W91QVN22R0021.pdf
PDF 1 MB Posted
- Solicitation number
- W91QVN22R0021
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W91QVN22R0021 AMD 0001.pdf | ||
| Attachment 2_Tax Exemption Declaration.pdf | ||
| Attachment 1_PWS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
W91QVN22R0021 05-Apr-2022
b. TELEPHONE NUMBER
315-755-2698
8. OFFER DUE DATE/LOCAL TIME
01:00 PM 05 May 2022
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA X ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W91QVN9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
MS. SCHMIDT, REYHAN E.
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED ORX
SMALL BUSINESS
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
411TH CONTRACTING SUPPORT BRIGADE, KOREA
HUMPHREYS CONTRACTING DIVISION
UNIT #15289
APO AP 96271
UNITED STATES
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE W582LE 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
CAMP CASEY
TEL: FAX:
FAX:
TEL: SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$41,500,000
NAICS:
562119
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF144
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W91QVN22R0021
Section SF 1449 - CONTINUATION SHEET
ITEM NO SUPPLIES/SERVICES ESTIMATED
QUANTITY
UNIT UNIT PRICE ESTIMATED AMOUNT
0001 59 Each Septic Tank
FFP
Removal/disposal of sewage and other deposit from septic tank (approx. 2,500 liter/ea).
POP: 1 JUL 2022 through 31 MAY 2023 FOB: Destination
PSC CD: S208
ESTIMATED
NET AMT
UNIT UNIT PRICE ESTIMATED AMOUNT
0002 448 Each Portable Latrine
FFP
Cleaning/removal/disposal of human waste from portable latrine (approx. 300 liter/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0003 140 Each Grease Trap(1-1.5CM)
FFP
Removal/disposal of grease and greasy sludge from grease trap (approx. 1-1.5 cm/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0004 92 Each Grease Trap(1.5-2.5CM)
FFP
Removal/disposal of grease and greasy sludge from grease trap (approx. 1.5-2.5 cm/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0005 22 Each Washrack(0.5-1CM)
FFP
REQUIREMENT CLIN. Removal/transportation of accumulated sediment/soil from wash rack (approx. 0.5-1 cm/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0006 24 Each Washrack(1-1.5CM)
FFP
REQUIREMENT CLIN. Removal/transportation of accumulated sediment/soil from wash rack (approx. 1-1.5 cm/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0007 4 Each Washrack(1.5-2CM)
FFP
Removal/transportation of accumulated sediment/soil from wash rack (approx. 1.5- 2 cm/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0008 4 Each Washrack(2-2.5CM)
FFP
Removal/transportation of accumulated sediment/soil from wash rack (approx. 2-
2.5 cm/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0009 34 Each Separator(3-8CM)
FFP
Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 3-8 cm/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0010 69 Each Separator(8-15CM)
FFP
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 8-15 cm/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0011 46 Each Separator(15-20CM)
FFP
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 15-20 cm/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0012 29 Each Separator(20-30CM)
FFP
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 20-30 cm/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0013 9 Each Water Tank(20-25CM)
FFP
Removal/transportation of oil/water mixture and sediment from water tank (approx. 20-25 cm/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0014 4 Each Mixture Storage Tank
FFP
Removal/transportation of oil/water mixture and sediment from mixture storage tank (approx. 15-20 cm).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0015 48 Each Mixture Holding Chamber
FFP
Removal/transportation of oil/water mixture and sediment from oil/water mixture holding chamber (approx. 10-15 cm).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0016 600,000 Liter Transportation of Sludge in WWTP
FFP
REQUIREMENT CLIN. Removal/transportation of sludge from wastewater treatment plant and lift station.
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0017 1,200,000 Liter Transportation of Sludge from RLFC
FFP
REQUIREMENT CLIN. Removal/transportation of sludge from RLFC and Camp Stanley to Camp Casey WWTP.
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0018 864 Metric Ton
De-watering Sludge
FFP
REQUIREMENT CLIN. Removal/disposal of de-watering sludge from wastewater treatment plant.
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0019 60 Metric
Equalization Tank at WWTP
REQUIREMENT CLIN. Removal/disposal of sediment from equalization tank at wastewater treatment plant.
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0020 147 Metric
Floated/Containerized Grease
REQUIREMENT CLIN. Removal/disposal of floated/containerized grease from lift station, sewer manhole, and WWTP.
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0021 8 Each Sediment from Main Lift Station
FFP
Removal/disposal of sediment from main sewage lift station (approx. 7 ton/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0022 50 Each Spill Site and Berm
FFP
REQUIREMENT CLIN. Removal/transportation of fuel and oil/water mixture from spill site and berm (approx. 4,000 liter/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0023 46,400 Liter Used Cooking Oil
FFP
REQUIREMENT CLIN. Removal/disposal of containerized used cooking oil from cooking facility.
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0024 62 Each Sewage from Lift Stn to WWTP
FFP
Removal/transportation of sewage and other deposit from lift station to wastewater treatment plant (approx. 5,000 liter/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0025 100 Metric
Sludge in Aerobic Digester Tank
REQUIREMENT CLIN. Removal/disposal of wet sludge in aerobic digester at wastewater treatment plant.
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0026 29 Each Septic Tank(WC)
FFP
Removal/disposal of sewage and other deposit from septic tank (approx. 2,500 liter/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0027 168 Each Portable Latrine(WC)
FFP
Cleaning/removal/disposal of human waste from portable latrine (approx. 300 liter/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0028 32 Each Grease Trap(WC)
FFP
Removal/disposal of grease and greasy sludge from grease trap (approx. 500 liter/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0029 12 Each Solid Grease from List Stn
FFP
REQUIREMENT CLIN. Removal/disposal of float solid grease from lift station and sewage plant (approx. 500 liter/ea).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0030 264,000 Liter Wet Sludge from WWTP
FFP
REQUIREMENT CLIN. Removal/disposal of wet sludge from sewage treatment plant.
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0031 488 Metric
Sewage from WWTP and Septic Tank
Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment from sewage treatment plants and septic tanks.
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0032 425 Metric
Sewage from Septic Tank to WWTP
Pick-up and transportation of sewage, sludge, human waste, and sediment from septic tank (Tango, S-3008) to sewage treatment plant (K-16, S-510).
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0033 78 Metric
Solid Grease from Grease Trap
Pick-up, transportation and disposal of floated solid grease, greasy sludge, and sediment from grease traps.
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0034 2,149 Metric
Sewage from WWTP and Lift Station
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment from sewage treatment plants, septic tanks, and sewage lift stations.
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0035 370 Metric
Sludge Storage Tank
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment mixed with oil and grease from sludge storage tank at sewage treatment plant.
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0036 204 Metric
Solid Grease and Grease Water
REQUIREMENT CLIN. Pick-up, transportation, and disposal of floated solid grease, greasy sludge, and sediment from grease traps.
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0037 15 Metric
Sediment from container at WWTP
REQUIREMENT CLIN. Pick up, transportation, and disposal of contaminated sediment, sand, soil, and other debris from containers (i.e. can, drum) at sewage treatment plants and sewage lift stations.
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
Estimated Cost for War Hazard
FFP
POP: 1 JUL 2022 through 31 MAY 2023
UNIT UNIT PRICE ESTIMATED AMOUNT
0039 1 Each Phase-In
FFP
POP: 1 JUN 2022 through 30 JUN 2022
UNIT UNIT PRICE ESTIMATED AMOUNT
1001 59 Each OPTION Septic Tank
FFP
Removal/disposal of sewage and other deposit from septic tank (approx. 2,500 liter/ea).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1002 448 Each OPTION Portable Latrine
FFP
Cleaning/removal/disposal of human waste from portable latrine (approx. 300 liter/ea).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1003 140 Each OPTION Grease Trap(1-1.5CM)
FFP
Removal/disposal of grease and greasy sludge from grease trap (approx. 1-1.5 cm/ea).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1004 92 Each OPTION Grease Trap(1.5-2.5CM)
FFP
Removal/disposal of grease and greasy sludge from grease trap (approx. 1.5-2.5 cm/ea).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1005 22 Each OPTION Washrack(0.5-1CM)
FFP
REQUIREMENT CLIN. Removal/transportation of accumulated sediment/soil from wash rack (approx. 0.5-1 cm/ea).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1006 24 Each OPTION Washrack(1-1.5CM)
FFP
REQUIREMENT CLIN. Removal/transportation of accumulated sediment/soil from wash rack (approx. 1-1.5 cm/ea).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1007 4 Each OPTION Washrack(1.5-2CM)
FFP
Removal/transportation of accumulated sediment/soil from wash rack (approx. 1.5- 2 cm/ea).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1008 4 Each OPTION Washrack(2-2.5CM)
FFP
Removal/transportation of accumulated sediment/soil from wash rack (approx. 2-
2.5 cm/ea).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1009 34 Each OPTION Separator(3-8CM)
FFP
Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 3-8 cm/ea).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1010 69 Each OPTION Separator(8-15CM)
FFP
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 8-15 cm/ea).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1011 46 Each OPTION Separator(15-20CM)
FFP
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 15-20 cm/ea).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1012 29 Each OPTION Separator(20-30CM)
FFP
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 20-30 cm/ea).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1013 9 Each OPTION Water Tank(20-25CM)
FFP
Removal/transportation of oil/water mixture and sediment from water tank (approx. 20-25 cm/ea).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1014 4 Each OPTION Mixture Storage Tank
FFP
Removal/transportation of oil/water mixture and sediment from mixture storage tank (approx. 15-20 cm).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1015 48 Each OPTION Mixture Holding Chamber
FFP
Removal/transportation of oil/water mixture and sediment from oil/water mixture holding chamber (approx. 10-15 cm).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1016 600,000 Liter OPTION Transportation of Sludge in WWTP
FFP
REQUIREMENT CLIN. Removal/transportation of sludge from wastewater treatment plant and lift station.
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1017 1,200,000 Liter OPTION Transportation of Sludge from RLFC
FFP
REQUIREMENT CLIN. Removal/transportation of sludge from RLFC and Camp Stanley to Camp Casey WWTP.
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1018 864 Metric
OPTION De-watering Sludge
REQUIREMENT CLIN. Removal/disposal of de-watering sludge from wastewater treatment plant.
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1019 60 Metric
OPTION Equalization Tank at WWTP
REQUIREMENT CLIN. Removal/disposal of sediment from equalization tank at wastewater treatment plant.
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1020 147 Metric
OPTION Floated/Containerized Grease
REQUIREMENT CLIN. Removal/disposal of floated/containerized grease from lift station, sewer manhole, and WWTP.
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1021 8 Each OPTION Sediment from Main Lift Station
FFP
Removal/disposal of sediment from main sewage lift station (approx. 7 ton/ea).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1022 50 Each OPTION Spill Site and Berm
FFP
REQUIREMENT CLIN. Removal/transportation of fuel and oil/water mixture from spill site and berm (approx. 4,000 liter/ea).
POP: 1 JUN 2023 through 31 MAY 2024
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
1023 46,400 Liter OPTION Used Cooking Oil
FFP
REQUIREMENT CLIN. Removal/disposal of containerized used cooking oil from cooking facility.
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1024 62 Each OPTION Sewage from Lift Stn to WWTP
FFP
Removal/transportation of sewage and other deposit from lift station to wastewater treatment plant (approx. 5,000 liter/ea).
POP: 1 JUN 2023 through 31 MAY 2024
1025 100 Metric Ton OPTION Sludge in Aerobic Digester Tank
FFP
REQUIREMENT CLIN. Removal/disposal of wet sludge in aerobic digester at wastewater treatment plant.
POP: 1 JUN 2023 through 31 MAY 2024
1026 29 Each OPTION Septic Tank(WC)
FFP
Removal/disposal of sewage and other deposit from septic tank (approx. 2,500 liter/ea).
POP: 1 JUN 2023 through 31 MAY 2024
1027 168 Each OPTION Portable Latrine(WC)
FFP
Cleaning/removal/disposal of human waste from portable latrine (approx. 300 liter/ea).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1028 32 Each OPTION Grease Trap(WC)
FFP
Removal/disposal of grease and greasy sludge from grease trap (approx. 500 liter/ea).
POP: 1 JUN 2023 through 31 MAY 2024
1029 12 Each OPTION Solid Grease from List Stn
FFP
REQUIREMENT CLIN. Removal/disposal of float solid grease from lift station and sewage plant (approx. 500 liter/ea).
POP: 1 JUN 2023 through 31 MAY 2024
1030 264,000 Liter OPTION Wet Sludge from WWTP
FFP
REQUIREMENT CLIN. Removal/disposal of wet sludge from sewage treatment plant.
POP: 1 JUN 2023 through 31 MAY 2024
1031 488 Metric Ton OPTION Sewage from WWTP and Septic Tank
FFP
Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment from sewage treatment plants and septic tanks.
POP: 1 JUN 2023 through 31 MAY 2024
1032 425 Metric Ton OPTION Sewage from Septic Tank to WWTP
FFP
Pick-up and transportation of sewage, sludge, human waste, and sediment from septic tank (Tango, S-3008) to sewage treatment plant (K-16, S-510).
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1033 78 Metric
OPTION Solid Grease from Grease Trap
Pick-up, transportation and disposal of floated solid grease, greasy sludge, and sediment from grease traps.
POP: 1 JUN 2023 through 31 MAY 2024
1034 2,149 Metric Ton OPTION Sewage from WWTP and Lift Station
FFP
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment from sewage treatment plants, septic tanks, and sewage lift stations.
POP: 1 JUN 2023 through 31 MAY 2024
1035 370 Metric Ton OPTION Sludge Storage Tank
FFP
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment mixed with oil and grease from sludge storage tank at sewage treatment plant.
POP: 1 JUN 2023 through 31 MAY 2024
1036 204 Metric Ton OPTION Solid Grease and Grease Water
FFP
REQUIREMENT CLIN. Pick-up, transportation, and disposal of floated solid grease, greasy sludge, and sediment from grease traps.
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
1037 15 Metric
OPTION Sediment from container at WWTP
REQUIREMENT CLIN. Pick up, transportation, and disposal of contaminated sediment, sand, soil, and other debris from containers (i.e. can, drum) at sewage treatment plants and sewage lift stations.
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION Estimated Cost for War Hazard
FFP
POP: 1 JUN 2023 through 31 MAY 2024
UNIT UNIT PRICE ESTIMATED AMOUNT
2001 59 Each OPTION Septic Tank
FFP
Removal/disposal of sewage and other deposit from septic tank (approx. 2,500 liter/ea).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2002 448 Each OPTION Portable Latrine
FFP
Cleaning/removal/disposal of human waste from portable latrine (approx. 300 liter/ea).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2003 140 Each OPTION Grease Trap(1-1.5CM)
FFP
Removal/disposal of grease and greasy sludge from grease trap (approx. 1-1.5 cm/ea).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2004 92 Each OPTION Grease Trap(1.5-2.5CM)
FFP
Removal/disposal of grease and greasy sludge from grease trap (approx. 1.5-2.5 cm/ea).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2005 22 Each OPTION Washrack(0.5-1CM)
FFP
REQUIREMENT CLIN. Removal/transportation of accumulated sediment/soil from wash rack (approx. 0.5-1 cm/ea).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2006 24 Each OPTION Washrack(1-1.5CM)
FFP
REQUIREMENT CLIN. Removal/transportation of accumulated sediment/soil from wash rack (approx. 1-1.5 cm/ea).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2007 4 Each OPTION Washrack(1.5-2CM)
FFP
Removal/transportation of accumulated sediment/soil from wash rack (approx. 1.5- 2 cm/ea).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2008 4 Each OPTION Washrack(2-2.5CM)
FFP
Removal/transportation of accumulated sediment/soil from wash rack (approx. 2-
2.5 cm/ea).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2009 34 Each OPTION Separator(3-8CM)
FFP
Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 3-8 cm/ea).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2010 69 Each OPTION Separator(8-15CM)
FFP
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 8-15 cm/ea).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2011 46 Each OPTION Separator(15-20CM)
FFP
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 15-20 cm/ea).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2012 29 Each OPTION Separator(20-30CM)
FFP
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 20-30 cm/ea).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2013 9 Each OPTION Water Tank(20-25CM)
FFP
Removal/transportation of oil/water mixture and sediment from water tank (approx. 20-25 cm/ea).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2014 4 Each OPTION Mixture Storage Tank
FFP
Removal/transportation of oil/water mixture and sediment from mixture storage tank (approx. 15-20 cm).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2015 48 Each OPTION Mixture Holding Chamber
FFP
Removal/transportation of oil/water mixture and sediment from oil/water mixture holding chamber (approx. 10-15 cm).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2016 600,000 Liter OPTION Transportation of Sludge in WWTP
FFP
REQUIREMENT CLIN. Removal/transportation of sludge from wastewater treatment plant and lift station.
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2017 1,200,000 Liter OPTION Transportation of Sludge from RLFC
FFP
REQUIREMENT CLIN. Removal/transportation of sludge from RLFC and Camp Stanley to Camp Casey WWTP.
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2018 864 Metric
REQUIREMENT CLIN. Removal/disposal of de-watering sludge from wastewater treatment plant.
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2019 60 Metric
REQUIREMENT CLIN. Removal/disposal of sediment from equalization tank at wastewater treatment plant.
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2020 147 Metric
REQUIREMENT CLIN. Removal/disposal of floated/containerized grease from lift station, sewer manhole, and WWTP.
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2021 8 Each OPTION Sediment from Main Lift Station
FFP
Removal/disposal of sediment from main sewage lift station (approx. 7 ton/ea).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2022 50 Each OPTION Spill Site and Berm
FFP
REQUIREMENT CLIN. Removal/transportation of fuel and oil/water mixture from spill site and berm (approx. 4,000 liter/ea).
POP: 1 JUN 2024 through 31 MAY 2025
2023 46,400 Liter OPTION Used Cooking Oil
FFP
REQUIREMENT CLIN. Removal/disposal of containerized used cooking oil from cooking facility.
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2024 62 Each OPTION Sewage from Lift Stn to WWTP
FFP
Removal/transportation of sewage and other deposit from lift station to wastewater treatment plant (approx. 5,000 liter/ea).
POP: 1 JUN 2024 through 31 MAY 2025
2025 100 Metric Ton OPTION Sludge in Aerobic Digester Tank
FFP
REQUIREMENT CLIN. Removal/disposal of wet sludge in aerobic digester at wastewater treatment plant.
POP: 1 JUN 2024 through 31 MAY 2025
2026 29 Each OPTION Septic Tank(WC)
FFP
Removal/disposal of sewage and other deposit from septic tank (approx. 2,500 liter/ea).
POP: 1 JUN 2024 through 31 MAY 2025
2027 168 Each OPTION Portable Latrine(WC)
FFP
Cleaning/removal/disposal of human waste from portable latrine (approx. 300 liter/ea).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2028 32 Each OPTION Grease Trap(WC)
FFP
Removal/disposal of grease and greasy sludge from grease trap (approx. 500 liter/ea).
POP: 1 JUN 2024 through 31 MAY 2025
2029 12 Each OPTION Solid Grease from List Stn
FFP
REQUIREMENT CLIN. Removal/disposal of float solid grease from lift station and sewage plant (approx. 500 liter/ea).
POP: 1 JUN 2024 through 31 MAY 2025
2030 264,000 Liter OPTION Wet Sludge from WWTP
FFP
REQUIREMENT CLIN. Removal/disposal of wet sludge from sewage treatment plant.
POP: 1 JUN 2024 through 31 MAY 2025
2031 488 Metric Ton OPTION Sewage from WWTP and Septic Tank
FFP
Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment from sewage treatment plants and septic tanks.
POP: 1 JUN 2024 through 31 MAY 2025
2032 425 Metric Ton OPTION Sewage from Septic Tank to WWTP
FFP
Pick-up and transportation of sewage, sludge, human waste, and sediment from septic tank (Tango, S-3008) to sewage treatment plant (K-16, S-510).
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2033 78 Metric
Pick-up, transportation and disposal of floated solid grease, greasy sludge, and sediment from grease traps.
POP: 1 JUN 2024 through 31 MAY 2025
2034 2,149 Metric Ton OPTION Sewage from WWTP and Lift Station
FFP
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment from sewage treatment plants, septic tanks, and sewage lift stations.
POP: 1 JUN 2024 through 31 MAY 2025
2035 370 Metric Ton OPTION Sludge Storage Tank
FFP
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment mixed with oil and grease from sludge storage tank at sewage treatment plant.
POP: 1 JUN 2024 through 31 MAY 2025
2036 204 Metric Ton OPTION Solid Grease and Grease Water
FFP
REQUIREMENT CLIN. Pick-up, transportation, and disposal of floated solid grease, greasy sludge, and sediment from grease traps.
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
2037 15 Metric
REQUIREMENT CLIN. Pick up, transportation, and disposal of contaminated sediment, sand, soil, and other debris from containers (i.e. can, drum) at sewage treatment plants and sewage lift stations.
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION Estimated Cost for War Hazard
FFP
POP: 1 JUN 2024 through 31 MAY 2025
UNIT UNIT PRICE ESTIMATED AMOUNT
3001 59 Each OPTION Septic Tank
FFP
Removal/disposal of sewage and other deposit from septic tank (approx. 2,500 liter/ea).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3002 448 Each OPTION Portable Latrine
FFP
Cleaning/removal/disposal of human waste from portable latrine (approx. 300 liter/ea).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3003 140 Each OPTION Grease Trap(1-1.5CM)
FFP
Removal/disposal of grease and greasy sludge from grease trap (approx. 1-1.5 cm/ea).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3004 92 Each OPTION Grease Trap(1.5-2.5CM)
FFP
Removal/disposal of grease and greasy sludge from grease trap (approx. 1.5-2.5 cm/ea).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3005 22 Each OPTION Washrack(0.5-1CM)
FFP
REQUIREMENT CLIN. Removal/transportation of accumulated sediment/soil from wash rack (approx. 0.5-1 cm/ea).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3006 24 Each OPTION Washrack(1-1.5CM)
FFP
REQUIREMENT CLIN. Removal/transportation of accumulated sediment/soil from wash rack (approx. 1-1.5 cm/ea).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3007 4 Each OPTION Washrack(1.5-2CM)
FFP
Removal/transportation of accumulated sediment/soil from wash rack (approx. 1.5- 2 cm/ea).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3008 4 Each OPTION Washrack(2-2.5CM)
FFP
Removal/transportation of accumulated sediment/soil from wash rack (approx. 2-
2.5 cm/ea).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3009 34 Each OPTION Separator(3-8CM)
FFP
Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 3-8 cm/ea).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3010 69 Each OPTION Separator(8-15CM)
FFP
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 8-15 cm/ea).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3011 46 Each OPTION Separator(15-20CM)
FFP
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 15-20 cm/ea).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3012 29 Each OPTION Separator(20-30CM)
FFP
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 20-30 cm/ea).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3013 9 Each OPTION Water Tank(20-25CM)
FFP
Removal/transportation of oil/water mixture and sediment from water tank (approx. 20-25 cm/ea).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3014 4 Each OPTION Mixture Storage Tank
FFP
Removal/transportation of oil/water mixture and sediment from mixture storage tank (approx. 15-20 cm).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3015 48 Each OPTION Mixture Holding Chamber
FFP
Removal/transportation of oil/water mixture and sediment from oil/water mixture holding chamber (approx. 10-15 cm).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3016 600,000 Liter OPTION Transportation of Sludge in WWTP
FFP
REQUIREMENT CLIN. Removal/transportation of sludge from wastewater treatment plant and lift station.
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3017 1,200,000 Liter OPTION Transportation of Sludge from RLFC
FFP
REQUIREMENT CLIN. Removal/transportation of sludge from RLFC and Camp Stanley to Camp Casey WWTP.
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3018 864 Metric
REQUIREMENT CLIN. Removal/disposal of de-watering sludge from wastewater treatment plant.
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3019 60 Metric
REQUIREMENT CLIN. Removal/disposal of sediment from equalization tank at wastewater treatment plant.
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3020 147 Metric
REQUIREMENT CLIN. Removal/disposal of floated/containerized grease from lift station, sewer manhole, and WWTP.
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3021 8 Each OPTION Sediment from Main Lift Station
FFP
Removal/disposal of sediment from main sewage lift station (approx. 7 ton/ea).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3022 50 Each OPTION Spill Site and Berm
FFP
REQUIREMENT CLIN. Removal/transportation of fuel and oil/water mixture from spill site and berm (approx. 4,000 liter/ea).
POP: 1 JUN 2025 through 31 MAY 2026
3023 46,400 Liter OPTION Used Cooking Oil
FFP
REQUIREMENT CLIN. Removal/disposal of containerized used cooking oil from cooking facility.
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3024 62 Each OPTION Sewage from Lift Stn to WWTP
FFP
Removal/transportation of sewage and other deposit from lift station to wastewater treatment plant (approx. 5,000 liter/ea).
POP: 1 JUN 2025 through 31 MAY 2026
3025 100 Metric Ton OPTION Sludge in Aerobic Digester Tank
FFP
REQUIREMENT CLIN. Removal/disposal of wet sludge in aerobic digester at wastewater treatment plant.
POP: 1 JUN 2025 through 31 MAY 2026
3026 29 Each OPTION Septic Tank(WC)
FFP
Removal/disposal of sewage and other deposit from septic tank (approx. 2,500 liter/ea).
POP: 1 JUN 2025 through 31 MAY 2026
3027 168 Each OPTION Portable Latrine(WC)
FFP
Cleaning/removal/disposal of human waste from portable latrine (approx. 300 liter/ea).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3028 32 Each OPTION Grease Trap(WC)
FFP
Removal/disposal of grease and greasy sludge from grease trap (approx. 500 liter/ea).
POP: 1 JUN 2025 through 31 MAY 2026
3029 12 Each OPTION Solid Grease from List Stn
FFP
REQUIREMENT CLIN. Removal/disposal of float solid grease from lift station and sewage plant (approx. 500 liter/ea).
POP: 1 JUN 2025 through 31 MAY 2026
3030 264,000 Liter OPTION Wet Sludge from WWTP
FFP
REQUIREMENT CLIN. Removal/disposal of wet sludge from sewage treatment plant.
POP: 1 JUN 2025 through 31 MAY 2026
3031 488 Metric Ton OPTION Sewage from WWTP and Septic Tank
FFP
Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment from sewage treatment plants and septic tanks.
POP: 1 JUN 2025 through 31 MAY 2026
3032 425 Metric Ton OPTION Sewage from Septic Tank to WWTP
FFP
Pick-up and transportation of sewage, sludge, human waste, and sediment from septic tank (Tango, S-3008) to sewage treatment plant (K-16, S-510).
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3033 78 Metric
Pick-up, transportation and disposal of floated solid grease, greasy sludge, and sediment from grease traps.
POP: 1 JUN 2025 through 31 MAY 2026
3034 2,149 Metric Ton OPTION Sewage from WWTP and Lift Station
FFP
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment from sewage treatment plants, septic tanks, and sewage lift stations.
POP: 1 JUN 2025 through 31 MAY 2026
3035 370 Metric Ton OPTION Sludge Storage Tank
FFP
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment mixed with oil and grease from sludge storage tank at sewage treatment plant.
POP: 1 JUN 2025 through 31 MAY 2026
3036 204 Metric Ton OPTION Solid Grease and Grease Water
FFP
REQUIREMENT CLIN. Pick-up, transportation, and disposal of floated solid grease, greasy sludge, and sediment from grease traps.
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
3037 15 Metric
REQUIREMENT CLIN. Pick up, transportation, and disposal of contaminated sediment, sand, soil, and other debris from containers (i.e. can, drum) at sewage treatment plants and sewage lift stations.
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION Estimated Cost for War Hazard
FFP
POP: 1 JUN 2025 through 31 MAY 2026
UNIT UNIT PRICE ESTIMATED AMOUNT
4001 59 Each OPTION Septic Tank
FFP
Removal/disposal of sewage and other deposit from septic tank (approx. 2,500 liter/ea).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4002 448 Each OPTION Portable Latrine
FFP
Cleaning/removal/disposal of human waste from portable latrine (approx. 300 liter/ea).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4003 140 Each OPTION Grease Trap(1-1.5CM)
FFP
Removal/disposal of grease and greasy sludge from grease trap (approx. 1-1.5 cm/ea).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4004 92 Each OPTION Grease Trap(1.5-2.5CM)
FFP
Removal/disposal of grease and greasy sludge from grease trap (approx. 1.5-2.5 cm/ea).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4005 22 Each OPTION Washrack(0.5-1CM)
FFP
REQUIREMENT CLIN. Removal/transportation of accumulated sediment/soil from wash rack (approx. 0.5-1 cm/ea).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4006 24 Each OPTION Washrack(1-1.5CM)
FFP
REQUIREMENT CLIN. Removal/transportation of accumulated sediment/soil from wash rack (approx. 1-1.5 cm/ea).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4007 4 Each OPTION Washrack(1.5-2CM)
FFP
Removal/transportation of accumulated sediment/soil from wash rack (approx. 1.5- 2 cm/ea).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4008 4 Each OPTION Washrack(2-2.5CM)
FFP
Removal/transportation of accumulated sediment/soil from wash rack (approx. 2-
2.5 cm/ea).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4009 34 Each OPTION Separator(3-8CM)
FFP
Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 3-8 cm/ea).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4010 69 Each OPTION Separator(8-15CM)
FFP
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 8-15 cm/ea).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4011 46 Each OPTION Separator(15-20CM)
FFP
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 15-20 cm/ea).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4012 29 Each OPTION Separator(20-30CM)
FFP
REQUIREMENT CLIN. Removal/transportation of oil/water mixture and accumulated sediment from oil/water separator (approx. 20-30 cm/ea).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4013 9 Each OPTION Water Tank(20-25CM)
FFP
Removal/transportation of oil/water mixture and sediment from water tank (approx. 20-25 cm/ea).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4014 4 Each OPTION Mixture Storage Tank
FFP
Removal/transportation of oil/water mixture and sediment from mixture storage tank (approx. 15-20 cm).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4015 48 Each OPTION Mixture Holding Chamber
FFP
Removal/transportation of oil/water mixture and sediment from oil/water mixture holding chamber (approx. 10-15 cm).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4016 600,000 Liter OPTION Transportation of Sludge in WWTP
FFP
REQUIREMENT CLIN. Removal/transportation of sludge from wastewater treatment plant and lift station.
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4017 1,200,000 Liter OPTION Transportation of Sludge from RLFC
FFP
REQUIREMENT CLIN. Removal/transportation of sludge from RLFC and Camp Stanley to Camp Casey WWTP.
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4018 864 Metric
REQUIREMENT CLIN. Removal/disposal of de-watering sludge from wastewater treatment plant.
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4019 60 Metric
REQUIREMENT CLIN. Removal/disposal of sediment from equalization tank at wastewater treatment plant.
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4020 147 Metric
REQUIREMENT CLIN. Removal/disposal of floated/containerized grease from lift station, sewer manhole, and WWTP.
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4021 8 Each OPTION Sediment from Main Lift Station
FFP
Removal/disposal of sediment from main sewage lift station (approx. 7 ton/ea).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4022 50 Each OPTION Spill Site and Berm
FFP
REQUIREMENT CLIN. Removal/transportation of fuel and oil/water mixture from spill site and berm (approx. 4,000 liter/ea).
POP: 1 JUN 2026 through 31 MAY 2027
4023 46,400 Liter OPTION Used Cooking Oil
FFP
REQUIREMENT CLIN. Removal/disposal of containerized used cooking oil from cooking facility.
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4024 62 Each OPTION Sewage from Lift Stn to WWTP
FFP
Removal/transportation of sewage and other deposit from lift station to wastewater treatment plant (approx. 5,000 liter/ea).
POP: 1 JUN 2026 through 31 MAY 2027
4025 100 Metric Ton OPTION Sludge in Aerobic Digester Tank
FFP
REQUIREMENT CLIN. Removal/disposal of wet sludge in aerobic digester at wastewater treatment plant.
POP: 1 JUN 2026 through 31 MAY 2027
4026 29 Each OPTION Septic Tank(WC)
FFP
Removal/disposal of sewage and other deposit from septic tank (approx. 2,500 liter/ea).
POP: 1 JUN 2026 through 31 MAY 2027
4027 168 Each OPTION Portable Latrine(WC)
FFP
Cleaning/removal/disposal of human waste from portable latrine (approx. 300 liter/ea).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4028 32 Each OPTION Grease Trap(WC)
FFP
Removal/disposal of grease and greasy sludge from grease trap (approx. 500 liter/ea).
POP: 1 JUN 2026 through 31 MAY 2027
4029 12 Each OPTION Solid Grease from List Stn
FFP
REQUIREMENT CLIN. Removal/disposal of float solid grease from lift station and sewage plant (approx. 500 liter/ea).
POP: 1 JUN 2026 through 31 MAY 2027
4030 264,000 Liter OPTION Wet Sludge from WWTP
FFP
REQUIREMENT CLIN. Removal/disposal of wet sludge from sewage treatment plant.
POP: 1 JUN 2026 through 31 MAY 2027
4031 488 Metric Ton OPTION Sewage from WWTP and Septic Tank
FFP
Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment from sewage treatment plants and septic tanks.
POP: 1 JUN 2026 through 31 MAY 2027
4032 425 Metric Ton OPTION Sewage from Septic Tank to WWTP
FFP
Pick-up and transportation of sewage, sludge, human waste, and sediment from septic tank (Tango, S-3008) to sewage treatment plant (K-16, S-510).
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4033 78 Metric
Pick-up, transportation and disposal of floated solid grease, greasy sludge, and sediment from grease traps.
POP: 1 JUN 2026 through 31 MAY 2027
4034 2,149 Metric Ton OPTION Sewage from WWTP and Lift Station
FFP
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment from sewage treatment plants, septic tanks, and sewage lift stations.
POP: 1 JUN 2026 through 31 MAY 2027
4035 370 Metric Ton OPTION Sludge Storage Tank
FFP
REQUIREMENT CLIN. Pick-up, transportation, and disposal of sewage, sludge, human waste, and sediment mixed with oil and grease from sludge storage tank at sewage treatment plant.
POP: 1 JUN 2026 through 31 MAY 2027
4036 204 Metric Ton OPTION Solid Grease and Grease Water
FFP
REQUIREMENT CLIN. Pick-up, transportation, and disposal of floated solid grease, greasy sludge, and sediment from grease traps.
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
4037 15 Metric
REQUIREMENT CLIN. Pick up, transportation, and disposal of contaminated sediment, sand, soil, and other debris from containers (i.e. can, drum) at sewage treatment plants and sewage lift stations.
POP: 1 JUN 2026 through 31 MAY 2027
UNIT UNIT PRICE ESTIMATED AMOUNT
OPTION Estimated Cost for War Hazard
FFP
POP: 1 JUN 2026 through 31 MAY 2027
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions JUN 2020 52.203-3 Gratuities APR 1984 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
JUN 2020
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-13 System for Award Management Maintenance OCT 2018 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.212-4 Contract Terms and Conditions--Commercial Items OCT 2018 52.223-3 Hazardous Material Identification And Material Safety Data FEB 2021 52.225-14 Inconsistency Between English Version And Translation Of
Contract
FEB 2000
52.228-4 Workers' Compensation and War-Hazard Insurance Overseas APR 1984 52.232-40 Providing Accelerated Payments to Small Business
Subcontractors
DEC 2013
52.237-2 Protection Of Government Buildings, Equipment, And Vegetation
APR 1984
52.237-3 Continuity Of Services JAN 1991 52.243-1 Alt I Changes--Fixed Price (Aug 1987) - Alternate I APR 1984 52.247-34 F.O.B. Destination NOV 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7015 Notice of Authorized Disclosure of Information for Litigation
Support
MAY 2016
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services
JAN 2021
252.204-7023 Reporting Requirements for Contracted Services. JUL 2021 252.205-7000 Provision Of Information To Cooperative Agreement Holders DEC 1991 252.225-7041 Correspondence in English JUN 1997
252.225-7043 Antiterrorism/Force Protection Policy for Defense Contractors Outside the United States
JUN 2015
252.225-7048 Export-Controlled Items JUN 2013 252.228-7000 Reimbursement for War-Hazard Losses DEC 1991 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
DEC 2018
252.232-7008 Assignment of Claims (Overseas) JUN 1997 252.232-7010 Levies on Contract Payments DEC 2006 252.233-7001 Choice of Law (Overseas) JUN 1997 252.237-7010 Prohibition on Interrogation of Detainees by Contractor
Personnel
JUN 2013
252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012
CLAUSES INCORPORATED BY FULL TEXT
52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR
EXECUTIVE ORDERS--COMMERCIAL ITEMS (SEP 2021)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L.
113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Jul 2018) (Section 1634 of Pub. L. 115-91).
(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (AUG 2020) (Section 889(a)(1)(A) of Pub. L. 115-232).
(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).
(5) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(6) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Public Laws 108-77 and 108-78 (19 U.S.C. 3805 note)).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items: (Contracting Officer check as appropriate.)
X (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (JUN 2020), with Alternate I (Oct 1995) (41 U.S.C. 4704 and 10 U.S.C. 2402).
___ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (JUN 2020) (41 U.S.C. 3509).
___ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (JUN 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)
X (4) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) (Pub. L.
109-282) (31 U.S.C. 6101 note).
___ (5) [Reserved]
X (6) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).
___ (7) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub.
L. 111-117, section 743 of Div. C).
X (8) 52.209-6, Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (JUN 2020) (31 U.S.C. 6101 note).
X (9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018) (41 U.S.C. 2313).
____ (10) [Reserved]
____ (11) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (SEP 2021) (15 U.S.C. 657a).
____ (12) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (SEP 2021) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).
____ (13) [Reserved]
____ (14)(i) 52.219-6, Notice of Total Small Business Set-Aside (NOV 2020) (15 U.S.C. 644).
____ (ii) Alternate I (MAR 2020) of 52.219-6.
____ (15)(i) 52.219-7, Notice of Partial Small Business Set-Aside (NOV 2020) (15 U.S.C. 644).
____ (ii) Alternate I (MAR 2020) of 52.219-7.
____ (16) 52.219-8, Utilization of Small Business Concerns (OCT 2018) (15 U.S.C. 637(d)(2) and (3)).
____ (17)(i) 52.219-9, Small Business Subcontracting Plan (SEP 2021) (15 U.S.C. 637(d)(4)).
____ (ii) Alternate I (NOV 2016) of 52.219-9.
____ (iii) Alternate II (NOV 2016) of 52.219-9.
____ (iv) Alternate III (JUN 2020) of 52.219-9.
____ (v) Alternate IV (SEP 2021) of 52.219-9.
____ (18) (i) 52.219-13, Notice of Set-Aside of Orders (MAR 2020) (15…