This is a Schedule of Unit Pricing attachment for ITB-26-16-CW, a Water Treatment Plant Transfer Pump Station Modifications project in Port Orange, Florida. The project involves the rehabilitation of three transfer pump stations at the Port Orange Water Treatment Plant, with the replacement of two existing vertical transfer pumps in each station along with associated upgrades to piping, pipe supports, electrical systems, and concrete pump pads. The scope of work encompasses 22 line items including mobilization and general conditions, demolition of existing pump stations, installation of six transfer pumps with frames, couplings, motors, freight, startup and operator training, concrete work, aluminum grating, ductile iron piping in 10-inch and 12-inch sizes, check valves and gate valves, electrical work, and site restoration including sod, concrete, soil, and gravel replacement. Quantities vary by item, ranging from single lump-sum items for mobilization, insurance, bonds, testing, and closeout activities to multiple units for equipment installation (6 pumps and leveling pads) and materials measured in linear feet, cubic yards, and square feet.

Vendors are required to submit unit costs and total costs for each line item on this schedule, with the note that any modification to the attachment may result in a non-responsive bid. The pricing structure requires bidders to establish unit rates for lump-sum general conditions items as well as per-unit pricing for equipment and materials, allowing for transparent cost evaluation across the multiple components of the pump station rehabilitation project. Specific funding sources, contract term, award timeline, and set-aside provisions are not detailed in this pricing schedule document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TITLE: ITB-26-16-CW _ WATER TREATMENT PLANT TRANSFER PUMP STATION MODIFICATIONS

VENDOR NAME:_________________________________________________________________

DATE:______________________

Line Item Description Quantity Unit of Measure Unit Cost Total 1 Mobilization/General Conditions 1 LS

Insurance, Performance and Payment Bond 1 LS

3 Project Closeout/As-built Drawings 1 LS 4 Preconstruction video 1 LS 5 Construction Testing (All) 1 LS 6 General Site Restoration 1 LS 7 Pump Station Demolition (All) 1 LS

Transfer Pump Install (Including frame,coupling,motor,freight,startup and operator training 6 EA

9 Pump Leveling Pads 6 EA 10 Concrete Fill 4 CY 11 Bend Base Leveling Pads 4 EA 12 Aluminum Grating 100 SF

10" DIP Piping (Including fittings, reducers, flanges, spool pieces, etc.) 50 LF

12" DIP Piping (Including fittings, reducers, flanges, spool pieces, etc.) 50 LF

15 Concrete Pipe Supports (varying sizes) 1 LS

Stanchion Saddle Adjustable Metal Pipe Supports 6 EA

17 10" DI Check Valve 4 EA 18 12" DI Check Valve 2 EA 19 10" DI Gate Valve 4 EA 20 12" DI Gate Valve 2 EA 21 Electrical (Complete) 1 LS 22 Permitting Allowance 1 LS

Modification to "Attachment 1" may cause your bid to be non-responsive

Total

ATTACHMENT 1 SCHEDULE OF UNIT PRICING