material cost.
3.5.1.4 The Contractor shall provide a priced list of parts by ordering period at completion and acceptance of design.
3.5.1.5 Unless otherwise specified in the delivery order, the Contractor shall deliver items ordered to the Surface Forces Logistics Center Baltimore, FOB destination, at the address below.
Coast Guard Surface Forces Logistics Center Baltimore 2401 Hawkins Point Road Baltimore, MD 21226
3.5.1.6 The Contractor shall propose a loading rate to be applied to the price paid but shall not include fee or profit.
3.5.1.7 The numbers of and types of material purchases shall be limited to the minimum required to accomplish requirements and shall be coordinated with the COR. No purchases of any amount shall be executed by a subcontractor if they do not have a DCMA-approved purchasing system.
3.5.1.8 The Contractor shall provide a report detailing the unique voucher number used in invoicing, an item description (including noun/name, model, part number, and other relevant information), vendor, requisition order information (date, item required by date, item order date, item received date), work area supported, purchase purpose, purchase unit/quantity, the price per unit, quantity purchased, total purchase price, unbilled yes/no, invoice number in which the material is billed. The specific format of the report shall be pre-approved by the COR and Contracting Officer.
3.5.2 SLIN -005AB Engineering Labor and SLIN -005AC Non-Engineering Labor
3.5.2.1 Orders under SLIN -005AB Engineering Labor and SLIN -005AC Non-Engineering Labor will be placed by a Government approved Technical Instruction (TI). Prior to the placement of an order, the Contractor shall submit, as requested, a draft TI for approval by the Government detailing the specific effort to be accomplished, the period of performance covered by the TI, the FFP cost proposal for the work (including the breakout of engineering labor, non-engineering labor, and subcontracted/other), and a list of deliverables that will be submitted.
3.5.2.2 The Contractor shall conduct special studies, engineering change development and analyses in support of this contract, including but not limited to studies related to improvements in operating efficiencies and operational capability, engineering technical analysis, support of fielding the cutter boats, development of various engineering products and/or drawings. The requirements associated with this CLIN are over and above those specified in other contract CLINs.
3.5.2.3 Any material or subcontract required to conduct special studies, engineering change development or analyses will be under SLIN -005AA Material/Subcontracts.
3.5.3 SLIN -005AD Travel
3.5.3.1 Contractor travel is required to support this task order. Travel explicitly required by other CLINs shall not be covered under CLIN -005AD. All travel required by the Government outside the contractors local commuting area(s) will be reimbursed to the Contractor in accordance with the Federal Travel Regulations (FTR) for transportation, lodging, and per diem.
3.6 CLIN -006 Design and Prototype Production
3.6.1 The Contractor shall design and produce prototype boats(s) of the CB-ATON-S, as required within the Technical Specification.
3.6.2 The following systems and equipment are standardized in support of operability and sustainability.
3.6.2.1 The Contractor shall install Scalable Integrated Navigation System - 2 (SINS-2) in accordance with Spec 424.
3.6.2.2 The Contractor shall install Automatic Identification System - 2 (AIS-2) in accordance with Spec 444.
3.6.2.3 The supplier of the equipment and sensors which comprise SINS-2 and AIS-2 is:
FLIR Maritime U.S. Incorporated 9 Townsend West Nashua, NH 03063
3.6.3 SLIN -006AA Design and Engineering
3.6.3.1 The Contractor shall design a cutter boat that complies with the requirements of the Technical Specification.
3.6.3.2 Engineering Drawing and Models Formats: 2D drawings delivered to meet the requirements of 3.6.3 shall meet the requirements of Specification 085.3.3. 3D models delivered to meet the requirements of 3.6.3 shall be provided in their native format and an ISO 10303 STEP compliant formant.
3.6.3.3 The Contractor shall host a logistics conference, in accordance with Spec 082.1, no later than 30 days after contract award. The logistics conference shall also serve as the contract kickoff conference.
3.6.3.4 Preliminary Design Review (PDR): The Contractor shall demonstrate that the design is technically feasible, consistent with a product that can meet the Technical Specification and has converged on major design characteristics with minimal risk of subsequent adverse changes.
3.6.3.4.1 Required Deliverables: Preliminary drafts of the following deliverables shall be provided to the government 45 days prior to the PDR. Preliminary drafts may omit those deliverable requirements yet to be defined at the PDR level of design, but sufficient information shall be provided to meet the requirements of 3.6.3.4.
3.6.3.4.1.1 Calculations in accordance with Specification 085.6.
3.6.3.4.1.2 Master Equipment Configuration List (MECL) in accordance with Specification 083.2.
3.6.3.4.1.3 Engineering Drawings/Models: The Contractor shall provide sufficient preliminary 2D engineering drawings, and/or make available to the government a sufficiently detailed 3D CAD model, to meet the PDR requirements of 3.6.3.4. The following engineering drawings shall be provided as 2D engineering drawings:
3.6.3.4.1.3.1 301 Electrical System, General Arrangement, Specification 085.5.1.4.1
3.6.3.4.1.3.2 320 12 VDC Electrical One-Line Diagram/Schematic, Specification 085.5.1.4.3
3.6.3.4.1.3.3 410 Command and Control Arrangements, Specification 085.5.1.5.3
3.6.3.4.1.3.4 839 Hull Lines and Offsets, Specification 085.5.1.8.2
3.6.3.4.2 The PDR will be scheduled at a time, date, and location mutually agreed upon by the Government and the Contractor, but no later than 90 days from award of the SLIN - 006AA. Within 14 days of the PDR, the Government will confirm that PDR criteria have been met or will provide specific corrective action in writing.
3.6.3.5 Critical Design Review (CDR): The Contractor shall demonstrate that the vessel design satisfies the contract requirements and is developed to a level of maturity to begin prototype construction.
3.6.3.5.1 Required Deliverables: The following deliverables shall be provided to the government 45 days prior to the CDR. Deliverables shall represent the anticipated prototype construction.
3.6.3.5.1.1 Calculations in accordance with Specification 085.6
3.6.3.5.1.2 Master Equipment Configuration List (MECL) in accordance with Specification 083.2.
3.6.3.5.1.3 Engineering Drawings/Models: The Contractor shall provide sufficient 2D engineering drawings, and/or make available to the government a detailed 3D CAD model, to meet the CDR requirements of 3.6.3.5. Emphasis shall be placed on hull structural details, HMI systems, and the integration of propulsion controls and C5I systems.
3.6.3.5.2 The CDR will be scheduled at a time, date and location mutually agreed upon by the Government and the Contractor, but no later than 90 days from the Government certification of PDR criteria. Within 14 days, the Government will confirm that CDR criteria have been met or will provide specific corrective action in writing.
3.6.3.6 Production Readiness Review (PRR): The Contractor shall demonstrate that the vessel design satisfies the contract requirements as supported by First Article Testing, Special Testing, and that production planning and facility staffing and capacity are sufficient to begin full rate production of the CB-ATON-S.
3.6.3.6.1 Required Deliverables: The following deliverables shall be provided to the government 45 days prior to the PRR. Deliverables shall represent the final production design & construction:
3.6.3.6.1.1 Calculations, MECL, and Engineering Drawings/Models that have been updated from the CDR or as a result of First Article Testing results.
3.6.3.6.1.2 An up-to-date production schedule for at least the first three boats under full rate production; notional delivery dates will be provided by the government if task orders for the boats have not yet been issued. The Production Schedule shall include time to allow for Government inspection, testing, vendor shipping preparation and other key events.
3.6.3.6.1.3 A facility utilization assessment has been conducted (including other on-going and future scheduled work) demonstrating that facilities, e.g. cranes, jigs, special fixtures, are in place to support production.
3.6.3.6.2 The PRR will be scheduled at a time, date and location mutually agreed upon by the Government and the Contractor, but no later than 60 days from the completion of First Article Testing. Within 14 days, the Government will confirm that PRR criteria have been met or will provide specific corrective action in writing.
3.6.3.7 Prototype Testing
3.6.3.7.1 First Article Testing
3.6.3.7.1.1 The Contractor shall conduct the First Article Testing required to ensure the prototype(s) meets the requirements in accordance with Spec 095.
3.6.3.7.2 Special Tests
3.6.3.7.2.1 The Contractor shall conduct and support Special Tests in accordance with Spec 092.3.
3.6.3.7.3 The Contractor shall complete First Article Testing and Special Tests only for the prototype boat. In the event of Government procures multiple prototype boat(s), First Article Testing and Special Tests will only be completed for the first prototype boat.
3.6.3.7.4 The Contractor shall request of the Government a two-day period, no later than two weeks prior to scheduled delivery to witness First Article Testing and Special Tests, as outlined in the Technical Specification. The Government will accommodate scheduling for site visits, in the order in which requests are received. All tests must be completed prior to the Government’s departure.
3.6.3.8 Initial Operator Prototype Testing
3.6.3.8.1 After delivery of prototype and before PRR, the Government may conduct Initial Operator Prototype testing at a Coast Guard designated location.
3.6.3.8.2 The Contractor may be requested to attend and support Initial Operator Prototype Testing. If requested, all labor and travel, conducted by the Contractor, shall be exercised and charged under CLIN -005.
3.6.3.8.3 Any feedback and testing findings, identified during initial operator prototype testing by the Government, shall be incorporated into the final design for production units via Engineering Change(s) under CLIN -005.
3.6.4 SLIN -006AB Prototype Production
3.6.4.1 The Contractor shall produce prototype boat(s) of the CB-ATON-S that comply with the requirements of the Technical Specification.
3.6.4.2 Ordering of Critical Material Items
3.6.4.2.1 The Contractor shall identify the list of critical items, which shall include engines and SINS-II, to the Contracting Officer at the logistics conference.
3.6.4.2.2 The Contractor shall notify and provide supporting documentation to the Government upon order of critical material items. Notice shall include purchase orders and related information to substantiate the activities as complete.
3.6.4.3 Hull Welding
3.6.4.3.1 The Contractor shall demonstrate that hull fabrication is complete and no additional welding is required.
3.6.4.3.2 The Contractor shall weld in accordance with Spec 074.
3.6.4.3.3 The Contractor shall demonstrate the vessel’s preparedness for assembly and integration.
3.6.4.4 Assembly
3.6.4.4.1 The Contractor shall demonstrate that assembly is complete, and the vessel is prepared for acceptance trials.
3.6.4.5 Acceptance Testing
3.6.4.5.1 The Contractor shall conduct and support Acceptance Testing in accordance with Spec 092.1.
3.6.4.6 Outfitting
3.6.4.6.1 The Contractor shall outfit each prototype boat in accordance with Spec 600.1.
3.6.4.6.2 The Contractor shall place onboard the material specified by the authorized allowance documents, including ordering, funding, expediting, following-up, receipting, inspecting, and stowage of material.
3.6.4.7 Initial Maintenance Parts
3.6.4.7.1 The Contractor shall provide initial maintenance parts for each prototype boat in accordance with Spec 083.1.2.
3.6.4.8 Warranty
3.6.4.8.1 The Contractor shall provide a warranty for each prototype boat in accordance with Spec 041.2.
3.6.4.8.2 The rights and remedies of the Government provided in this clause are in addition to and do not limit any rights otherwise afforded to the Government under this contract.
3.6.4.9 Technical Manuals
3.6.4.9.1 The Contractor shall deliver a copy of the technical publications and manuals, in compliance with Spec 086, for each prototype boat.
3.6.4.10 Boat Information Book
3.6.4.10.1 The Contractor shall deliver the Boat Information Book, in compliance with Spec 086.3, for each prototype boat.
3.6.4.11 Serial Number Report
3.6.4.11.1 The Contractor shall deliver Serial Number Report, in accordance with Spec 083.3, for each prototype boat.
3.6.4.12 Prototype Delivery
3.6.4.12.1 The Contractor shall prepare the prototype boat for delivery in accordance with Spec 084.
4 Period of Performance
4.1 The period of performance shall include a five-year base ordering period and one (1) two-year optional ordering period. Planned periods are detailed below.
4.1.1 Base Ordering Period
4.1.1.1 Base OP: 08/01/2025-07/31/2026
4.1.1.2 OP1: 08/01/2026-07/31/2027
4.1.1.3 OP2: 08/01/2027-07/31/2028
4.1.1.4 OP3: 08/01/2028-07/31/2029
4.1.1.5 OP4: 08/01/2029-07/31/2030
4.1.2 Optional Ordering Period
4.1.2.1 OP5: 08/01/2030-07/31/2031
4.1.2.2 OP6: 08/01/2031-07/31/2032
5 Ordering Procedures
5.1 The Contracting Officer located at the USCG Headquarters (CG-912) shall have the overall responsibility for the administration of the Indefinite-Delivery/Indefinite-Quantity (IDIQ) Contract.
5.2 The CG-912 Contracting Officer shall be the only individual authorized to take actions on behalf of the Government to amend, modify or deviate from the IDIQ Contract terms, conditions, requirements, specifications, details, and delivery schedules.
5.3 The Contracting Officer is responsible for the overall administration and final closeout of the IDIQ Contract and delivery orders, and when necessary, will provide scope oversight;
serve as liaison between the Contractor and USCG; issuing delivery orders; ensure compliance with the IDIQ Contract requirements; and issue needed modifications against the IDIQ Contract.
5.4 Procedures for orders/modifications requiring a proposal in accordance with the Technical Specification: The Contractor will be notified of the work to be performed in writing. The Contractor shall respond within the time established by the Government for response (will vary on an Order by Order basis but is typically within seventy-two (72) hours) with a formal proposal that identifies the number of composite labor hours, travel costs required, materials, and sub-contractor costs. Supporting data to the price proposal shall include a basis of estimate to include a breakdown of labor and materials as applicable, broken down by task. Any amount proposed for subcontracts shall be supported by a separate, similar price breakdown and upon the Government’s request confirmation that the subcontracts were competed and a summary of the competition. The Government will not reimburse proposal preparation costs. The Contractor will be directed to commence work via an order or modification sent from the Contracting Officer. The Contractor shall provide notice of acceptance of the order or modification by signing the Standard Form (SF-30 or SF-1449) and returning it to the Contracting Officer, or by starting work when the Contracting Officer issues a unilateral task order via Optional Form 347.
6 Intellectual Property Rights
6.1 The Government will require deliverables of drawings and other technical data under this contract.
6.2 The Contractor shall identify and mark data subject to limited rights, unless otherwise required by the delivery order.
7 Inspection / Acceptance
7.1 The following supplements FAR 52.212-4 (a): The Contractor shall inspect and test each boat to verify that all requirements and performance specifications conform to the contract prior to delivery and acceptance. The Contractor shall fill out a DD-250 “Material Inspection and Receiving Report” and provide to the Contracting Officer’s Representative (COR) at boat delivery. If discrepancies are discovered at delivery they will be handled in accordance with 52.212-4 (a). Only the Contracting Officer can make the decision and sign the DD-250 if the boat is not fully conforming to the requirements of the contract. The Contracting Officer or designated representative will provide the Contractor with a list of all discrepancies discovered during a delivery.
7.2 Sensitive Information Requirements
7.2.1 Contractor shall protect all sensitive information (e.g. For Official Use Only) to which they have access under this contract. All Contractor employees with access to sensitive information shall execute DHS Form 11000-6, Department of Homeland Security Non- Disclosure Agreement (NDA), as a condition of access to such information.
7.2.2 Sensitive information shall be protected in accordance with HSAR Clause 3052.204-71, Contractor Employee Access, for proper handling and safeguarding of the security of all such USCG information, as defined in the terms and conditions of this contract.
7.3 Protection of Information
7.3.1 Contractor access to information protected under the Privacy Act is required under this SOW. Contractor employees shall safeguard this information against unauthorized disclosure or dissemination in accordance with the law and Government policy and regulation.
8 Contract Type
8.1 This will be an indefinite delivery indefinite quantity (IDIQ) contract with firm-fixed price task orders.
9 Electronic Submission of Payment Requests
9.1 Definitions. As used in these instructions:
9.1.1 “Payment request” means a bill, voucher, invoice, or request for contract financing payment with associated supporting documentation. The payment request must: comply with the requirements identified in FAR 32.905(b), “Content of Invoices” and the applicable Payment clause included in this contract. In addition, discount offerings and small business status if available shall be stated. If travel was allowable and approved, components in accordance with FAR 31.205-46 shall be provided.
9.2 Except as provided in paragraph (c) of this clause, the contractor shall submit payment requests electronically using the Invoice Processing Platform (IPP). Information regarding IPP, including IPP Customer Support contact information, is available at www.ipp.gov or any successor site.
9.3 The contractor may submit payment requests using a method other than IPP only when the contracting officer authorizes alternate procedures in writing in accordance with Coast Guard procedures.
9.4 If alternate payment procedures are authorized, the contractor shall include a copy of the contracting officer's written authorization with each payment request.
9.5 IPP enrollment information is at https://www.uscg.mil/fincen/IPP/.