AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to fix CLIN descriptions and remove w ar hazard CLINs.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 35
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 06-Apr-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W91QVN22R0021
X 9B. DATED (SEE ITEM 11)
05-Apr-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
06-Apr-2022
CODE
411TH CONTRACTING SUPPORT BRIGADE, KOREA
HUMPHREYS CONTRACTING DIVISION
UNIT 15289
APO AP 96271-5584
UNITED STATES
W91QVN 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W91QVN22R0021
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
SUPPLIES OR SERVICES AND PRICES
Global Changes
CLIN 0001 -- CLIN 4038
The PSC code has changed from S208 to S222.
The NAICS code has changed from 221320 to 562119.
CLIN 0005
The CLIN extended description has changed from:
REQUIREMENT CLIN. Removal/transportation of accumulated sediment/soil from wash rack (approx. 0.5-1 cm/ea).POP: 1 JUL 2022 through 31 MAY 2023
To:
Removal/transportation of accumulated sediment/soil from wash rack (approx. 0.5-1 cm/ea).POP: 1 JUL 2022 through 31 MAY 2023
CLIN 0006
(approx. 1-1.5 cm/ea).POP: 1 JUL 2022 through 31 MAY 2023
Removal/transportation of accumulated sediment/soil from wash rack (approx. 1-1.5 cm/ea).POP: 1 JUL 2022 through 31 MAY 2023
CLIN 0010
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 8-15 cm/ea).POP: 1 JUL 2022 through 31 MAY 2023
Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 8-15 cm/ea).POP: 1 JUL 2022 through 31 MAY 2023
CLIN 0011
from oil/water separator (approx. 15-20 cm/ea).POP: 1 JUL 2022 through 31 MAY 2023
(approx. 15-20 cm/ea).POP: 1 JUL 2022 through 31 MAY 2023
CLIN 0012
from oil/water separator (approx. 20-30 cm/ea).POP: 1 JUL 2022 through 31 MAY 2023
(approx. 20-30 cm/ea).POP: 1 JUL 2022 through 31 MAY 2023
CLIN 0016
REQUIREMENT CLIN. Removal/transportation of sludge from wastewater treatment plant and lift station.POP: 1 JUL 2022 through 31 MAY 2023
Removal/transportation of sludge from wastewater treatment plant and lift station.POP: 1 JUL 2022 through 31 MAY 2023
CLIN 0017
REQUIREMENT CLIN. Removal/transportation of sludge from RLFC and Camp Stanley to Camp Casey WWTP.POP: 1 JUL 2022 through 31 MAY 2023
Removal/transportation of sludge from RLFC and Camp Stanley to Camp Casey WWTP.POP: 1 JUL 2022 through 31 MAY 2023
CLIN 0018
REQUIREMENT CLIN. Removal/disposal of de-watering sludge from wastewater treatment plant.POP: 1 JUL 2022 through 31 MAY 2023
Removal/disposal of de-watering sludge from wastewater treatment plant.POP: 1 JUL 2022 through 31 MAY 2023
CLIN 0019
REQUIREMENT CLIN. Removal/disposal of sediment from equalization tank at wastewater treatment plant.POP: 1 JUL 2022 through 31 MAY 2023
Removal/disposal of sediment from equalization tank at wastewater treatment plant.POP: 1 JUL
CLIN 0020
REQUIREMENT CLIN. Removal/disposal of floated/containerized grease from lift station, sewer manhole, and WWTP.POP: 1 JUL 2022 through 31 MAY 2023
Removal/disposal of floated/containerized grease from lift station, sewer manhole, and WWTP.POP: 1 JUL 2022 through 31 MAY 2023
CLIN 0022
REQUIREMENT CLIN. Removal/transportation of fuel and oil/water mixture from spill site and berm (approx. 4,000 liter/ea).POP: 1 JUL 2022 through 31 MAY 2023
Removal/transportation of fuel and oil/water mixture from spill site and berm (approx. 4,000 liter/ea).POP: 1 JUL 2022 through 31 MAY 2023
CLIN 0023
REQUIREMENT CLIN. Removal/disposal of containerized used cooking oil from cooking facility.POP: 1 JUL 2022 through 31 MAY 2023
Removal/disposal of containerized used cooking oil from cooking facility.POP: 1 JUL 2022
CLIN 0025
REQUIREMENT CLIN. Removal/disposal of wet sludge in aerobic digester at wastewater treatment plant.POP: 1 JUL 2022 through 31 MAY 2023
Removal/disposal of wet sludge in aerobic digester at wastewater treatment plant.POP: 1 JUL
CLIN 0029
REQUIREMENT CLIN. Removal/disposal of float solid grease from lift station and sewage plant (approx. 500 liter/ea).POP: 1 JUL 2022 through 31 MAY 2023
Removal/disposal of float solid grease from lift station and sewage plant (approx. 500 liter/ea).POP: 1 JUL 2022 through 31 MAY 2023
CLIN 0030
REQUIREMENT CLIN. Removal/disposal of wet sludge from sewage treatment plant.POP: 1 JUL 2022 through 31 MAY 2023
Removal/disposal of wet sludge from sewage treatment plant.POP: 1 JUL 2022 through 31 MAY
CLIN 0034
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment from sewage treatment plants, septic tanks, and sewage lift stations.POP: 1 JUL
Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment from sewage treatment plants, septic tanks, and sewage lift stations.POP: 1 JUL 2022 through 31 MAY 2023
CLIN 0035
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment mixed with oil and grease from sludge storage tank at sewage treatment plant.POP:
1 JUL 2022 through 31 MAY 2023
Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment mixed with oil and grease from sludge storage tank at sewage treatment plant.POP: 1 JUL 2022 through 31
MAY 2023
CLIN 0036
REQUIREMENT CLIN. Pick-up, transportation, and disposal of floated solid grease, greasy sludge, and sediment from grease traps.POP: 1 JUL 2022 through 31 MAY 2023
Pick-up, transportation, and disposal of floated solid grease, greasy sludge, and sediment from grease traps.POP: 1 JUL 2022 through 31 MAY 2023
CLIN 0037
REQUIREMENT CLIN. Pick up, transportation, and disposal of contaminated sediment, sand, soil, and other debris from containers (i.e. can, drum) at sewage treatment plants and sewage lift stations.POP: 1 JUL 2022 through 31 MAY 2023
Pick up, transportation, and disposal of contaminated sediment, sand, soil, and other debris from containers (i.e. can, drum) at sewage treatment plants and sewage lift stations.POP: 1 JUL 2022
CLIN 0038
POP: 1 JUL 2022 through 31 MAY 2023
THIS CLIN IS REMOVED PER SOLICITATION AMENDMENT 0001.
CLIN 1005
(approx. 0.5-1 cm/ea).POP: 1 JUN 2023 through 31 MAY 2024 cm/ea).POP: 1 JUL 2023 through 31 MAY 2024
CLIN 1006
(approx. 1-1.5 cm/ea).POP: 1 JUN 2023 through 31 MAY 2024 cm/ea).POP: 1 JUN 2023 through 31 MAY 2024
CLIN 1010
from oil/water separator (approx. 8-15 cm/ea).POP: 1 JUN 2023 through 31 MAY 2024
(approx. 8-15 cm/ea).POP: 1 JUN 2023 through 31 MAY 2024
CLIN 1011
from oil/water separator (approx. 15-20 cm/ea).POP: 1 JUN 2023 through 31 MAY 2024
(approx. 15-20 cm/ea).POP: 1 JUN 2023 through 31 MAY 2024
CLIN 1012
from oil/water separator (approx. 20-30 cm/ea).POP: 1 JUN 2023 through 31 MAY 2024
(approx. 20-30 cm/ea).POP: 1 JUN 2023 through 31 MAY 2024
CLIN 1016
lift station.POP: 1 JUN 2023 through 31 MAY 2024
Removal/transportation of sludge from wastewater treatment plant and lift station.POP: 1 JUN 2023 through 31 MAY 2024
CLIN 1017
Camp Casey WWTP.POP: 1 JUN 2023 through 31 MAY 2024
JUN 2023 through 31 MAY 2024
CLIN 1018
plant.POP: 1 JUN 2023 through 31 MAY 2024
Removal/disposal of de-watering sludge from wastewater treatment plant.POP: 1 JUN 2023 through 31 MAY 2024
CLIN 1019
treatment plant.POP: 1 JUN 2023 through 31 MAY 2024
Removal/disposal of sediment from equalization tank at wastewater treatment plant.POP: 1 JUN
CLIN 1020
sewer manhole, and WWTP.POP: 1 JUN 2023 through 31 MAY 2024
WWTP.POP: 1 JUN 2023 through 31 MAY 2024
CLIN 1022
berm (approx. 4,000 liter/ea).POP: 1 JUN 2023 through 31 MAY 2024 liter/ea).POP: 1 JUN 2023 through 31 MAY 2024
CLIN 1023
facility.POP: 1 JUN 2023 through 31 MAY 2024
Removal/disposal of containerized used cooking oil from cooking facility.POP: 1 JUN 2023
CLIN 1025
treatment plant.POP: 1 JUN 2023 through 31 MAY 2024
Removal/disposal of wet sludge in aerobic digester at wastewater treatment plant.POP: 1 JUN
CLIN 1029
plant (approx. 500 liter/ea).POP: 1 JUN 2023 through 31 MAY 2024 liter/ea).POP: 1 JUN 2023 through 31 MAY 2024
CLIN 1030
JUN 2023 through 31 MAY 2024
Removal/disposal of wet sludge from sewage treatment plant.POP: 1 JUN 2023 through 31
MAY 2024
CLIN 1034
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment from sewage treatment plants, septic tanks, and sewage lift stations.POP: 1 JUN treatment plants, septic tanks, and sewage lift stations.POP: 1 JUN 2023 through 31 MAY 2024
CLIN 1035
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, 1 JUN 2023 through 31 MAY 2024 oil and grease from sludge storage tank at sewage treatment plant.POP: 1 JUN 2023 through 31
MAY 2024
CLIN 1036
sludge, and sediment from grease traps.POP: 1 JUN 2023 through 31 MAY 2024 grease traps.POP: 1 JUN 2023 through 31 MAY 2024
CLIN 1037
REQUIREMENT CLIN. Pick up, transportation, and disposal of contaminated sediment, sand, stations.POP: 1 JUN 2023 through 31 MAY 2024 containers (i.e. can, drum) at sewage treatment plants and sewage lift stations.POP: 1 JUN 2023
CLIN 1038
POP: 1 JUN 2023 through 31 MAY 2024
CLIN 2005
(approx. 0.5-1 cm/ea).POP: 1 JUN 2024 through 31 MAY 2025 cm/ea).POP: 1 JUL 2024 through 31 MAY 2025
CLIN 2006
(approx. 1-1.5 cm/ea).POP: 1 JUN 2024 through 31 MAY 2025 cm/ea).POP: 1 JUN 2024 through 31 MAY 2025
CLIN 2010
from oil/water separator (approx. 8-15 cm/ea).POP: 1 JUN 2024 through 31 MAY 2025
(approx. 8-15 cm/ea).POP: 1 JUN 2024 through 31 MAY 2025
CLIN 2011
from oil/water separator (approx. 15-20 cm/ea).POP: 1 JUN 2024 through 31 MAY 2025
(approx. 15-20 cm/ea).POP: 1 JUN 2024 through 31 MAY 2025
CLIN 2012
from oil/water separator (approx. 20-30 cm/ea).POP: 1 JUN 2024 through 31 MAY 2025
(approx. 20-30 cm/ea).POP: 1 JUN 2024 through 31 MAY 2025
CLIN 2016
lift station.POP: 1 JUN 2024 through 31 MAY 2025
2024 through 31 MAY 2025
CLIN 2017
Camp Casey WWTP.POP: 1 JUN 2024 through 31 MAY 2025
JUN 2024 through 31 MAY 2025
CLIN 2018
plant.POP: 1 JUN 2024 through 31 MAY 2025
Removal/disposal of de-watering sludge from wastewater treatment plant.POP: 1 JUN 2024 through 31 MAY 2025
CLIN 2019
treatment plant.POP: 1 JUN 2024 through 31 MAY 2025
CLIN 2020
sewer manhole, and WWTP.POP: 1 JUN 2024 through 31 MAY 2025
WWTP.POP: 1 JUN 2024 through 31 MAY 2025
CLIN 2022
berm (approx. 4,000 liter/ea).POP: 1 JUN 2024 through 31 MAY 2025 liter/ea).POP: 1 JUN 2024 through 31 MAY 2025
CLIN 2023
facility.POP: 1 JUN 2024 through 31 MAY 2025
Removal/disposal of containerized used cooking oil from cooking facility.POP: 1 JUN 2024
CLIN 2025
treatment plant.POP: 1 JUN 2024 through 31 MAY 2025
CLIN 2029
plant (approx. 500 liter/ea).POP: 1 JUN 2024 through 31 MAY 2025 liter/ea).POP: 1 JUN 2024 through 31 MAY 2025
CLIN 2030
JUN 2024 through 31 MAY 2025
Removal/disposal of wet sludge from sewage treatment plant.POP: 1 JUN 2024 through 31
MAY 2025
CLIN 2034
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, treatment plants, septic tanks, and sewage lift stations.POP: 1 JUN 2024 through 31 MAY 2025
CLIN 2035
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, 1 JUN 2024 through 31 MAY 2025 oil and grease from sludge storage tank at sewage treatment plant.POP: 1 JUN 2024 through 31
MAY 2025
CLIN 2036
sludge, and sediment from grease traps.POP: 1 JUN 2024 through 31 MAY 2025 grease traps.POP: 1 JUN 2024 through 31 MAY 2025
CLIN 2037
REQUIREMENT CLIN. Pick up, transportation, and disposal of contaminated sediment, sand, stations.POP: 1 JUN 2024 through 31 MAY 2025 containers (i.e. can, drum) at sewage treatment plants and sewage lift stations.POP: 1 JUN 2024
CLIN 2038
POP: 1 JUN 2024 through 31 MAY 2025
CLIN 3005
(approx. 0.5-1 cm/ea).POP: 1 JUN 2025 through 31 MAY 2026 cm/ea).POP: 1 JUL 2025 through 31 MAY 2026
CLIN 3006
(approx. 1-1.5 cm/ea).POP: 1 JUN 2025 through 31 MAY 2026 cm/ea).POP: 1 JUN 2025 through 31 MAY 2026
CLIN 3010
from oil/water separator (approx. 8-15 cm/ea).POP: 1 JUN 2025 through 31 MAY 2026
(approx. 8-15 cm/ea).POP: 1 JUN 2025 through 31 MAY 2026
CLIN 3011
from oil/water separator (approx. 15-20 cm/ea).POP: 1 JUN 2025 through 31 MAY 2026
(approx. 15-20 cm/ea).POP: 1 JUN 2025 through 31 MAY 2026
CLIN 3012
from oil/water separator (approx. 20-30 cm/ea).POP: 1 JUN 2025 through 31 MAY 2026
(approx. 20-30 cm/ea).POP: 1 JUN 2025 through 31 MAY 2026
CLIN 3016
lift station.POP: 1 JUN 2025 through 31 MAY 2026
2025 through 31 MAY 2026
CLIN 3017
Camp Casey WWTP.POP: 1 JUN 2025 through 31 MAY 2026
JUN 2025 through 31 MAY 2026
CLIN 3018
plant.POP: 1 JUN 2025 through 31 MAY 2026
Removal/disposal of de-watering sludge from wastewater treatment plant.POP: 1 JUN 2025 through 31 MAY 2026
CLIN 3019
treatment plant.POP: 1 JUN 2025 through 31 MAY 2026
CLIN 3020
sewer manhole, and WWTP.POP: 1 JUN 2025 through 31 MAY 2026
WWTP.POP: 1 JUN 2025 through 31 MAY 2026
CLIN 3022
berm (approx. 4,000 liter/ea).POP: 1 JUN 2025 through 31 MAY 2026 liter/ea).POP: 1 JUN 2025 through 31 MAY 2026
CLIN 3023
facility.POP: 1 JUN 2025 through 31 MAY 2026
Removal/disposal of containerized used cooking oil from cooking facility.POP: 1 JUN 2025
CLIN 3025
treatment plant.POP: 1 JUN 2025 through 31 MAY 2026
CLIN 3029
plant (approx. 500 liter/ea).POP: 1 JUN 2025 through 31 MAY 2026 liter/ea).POP: 1 JUN 2025 through 31 MAY 2026
CLIN 3030
JUN 2025 through 31 MAY 2026
Removal/disposal of wet sludge from sewage treatment plant.POP: 1 JUN 2025 through 31
MAY 2026
CLIN 3034
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, treatment plants, septic tanks, and sewage lift stations.POP: 1 JUN 2025 through 31 MAY 2026
CLIN 3035
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, 1 JUN 2025 through 31 MAY 2026 oil and grease from sludge storage tank at sewage treatment plant.POP: 1 JUN 2025 through 31
MAY 2026
CLIN 3036
sludge, and sediment from grease traps.POP: 1 JUN 2025 through 31 MAY 2026 grease traps.POP: 1 JUN 2025 through 31 MAY 2026
CLIN 3037
REQUIREMENT CLIN. Pick up, transportation, and disposal of contaminated sediment, sand, stations.POP: 1 JUN 2025 through 31 MAY 2026 containers (i.e. can, drum) at sewage treatment plants and sewage lift stations.POP: 1 JUN 2025
CLIN 3038
POP: 1 JUN 2025 through 31 MAY 2026
CLIN 4005
(approx. 0.5-1 cm/ea).POP: 1 JUN 2026 through 31 MAY 2027 cm/ea).POP: 1 JUL 2026 through 31 MAY 2027
CLIN 4006
(approx. 1-1.5 cm/ea).POP: 1 JUN 2026 through 31 MAY 2027 cm/ea).POP: 1 JUN 2026 through 31 MAY 2027
CLIN 4010
from oil/water separator (approx. 8-15 cm/ea).POP: 1 JUN 2026 through 31 MAY 2027
(approx. 8-15 cm/ea).POP: 1 JUN 2026 through 31 MAY 2027
CLIN 4011
from oil/water separator (approx. 15-20 cm/ea).POP: 1 JUN 2026 through 31 MAY 2027
(approx. 15-20 cm/ea).POP: 1 JUN 2026 through 31 MAY 2027
CLIN 4012
from oil/water separator (approx. 20-30 cm/ea).POP: 1 JUN 2026 through 31 MAY 2027
(approx. 20-30 cm/ea).POP: 1 JUN 2026 through 31 MAY 2027
CLIN 4016
lift station.POP: 1 JUN 2026 through 31 MAY 2027
2026 through 31 MAY 2027
CLIN 4017
Camp Casey WWTP.POP: 1 JUN 2026 through 31 MAY 2027
JUN 2026 through 31 MAY 2027
CLIN 4018
plant.POP: 1 JUN 2026 through 31 MAY 2027
Removal/disposal of de-watering sludge from wastewater treatment plant.POP: 1 JUN 2026 through 31 MAY 2027
CLIN 4019
treatment plant.POP: 1 JUN 2026 through 31 MAY 2027
CLIN 4020
sewer manhole, and WWTP.POP: 1 JUN 2026 through 31 MAY 2027
WWTP.POP: 1 JUN 2026 through 31 MAY 2027
CLIN 4022
berm (approx. 4,000 liter/ea).POP: 1 JUN 2026 through 31 MAY 2027 liter/ea).POP: 1 JUN 2026 through 31 MAY 2027
CLIN 4023
facility.POP: 1 JUN 2026 through 31 MAY 2027
Removal/disposal of containerized used cooking oil from cooking facility.POP: 1 JUN 2026
CLIN 4025
treatment plant.POP: 1 JUN 2026 through 31 MAY 2027
CLIN 4029
plant (approx. 500 liter/ea).POP: 1 JUN 2026 through 31 MAY 2027 liter/ea).POP: 1 JUN 2026 through 31 MAY 2027
CLIN 4030
JUN 2026 through 31 MAY 2027
Removal/disposal of wet sludge from sewage treatment plant.POP: 1 JUN 2026 through 31
MAY 2027
CLIN 4034
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, treatment plants, septic tanks, and sewage lift stations.POP: 1 JUN 2026 through 31 MAY 2027
CLIN 4035
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, 1 JUN 2026 through 31 MAY 2027 oil and grease from sludge storage tank at sewage treatment plant.POP: 1 JUN 2026 through 31
MAY 2027
CLIN 4036
sludge, and sediment from grease traps.POP: 1 JUN 2026 through 31 MAY 2027 grease traps.POP: 1 JUN 2026 through 31 MAY 2027
CLIN 4037
REQUIREMENT CLIN. Pick up, transportation, and disposal of contaminated sediment, sand, stations.POP: 1 JUN 2026 through 31 MAY 2027 containers (i.e. can, drum) at sewage treatment plants and sewage lift stations.POP: 1 JUN 2026
CLIN 4038
POP: 1 JUN 2026 through 31 MAY 2027
(End of Summary of Changes)