Water_Treatment_Plant_Transfer_Pump_Station_Modifications_(Addendum_#6_Revision).pdf
PDF 426 KB Posted
- Solicitation number
- ITB-26-16-CW
- Issued by
- Volusia County, Florida
About this file
This is an Invitation to Bid (ITB) document issued by the City of Port Orange, Florida for the Water Treatment Plant Transfer Pump Station Modifications project (ITB-26-16-CW). The project involves rehabilitation of three transfer pump stations at the Port Orange Water Treatment Plant serving the North, Central, and South treatment trains. The scope of work includes replacement of six existing vertical transfer pumps (two per station) along with upgraded associated piping, pipe supports, electrical infrastructure, concrete pump pads, and restoration of disturbed areas including sod, concrete, soil, and gravel replacement in kind. A non-mandatory pre-submittal conference and site visit is scheduled for September 28, 2026 at 10:00 a.m. EST at Port Orange City Hall. Bids are due October 23, 2026 at 2:30 p.m. EST. The response must include both electronic submission through OpenGov and hand-delivered hard copies (one original and one digital PDF on flash drive). The contract term is 365 days, and the City anticipates awarding to one responsible and responsive bidder.
Pricing must be firm and all-inclusive with no escalator clauses unless specified by the City, including all transportation, freight, and drayage costs. A Bid Bond equal to 5 percent of the bid amount is required at submittal, and a Payment and Performance Bond equal to 100 percent of the total contract amount is required upon award. Bidders must be Florida-licensed General Contractors with a minimum of three verifiable references from similar projects and current active Sunbiz registration. Required insurance includes Comprehensive General Liability ($1 million per occurrence, $2 million aggregate), Commercial Auto Liability ($1 million), and Workers' Compensation at statutory limits. The City will evaluate bidders on qualifications, experience, and past performance in addition to price. Questions must be submitted by October 9, 2026 at 4:00 p.m. EST with responses provided by October 14, 2026. The project is anticipated to be funded through the City's capital improvement program.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For more information, please visit our online supplier portal, located at https://procurement.opengov.com/portal/portorangefl
City of Port Orange
ITB-26-16-CW
WATER TREATMENT PLANT TRANSFER PUMP STATION
MODIFICATIONS
RELEASE DATE: September 18, 2026
RESPONSE DEADLINE: October 23, 2026, 2:30 pm
Please refer to the project timeline in this document for all important deadlines.
#ITB-26-16-CW
Title: Water Treatment Plant Transfer Pump Station Modifications
Table Of Contents
1. LEGAL NOTICE TO BIDDERS (Non-Mandatory)
2. SECTION 1 - PURPOSE AND OVERVIEW
3. SECTION 2 - INSTRUCTIONS TO BIDDERS
4. SECTION 3 - SCOPE OF WORK
5. SECTION 4 - STANDARD PURCHASE DEFINITIONS
6. SECTION 5 - GENERAL TERMS AND CONDITIONS
7. SECTION 6 - SPECIAL REQUIREMENTS/INSTRUCTIONS
8. SECTION 7 - REQUIRED DOCUMENTATION
9. ATTACHMENT 1 - SCHEDULE OF UNIT PRICING
10. ATTACHMENTS
Attachments:
A - Port_Orange_Transfer_Pump_Station_Upgrades_100__Plans
B - Attachment 1 - Schedule of Unit Pricing
C - Attachment 1 - Schedule of Unit Pricing
D - Port_Orange_-_Transfer_Pump_Station_Upgrades_100__Specifications (2)
E - WATERMARKED_DRAFT_-_Standard_Contract_for_Services_with_Bond_(021323)_Attached
P&P
1. LEGAL NOTICE TO BIDDERS (Non-Mandatory)
ITB-26-16-CW - Water Treatment Plant Transfer Pump Station Modifications
Notice is hereby given that the City of Port Orange is soliciting proposals for ITB-26-16-CW - Water
Treatment Plant Transfer Pump Station Modifications. Proposals will be accepted in the City Clerk’s Office, Port Orange City Hall, 1000 City Center Circle, Port Orange, Florida 32129 until 2:30 pm Eastern Standard
Time (EST) on Friday, October 23, 2026, which may be amended by addendum issued by the City. All untimely proposals will not be considered and will be returned to the Respondent unopened. All proposals will be evaluated to ensure they contain all the required forms in order to deem the Respondent responsive or non-responsive.
Proposals will be opened and Respondents names will be read aloud at 2:30 pm EST in the Council
Chambers located on the first floor of City Hall, 1000 City Center Circle, Port Orange, Florida 32129.
There will be a Non-Mandatory Pre-Submittal Conference and site visit for the project at 10:00 am EST on
Monday, September 28, 2026 at Council Chambers, located at the City of Port Orange at 1000 City Center Circle, Port Orange, FL 32129 Microsoft Teams meeting Join: https://teams.microsoft.com/meet/28209974380083
0?p=AfkXoJFvoogu0GJPdX Meeting ID: 282 099 743 800 830 Passcode: cH6CD9qb. All attendees to the Pre-
Submittal Conference MUST sign in. The representative of each Respondent shall be an authorized employee of the Respondent and shall sign in accordingly. Respondents are urged to obtain proposal documents and familiarize themselves with the documents prior to the Pre-Submittal Conference.
DESCRIPTION: Water Treatment Plant Transfer Pump Station Modifications
Bidders must be a commercial entity licensed to do business in the State of Florida and perform the services identified herein. Bidder(s) shall be a certified General Contractor. Bidders must be properly registered and licensed to provide the services identified in the scope of work, by all applicable state and local agencies.
All Invitation to Bid (ITBs) are solicited and will be evaluated on the requirements outlined in the ITB.
Copies of the bid documents, requirements, scope of service and all other pertinent information necessary to submit a complete package may be obtained electronically from the City of Port Orange Purchasing web page at www.port-orange.org/bids.aspx and OpenGov at https://procurement.opengov.com/portal/portorangefl.
All questions must be submitted electronically via https://procurement.opengov.com/portal/portorangefl. Last day for questions will be Friday, October 9, 2026 at 4:00 pm EST.
The Cone of Silence begins with the issuance of the solicitation document and continues until City Council meets to make a final decision on an award. During this time respondents, suppliers, contractors and sub-contractors are prohibited from all communications regarding the solicitation with City staff, City consultants, City legal counsel, City agents, or elected officials. Any respondent who initiates any discussions or attempts to influence a member or members of the aforementioned shall be disqualified from continued participation in the procurement process with regard to that particular solicitation. While the Cone of Silence is in effect, all communications from potential respondents, suppliers, contractors and sub-contractors must be directed to the
Purchasing Division @ purchdiv@port-orange.org.
SPECIAL NOTE: The City of Port Orange has transition from DemandStar to OpenGov for our solicitations.
Since this is a new platform for the City, and for the Bidders submitting, we will be offering two different ways in submitting a bid, which is considered a Hybrid submittal for soliciting projects for a limited time only. The http://www.port-orange.org/bids.aspx https://procurement.opengov.com/portal/portorangefl mailto:purchdiv@port-orange.org timeframe for using this method will end on or about October 1, 2026, for which the City will be requesting electronic bids only. As of right now, Bidders are required to submit BOTH an electronic submittal and a hand-delivered submittal. In addition to submitting electronic bids, bidders are also required to submit a hard copy to the City desiring to provide services, as described herein shall submit sealed bids in addition to submitting one (1) original and one (1) digital (flash drive) version in PDF format, in conformance with the detailed submittal instructions. If Bidders are not familiar with OpenGov, the platform is FREE in creating an account and signing with OpenGov by signing up at https://procurement.opengov.com/login. For more information, please refer to the solicitation documents on this change.
[Remainder of this page left intentionally blank] https://procurement.opengov.com/login
2. SECTION 1 - PURPOSE AND OVERVIEW
The purpose of this Invitation to Bid (ITB) is to solicit competitive bids from Firms or Companies (Bidders) for the Water Treatment Plant Transfer Pump Station Modifications. This project consists of the rehabilitation of the
(3) three Transfer Pump Stations at the Port Orange Water Treatment Plant for the North, Central and South treatment trains. The (2) two existing vertical transfer pumps in each station will be replaced with upgraded associated piping, pipe supports, electrical and concrete pump pads
It is the intent and purpose of the City of Port Orange (City) that this ITB promotes competitive selection. It shall be the Bidder’s responsibility to advise the Purchasing Division if any language, requirements, etc. or any combination thereof, inadvertently restricts or limits the requirements stated in the ITB to a single source.
[Remainder of this page left internationally blank]
3. SECTION 2 - INSTRUCTIONS TO BIDDERS
The City invites bidders to respond to this Initiation to Bid (ITB) for the Water Treatment Plant Transfer Pump
Station Modifications. The City anticipates to awarding to one (1) responsible and responsive bidder. The contract term will be 365-days.
The City of Port Orange is now using OpenGov for soliciting city projects. Since this is a new platform for the
City, and to the Bidders, we will be offering two different ways in submitting a bid, which is considered a
Hybrid submittal for soliciting projects for a limited time only. The timeframe for using this method will end on or about October 1, 2026, for which the City will be requesting electronic bids only. Bidders are required to submit both an electronic submittal and a hand-delivered submittal. In addition to submitting electronic bids, bidders are also required to submit a hard copy to the City desiring to provide services, as described herein shall submit sealed bids in addition to submitting one (1) original and one (1) digit (flash drive) version in PDF format, in conformance with the detailed submittal instructions.
Responses received after the submission deadline will be rejected.
Important Instructions for Electronic Submittal - The City is using a hybrid submittal package. Respondents who are not listed in OpenGov, will need to be register as soon as possible so in order to submit on this project electronical.
Respondents shall create a FREE account with OpenGov by signing up at https://procurement.opengov.com/login. Once you have completed account information, browse back to this page, click on "Submit Response", and follow the instructions to submit the electronic submittal.
It is the respondent's responsibility to ensure they commence their upload submittal timely to meet the submission deadline. The City shall not be responsible for delays caused by an occurrence, including the respondent's network delays, bandwidth issues, internet outages, or technical difficulties.
Important Instructions for Hand-delivery Submittals - In addition to the receiving of electronic responses, Respondents are also responsible for submitting hand-delivered submittals.
Bids must be delivered in a sealed envelope/package and delivered to:
City of Port Orange City Clerk’s Office
Attn: Catrina Wilson, Purchasing Manager
Purchasing Division
1000 City Center Circle
Port Orange, FL 32129
Due to the timing of mail service, the City cautions Bidders to ensure actual delivery of bids to the City prior to the deadline set for receiving bids. Carrier and hand deliveries of bids will be accepted in the City Clerk’s
Office, Port Orange City Hall, 1000 City Center Circle, Port Orange, Florida 32129 until the date and time referenced in the Timeline above or as amended by addendum issued by the City. Bids received after the established deadline shall not be considered.
Bidders are cautioned that they are responsible for delivery to the specific location cited above. Therefore, if your bid, proposal, statement or quotation is delivered by an express mail carrier or by any other means, it is your responsibility to ensure delivery to the above address. The City will not be responsible for deliveries made to any place other than the specified address.
Offers by telephone, email or fax will not be accepted.
All bids will be opened publicly and the names of all Bidders shall be read aloud. All conferences and meetings regarding this ITB are recorded electronically (audio only). The City of Port Orange reserves the right to reject any or all bids or parts of bids if it is in the best interest of the City
OpenGov Technical Support:
For Technical Support, Respondents can reach the OpenGov Service Desk: Chat (preferred): Click the button in the lower right-hand corner of the portal.
Email: https://procurement.opengov.com/login Phone: 1 (605) 336-7176 Hours: Mon-Fri 7am - 10pm ET
Timely Questions Regarding this Solicitation
The questions and answer module of OpenGov is being utilized for this solicitation. Timely questions concerning this solicitation shall be submitted in accordance with the deadline for questions: Friday, October 9, 2026 at 4:00 pm ET. Respondents are instructed not to contact the initiating division directly. Consideration for modification or alternation of the documents contained in this solicitation shall be requested during the specified question period, before the applicable deadline. No oral interpretation of the meaning of the plans, specifications, or other contract documentation shall be considered binding. The City shall be bound by information and statements only when such statements are written and executed under the authority of the
Manager, Purchasing Division. Answers for timely questions will be addressed in the OpenGov questions and answer module and an addendum to those questions will be issued and uploaded onto OpenGov.
Beyond questions and answers, any and all modifications, clarifications, interoperations and supplemental instructions will be in the form of a written addenda which, if issued, will be available for download. All addenda and questions/answers so issued shall become part of the Contract Documentation and receipt shall be acknowledged of any addenda before formally submitting a bid for this project.
Untimely questions are unable to be submitted in the question-and-answer module, thereafter, Respondents raising critical concerns must email purchdiv@port-orange.org. Critical clarifications may be made via addenda; however, untimely questions may not be considered.
ADDENDA
The City will issue responses to inquiries and any other corrections or amendments it deems necessary in written addenda issued prior to the bid due date. Bidders should not rely on any representations, statements or explanations other than those made in this ITB or in any addendum to this ITB. Where there appears to be a conflict between the ITB and any addenda issued, the last addendum issued will prevail. The Bidder should verify prior to submitting a bid that all addenda have been received and reviewed. All addenda will be published on the City Purchasing web page at www.port‐orange.org/bids.aspx and the OpenGov website at https://procurement.opengov.com/login .
The City of Port Orange reserves the right to consider the omission of an acknowledgment of addendum as cause for rejection of the ITB submittal.
mailto:purchdiv@port-orange.org http://www.port‐orange.org/bids.aspx
This provision exists solely for the convenience and administrative efficiency of the City of Port Orange. No Bidder or other third party gains any rights by virtue of this provision or the application thereof, nor shall any Bidder or third party have any standing to sue or cause of action arising therefrom.
CLARIFICATIONS
It is the Bidder’s responsibility to become familiar with and fully informed regarding the terms, conditions and specifications of this ITB. Lack of understanding and/or misinterpretation of any portions of this ITB shall not be cause for withdrawal of your bid after opening or for subsequent protest of award.
MINIMUM QUALIFICATIONS
Bidders shall be licensed to do business in the State of Florida. Submit Sunbiz report showing your company registered as
“Active”. Bidders shall also hold a General Contractor (GC) License.
Bidders must provide a minimum of three (3) verifiable references from similar scopes of work as identified in this ITB on the provided Professional References form (Form 7.8). Failure to provide verifiable references may cause the Bidder to be deemed non‐responsive. The City of Port Orange is not to be used as a reference.
NO LOBBYING
All Bidders are hereby placed on notice that the City of Port Orange Council, City Employees/Staff, nor Members of the
Evaluation Committee (with the exception of the City of Port Orange Purchasing Division personnel designated to receive requests for interpretations or corrections) are not to be lobbied, directly or indirectly either individually or collectively, regarding this ITB. During the entire procurement process, all Bidders and their subcontractors, sub‐consultants, or agents are hereby placed on notice that they are not to contact any persons listed above for such purposes as holding meetings of introduction, dinners, etc. if they intend to submit or have submitted bids for this project. Any Bidder contacting individuals mentioned herein in violation of this warning may automatically be disqualified from further consideration for this ITB.
SCHEDULE OF UNIT PRICING
Schedule of Unit Pricing is to be completed as directed and without modification and returned as part of the ITB submittal prior to the ITB deadline for submission. Failure to fill out the Schedule of Unit Pricing as directed and without modification will negatively affect the evaluation of your bid. If the City has a need to revise the Schedule of Unit Pricing prior to the bid submittal deadline, it will do so in a published addendum. If the City does revise the Schedule of Unit Pricing, bidders must complete and return the City issued revised version of the Schedule of Unit Pricing. If bidder does NOT complete and return the City issued revised version of the Schedule of Unit Pricing their bid submittal will be deemed non-responsive.
EXCEPTIONS TO SPECIFICATIONS
If taking exception to any portion of the ITB specifications, the Bidder must indicate those exceptions as stated on the
Bidder’s Acknowledgement (Form 7.2).
BID SUBMISSION AND WITHDRAWAL
Unless otherwise specified, Bidder shall use the forms supplied by the Purchasing Division. Bids, once opened, become the property of the City, cannot be withdrawn, and will not be returned to the Bidders. Upon opening, bids become subject to public disclosure in accordance with Chapter 119, Florida Statutes.
CORRECTION OF BIDS
Correction of inadvertently erroneous bids shall be permitted up to the time of ITB opening. Bidders shall not be allowed to modify their bids after the opening time and date.
WITHDRAWAL OF BIDS
NO bid shall be withdrawn for a period of one-hundred-twenty (120) days subsequent to the bid opening without the consent of the City of Port Orange. Negligence on the part of the Bidder’s firm in preparing their bid confers no right of withdrawal or modification after the bid has been opened at the appointed time and place by the City of Port Orange. Any such withdrawn bid shall not be resubmitted.
OPENING OF BIDS
Bids will be received until the date and time stated in this ITB and will be publicly opened and read at the place, time and date stated. The City bears no responsibility for the premature opening of a bid not properly addressed and identified.
LITIGATION HISTORY
The City will consider a Bidder’s litigation history information in its review and determination of responsibility. All Bidders are required to disclose to the City all “material” cases filed, pending, or resolved during the last five (5) years prior to the solicitation response due date, whether such cases were brought by or against the Bidder, any parent or subsidiary of the
Bidder, or any predecessor organization. If the Bidder is a joint venture, the information provided should encompass the joint venture (if it is not newly formed for purposes of responding to the solicitation) and each of the entities forming the joint venture. Although the review of a Bidder’s litigation history is an issue of responsibility, the failure to provide litigation history as required in the Evaluation Criteria may result in a recommendation of non‐ responsive by the Purchasing Manager.
DEBARMENT HISTORY
The City will consider a Bidder’s debarment history information in its review and determination of responsibility. All
Bidders are required to disclose to the City all cases of debarment filed, pending, or resolved by the City or other public entity during the last five (5) years prior to the solicitation response due date, whether such actions were brought by or against the Bidder, any parent or subsidiary of the Bidder, or any predecessor organization. If the Bidder is a joint venture, the information provided should encompass the joint venture (if it is not newly formed for purposes of responding to the solicitation) and each of the entities forming the joint venture. Although the review of a Bidder’s debarment history is an issue of responsibility, the failure to provide debarment history as required on the Certification Regarding Debarment, Suspension and Other Responsibility Matters (contained herein) may result in a recommendation of non‐responsive by the
Purchasing Manager.
REJECTION OF BIDS
The City reserves the right to reject any and/or all bids when such rejection is in the best interest of the City.
BIDS MAY BE REJECTED AND/OR BIDDER(S) DISQUALIFIED FOR THE FOLLOWING REASONS:
(a) Failure to update the information on file including address, product, service or business descriptions.
(b) Failure to perform according to contract provisions.
(c) Conviction in a court of law of any criminal offense in connection with the conducting of business.
(d) Evidence of a violation of any federal or state antitrust law based on the submission of bids or proposals, or the awarding of contracts.
(e) Evidence that the Bidder has attempted to give a City employee a gratuity of any kind for the purpose of influencing a recommendation or decision in connection with any part of the City’s purchasing activity.
(f) Other reasons deemed appropriate by the City.
OWNERSHIP OF DOCUMENTS
All documents resulting from this solicitation will become the sole property of the City of Port Orange. The Bidder must meet all requirements for retaining public records and transfer, at no cost, to the City all public records in the possession of the Bidder upon termination of this Agreement and destroy any duplicate public records that are exempt or confidential and exempt from public records disclosure requirements. All records stored electronically must be provided to the City in a format that is compatible with the information technology systems of the City.
AMERICANS WITH DISABILITIES ACT (ADA)
If you need special services provided under the Americans with Disabilities Act, contact the ADA Coordinator in our Human
Resources office at 386‐506‐5560 at least 48 hours before the scheduled event.
REQUIRED DOCUMENTS FOR AWARDED BIDDER
The awarded Bidder shall return all the required post‐award documents within 10 days after the issuance of the Notice of
Intent to Award in order to execute the contract
2.1 Timeline:
Release
Project
Date:
September 18, 2026
Pre-Bid
Meeting and Site
Visit (Non-
Mandatory):
September 28, 2026, 10:00am
Council Chambers, located at the City of Port Orange at 1000 City Center
Circle, Port Orange, FL 32129
Microsoft Teams meeting
Join: https://teams.microsoft.com/meet/28209974380083
0?p=AfkXoJFvoogu0GJPdX
Meeting ID: 282 099 743 800 830
Passcode: cH6CD9qb
Question
Submission
Deadline:
October 9, 2026, 4:00pm
Question
Response
Deadline:
October 14, 2026, 4:00pm
Response
Submission
Deadline:
October 23, 2026, 2:30pm
Council Chambers, located at the City of Port Orange at 1000 City Center
Circle, Port Orange, FL 32129
Microsoft Teams meeting
Join:
https://teams.microsoft.com/meet/218330268894117?p=35seDWfnJCgl7CbdQx
Meeting ID: 218 330 268 894 117
Passcode: w4Mq95Pu
2.2 Procurement Contact
https://teams.microsoft.com/meet/28209974380083 https://teams.microsoft.com/meet/218330268894117?p=35seDWfnJCgl7CbdQx
Catrina Wilson
Purchasing Manager
1395 Dunlawton Ave
Port Orange, FL, 32129
(386) 506-5718 cwilson@port-orange.org
4. SECTION 3 - SCOPE OF WORK
4.1. Water Treatment Plant Transfer Pump Station Upgrades
This project consists of the rehabilitation of the (3) three Transfer Pump Stations at the Port Orange Water
Treatment Plant for the North, Central and South treatment trains. The (2) two existing vertical transfer pumps in each station will be replaced with upgraded associated piping, pipe supports, electrical and concrete pump pads. Restoration including sod replacement, concrete, soil, and gravel replacement in kind will be required at all disturbed areas.
To access the drawings and specification for this solicitation refer to "Attachment A" - Drawings and
"Attachment B" - Specifications attached to this solicitation.
Please refer to this solicitation in order to access all necessary technical documentation and attachments related to this solicitation.
5. SECTION 4 - STANDARD PURCHASE DEFINITIONS
The City will use the following definitions in instructions to Bidders, terms and conditions, special provisions, technical specifications and any other solicitation documents.
1. Addendum is a formal written document, released prior to the public opening that modifies any aspect of a
Solicitation. Plural: Addenda
2. Alternate Bid means multiple bids with substantive variations from the same Bidder in response to a Solicitation.
3. Amendment is a formal written agreement, signed by both parties, that modifies an existing contractual agreement.
4. Appropriate, Appropriated, or Appropriation means the adoption by the City Council of the City of a budget fora fiscal year that includes payments to be made under the Contract during the respective fiscal year.
5. Best Value means the highest overall value to the City based on factors that include, but are not limited to, price, quality, design, and workmanship.
6. Bid is a complete, properly signed response to an Invitation to Bid, which if accepted, would bind the Bidder to perform the resultant Contract.
7. Bid Guaranty (Bid Bond) guarantees that the Bidder (a) will not withdraw the bid within the period specified for acceptance, and (b) will execute a Contract and furnish required bonds and any necessary insurance within the time specified in the Solicitation, unless a longer time is allowed by the City. The guarantee will be returned to the
Bidder upon execution of a Contract
8. Bidder or Proposer is a person, firm, or entity that that submits a Response to a Solicitation. Any Bidder/Proposer may be represented by an agent after submitting evidence demonstrating the agent’s authority. The agent cannot certify as to his own agency status.
9. City means the City of Port Orange.
10. Competitive Negotiation means a method for acquiring goods, services, and construction for public use in which discussions or negotiations may be conducted with responsible offerers who submit Responses through a Request for Proposals, Request for Statements of Qualifications, or Invitation to Negotiate.
11. Competitive (Formal) Solicitation is the process of requesting and receiving two or more sealed bids, proposals, statements of qualifications or replies submitted by responsive Bidders/Proposers in accordance with the terms of a competitive process, regardless of the method of procurement.
12. Competitive Range means the responsive submissions that meet the evaluation criteria and are considered to be reasonably susceptible of award.
13. Construction means the process of building, repairing, improving, and alterations, conversion or extension of building, parks, utilities, streets or other improvements or alterations to real property.
14. Contract is a written agreement or purchase order issued for the purchase of goods or services.
15. Contractor means the person, firm or entity selling goods or services to the City under a Contract.
16. Deliverables means the goods, products, materials, and/or services to be provided to the City by a Bidder.
17. Due Date means the date and time specified for receipt of Responses to a Solicitation.
18. End User is a person, program, agency, or other eligible user who uses a contract to purchase a commodity or contractual service.
19. Evaluation Committee/Team is a temporary group of City personnel who are responsible for the evaluation of proposals, statements of qualifications or replies as part of a Request for Proposals (RFP), Request for Submission of Qualifications (RFSQ), or Invitation to Negotiate (ITN), or competitive grant process.
20. Evaluator is a member of the evaluation committee/team.
21. Goods are supplies, materials, or equipment.
22. Intent to Award is a document, published on DemandStar, that informs the public and respondents of the City’s decision to award a contract pursuant to a previously issued competitive solicitation.
23. Invitation to Bid (ITB) or Bid means a formal request to prospective Bidders requesting pricing for a specified
Good or Service wh
6. SECTION 5 - GENERAL TERMS AND CONDITIONS
These terms and conditions are standard for and apply to all solicitations for commodities or services issued through the City of Port Orange Purchasing Division; however, said terms and conditions are hereby superseded, in whole or in part, by Section 6, Special Requirements/Instructions. Any conflict between Section
5 and 6, then Section 6, shall prevail.
1. ACCEPTANCE BY CITY
The City shall have a reasonable time (but not less than 30 days) after receipt to inspect the goods and services tendered by the Bidder. The City at its option may reject all or any portion of such goods or services which do not, in City’s sole discretion, comply in every respect with all terms and conditions of the contract. The City may elect to reject the entire goods and services tendered even if only a portion thereof is nonconforming. If the
City elects to accept nonconforming goods and services, the City, in addition to its other remedies, shall be entitled to deduct a reasonable amount from the price thereof to compensate the City for the nonconformity.
Any acceptance by the City, even if non‐conditional, shall not be deemed a waiver or settlement of any defect in such goods and services. The material delivered as a result of this solicitation shall remain the property of the seller until a physical inspection and actual usage of the item(s) is made and thereafter deemed acceptable to the satisfaction of the City, in compliance with the terms and specifications contained herein. In the event that the item(s) supplied to the City is/are found to be defective, or does/do not conform to specifications, the City reserves the right to cancel the order upon written notice to the seller and return the item(s) to the seller at the seller's expense.
2. ADDENDA
When specifications are revised, the City of Port Orange Purchasing Division will issue an addendum addressing the nature of the change. Bidders must acknowledge all addenda by completing Form 7.3 Addendum and Change Order Procedure Acknowledgement and include it in the returned response package. Failure to acknowledge the correct number of addenda issued may result in rejection of the response. It is the responsibility of the Bidder to ensure all addenda have been received and reviewed prior to submitting a bid. All addenda shall be posted by the City on DemandStar at www.demandstar.com and the City of Port Orange
Purchasing web page at https://www.port-orange.org/bids.aspx. The City shall issue responses to inquiries and any other corrections or amendments it deems necessary in written addenda issued prior to the solicitation response due date. Bidders should not rely on any representations, statements or explanations other than those made in this solicitation or in any addendum to the solicitation. Where there appears to be a conflict between the solicitation and any addenda issued, the last addendum issued shall prevail.
3. ADDITIONAL GOODS
Products, materials and goods not specifically identified in this bid request may be added to any resultant contract upon mutual consent of the contracting parties. The City reserves the right to add or delete products or materials of similar nature, within the family of products of “ITB Item(s)” and their commodity codes, to those items requested in this bid.
4. ANTI‐COLLUSION STATEMENT
By submitting a response to a formal solicitation, the Bidder affirms that this response is without previous understanding, agreement, or connection with any person, business, or corporation submitting a response for the same materials, supplies, or equipment, and that the response is in all respects fair, and without collusion or fraud. Additionally, Bidder agrees to abide by all conditions of this solicitation and certifies that he/she is authorized to sign the response for the bidding company/firm. In submitting a response to the City of Port
Orange, the Bidder offers and agrees that if the response is accepted, the Bidder shall convey, sell, assign or https://www.demandstar.com/ https://www.port-orange.org/bids.aspx transfer to the City of Port Orange all rights, title and interest in and to all causes of action it may now or hereafter acquire under the Anti‐trust laws of the United States and the State of Florida for price fixing relating to the particular commodities or services purchased or acquired by the City of Port Orange. At the City’s discretion, such assignment shall be made and become effective at the time the City tenders final payment to the
Bidder.
5. APPLICABLE LAWS
In connection with the furnishing of supplies or performance of work under the contract, the Bidder agrees to comply with the Fair Labor Standards Act, Equal Opportunity Employment Act, and all other applicable federal and state laws, regulations and executive orders to the extent that the same may be applicable.
6. ASSIGNMENT
The successful Bidder shall not sell, assign, transfer or convey this contract in whole or in part, without the prior written consent of the City of Port Orange. Any such assignment or transfer shall not release the Bidder from all contractual obligations.
7. AUTHORITY TO CONDUCT BUSINESS IN FLORIDA
A Florida corporation or partnership is required to provide evidence with its response that it is authorized to transact business in Florida and is in good standing with the Florida Department of State. If not with its response, such evidence must be submitted to the City no later than five (5) business days from request of the
Purchasing Manager. A foreign (out‐of‐state) corporation or partnership is required to provide evidence with its response that it is authorized to transact business in Florida and is in good standing with the Florida Department of State. If not with its response, such evidence must be submitted to the City no later than five (5) business days from request of the Purchasing Manager. A joint venture is required to provide evidence with its response that it, or at least one of the joint venture partners, is authorized to transact business in Florida and is in good standing with the Florida Department of State. If not with its response, such evidence must be submitted to the
City no later than five (5) business days from request of the Purchasing Manager. However, the joint venture is required to provide evidence prior to contract execution that the joint venture is authorized to transact business in Florida and provide the City with a copy of the joint venture Agreement. A joint venture is also required to provide with its response a Statement of Authority indicating that the individual submitting the joint venture’s proposal has the legal authority to bind the joint venture. If not with its response, such evidence must be submitted to the City no later than five (5) business days from the request of the Purchasing Manager.
8. AWARDS
Recommendation for award will be considered by the City of Port Orange City Council at the earliest possible regular meeting subsequent to the evaluation process. This ITB is issued in accordance with and shall be governed by the provisions of the City’s Purchasing Manual. The City of Port Orange City Council reserves the right to make award(s) by individual sections, groups, all or none, or a combination thereof, with one or more
Bidders; to reject any and all bids, or to waive any informality or technicality in bids received as deemed to be in the best interest of the City. The City does not award publicly funded contracts to those who knowingly employ unauthorized alien workers in violation of section 274A(e) of the Immigration and Naturalization Act, 8
United States Code s1324a(e). Such employment deprives legal workers of job opportunities. Violation of section 274A(e) shall be grounds for unilateral cancellation of the contract, bid or quote for purchase of services and goods by the City of Port Orange.
9. AWARD AND EXECUTION OF CONTRACT
When a bid received has been determined to be satisfactory, a contract will be awarded, or Purchase Order issued to the lowest responsive and responsible Bidder within the time designated in the contract documents.
The Bidder(s) to whom the award is made shall execute the contract(s) and return it, together with the properly executed bonds and insurance certificates to the City within the time specified.
10. BID RETURNS
Bidders shall return all completed responses to the City of Port Orange at the address set forth in Section 2 of this document on the date and at the time specified. Late submissions will not be accepted and shall be returned to Bidders unopened.
11. BID PROTEST
Any person who is adversely affected by the City’s decision or intended decision shall file with the City
Purchasing Manager a notice of protest in writing within 72 hours after the posting of the notice of decision or intended decision. With respect to a protest of the terms, conditions, and specifications contained in a solicitation, including any provisions governing the methods for ranking bids, proposals, statements, or replies, awarding contracts, reserving rights of further negotiation, or modifying or amending any contract, the notice of protest shall be filed in writing within 72 hours after the posting of the solicitation. Saturdays, Sundays, and state holidays shall be excluded in the computation of the 72‐hour time established herein. The formal written protest shall be filed with the Purchasing Manager in writing within ten (10) days after the date the notice of protest is filed. The formal written protest shall state with particularity the facts and law upon which the protest is based. Failure to file a notice of protest or failure to file a formal written protest shall constitute a waiver of proceedings. Upon receipt of the formal written protest that has been timely filed, the City shall stop the solicitation or contract award process until the subject of the protest is resolved by final City action. However, the City may continue the solicitation or award process, provided the City Manager sets forth in writing particular facts and circumstances which require the continuance of the solicitation or contract award process without delay in order to avoid an immediate and serious danger to the public health, safety, or welfare. The
City shall provide an opportunity to resolve the protest by mutual agreement between the parties. The policy this City has established is as follows:
a. As soon as possible after receipt, the Purchasing Manager shall provide written bid protest to City Manager, City Attorney, Department Head involved, and Supervisor directly involved in the acquisition.
b. Purchasing Manager shall schedule within seven (7) business days, excluding weekends and holidays, a meeting with the above‐mentioned individuals or designee and protestor. The intent of the meeting is to provide a review and/or solution prior to going before Council. After reviewing all relevant information, the City
Manager shall render a decision.
c. If the protestor disagrees, he/she may appeal to the City Council at a formal council meeting. After reviewing the evidence, the City Council will issue their decision. The City Council's decision is final; however, the protestor can appeal the decision to the Circuit Court in Volusia County, Florida within thirty (30) days of the City Council’s final decision. Decisions at all levels shall be in writing to the protester.
12. BID TABULATION
Bidders who wish to receive a copy of the bid tabulation may obtain it via DemandStar at www.demandstar.com or on the City Purchasing web page at www.port‐orange.org/bids.aspx.
13. BIDDER’S PRODUCT OR SERVICES
The Bidder’s product (if applicable) delivered to the City shall be free of all liens, claims or encumbrances, and the Bidder warrants that it has a clear title to the product being delivered.
a. If the Bidder is contracted to provide services, such services shall be fully satisfactory to the City as determined by the City.
b. The Bidder shall provide the City with any data, reports or other information as required and requested by the City to enable it to utilize the product or service furnished by the Bidder.
c. In furnishing the service or product to the City, the Bidder shall comply with all federal, state, county laws, and city rules, regulations and codes and their successors or amendments. Violation of such laws, rules, regulations and codes may be grounds for delaying or reducing the amount due, or in rescinding the contract, https://www.demandstar.com/ https://www.port/ proposal or quote.
14. BONDS
If this solicitation requires submission of bid guarantee and payment and performance bonds, there will be a separate section explaining those requirements. When the Purchasing Manager deems it necessary, bid bonds/deposits shall be prescribed and are advertised in the public notices inviting bids. Responses submitted without the required bid bond or certified check shall be deemed non-responsive. Normally, if a bid bond/deposit is requested, it is in the amount of five percent (5%) of the bid amount.
Depending on the amount and/or nature of the work to be performed, a Payment and Performance Bond may be requested and shall be in an amount equal to one hundred percent (100%) of the total contract amount which will be recorded by the City, at the awarded Bidder’s sole cost and expense, with the Clerk of the Circuit Court, Volusia County, Florida. After recording, the City will furnish to the awarded Bidder the recording information for the bond to evidence that the Bidder has met the requirements of Florida law. The City will bill the cost of recording to the awarded Bidder. Unsuccessful respondents are entitled to the return of their bid bond. A successful respondent shall forfeit any surety required by the Purchasing Manager upon failure of the respondent to enter into a contract within the time specified after the award of bid.
15. CERTIFICATE OF INSURANCE
Upon issuance of a notice of intent to award, the selected Bidder will be required to submit a Certificate of
Insurance showing proof of adequate coverage for professional general liability, errors and omissions and workers’ compensation as identified under the insurance requirements of this solicitation and listing the City of
Port Orange as Additional Insured prior to execution of the contract.
16. CHANGE ORDERS
No oral statement of any person shall modify or otherwise change, or affect the terms, conditions or specifications stated in the resulting contract. All change order requests shall be made in writing by the supplier/contractor for review by the Contract Administrator for the City of Port Orange. No work shall be performed as set forth in the change order until the Bidder receives an executed Purchase Order for the requested change.
17. CHANGE ORDER REQUEST NOTIFICATION
The awarded Bidder is responsible for giving the City of Port Orange, prior to the contract expiration date, at least forty‐five (45) calendar days of advance notice for any anticipated changes in price greater than $25,000, and any changes in time and/or scope of the awarded contract. The Bidder shall not continue to provide services past the contract expiration date unless approved by a written Change Order Notice from the City.
18. CLEAN UP
Upon completion of the delivery of materials, the Bidder shall restore any/all public and private property which may have been damaged during delivery. Restoration is meant to include removal of any spillage or restoring damage to the edge of pavement, sidewalks, driveways, landscaped areas, etc. Bidder shall make repairs consistent with or better than what existed prior to delivery. This shall be understood to include the use of sod or seed and mulch to replace (if necessary) existing grass that has been damaged. If sod is used it shall match the sod present on the effected property. Bidder shall make all repairs and restorations at his/her expense.
19. CONDUCT OF BIDDERS
All Bidders or individuals acting on behalf of a Bidder are hereby prohibited from lobbying or otherwise attempting to persuade or influence any member of the Evaluation Committee, City Council members, or City staff at any time during the course of the solicitation process. The solicitation process shall end upon issuance of the written staff recommendation (Notice of Intent to Award) for selection of a Bidder. All Bidders or individuals acting on behalf of a Bidder are further prohibited from contacting or otherwise attempting to communicate with any member of the staff, Evaluation Committee or City Council members regarding the pending solicitation or its outcome until after the issuance of the written recommendation of the most qualified
Bidder. Until such recommendation is issued in writing, any questions regarding the pending solicitation shall be submitted to the Purchasing Division. Failure to comply with this procedure shall result in rejection/disqualification of said submittal without exception. Contact with staff, City Council members or the
Evaluation Committee during a public meeting shall not be considered a violation of this requirement.
20. CONE OF SILENCE
The Cone of Silence is designed to protect the integrity of the procurement process by shielding it from undue influences prior to the execution of the award. The Cone of Silence is defined as the period beginning with the issuance of the solicitation document and continues through the execution of the award document. During this time Bidders, service providers and the like are prohibited from all communications regarding the solicitation with City staff, City consultants, City legal counsel, City Agents, or elected officials. Any Bidder who initiates any discussions or attempts to influence a member or members of the aforementioned shall be disqualified from continued participation in the procurement process with regard to that particular solicitation.
Exceptions to the Cone of Silence:
• Written communication directed to the Procurement Officer;
• All communications occurring at Pre‐Proposal Conferences;
• Oral presentations before publicly noticed committee meetings;
• Procurement of goods and services for Emergency situations; and
• Contractors already on contract with the City to perform services for the City are allowed discussions necessary for the completion of an existing contract.
21. CONFLICT OF INTEREST
For purposes of determining any possible conflict of interest, all Bidders must disclose if any City of Port
Orange employee is also an owner, corporate officer, or employee of Bidder’s business. No official or employee of the City who exercises any functions or responsibilities in the review or approval of the undertaking or carrying out of the Scope of Work covered by the contract shall voluntarily acquire any personal interest, directly or indirectly, in the contract or proposed contract.
22. CONFLICT OF INSTRUCTIONS
If a conflict exists between the General Terms and Conditions and instructions contained herein, and the Special
Terms and Conditions and instructions contained herein, the Special Terms and Conditions shall govern.
23. CONTRACT OBLIGATION
Except as otherwise stated herein, the City of Port Orange City Council shall approve the contract if greater than $25,000.00 annually. The Mayor or other person authorized by the Mayor must sign the contract before it becomes binding on the City of Port Orange or the Bidder. Department heads are NOT authorized to sign contracts for the City of Port Orange. Binding agreements shall remain in effect until all products and/or services covered by this purchase have been satisfactorily delivered and accepted.
24. CONTRACT RENEWALS
Renewals may be made ONLY by written agreement between the City of Port Orange and the Bidder. Any price escalations are limited to those stated by the Bidder on the original response.
25. COPYRIGHT AND PATENT RIGHTS
Bidder warrants that there has been no violation of copyrights or patent rights in manufacturing, producing and/or selling the item(s) ordered or shipped as a result of this response, and successful Bidder agrees to hold the City harmless from any and all liability, loss or expense by any such violation.
26. COST INCURRED BY BIDDER
All expenses, including costs for required bonds, involved with the preparation and submission of Responses to the City, or any work performed in connection therewith shall be borne by the Bidder. No payment shall be made for any response received, nor for any other effort required of or made by the Bidder prior to commencement of work as defined by the contract approved by the City Council.
27. DAMAGE
Any damage to driveways, irrigation systems, sidewalks, pavement, or landscaping will be evaluated by the
City’s representative and the Bidder. If the Bidder is found to be at fault, all repairs, restitution, or reimbursements to the City must be completed within one week of discovery.
28. DEBARMENT HISTORY
The City will consider a Bidder’s debarment history information in its review and determination of responsibility. All Bidders are required to disclose to the City all cases of debarment filed, pending, or resolved by the City or other public entity during the last five (5) years prior to the solicitation response due date, whether such actions were brought by or against the Bidder, any parent or subsidiary of the Bidder, or any predecessor organization. If the Bidder is a joint venture, the information provided should encompass the joint venture (if it is not newly formed for purposes of responding to the solicitation) and each of the entities forming the joint venture. Although the review of a Bidder’s debarment history is an issue of responsibility, the failure to provide debarment history as required on the Certification Regarding Debarment, Suspension and Other
Responsibility Matters (contained herein) may result in a recommendation of non‐responsive by the Purchasing
Manager.
29. DEFAULT PROVISIONS
In the event of default by the Bidder, the City reserves the right to procure the item(s) bid from other sources and hold the Bidder responsible for excess costs incurred as a result. If a Bidder defaults on a City contract, the
City Council may elect to refrain from doing business with the Bidder for a period of 36 months from the date of default.
30. DELIVERY OF GOODS/SERVICES
All materials are to be delivered F.O.B.; City of Port Orange designated facility. Delivery dates pertaining to this invitation must be clearly stated in the bid form where required and include weekends and holidays. Failure to comply with this requirement may be a cause for disqualification of bid. Unless otherwise specified, delivery at the earliest date is required.