Waste Diversion Plan

(Anticipated):

Waste Diversion

Report (Final) :

The general info in these gray cells replicates onto the Report tabs.

Project Name:

ECC (estimated construction cost):

Project Manager: ePM/ePMX Project # :

Project Short Description: PM email or phone: gBUILD Project # :

Building Number:

Service Center / Field

Office:

Budget Activity: (list all applicable) RWA # :

Reuse* Recycle or

Compost Donation

Asphalt 0 0 0 n/a

Brick, Masonry, and Tile 0 0 0 n/a

Cardboard 0 0 0 n/a

Carpet, including Padding 0 0 0 n/a

Ceiling tile 0 0 0 n/a

Concrete 0 0 0 n/a

Drywall/ sheetrock (unpainted) 0 0 0 n/a

Metals 0 0 0 n/a

Painted wood, drywall, or plywood 0 0 0 n/a

Reusable items 0 0 0 n/a

Roofing 0 0 0 n/a

Soil, Rock, Land Clearing Debris 0 0 0 n/a

Wood (unpainted) 0 0 0 n/a

Other: ____________________ 0 0 0 n/a

Other: ____________________ 0 0 0 n/a

Other: ____________________ 0 0 0 n/a

0 0 0 n/a

Reuse is encouraged. Please list any items such as cabinets, doors, shelves, bricks, framing lumber, siding, fill material, misc. millwork, etc. planned for reuse.

Reuse Onsite Off-Site Recipient or Salvage/ Deconstruction Company

Submittal Type:Project Waste Management Plan

Actual Waste Diversion Report

To be submitted during Project Close-Out (Reports tab figures auto-populate this green section)

Landfilled (lbs)

Total C&D material weight (Diverted +

Landfilled) (lbs)

Diversion

Rate

Anticipated Waste Diversion Plan

To be filled out and submitted Pre-Construction, with final Construction Documents (PM or contractor populates this pink section)

Target Diversion Rate for each material, by weight (Change to actual target(s) as needed)

Diverted (lbs)

Diversion Method

50%

50%

Total**:

Item

50%

50%

Material*

(see weight conversion factors below)

50%

50%

50%

50%

Reuse Offsite

50%

50%

50%

50%

50%

50%

50%

50%

DocuSign Envelope ID: A1A21171-1EFF-422C-AA8D-5D6C0B562360DocuSign Envelope ID: BD3B9447-A972-4B9F-B6E5-F927FCD5A5DE

Volume-to-Weight Conversion Factor Reference Table

*Only non-hazardous materials need to be included in this document. C&D mandates governing GSA exclude hazardous materials such as asbestos or lead-containing paint.

**At substantial completion, the final number of (a) diverted tons, and (b) total non-hazardous C&D material tons must be reported via the ePMXpress Project Detail tab. ePMXpress powers GSA's tracking metrics.

Concrete: 1 cubic yard = 860 lbs Wood: 1 cubic yard = 169 lbs

Brick, laid flat: 1 flat square foot = 20 lbs

Brick, loose: 1 cubic yard = 3,200 lbs. (1 cubic foot = 120 lbs) Sheetrock (drywall), loose: 1 cubic yard = 393.5 lbs

Mixed (composite) C&D material: 1 cubic yard = 417 lbs

Asphalt or composite roof shingles: 1 cubic yard = 731 lbs

If a hauler reports materials by volume, this table enables conversion to weight, for reporting actual diversion and disposal.

Asphalt paving: 1 cubic yard = 773 lbs

Rock, crushed: 1 cubic yard = 2,570 lbsCeramic tile, scrap, loose: 1 cubic yard = 1,214 lbs

Dirt or sand: 1 cubic yard = 929 lbs

Fiberglass insulation, loose: 1 cubic yard = 17 lbs

DocuSign Envelope ID: A1A21171-1EFF-422C-AA8D-5D6C0B562360DocuSign Envelope ID: BD3B9447-A972-4B9F-B6E5-F927FCD5A5DE

2021-03-16T12:55:38-0700
Digitally verifiable PDF exported from www.docusign.com

File details come from the government source that posted it. Updated .