This general wage decision establishes prevailing wage rates for heavy and highway construction projects in ten Illinois counties. Relevant classifications and wages are provided for carpentry, electrical work, ironwork, labor, operating engineering, painting, cement work, truck driving, and other construction specialties. The related solicitation seeks bids for repairs to an army drop zone located in Ipava, Illinois, as described in the attached specification and drawing documents. Interested contractors should reference solicitation W50S7T-20-R-9998 for the Drop Zone Repair opportunity with the Department of the Army Illinois Army National Guard. Submittal date and additional details are specified in the solicitation package.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W50S7T-20-R-9998 - Abstract of Bids.pdf | ||
| W50S7T-20-R-9998 - Pre-Bid Slides - Repair Drop Zone.pdf | ||
| Site Visit Sign In Sheet.pdf | ||
| W50S7T-20-R-9998-Drop Zone Repair Solicitation.pdf | ||
| Attachment 3 - Drawings_Ipava Drop Zone Repair.pdf | ||
| Attachment 1 - AF Form 66_Ipava Drop Zone Repair.pdf | ||
| W50S7T-20-R-9998-Drop Zone Repair Solicitation.pdf | ||
| Attachment 2 - Specifications_Ipava Drop Zone Repair.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
"General Decision Number: IL20200014 06/19/2020
Superseded General Decision Number: IL20190014
State: Illinois
Construction Types: Heavy and Highway
Counties: Fulton, Hancock, Henderson, Knox, McDonough, Mercer, Peoria, Stark, Tazewell and Warren Counties in Illinois.
KNOX, PEORIA, TAZEWELL (N 1/3) & WARREN COUNTIES:
HEAVY CONSTRUCTION PROJECTS (including Sewer & Water Line Construction & Drainage Projects) & HIGHWAY CONSTRUCTION PROJECTS (excluding tunnels, building structures in rest area projects, and railroad construction; bascule, suspension & spandrel arch bridges; bridges designed for commercial navigation; bridges involving marine construction, other major bridges).
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis‐Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above‐mentioned types of contracts entered into by the federal government that are subject to the Davis‐Bacon Act itself, but it does not apply to contracts subject only to the Davis‐Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)‐(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2020 1 01/24/2020
2 04/10/2020 3 05/01/2020 4 05/08/2020 5 06/05/2020 6 06/19/2020
CARP0004‐009 05/01/2020
HENDERSON and MERCER COUNTIES
Rates Fringes
CARPENTER........................$ 33.25 29.94
CARP0174‐003 05/01/2020
STARK COUNTY
Rates Fringes
CARPENTER........................$ 36.65 31.79
CARP0237‐003 05/01/2019
FULTON and TAZEWELL (Southern 2/3) COUNTIES
Rates Fringes
CARPENTER........................$ 35.43 28.77
CARP0237‐013 05/01/2017
FULTON, KNOX, PEORIA, AND TAZEWELL (Northern 1/3) COUNTIES
Rates Fringes
CARPENTER........................$ 34.04 26.47
PILEDRIVERMAN....................$ 35.04 26.47
CARP0270‐010 05/01/2017
MCDONOUGH AND WARREN COUNTIES
Rates Fringes
CARPENTER........................$ 34.54 25.97
PILEDRIVERMAN....................$ 35.54 25.97
CARP0270‐011 05/01/2017
HANCOCK COUNTY
Rates Fringes
CARPENTER........................$ 32.15 25.97
PILEDRIVERMAN....................$ 33.15 25.97
ELEC0034‐006 03/01/2018
FULTON (Fairview, Farmington, Joshua, Canton, Orion, Putnam, Buckheart, Banner, Farmers, Bernadotte, Lewistown, Liverpool, Vermont, Pleasant, Isabel, Waterford, Astoria, Woodland, and Kerton Twps), PEORIA, STARK (West Jersey, Essex, and Valley Twps), & TAZEWELL Counties
Rates Fringes
ELECTRICIAN......................$ 36.51 21.19
ELEC0034‐007 03/01/2018
FULTON (Cass, Deerfield, Ellisville, Harris, Lee, Union, Young, & Hickory Twps), HENDERSON, KNOX, MCDONOUGH (Blandinsville, Prairie City, Emmet, Tennesee, Scotland, Sciota, Bushnell, Chalmers Twps), MERCER (Ohio Grove, North Henderson, and Suez twps), and WARREN Counties
Rates Fringes
ELECTRICIAN......................$ 32.00 19.88
ELEC0051‐002 01/06/2020
FULTON, HANCOCK, HENDERSON, KNOX, MCDONOUGH, MERCER (N.
Henderson & Suez Twps), PEORIA, STARK, TAZEWELL, and WARREN
COUNTIES
Rates Fringes
Line Construction Groundman/Equipment Operator (All crawler type equipment larger than D‐4, 15 ton crane or larger).....$ 46.09 32.5%+6.50 Groundman/Truck Driver......$ 34.95 32.5%+6.50 Lineman and Substation Technician..................$ 51.29 32.5%+6.50
* ELEC0145‐006 06/01/2020
MERCER COUNTY (Except Ohio Grove, North Henderson, and Suez Twps)
Rates Fringes
CABLE SPLICER....................$ 37.30 24.17
ELECTRICIAN......................$ 36.30 24.09
ELEC0145‐007 12/02/2019
MERCER COUNTY (Except North Henderson and Suez Twps)
Rates Fringes
Line Construction Cable Splicer...............$ 45.80 33% + 6.50 Dynamiter...................$ 37.86 33% + 6.50 Groundman Equipment Operator....................$ 35.87 33% + 6.50 Groundman Truck Driver......$ 31.16 33% + 6.50 Groundman...................$ 29.86 33% + 6.50 Lineman, Technician, Heavy Equipment Operator..........$ 45.39 33% + 6.50
FOOTNOTE:
A. PAID HOLIDAYS: Memorial Day, Independence Day, Labor Day, and Thanksgiving Day
ENGI0150‐021 06/01/2019
MERCER COUNTY
Rates Fringes
OPERATOR: Power Equipment Group 1.....................$ 36.00 33.30 Group 2.....................$ 35.00 33.30 Group 3.....................$ 32.35 33.30 Group 4.....................$ 31.30 33.30
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Crane (Friction or Hydraulic, regardless of size or attachments); Tow or Push Boat
GROUP 2: Asphalt Heater‐Planer Unit; Asphalt Paver; Asphalt Paver Screed; Asphalt Plant; Automatic Curbing Machine;
Backfiller (throw bucket); Blastholer Self‐Propelled Rotary Drill or Similar Machines; Boom Tractor or Side Boom;
Boring Machine (Directional, Vertical or Horizontal);
Building Hoist (1,2 or 3 drums); Caisson Auguring Machines;
Central Redi‐Mix Plant; Chip Spreader; Cleaning & Priming Machine; Combination Backhoe Front End Loader; Combination Concrete Finishing Machine and Float; Concrete Breaker or Hydro‐Hammer; Concrete Conveyor or Pump; Concrete Paver;
Concrete Spreader; Concrete Wheel Saw (Large self‐propelled); Crusher (Stone, Concrete, Asphalt, etc.);
Curing‐Tinning Machine; Dipper Dredge Crane man; Dipper Dredge Operator; Dual Purpose Truck (Boom, Winch, etc.);
Excavator; Farm‐Type Tractor Operating Scoop or Scraper or with Power Attachment; Forklift (6000 lb. capacity);
Grader, Motor Grader, Motor Patrol, Auto Grader, Form Grader, Pull Grader, Sub Grader, Elevating Grader; Group Equipment Greaser; Guard Rail Post Driver; Hoists;
Hydraulic Dredge Leverman or Engineer; Hydro‐Vac Truck Mounted or Pull Type, and Similar Equipment; Laser Screed;
Loader (Track, Rubber Tire or Articulated); Locomotive Engineer; Mechanic‐Welder; Mechanical Loaded Log Chippers or Similar Machines; Milling Machine; Mucking Machine; Pile Driver; Pipe Bending; Pug Mill; Road Widener‐Shoulder Spreader; Scraper (self‐propelled); Self‐Propelled Roller or Tire Roller (on Asphalt or Blacktop), Sheep Foot or Pad Foot Compactor; Shovel; Slip Form Paver; Steel Track‐Type Tractor (Dozer, Push Cat, etc.); Transfer or Shuttle Buggy;
Trenching Machine (40 H.P. & over); Work Boat.
GROUP 3: Articulated Off‐Road Haul Unit; Asphalt Booster;
Boiler (Engineer or Fireman); Conveyor Over 20 H.P.;
Distributor; Driver on Truck Crane or Similar Machines;
Elevator; Farm‐Type Tractor (Without Power Attachment);
Fireman & Pump Operator at Asphalt Plant; Forklift (Less than 6000 lb. capacity); Grout Pump; Light Plant;
Mechanical Broom; Mud Jack; Self‐Propelled Roller (Other than listed in Group 2); Straddle Carrier; Trench Machine (Under 40 H.P.).
GROUP 4: Air Compressor (400 C.F.M. or over); Compact Loader (Rubber Tire, Track & Utility); Engine Driven Welding Machine; Mechanical Heater (other than steam boiler); Small Outboard Motor Boat (Safety Boat & Life Boat); Water Pump (More than one well point pump).
ENGI0649‐002 04/01/2018
FULTON, HANCOCK, HENDERSON, KNOX, MCDONOUGH, PEORIA, STARK,
TAZEWELL, and WARREN COUNTIES
Rates Fringes
OPERATOR: Power Equipment Group 1.....................$ 40.02 33.03+A Group 2.....................$ 37.08 33.03+A Group 3.....................$ 32.22 33.03+A
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Cranes: Overhead Cranes; Hydro Crane; Shovels;
Crane type Backfiller; Tower Cranes‐Mobile, Crawler, Stationary; Derricks, Hoist (3 drum); Draglines; Drott Yumbo & similar types considered as Cranes; 360 Degrees Swing Excavator, Backhoe; Derrick Boats; Pile Driver and Skid Rigs; Clam Shell; Locomotive Cranes; Road Pavers (Single Drum, Dual Drum, Tri Batcher); Motor Patrol & Power Blades (Dunmore, Elevating & similar types); Mechanics;
Central Concrete Mixing Plant Operator; Asphalt Batch Plant Operator and Plant Engineer; Gradall; Caisson Rigs; Skimmer Scoop, Koehring Scooper; Dredges (all types); Hoptoe; All Cherry Pickers; Work Boat; Ross Carrier; Helicopter; Dozer;
Tournadozer; Tournapulls (all & similar types); Concrete and all recycle machines, Multiple Unit Earth Movers; 75 cents per hour for each scoop over one; Scoops (all sizes);
Pushcats; Endloaders (all types); Asphalt Surfacing Machine; Slip Form Paver; Rock Crusher; Material Crusher (outside pits and quarries); Screening Plants (outside pits and quarries); Tunnel Boring Machine; Heavy Equipment Greaser (Top Greaser on Spread); CMI, Auto Grade, CMI Belt Placer (3 track & similar types); Side Booms; Starting Engineer on Pipeline or Construction (eleven 11 pieces or more); Asphalt Heater & Planer Combination; Wheel Tractors with Dozer, Hoe or End Loader attachements; CAT Earthwork Compactors and similar types; Blaw Knox Spreader & similar types; Trench Machines; Pump Crete, Belt Crete, Squeeze Crete, Screw Type Pumps & Gypsum; Creter Crane; Concrete Pump Truck; Formless Finishing Machines; Flaherty Spreader or similar types; Screedman on Laydown Machine; Vermeer Concrete Saw; Laser Screed; Span Saw; Dredge Leverman;
Dredge Engineer; Lull or similar type; Hydro‐Boom Truck;
Guard Rail Machine.
GROUP 2: Bulker & Pump; Power Launches; Boring Machine & Pipe Jacking Machine; Dinkeys; Carts, powered haul unit for a boring machine; P‐H one Pass Soil Cement Machines and similar types: Wheel Tractor; Back Fillers; Euclid Loader;
Fork LIfts; Jeep with Ditching Machines or other attachments; Tuneluger; Automatic Cement & Gravel Batching Plants; Mobile Drills Soil Testing and similar types);
Pugmill with Pump; All 1 and 2 Drum Hoists; De‐watering Systems; Straw Blower; Hydro Seeder; Bump Grinders, Self Propelled; Assistant Heavy Equipment Greaser; Apsco Spreader Tractors (Track‐Type w/o Power Units pulling Rollers); Rollers on Asphalt, Brick, or Macadam; Concrete Breakers; Concrete Spreaders; Cement Strippers; Cement Finishing Machines & CMI Texture & Reel Curing Machines;
Vibro‐Tampers & similar types self‐propelled; Mechanical Bull‐Floats; Self‐Propelled Concrete Saw; Truck Mounted Power Saws; Curb Cutters; Mixers over 3 bags to 27E; Winch & Boom Trucks; Tractor pulling Power Blade or Elevating Grader; Porter Rex Rail; Clary Screed; Mule pulling Rollers; Pugmill w/o Pump; Barber Greene or similar Loaders; Track Type Tractor with power unit attached;
Fireman; Spray Machine on paving; Curb Machine; Paved Ditch Machine; Power Broom; Self‐Propelled Sweepers; Self‐ Propelled Conveyors; Power Subgrader; Oil Distributor;
Straight Tractor; Truck Crane Oiler; Truck Type Oilers;
Directional Boring Machine; Horizontal Directional Drill;
Articulating End Dump Vehicles; Starting Engineer (6 to 10 pieces).
GROUP 3: Straight Framed Truck and Truck Mounted Vac Unit, Starting Engineer (3 to 5 pieces); Trac Air Machine w/o attachments; Rollers, 5 tons & under on earth & gravel;
Form Grader; Bulk Cement Plant; Oilers.
‐ Escalated Rate on Crane, Derrick Booms, and Tower Cranes:
Additional $1.00 per hour over scale when Crane or Derrick is positioned 50 ft. or more above adjacent ground level or water level. $.05 per hour, per foot, over 90 feet including jib. $0.02 per hour, per ton ‐ over 50‐ton capacity.
‐ Operating engineers who operate Lattice Boom Crawler Cranes, Lattice Boom Truck Cranes, Telescopic Boom Cranes less than 17.5 Tons, Tower Cranes, Overhead Cranes and have been Certified by hte National Commission for the Certification of Crane Operators on the equipment they operate shall receive $1.60 per hour over scale.
A. On designated Hazardous Waste jobs, operators shall receive:
Level A add $4.00 to the appropriate group rate; Levels B and C add $3.00 to the appropriate group rate; and Level D add $2.00 to the appropriate group rate.
IRON0046‐005 05/01/2020
FULTON COUNTY (Southern tip including Marbletown Astoria, & Summum Twps)
Rates Fringes
IRONWORKER.......................$ 34.14 28.76
IRON0111‐004 07/01/2018
KNOX (Galesburg and area North thereof), MERCER (except Southwest Part), and WARREN (Northwest Part) COUNTIES
Rates Fringes
IRONWORKER.......................$ 31.75 25.52
IRON0112‐004 05/01/2018
FULTON (Eastern 2/3), KNOX (South and East of Galesburg), PEORIA, STARK, and TAZEWELL COUNTIES
Rates Fringes
IRONWORKER.......................$ 37.44 28.07
IRON0577‐006 08/01/2018
FULTON (North of Summum & Marbletown Twps, West 1/3), HANCOCK, HENDERSON, KNOX (West and Southwest of Galesburg), McDONOUGH, MERCER, and WARREN (except Northwest Part) COUNTIES
Rates Fringes
IRONWORKER.......................$ 26.25 23.10
LABO0165‐002 05/01/2019
PEORIA and TAZEWELL (Northwest) COUNTIES
Rates Fringes
LABORER
Group 1.....................$ 30.02 31.92
Group 2.....................$ 30.32 31.92 Group 3.....................$ 30.77 31.92
LABORER CLASSIFICATIONS
GROUP 1 ‐ General Laborer ‐ Laying of temporary gas, oil, air, and water lines; All Laborer Work pertaining to Asphalt and Asphalt Plants if needed; Waterproofing Membrane Systems for bridge decks and waterproofing for box culverts on site; Laying, placing, and installation of all steel casing, corrugated casings, multiple plate and precast concrete and all other material used for casing, tunnels and tunnel lining; Removal of snap ties, the placing and removing and tending of barricades, concrete barricade wall, flares and signal lights; Maintenance of Nelson Heaters; Dirt fill jobs, spotter and grade employee and signal employee; Scaffolding; Temporary Fencing;
Placing of Concrete to grade by any mode or method;
Carpenter Tenders, the conveying, handling, unloading and loading, hoisting, assorting of all lumber, all laborer work required around carpenters including the clean up after carpenters; Horizontal Directional Drill Locator;
Waterproofing with cold stuff; Bricklayer Tenders; Cement Mason Tender; Curing all concrete by hand method; Drive stakes and string lines for all machinery; Concrete Form Dismantlers; Handling and maintaining all lights; flares and flasher flares; Flagman; Landscaping on all jobs, the loading, unloading, distribution, planting, and placing of trees, shrub, sod, and seeding on work covered by the agreement; Covering of Concrete in any manner; High Pressure Nozzle (water blast); Pile Driver Tenders;
Surveyor Helper; Tool Crib Man; Water Carrier; Expansion joint assembler; All other excavating; Deck Hand, Dredge Hand, and Shore Laborer; Unloading and Distributing of Rebars; All Power Operated Tools and Chain Saws; Curb Asphalt Maching Operator; Asphalt Kettlemen and Carriers;
Waterproofing with hot stuff; Cement Men and Sack Shakers;
Chipping Hammer Man; Kettlemen and Carriers or men handling hot stuff; Powder Man Helper; Power Concrete Saw; Power Form Tampers; Rig Men; Signaling and spotting of rigs and equipment; Walk behind concrete breaker; Stripping Concrete Forms with composite crew of laborers and carpenters; all other work not listed below
GROUP 2 ‐ Skilled Laborer ‐ Jackhammer & Drill Operator;
Gunite Pump and Pot Man; Puddlers, Vibrator Men; Wire Fabric Placer; Sandblast Pump and Pot Man; Strike Off Concrete; Unloading, handling and carrying of all creosoted piles, ties, or timer; Concrete Burning Bars; Power Wheelbarrows or Buggies; Asphalt Raker; Bricksetters;
Cutting Torchmen (elec. and acetylene); Men setting lines to level forms; Form Setters; Gunite Nozzle Man and Sandblasting Nozzle Man; Powder Man; Rip‐rapping (by hand)
GROUP 3 ‐ Abestos Abatement Worker; Hazardous Waste Worker (including maintaining of manifest sheet); Lead Base Paint Abatement Worker
LABO0231‐002 05/01/2020
FULTON and TAZEWELL (Southeast) COUNTIES
Rates Fringes
LABORER..........................$ 33.50 30.17
LABO0231‐005 05/01/2020
HANCOCK AND MCDONOUGH COUNTIES
Rates Fringes
LABORER..........................$ 29.50 26.85
LABO0309‐003 01/01/2019
MERCER COUNTY
Rates Fringes
LABORER
GROUP 1.....................$ 28.13 21.07
GROUP 2.....................$ 28.63 21.07
GROUP 3.....................$ 29.26 21.07
LABORER CLASSIFICATIONS
GROUP 1: Flagman, Dumpman, Spotter, Broom Man, Removal of Trees, Fencing Laborers, Cleaning of Forms or Lumber (In Bone Yard), Moving and/or Maintenance of Flares and Barricades, Operation of all Hand, Electric, Air, Hydraulic, or Mechanically Powered Tools Under the Jurisdiction of the Laborers; Including Jackhammers, Tampers; Air Spades, Augers, Concrete Saws, Chains Saws, Utility Saws, Rock Drills, Vibrators, Mortar Mixer, Power and Hand Saw (When Cleaning Timber), General Laborers (Not Elsewhere Covered), Craft‐Tender, Material Checker, Material Handler, Form Handler, Concrete Dumper, Puddler, Explosives Handler, Center Strip, Reinforcing in Concrete, Wire Mesh Handler and Installer, Prime Mover or Any Mechanical Device Taking the Place of Concrete Buggy or Wheel‐Barrow, Sandpoint Setter, Asphalt Kettleman, Sheeting Hammer Drivers, Laying and Joining of telephone Conduit, Gas Distribution Men, Pipe Setter On laterals, Drain Tiles, Culvert Pipe, and Storm Sewer Catch Basin Leads, Catch Basins, Manholes, Batch Dumpers, Tank Cleaners, Cofferdam Worker, Bankman On Floating Plant, Jointman with Pipelayers. Back‐Up Man (Corker, Joint Maker) With Pipe Setter on Sewer and Water Mains, Batterboard Man or Laser Operator on Sewer and Water Main, Laborer in Ditch, or Tunnel, on Sewer or Water Mains and Telephone Conduit, Cutters, Burners, Torchman, Gravel Box Man, Asphalt Plant Laborer, Concrete Plant Laborer, Deck Hand, Unloading of Steel and Rebar, Laser Beam Operator, Wrecking Laborers
GROUP 2 ‐ Asphalt Raker or Luteman, Head Form Setter, Head Dynamite Man (Powderman) Head String or Wireline Man (On Paving), Pipe Setter On Sewer or Water Main, Gunnite Nozzie Man, Asphalt Or Concrete Curb Machine Operator, Head Grade Man, Head Tunnel Miner, Concrete Burning Machine Operator, Coring Machine Operator, Welder, Asbestos Abatement and Hazardous Waste Workers
GROUP 3 ‐ Concrete Specialist
LABO0538‐001 05/01/2019
HENDERSON, KNOX, WARREN, AND STARK (WEST) COUNTIES
Rates Fringes
LABORERS
General Laborer.............$ 29.49 24.83 Skilled Laborer.............$ 30.49 24.83
LABORER CLASSIFICATIONS
General Laborer: All classifications not listed below.
Skilled Laborer: Flaggers; Traffic Control and all associated work; Handling of materials treated with oil, creosote, asphalt and/or foriegn material harmful to skin or clothing; Track Laborers; Chloride Handlers; Unloading and Laborers with Steel Workers and Re‐bars; Concrete Workers (wet); Batch Dumpers; Mason Tenders; Kettle and Tar Men;
Plastic Installers; Scaffold Workers; Motorized buggies or motorized unit used for wet concrete or handling of building materials; Laborers with de‐watering systems;
Sewer workers plus depth; Vibrator Operators; Motor Mixer Operators; Cement Silica, clay, fly ash, lime and plasters, handlers (bulk or bag); Cofferdam Workers plus depth;
Concrete paving, placing, cutting and tying of reinforcing;
Deckhand, dredge hand and shore laborers; Backmen on floating plant; Asphalt Workers with machine and layers;
Grade Checker; Power Tools; Stripping of all concrete forms except paving forms, dumpmen and spotters, when necessary;
Caisson Workers plus depth; Gunnite Nozzle Men; Tunnel Helpers in free air; Rod and Chainmen; Welders, Cutters, Burners, and Torchmen; Chainsaw Operator; Paving Breaker, Jackhammer and Drill Operator, Layout man and /or Tile Layer; Steel Form Setters ‐ street and highway, Air Tamping Hammerman; Signalman on Crane Concrete Saw Operator;
Screedman on Asphalt Pavers; Front End Man on Chip Spreader; Multiple Concrete Duct; Luteman, Asphalt Raker;
Curb Asphalt Machine Operator.
LABO0996‐003 05/01/2018
STARK COUNTY (East)
Rates Fringes
LABORER
GROUP 1.....................$ 32.73 23.74
GROUP 2.....................$ 33.73 23.74
LABORER CLASSIFICATIONS
GROUP 1: All classifications not listed below
GROUP 2: Dynamite Man; Asbestos Abatement Worker and Hazardous Waste Worker; and Lead Base Paint Worker
PAIN0030‐010 07/01/2018
BUREAU, FORD, HANCOCK, LA SALLE, LIVINGSTON, MCDONOUGH, MCLEAN,
PUTNAM AND STARK COUNTIES
Rates Fringes
PAINTER
Brush, Roller, Pressure Roller, Spray, Airless Spray, Sandblasting, Taper, Drywall
Taper/Finisher, Structural Steel, and Bridges..........$ 36.85 21.80
PAIN0157‐001 07/01/2018
FULTON, MARSHALL, MASON, PEORIA, SCHUYLER, TAZEWELL AND
WOODFORD COUNTIES
Rates Fringes
PAINTER
Brush, Spray, Pressure Roller, Sandblasting, Bridges, & New Structural Steel Work..................$ 36.85 21.80
PAIN0502‐003 05/01/2017
HENDERSON, KNOX, MERCER, and WARREN COUNTIES
Rates Fringes
PAINTER
Bridges.....................$ 30.42 14.25 Brush and Roller............$ 28.42 14.25 Spray, Structural Steel, & Sandblasting................$ 28.92 14.25
PLAS0018‐011 05/01/2017
FULTON (Northwestern Part), KNOX, MERCER (Southeastern Corner), and WARREN COUNTIES
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 29.00 20.10
PLAS0018‐012 06/01/2015
STARK COUNTY
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 36.70 22.08
PLAS0018‐013 05/01/2017
FULTON (Except Northwest Part), PEORIA, and TAZEWELL COUNTIES
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 32.11 25.52
PLAS0018‐028 05/01/2016
HANCOCK, HENDERSON (Southern half), and MCDONOUGH COUNTIES
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 28.64 24.57
PLAS0018‐037 01/01/2020
HENDERSON (Northern Half) and MERCER (Except Southeastern Corner) COUNTIES
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 28.52 24.04
TEAM0371‐003 05/01/2019
MERCER COUNTY
Rates Fringes
TRUCK DRIVER
Group 1.....................$ 38.17 19.85 Group 2.....................$ 38.71 19.85 Group 3.....................$ 39.01 19.85 Group 4.....................$ 39.34 19.85 Group 5.....................$ 40.39 19.85
CLASSIFICATIONS:
GROUP 1: Drivers on 2 axles hauling less than 9 tons; air compressor & welding machines and brooms, including those pulled by separate units; Truck Driver Helper, warehouse employees; Mechanic Helpers; greasers and tiremen; pick‐up trucks when hauling material, tools, or workers to and from and on the job site; and forklifts up to 6,000 lb capacity.
GROUP 2: 2 or 3 axles hualing more than 9 tons but hauling less than 16 tons; A‐frame winch trucks; hydrolift trucks;
Vactor Trucks or similar equipment when used for transportation purposes; Forklift over 6,000 lb.capacity;
winch trucks; and four axle combiation units.
GROUP 3: 2, 3 or 4 Axles hauling 16 tons or more; 5‐Axles or more combination units; drivers on water pulls; articulated dump trucks; mechanics and working forepersons.
GROUP 4: Low Boy and Oil Distributors.
GROUP 5: Drivers who require special protective clothing while employed on hazardous waste work.
TEAM0627‐002 05/01/2019
FULTON, HANCOCK, HENDERSON, KNOX, MCDONOUGH, PEORIA, STARK,
TAZEWELL, and WARREN COUNTIES
Rates Fringes
TRUCK DRIVER
GROUP 1.....................$ 38.06 19.62
GROUP 2.....................$ 38.61 19.62
GROUP 3.....................$ 38.87 19.62
GROUP 4.....................$ 39.23 19.62
GROUP 5.....................$ 40.27 19.62
CLASSIFICATIONS:
GROUP 1: Drivers on 2 axles hauling less than 9 tons; air compressor & welding machines and brooms, including those pulled by separate units; Truck Driver Helper, warehouse employees; Mechanic Helpers; greasers and tiremen; pick‐up trucks when hauling material, tools, or workers to and from and on the job site; and forklifts up to 6,000 lb capacity.
GROUP 2: 2 or 3 axles hualing more than 9 tons but hauling less than 16 tons; A‐frame winch trucks; hydrolift trucks;
Vactor Trucks or similar equipment when used for transportation purposes; Forklift over 6,000 lb.capacity;
winch trucks; and four axle combiation units.
GROUP 3: 2, 3 or 4 Axles hauling 16 tons or more; 5‐Axles or more combination units; drivers on water pulls; articulated dump trucks; mechanics and working forepersons.
GROUP 4: Low Boy and Oil Distributors.
GROUP 5: Drivers who require special protective clothing while employed on hazardous waste work.
WELDERS ‐ Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis‐Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health‐related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health‐related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198‐005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non‐union rates. Example: SULA2012‐007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG‐OH‐0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis‐Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION"