Questions and Answers Eaton UPS Update2.pdf
PDF 463 KB Posted
- Attached to
- Brand Name Only: EATON 150kVA & 300kVA UPS
- Solicitation number
- W91ZLK24Q0014
About this file
This document contains Questions and Answers related to a federal contract opportunity for the decommissioning and replacement of Vycon flywheel battery cabinets and Eaton UPS systems at two buildings at Aberdeen Proving Ground in Maryland.
The key details are: The government is seeking a contractor to decommission and remove 3 existing Vycon flywheel units, deliver and install 3 new battery cabinets (1 for a 150kVA UPS and 2 for 300kVA UPS), and wire the new cabinets to the existing UPS systems. The government will not provide site photos due to security concerns, but has confirmed there is a loading dock, space to store the units on-site, and no obstacles to the UPS room. The contractor must specify an estimated delivery date, unit prices, and any commercial warranties. Award will be made to the lowest priced, technically acceptable offer. Quotes are due by August 30, 2023 and the contract will be firm-fixed price.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SAM EATON UPS SOW Revised.pdf | ||
| Questions and Answers Eaton UPS.pdf | ||
| SAM JA_Redacted.pdf | ||
| SAM EATON UPS SOW.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
- What is the desired runtime of each UPS? – 30 seconds depending on the load
- It’s very hard/almost impossible to estimate the electrical/rigging/labor required to replace the units without a site visit. Can you provide pictures of the site and each UPS room? – Due to security concerns, this will not be possible.
- Is there a loading dock for delivery of the units? - Yes
- Is there room to store the units on site before install? - Yes
- Are the units on the first floor? If not, is there an elevator available for use? – On the first floor
- Are there any obstacles between the loading dock/entry point and UPS room(s)? (steps, ramps, narrow doors, etc.) - No