Attachment_1_-_Schedule_of_Unit_Pricing.xlsx

XLSX spreadsheet 209 KB Posted

Attached to
Water Treatment Plant Transfer Pump Station Modifications
Solicitation number
ITB-26-16-CW
Issued by
Volusia County, Florida

About this file

This is a Schedule of Unit Pricing attachment for Invitation to Bid ITB-26-16-CW issued by the Port Orange Water Treatment Plant in Florida. The project involves the rehabilitation of three Transfer Pump Stations serving the North, Central, and South treatment trains. The scope of work includes replacement of six existing vertical transfer pumps (two per station) with upgraded associated piping, pipe supports, electrical systems, and concrete pump pads, along with site restoration including sod, concrete, soil, and gravel replacement in kind at all disturbed areas. The pricing schedule contains 22 line items encompassing mobilization and general conditions, insurance and bonding, demolition, pump installation, materials including DIP piping in 10-inch and 12-inch diameters, valves, electrical work, and project closeout with as-built drawings.

Bidders are required to submit unit prices for each line item, with costs listed as either lump sum (LS), each (EA), cubic yard (CY), linear foot (LF), or square foot (SF). The schedule specifies quantities for each item, including six transfer pump installations, 100 square feet of aluminum grating, 50 linear feet each of 10-inch and 12-inch DIP piping, and associated fittings and valves. Bidders must complete the vendor name and date fields and are cautioned that modifications to Attachment 1 may render their bid non-responsive. The document does not specify pricing amounts, response deadlines, or award dates, as this is the pricing template provided to prospective contractors for completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Untitled

ATTACHMENT 1 SCHEDULE OF UNIT PRICING
ERROR:#VALUE!
TITLE: ITB-26-16-CW _ WATER TREATMENT PLANT TRANSFER PUMP STATION MODIFICATIONS
VENDOR NAME:_________________________________________________________________
DATE:______________________
Modification to "Attachment 1" may cause your bid to be non-responsive
Line ItemDescriptionQuantityUnit of MeasureUnit CostTotal
1Mobilization/General Conditions1LS
2Insurance, Performance and Payment Bond1LS
3Project Closeout/As-built Drawings1LS
4Preconstruction video1LS
5Construction Testing (All)1LS
6General Site Restoration1LS
7Pump Station Demolition (All)1LS
8Transfer Pump Install (Including frame,coupling,motor,freight,startup and operator training6EA
9Pump Leveling Pads6EA
10Concrete Fill4CY
11Bend Base Leveling Pads4EA
12Aluminum Grating100SF
1310" DIP Piping (Including fittings, reducers, flanges, spool pieces, etc.)50LF
1412" DIP Piping (Including fittings, reducers, flanges, spool pieces, etc.)50LF
15Concrete Pipe Supports (varying sizes)1LS
16Stanchion Saddle Adjustable Metal Pipe Supports6EA
1710" DI Check Valve4EA
1812" DI Check Valve2EA
1910" DI Gate Valve4EA
2012" DI Gate Valve2EA
21Electrical (Complete)1LS
22Permitting Allowance1LS

Total