About this file
This is a Wage Decision Approval document issued by the New Mexico Department of Workforce Solutions, Labor Relations Division, for the City of Gallup's Carbon Coal Road and McKinley County Industrial Park Waterline Project. The project involves installing approximately 2,395 linear feet of 12-inch CL350 ductile iron pipe on Carbon Coal Road and 535 linear feet of 8-inch CL350 ductile iron pipe in the Industrial Park, along with associated components including gate valves, air release valves, fire hydrant assemblies, waterline tie-ins, fittings, trenching, rock excavation, backfilling, and traffic control. The project is located in Gallup, McKinley County, New Mexico, with an estimated total cost of $834,458.63 and an estimated contract award date of December 15, 2025. The wage decision (MC-25-3375-A) was approved on October 15, 2025, and is effective through February 12, 2026. The project is classified as Highway/Utilities (Type A) construction.
The project is funded entirely with federal funds through the US Department of Commerce Economic Development Administration. The wage decision establishes prevailing wage and fringe benefit rates applicable to all workers on this public works project, with rates varying by trade classification and geographic location within New Mexico. Classifications include laborers (ranging from $17.39 to $19.39 base wage with $7.51 fringe), operators (ranging from $23.00 to $42.19 base wage with $6.95 fringe), equipment operators ($38.99 base wage, $17.67 fringe), plumbers/pipefitters ($43.07 base wage, $17.25 fringe), carpenters ($30.89 base wage, $13.26 fringe), and various electrician classifications. All contractors and subcontractors must be registered with the New Mexico Labor and Industrial Division and must comply with these prevailing wage requirements on this project exceeding $60,000.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Wage Decision Approval Summary
1) Project Title: Carbon Coal Road McKinley County Industrial Park Waterline Requested Date: 10/13/2025 Approved Date: 10/15/2025 Approved Wage Decision Number: MC-25-3375-A
Wage Decision Expiration Date: 02/12/2026
2) Physical Location of Jobsite for Project:
Job Site Address: Carbon Coal Road Job Site City: Gallup Job Site County: McKinley
3) Contracting Agency Name (Department or Bureau): City of Gallup Contracting Agency Contact's Name: Frances Rodriguez Contracting Agency Contact's Phone: (505) 863-1334 Ext.
4) Estimated Contract Award Date: 12/15/2025
5) Estimated total project cost: $834,458.63
a. Are any federal funds involved?: Yes - $834,458.63
b. Does this project involve a building?: No
c. Is this part of a larger plan for construction on or appurtenant to the property that is subject to this project?: No
d. Are there any other Public Works Wage Decisions related to this project?: No
e. What is the ultimate purpose or functional use of the construction once it is completed?:
The Carbon Coal Road waterline will consist of installing approximately 2,395 linear feet of 12-inch CL350 ductile iron pipe. Work will also include gate valves, air release valves, a fire hydrant assembly, waterline tie-in, fittings, specials, trenching, rock excavation, backfilling, and traffic control.
The Industrial Park waterline will consist of installing approximately 535 linear feet of 8-inch CL350 ductile iron pipe. Work will also include gate valves, air release valves, a fire hydrant assembly, fire post indicator, high pressure water service meter, fittings, specials, trenching, rock excavation, backfilling, and traffic control.
6) Classifications of Construction:
Classification Type and Cost Total
Description
Highway/Utilities (A) Cost: $834,458.63
The Carbon Coal Road waterline will consist of installing approximately 2,395 linear feet of 12-inch CL350 ductile iron pipe.
Work will also include gate valves, air release valves, a fire hydrant assembly, waterline tie-in, fittings, specials, trenching, rock excavation, backfilling, and traffic control.
The Industrial Park waterline will consist of installing approximately 535 linear feet of 8-inch CL350 ductile iron pipe. Work will also include gate valves, air release valves, a fire hydrant assembly, fire
LABOR RELATIONS DIVISION WWW.DWS.STATE.NM.US
401 Broadway NE Albuquerque, NM 87102 Phone: 505-841-4400 Fax: 505-841-4424
226 South Alameda Blvd Las Cruces, NM 88005 Phone: 575-524-6195 Fax: 575-524-6194
An Equal Opportunity Employer Page 1 of 2 post indicator, high pressure water service meter, fittings, specials, trenching, rock excavation, backfilling, and traffic control.
An Equal Opportunity Employer Page 2 of 2
11.1.2.20 PREVAILING WAGE AND FRINGE BENEFIT AND APPRENTICESHIP
CONTRIBUTION RATES: Pursuant to 11.1.2.13 NMAC, the director of the labor relations division of the department of workforce solutions hereby publishes the 2025 prevailing wage and fringe benefit rates and apprenticeship contributions that will apply to all wage rate decisions issued from January 1, 2025 through December
31, 2025.
TYPE “A” - STREET, HIGHWAY, UTILITY AND LIGHT ENGINEERING
Effective January 1, 2025
A. TYPE A: STREET, HIGHWAY, UTILITY
AND LIGHT ENGINEERING
Trade Classification Base Rate Fringe Rate Apprenticeship
Bricklayer/block layer/stonemason 27.03 10.99
Bricklayer/block layer/stonemason: Curry, DeBaca, Quay and Roosevelt counties
23.10 8.98
Bricklayer/block layer/stonemason: Dona Ana, Otero, Eddy, and Lea counties
29.56 14.10
Carpenter/lather 30.89 13.26
Carpenter: Los Alamos county 37.39 14.18
Cement mason 20.52 7.61
Drywall Finisher/Taper 29.60 9.63
Glazier/Fabricator 22.25 7.40
Ironworker
Ironworker journeyman 28.96 19.51
Probationary ironworker 23.17 19.51
Painter – Commercial 21.00 5.75
Paper Hanger 21.00 5.75
Plumber/pipefitter 43.07 17.25
Electricians – outside classifications: Zone 1
Ground man 27.18 13.32
Equipment operator 38.99 17.67
Lineman 49.25 20.82
Journeyman technician 45.86 19.97
Cable splicer 50.46 21.11
Electricians – outside classifications: Zone 2
Ground man 27.18 13.32
Equipment operator 38.99 17.67
Lineman 49.25 20.82
Journeyman technician 45.86 19.97
Cable splicer 50.46 21.11
Electricians – outside classifications: Los Alamos county
Ground man 27.95 13.34
Equipment Operator 40.11 17.70
Lineman/Technician 50.54 21.14
Journeyman technician 47.19 20.29
Cable Splicer 55.50 22.38
Laborers
Group I – Unskilled 17.39 7.51
Group II – Semi-Skilled 17.39 7.51
Group III – Skilled 18.89 7.51
Group IV - Specialty 19.39 7.51
Operators
Group I 23.00 6.95
Group II 24.00 6.95
Group III 25.50 6.95
Group IV 27.03 6.95
Group V 27.16 6.95
Group VI 27.41 6.95
Group VII 27.62 6.95
Group VIII 28.56 6.95
Group IX 37.81 6.95
Group X 42.19 6.95
Soft Floor Layer 21.00 9.20
Truck drivers
Group I – IX 20.55 9.40