About this file

Amendment 0007

View the file

Other files

File Type Posted
Am_0006.pdf PDF
Am_0005.pdf PDF
Am_0004.pdf PDF
Am_0003.pdf PDF
Am_0002.pdf PDF
Am_0001.pdf PDF
WBV083-11-H-0023.pdf PDF
100__PLANS_WBV-83.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General Decision Number: LA120007 12/14/2012 LA7

Superseded General Decision Number: LA20100008

State: Louisiana

Construction Type: Heavy

Counties: Jefferson, Orleans, Plaquemines, St Bernard, St Charles, St James, St John the Baptist and St Tammany Counties in Louisiana.

HEAVY CONSTRUCTION PROJECTS (Includes flood control, water & sewer lines, and water wells. Also includes elevated storage tanks in all listed parishes except Plaquemines and St. James.

Excludes industrial construction-chemical processing, power plants, and refineries.)

Modification Number Publication Date 0 01/06/2012 1 03/09/2012 2 04/13/2012 3 06/01/2012 4 06/15/2012 5 07/06/2012 6 07/27/2012 7 08/03/2012 8 09/28/2012 9 12/14/2012

CARP0729-001 07/01/2012

Rates Fringes

MILLWRIGHT.......................$ 25.80 9.50

CARP1846-006 07/01/2012

Rates Fringes

CARPENTER

(formbuilding/formsetting and Piledrivers).....................$ 22.21 7.75

* ELEC0130-005 12/01/2012

JEFFERSON, ORLEANS, PLAQUEMINES, ST. BERNARD, ST. CHARLES, ST.

JAMES, AND ST. JOHN THE BAPTIST PARISHES

Rates Fringes

ELECTRICIAN (including low voltage wiring)..................$ 28.50 9.24

ELEC1077-002 09/01/2012

ST. TAMMANY PARISH

ELECTRICIAN (including low voltage wiring)..................$ 22.50 7.17

ENGI0406-018 07/01/2009

Rates Fringes

OPERATOR: Power Equipment Bulldozer...................$ 21.26 6.70 Mechanic....................$ 23.31 6.70

PLAS0567-003 07/01/2012

JEFFERSON, ORLEANS, PLAQUEMINES, ST. BERNARD, ST. CHARLES, ST.

JOHN THE BAPTIST, and ST. TAMMANY PARISHES

Cement Mason/Concrete Finisher...$ 20.58 5.69

PLAS0812-003 06/01/2004

ST. JAMES PARISH

Rates Fringes

Cement Mason/Concrete Finisher...$ 21.85 0.00

PLUM0060-002 06/04/2012

JEFFERSON, ORLEANS, PLAQUEMINES, ST. BERNARD, ST. CHARLES, ST.

JAMES (Southeastern Portion), ST. JOHN THE BAPTIST, and ST.

TAMMANY PARISHES

Plumbers (excluding pipe laying)..........................$ 26.88 10.42

PLUM0198-005 07/01/2012

ST. JAMES PARISH (Northwestern Portion)

Rates Fringes

PLUMBER (excluding pipe laying)..........................$ 24.54 10.38

SULA2004-007 05/13/2004

Rates Fringes

CARPENTER (all other work).......$ 13.75 2.60

Laborers:

Common/Landscape............$ 9.88 0.00 Fence.......................$ 11.24 0.00 Flagger.....................$ 8.58 0.00 Mason Tender................$ 7.25 0.00 Pipelayer...................$ 9.84 0.00

PIPEFITTER (excluding pipelaying)......................$ 17.52 4.51

Power equipment operators:

Backhoe/Excavator...........$ 14.42 0.00 Crane.......................$ 16.34 3.30 Dragline....................$ 16.50 0.00 Front End Loader............$ 13.89 0.00 Oiler.......................$ 10.03 0.00

Truck drivers:

Dump........................$ 11.01 0.00 Pickup......................$ 12.25 0.00

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is union or non-union.

Union Identifiers

An identifier enclosed in dotted lines beginning with characters other than "SU" denotes that the union classification and rate have found to be prevailing for that classification. Example: PLUM0198-005 07/01/2011. The first four letters , PLUM, indicate the international union and the four-digit number, 0198, that follows indicates the local union number or district council number where applicable , i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2011, following these characters is the effective date of the most current negotiated rate/collective bargaining agreement which would be July 1, 2011 in the above example.

Union prevailing wage rates will be updated to reflect any changes in the collective bargaining agreements governing the rate.

0000/9999: weighted union wage rates will be published annually each January.

Non-Union Identifiers

Classifications listed under an "SU" identifier were derived from survey data by computing average rates and are not union rates; however, the data used in computing these rates may include both union and non-union data. Example: SULA2004-007 5/13/2010. SU indicates the rates are not union rates, LA indicates the State of Louisiana; 2004 is the year of the survey; and 007 is an internal number used in producing the wage determination. A 1993 or later date, 5/13/2010, indicates the classifications and rates under that identifier were issued as a General Wage Determination on that date.

Survey wage rates will remain in effect and will not change until a new survey is conducted.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

SECTION 00010

Page 00010-3 thru 6. Delete these pages in their entirety and replace with the revised attached pages 00010-3 thru 6.

SECTION 01 57 23.00 12

Page 67, paragraph 3.6, subparagraph (a), item 5. Delete this item and replace with the following:

“5. Modifications to Existing Utilities: The existing 42" S.F.M will be sleeved through the steel A-Frame walls. For the 12" waterline, new water line will be installed up-and-over the levee.

The existing water line will be removed from within the levee section as shown on the drawings.”

SECTION 33 11 00

1. Page 2, paragraph 1.2, item (1). Delete this item and replace with the following:

“(1) The Contractor shall furnish all labor, supervision, materials, and equipment required for installation of new and existing water mains and fittings, and removal of the existing water main as required by the project drawings and specifications. All tie-ins to the new and existing water mains shall be made by the Contractor.”

2. Page 3, paragraph 1.4. Delete this paragraph and replace with the following:

“1.4 MEASUREMENT AND PAYMENT

No measurement will be made for the water main. Payment will be made at the contract lump sum price for "12" Waterline". Price and payment shall constitute full compensation for furnishing all plant, labor, materials, tools and equipment and performing all operations necessary to install the permanent water mains including tie-ins; pipe; ductile iron fittings; and other appurtenances, piping and setups required for hydrostatic testing; coordination of testing with S&WB; chlorination; and tie-ins to the existing water mains, all as required to complete the work specified herein and as shown on the drawings.”

3. Page 7, Add new paragraph 2.4 WATER VALVE MANHOLES as follows:

“2.4 WATER VALVE MANHOLES

New 12” water valve manholes shall conform to SECTION 33 40 00, “WATER VALVE MANHOLES”, and S&WB Standard Drawing No. 6179-F-2.”

NEW SECTION 33 40 00

Add the attached new Section 33 40 00.

NEW SECTION 35 31 19.04 12

Add the attached new Section 35 31 19.04 12.

DRAWINGS

1. SHEET IDENTIFICATION Nos. C-203 and C-204. Delete these drawings in their entirety and substitute the attached revised drawing SHEET IDENTIFICATION Nos. C-203 and C-204 therefore.

2. Add the attached new drawings SHEET IDENTIFICATION Nos. C-601 thru C-607.

00010-3 Ed 12-064

SECTION 00010 – BIDDING SCHEDULE

West Bank & Vicinity, Hurricane Protection Project, East & West of Algiers Canal, Orleans Parish, Louisiana, WBV-83 N.O. Sewerage & Water Board (S&WB) 42” Sewer Force Main & 12” Waterline

Item DESCRIPTION Estimated Quantity Unit Unit Price Estimated Amount

0001 Mobilization and Demobilization 1 LS

Temporary Retaining Structures/Temporary Flood Protection

1 LS

0003 Silt Fences 3,000 LF

0004 Truck Wash-Down Racks 1 LS

0005 Clearing and Grubbing 1 LS

0006 Structural Excavation 1 LS

0007 Structural Backfill 1 LS

0008 Construction Dewatering 1 LS

009 Embankment, Compacted Fill 3,614 CY

0010 Sheet Piling, Steel, Type PZ-27 8,910 SF

00011 Steel H-Piling HP 14 X 73 1,756 LF

0012 Seeding and Mulching 3 AC

0013++ Lime Soil Amendment 3 TON

0014++ Sulfur Soil Amendment 1.5 TON

0015 Fertilizer

0015AA First 180 LBS 180 LBS

0015AB All Over 180 LBS 150 LBS

0016 Modifications to Existing Utilities

(42" SFM) 1 LS

0017 12" Waterline 1 LS

0018** Concrete Scour Protection 1,988 SY

0019 Rip Rap 8,100 TON

0020** Water Line Valve 1 EA

0021** Water Valve Manhole 1 EA

TOTAL: $

**Denotes Change from previous bidding schedule.

00010-4 Ed 12-064

++Items not subject to the requirements of FAR 52.211-18 VARIATION IN ESTIMATED QUANTITY.

Award will be made as a whole to one bidder.

NOTE 1: Bidders shall furnish unit prices for each item listed in the Schedule requiring a unit price. If the bidder fails to insert a unit price in the appropriate blank for required item(s), but does furnish an extended total, or an estimated amount for such item(s), the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF A BIDDER OMITS BOTH THE UNIT PRICE AND THE EXTENDED

TOTAL OR ESTIMATED AMOUNT FOR ANY ITEM, ITS BID SHALL BE

DECLARED NON-RESPONSIVE AND THEREFORE INELIGIBLE FOR

AWARD.

NOTE 2: Any bid may be rejected if the Contracting Officer determines in writing that it is unreasonable as to price. Unreasonableness of price includes not only total price of bid, but the price for individual line items as well. Any bid may be rejected if the prices for any line items or sub line items are materially unbalanced (See FAR 14.404-2).

NOTE 3: THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442. The NTP will be issued immediately after verification of acceptable performance and payment bonds. Within seven (7) days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Area or Resident Engineer or his authorized representative. Physical work cannot start until the Accident Prevention Program, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract, have been conducted.

NOTE 4: RAPID VENDOR PAYMENT: Web based instructions for the submission of invoices;

http://www.mvn.usace.army.mil/ebs/rapid_vendor_payment.asp http://www.mvn.usace.army.mil/ebs/rapid_vendor_payment.asp�

00010-5 Ed 12-064

EVALUATION OF SUBDIVIDED ITEMS. (EFARS 52.211-5000 - MAR 95).

Item No. 0015 is subdivided into two or more estimated quantities and are to be separately priced. The Government will evaluate each of these items on the basis of total price of its sub-items.

(End of Clause)

VARIATIONS IN ESTIMATED QUANTITIES - SUBDIVIDED ITEMS. (EFARS

52.211-5001 - MAR 95).

The Variations in Estimated Quantities Subdivided Items clause is applicable only in Item No. 0015.

a. Variations from the estimated quantity in the actual work performed under any second or subsequent sub-item or elimination of all work under such a second or subsequent sub-item will not be the basis for an adjustment in contract unit price.

b. Where the actual quantity of work performed for Item No. 0015 is less than 85% of the quantity of the first sub-item listed under such items, the Contractor will be paid at the contract unit price for that sub-item for the actual quantity of work performed and, in addition, an equitable adjustment in contract price shall be made in accordance with the clause FAR 52.211-18, Variation in Estimated Quantity .

c. If the quantity of work performed under Item No. 0015 exceeds 115% or is less than 85% of the total estimated quantity of the sub-items under that item, and/or if the quantity of work performed under the second sub-item or any subsequent sub-item under Item No. NONE exceeds 115% or is less than 85% of the estimated quantity of any such sub-item, and if such variation causes an increase or a decrease in the time required for performance of this contract, the contract completion time will be adjusted in accordance with the clause FAR 52.211-18, Variation in Estimated Quantity.

(End of Clause)

WBV-83_S&WB Sewer Force Main and Waterline Ed 12-064

SECTION TABLE OF CONTENTS

DIVISION 33 - UTILITIES

SECTION 33 40 00

WATER VALVE MANHOLES

PART 1 GENERAL

1.1 SCOPE

1.2 MEASUREMENT AND PAYMENT

1.2.1 Precast Reinforced Concrete Water Valve Manhole

1.3 QUALITY CONTROL

1.3.1 General

1.3.2 Reporting

1.4 SUBMITTALS

1.5 DELIVERY, STORAGE, AND HANDLING

1.5.1 Delivery and Storage

PART 2 PRODUCTS

2.1 Precast Reinforced Concrete Water Valve Manhole

2.2 Concrete

2.3 Reinforcing Steel

2.4 Bedding

2.5 Frame and Cover

2.6 Mortar

2.7 Sewer Brick

PART 3 EXECUTION

3.1 INSTALLATION

-- End of Section Table of Contents --

SECTION 33 40 00 Page 2

SECTION 33 40 00

WATER VALVE MANHOLES

PART 1 GENERAL

1.1 SCOPE

The work covered by this section consists of furnishing all plant, labor, materials, and performing all operations in connection with furnishing and installing the precast reinforced concrete water valve manhole as indicated on the drawings and specified herein.

1.2 MEASUREMENT AND PAYMENT1.2.1 Precast Reinforced Concrete Water Valve Manhole

Measurement for the precast reinforced concrete water valve manhole will be measured per each unit satisfactorily installed. Payment for the precast reinforced concrete water valve manhole will be made at the contract unit price per each for "Water Valve Manhole". Price and payment shall include the cost of all labor, materials, and the use of all equipment and tools required to complete the work and furnishing, installing all miscellaneous and other components incidental thereto.1.3 QUALITY CONTROL

1.3.1 General

The Contractor shall establish and maintain quality control for excavation and backfill for installing the water valve manhole. The Contractor shall maintain records of his quality control for all construction operations and checking materials to be used including but not limited, to the following:

(1) Checking construction operations and certifying compliance with applicable sections of the specifications.

(2) Checking materials to be used in installing the water valve manhole. The Contractor shall certify that all materials are in compliance with applicable regulations.

1.3.2 Reporting

The original and two copies of these records, test results, test data, hydrostatic tests and other tests, as well as the records of corrective action taken, shall be furnished to the Government daily. Format of report shall be as prescribed in Section 01 45 04.00 10 CONTRACTOR QUALITY CONTROL.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

SECTION 33 40 00 Page 3

Water Valve Manhole

Printed copies of the manufacturer's recommendations for installation procedures of the material being placed, prior to installation.

SD-07 Certificates

Certified copies of test reports demonstrating conformance to applicable ASTM specifications, before the manhole is installed.

1.5 DELIVERY, STORAGE, AND HANDLING

1.5.1 Delivery and Storage

Materials delivered to site shall be inspected for damage, unloaded, and stored with a minimum of handling. Materials shall not be stored directly on the ground. The inside of pipes and fittings shall be kept free of dirt and debris. Keep a copy of the manufacturer's instructions available at the construction site at all times and follow these instructions unless directed otherwise by the Contracting Officer.PART 2 PRODUCTS2.1

Precast Reinforced Concrete Water Valve Manhole

The precast reinforced concrete water valve manhole shall be manufactured in accordance with and conform to ASTM C 478.

2.2 Concrete

The concrete for the precast reinforced concrete water valve manhole shall be 4,000 psi in 28 days as shown on S&WB Standard Dwg. 6178-B-6A.

2.3 Reinforcing Steel

The reinforcing steel for the precast reinforced concrete water valve manhole shall meet ASTM A-615 Grade 60, and as shown on S&WB Standard Dwg.

6178-B-6A.

2.4 Bedding

Bedding for the water valve manhole shall conform to the requirements as stated in SECTION 35 31 19.04 12, and as shown on the S&WB Standard Dwg.

6178-B-6A.

2.5 Frame and Cover

The frame and cover shall conform to the requirements as shown on S&WB Standard Dwg. 3143-E-1.

2.6 Mortar

Mortar shall consist of one (1) part portland cement, two (2) parts mortar sand, and water as requried for proper consistency. Mortar shall be used within 30 minutes after mixing. Portland Cement and Mortar sand shall conform to LSRRB Section 1001.01 and Section 1003.02(b) respectively.

2.7 Sewer Brick

Sewer Brick shall be in accordance with LSRRB Section 1004.01.

SECTION 33 40 00 Page 4

PART 3 EXECUTION

3.1 INSTALLATION

The Contractor shall construct and install the precast reinforce concrete water valve manhole to the details, dimensions, and grades as shown in S&WB Standard Dwgs 6178-B-6A and 3143-E-1.

-- End of Section --

SECTION 33 40 00 Page 5

SECTION TABLE OF CONTENTS

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

SECTION 35 31 19.04 12

BEDDING

PART 1 GENERAL

1.1 SCOPE

1.2 MEASUREMENT AND PAYMENT

1.3 REFERENCES

1.4 QUALITY CONTROL

1.4.1 General

1.4.2 Reporting

PART 2 PRODUCTS

2.1 MATERIALS

2.1.1 Bedding

PART 3 EXECUTION

3.1 INSTALLATION

-- End of Section Table of Contents --

SECTION 35 31 19.04 12 Page 1

SECTION 35 31 19.04 12

BEDDING

PART 1 GENERAL

1.1 SCOPE

The work covered by this section consists of furnishing all plant, labor, equipment and materials, and performing all operations in connection with furnishing and placing the bedding material under the valve manhole as shown on the drawings and as herein after specified.

1.2 MEASUREMENT AND PAYMENT

No seperate measurement and payment will be made for bedding. Payment for the bedding shall be distributed throughout the existing bid items for which the work is incidental thereto.

1.3 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D 698 (2007e1) Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft-lbf/cu. ft. (600 kN-m/cu. m.))

LOUISIANA STANDARD SPECIFICATIONS FOR ROADS AND BRIDGES (2006

Edition), LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT

(LADOTD)

LSSRB 1003.02 Aggregates for Portland Cement Concrete and Mortar

1.4 QUALITY CONTROL

1.4.1 General

The Contractor shall inspect all materials before they are incorporated into the work for compliance with contract requirements and any material found to be defective will be rejected. All information pertaining to the inspection shall be recorded and included in quality control reports furnished the Contracting Officer. The Contractor shall establish and maintain quality control for construction operations to assure compliance with contact requirements, and maintain records of his quality control for all construction operations. The quality control reports shall include, but not be limited to, the following:

(1) Equipment. Type, size, and suitability for construction of the prescribed work.

SECTION 35 31 19.04 12 Page 2

(2) Submission of bedding samples for quality testing, if from other than approved sources, as specified in paragraph Sources and Evaluation Testing.

(3) Quality of bedding meets the requirements specified.

(4) Quantity bedding delivered and placed each day.

1.4.2 Reporting

The original and two copies of these records, as well as the records of corrective action taken, shall be furnished the Government daily. Format of report shall be as prescribed in Section 01 45 04.00 10 CONTRACTOR

QUALITY CONTROL.

PART 2 PRODUCTS

2.1 MATERIALS

2.1.1 Bedding

Bedding material shall be crushed stone and shall meet the requirements of LSSRB 1003.02(a). The stone source shall be from the General Provisions clause entitled "STONE SOURCES", and shall conform to the following gradation:

U. S. Sieve Percent Passing

1-1/2 95 - 100 No. 4 0 - 15 No. 200 0 - 2

PART 3 EXECUTION

3.1 INSTALLATION

The bedding shall be placed in a six (6) inch minimum layer using compacted stone bedding material conforming to paragraph "Bedding", and in accordance with the details as shown on S&WB Standard Dwg. 6179-F-2. The stone bedding shall be compacted using mechanical vibrating equipment to a minimum ninety-five percent (95%) of its maximum dry density in accordance with ASTM D 698 at a moisture content of plus three percent to minus two percent (+3 to -2%) of optimum water content. -- End of Section --

SECTION 35 31 19.04 12 Page 3

H447693_C-203---.dgn 12/18/2012 12:02:47 PM

H447693_C-204---.dgn 12/18/2012 12:05:09 PM

H447693_C-601---.dgn 12/11/2012 1:10:49 PM

H447693_C-602---.dgn 12/11/2012 1:00:04 PM

H447693_C-603---.dgn 12/11/2012 1:20:01 PM

H447693_C-604---.dgn 12/11/2012 1:26:24 PM

H447693_C-605---.dgn 12/11/2012 1:40:48 PM

H447693_C-606---.dgn 12/11/2012 1:40:04 PM

H447693_C-607---.dgn 12/11/2012 1:42:32 PM

Amend 0007.pdf
Amend_WBV-83
00010
33 40 00
33 40 00 - WATER VALVE MANHOLES
33 40 00 - WATER VALVE MANHOLES
PART 1 GENERAL
1.1 SCOPE
1.2 MEASUREMENT AND PAYMENT1.2.1 Precast Reinforced Concrete Water Valve
1.3 QUALITY CONTROL
1.3.1 General
1.3.2 Reporting
1.4 SUBMITTALS
1.5 DELIVERY, STORAGE, AND HANDLING
1.5.1 Delivery and Storage
PART 2 PRODUCTS2.1
2.2 Concrete
2.3 Reinforcing Steel
2.4 Bedding
2.5 Frame and Cover
2.6 Mortar
2.7 Sewer Brick
PART 3 EXECUTION
3.1 INSTALLATION
35 31 19.04 12
H447693_C-203--2.pdf
H447693_C-204--2.pdf
Plans

File details come from the government source that posted it. Updated .