Renovate Two (2) Engine Dynamometer Test Cell, Bldg. No. S-326 and Replace Cooling Tower, Bldg. No. T-317 (MSC-K)
Solicitation number
W91QVN17R0212
Issued by

About this file

Solicitation

View the file

Other files

File Type Posted
H1_Drawings_HA-00556-5J.pdf PDF
A2_Submittal_Register.xls XLS spreadsheet
H1_Drawings_HA-00588-5J.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W91QVN-17-R-0212

Section B - Supplies or Services and Prices

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Job

K Work (Repair Work)

FFP

Renovate Dynamometer Test Cell, B326,Camp Carroll. Project No. HA-00588-5J FOB: Destination

PURCHASE REQUEST NUMBER: 0011070181

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Job

K Work (Repair Work)

Replace Cooling Tower, B317, Camp Carroll. Project No. HA-00556-5J

PURCHASE REQUEST NUMBER: 0011070181

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Job

Estimated Cost for War Hazard is Zero(0)

NET AMT

Section C - Descriptions and Specifications

TECHNICAL PROVISIONS - I

STATEMENT OF WORK

PROJECT NO TITLE LOCATION

HA-00588-5J Renovate Two (2) Engine Dynamometer Test Cell, Bldg. No. S-326 Camp Carroll

DESCRIPTION: The work to be performed shall be in accordance with all drawings and specifications provided under this contract.

a. Work by Contractor:

(1) The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings the specifications.

(2) The contractor shall renovate two (2) engine dynamometer test cell, Bldg. No. S-326, Camp Carroll in accordance with the specifications and drawings.

b. Work by In-House Labor: Not applicable to this project.

c. Work by Troop Labor: Not applicable to this project.

PRINCIPAL FEATURES: This project shall include the following:

General Services:

The contractor shall submit completed material lists and shop drawings to DPW, Engineering Division, Design & Technical Review Branch for approval prior to commencement of work at the jobsite.

Schedule #I, Repair (K): All work shall be in accordance with the attached drawings and specifications.

A. Architectural Work

1. Replace existing ceiling system with new including suspension system, insulation and necessary accessories. (Drawing No. AE-02~AE-04)

2. Replace existing wall with new perforated metal acoustical wall panel including insulation, metal frame and necessary accessories. (Drawing No. AE-02~AE-04)

3. Replace existing wall finish with new acoustical tile and gypsum wall board including necessary accessories. (Drawing No. AE-02~AE-04)

4. Replace existing door with new acoustical door including metal frame and necessary accessories. (Drawing No. AE-02~AE-04)

5. Replace existing sliding door with new including metal rail, weather strip, manual lock system and necessary accessories. (Drawing No. AE-02, AE-04)

6. Replace deteriorated existing fixed window with new acoustical fixed window including oak wood trim, and necessary accessories. (Drawing No. AE-02, AE-05)

7. Replace existing concrete slab with new for dynamometer system of mechanical work including reinforcing bar, steel beam, steel angle, steel plate, ditch, expansion joint and necessary accessories. (Drawing No. AE-02, AE-07, AE-08)

8. Paint on interior & exterior walls, floor, and metal doors by MPI (master painters institute). (Drawing No. AE-02)

9. Replace existing acrylic fluid-applied waterproofing system including necessary accessories at whole roof area for mechanical work. (Drawing No. AE-02)

B. Mechanical Work

1. Replace existing deteriorated tank engine dynamometer test cell with new tank engine dynamometer test cell system including supply fan, exhaust fan, engine exhaust gas fan, combustion air supply air handling unit, condensing unit, engine surface plate, electric unit heater, hose bibb, piping, valves, insulation and all necessary accessories. (Drawing No. M-2, M-3, M-5~M-9)

2. Replace deteriorated wet type fire sprinkler head with new including all necessary accessories and parts also contractor shall perform the work as notes for fire sprinkler system. (Drawing No. M-4)

3. The new tank engine dynamometer test cell system need to be installed compatible with new tank engine dynamometer test equipment also the contractor shall submit detailed shop drawing & sequence of operation drawing of new tank engine dynamometer test cell system to Design & Technical Review branch prior to construction.

4. The contractor shall perform performance test of new tank engine dynamometer test cell system and submit test report to Design & Technical review Branch.

C. Electrical Work

1. Replace deteriorated existing lighting fixture with new LED lighting fixture, toggle switches and necessary associated wiring. (Drawing No. E-2, E-3)

2. Replace deteriorated existing power and control system including motor control centers, safety switches, receptacles and necessary associated wiring. (Drawing No. E-4)

3. Replace deteriorated existing service lateral with new including transformer, high voltage lines, cut out switches, panel board, circuit breakers, watt hour meter and necessary associated wiring. (Drawing No. E-5~E-7)

PROJECT NO TITLE LOCATION

HA-00556-5J Replace Cooling Tower, Bldg. No. T-317 (MSC-K) Camp Carroll

DESCRIPTION: The work to be performed shall be in accordance with all drawings and specifications provided under this contract.

a. Work by Contractor:

(1) The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings the specifications.

(2) The contractor shall replace cooling tower, Bldg. No. T-317 (MSC-K), Camp Carroll in accordance with the specifications and drawings.

b. Work by In-House Labor: Not applicable to this project.

c. Work by Troop Labor: Not applicable to this project.

PRINCIPAL FEATURES: This project shall include the following:

General Services:

The contractor shall submit completed material lists and shop drawings to DPW, Engineering Division, Design & Technical Review Branch for approval prior to commencement of work at the jobsite.

Schedule #I, Repair (K): All work shall be in accordance with the attached drawings and specifications.

A. Mechanical Work

1. Replace existing deteriorated all cooling tower circulating systems with new one including all cooling towers, make up water system, all pumps, all control system, electric unit heaters, concrete pad, valves, filters, piping, insulation, and all necessary accessories & part. (Drawing M-4 & M-5)

2. The contractor shall provide a temporary cooling system during the construction period also temporary cooling system shall contain the cooling coil (73,700 KCAL/H) with condensing unit (85KW, 208V, 3PH, 60HZ) for water tank under pump room, circulating pump (350 GPM, 184 FT TDH, 1750RPM), piping, valves and all necessary accessories & part.

3. The contractor shall submit detailed shop drawing & sequence of operation drawing for all cooling tower circulating system to Design & Technical Review branch prior to construction.

4. The contractor shall perform performance test of new all cooling tower circulating systems and submit test report to Design & Technical Review branch.

TECHNICAL PROVISIONS - II

TECHNICAL DETAIL SPECIFICATIONS

PROJECT NO TITLE LOCATION

HA-00588-5J Renovate Two (2) Engine Dynamometer Test Cell, Bldg. No. S-326 Camp Carroll

HA-00556-5J Replace Cooling Tower, Bldg. No. T-317 (MSC-K) Camp Carroll

GENERAL: The specifications are from the "Standard Technical Specifications for O&MA Projects, Korea", dated 30 October 2015, issued by the Department of the Army, Installation Management Command. The most current specifications are available (for referral purposes only) on the USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK. The electronic version of the specifications are Acrobat® PDF format and can be read with the Acrobat Reader® software.

TECHNICAL PROVISIONS - III

SPECIAL CONDITIONS

PROJECT NO TITLE LOCATION

HA-00588-5J Renovate Two (2) Engine Dynamometer Test Cell, Bldg. No. S-326 Camp Carroll

HA-00556-5J Replace Cooling Tower, Bldg. No. T-317 (MSC-K) Camp Carroll

1. GENERAL: In addition to the requirements specified under "GENERAL PROVISIONS" for the Fixed Price Construction Contract for this project, the Contractor shall comply with the following "SPECIAL CONDITIONS" which form a part of the contract.

2. WORK HOURS: The work will be accomplished from 0730 hours through 1730 hours (Monday through Saturday) except for Korean Legal Holidays. Any proposed change in working hours should be approved by the Contracting Officer (KO) and Contracting Officer's Representative (COR).

3. NOTIFICATION OF INSPECTION SECTION: The contractor shall also give the project inspector seven (7) working days notice prior to each concrete placement, field test, weld application, protective coating application, or any other work deemed to require inspection.

4. COORDINATION: The contractor shall coordinate his work with all others (subcontractor and government agencies) involved in this project and shall cooperate with all other contractors and government agencies so as to facilitate the general progress of the work. Before proceeding with any work, the contractor and/or subcontractor shall consult applicable drawings and specifications for each trade involved.

5. CONSTRUCTION: The contractor shall submit a request for the construction permit at least ten (10) working days prior to the starting of work. The request shall be submitted to the COR for approval.

6. MATERIALS COMPLIANCE: The contractor shall make certain all materials used meet the requirements of the contract and proof thereof upon request of the COR. Materials not meeting the requirements of the contract shall not be brought to the job site. All materials shall be new and the standard products of a manufacturer regularly engaged in the manufacturing of such materials.

7. HOISTING AND MOVING EQUIPMENT: The Contractor and each subcontractor shall provide and be responsible for all cranes, lifts, etc., necessary for the proper and efficient movement of materials. The equipment shall be provided with proper guys, bracing, safety devices, etc., as required by law.

8. EQUIPMENT: All contractor equipment shall be subject to functional and safety inspection by the COR. Equipment not completely safe or functional shall be repaired before work is started.

9. RECORD DRAWINGS: During performance of work, the contractor shall accurately record and delineate on a set of full-size blue line prints of contract drawings all changes in such work which constitute departures from the original contract drawings. The set of drawings (one original and one blue line print), thus corrected and changed, usually referred to as “As-Built Drawings”, shall be delivered to the COR at the final acceptance/inspection of the completed work by the Government.

10. US ORIGIN MATERIALS: If applicable, all US Origin Materials will be ordered immediately after Notice to Proceed.

11. RELEASE OF FACILITIES WITH U.S. ORIGIN MATERIALS: If applicable, Building/facility will not be released to the contractor by the COR until all U.S. origin building construction supplies are available or due within such a time frame that there will be no delay in project completion.

12. UTILITY CUTOVERS AND INTERRUPTIONS: Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and U. S. Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours." Ensure that new utility lines are complete, except for the connection, before interrupting existing service. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours." Such interruption shall be limited to 4 hours. This time includes for deactivation and reactivation.

13. WORK OUTSIDE REGULAR HOURS: Work outside regular working hours requires Contracting Officer approval. Make application 14 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During the period of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours on Saturdays, Sundays, and U. S. Government holidays unless directed otherwise.

14. WINTERIZATION: The contractor may be required to perform the work during the winter season, which may cause the contractor for additional cost. These additional costs are the contractor’s responsibility in the event of working during this period. The Contractor shall reflect these costs in the preparation of his proposal.

15. SAFETY: The safety plan must be approved before any work can be performed on this contract. Hard hats, suitable work boots and other necessary personnel protective gear are mandatory. Contractors are required to get a written permission from safety office (POC: Mr. To, Pong Uk, DSN: 768-8971) and fire & Emergency Service (POC: Fire Communication office, DSN: 768-4120) prior to enter confined spaces (i.e. manholes). Contractors should be properly trained and equipped with PPEs, calibrated air monitoring instrument, to work at confined spaces to insure compliance with OSHA (Occupational Safety and Health Administration) 29 CFR 1910.146.

16. SECURITY: All prime contractor and subcontractor personnel will be required to obtain a station pass from the Base Security Office. It is the prime contractor’s responsibility to supply information to security regarding all prime and subcontractor personnel and a list of all vehicles that will be driven on the site.

17. WARRANTY: The contractor shall be responsible for remedy of failure in government contract during the one (1) year warranty time. The contractor shall be refurnishing services or/and repair and replacement for remedy. The one (1) year warranty starts the day after final inspection approval from the authorized personnel.

18. ANTITERRORISM/OPRATIONS SECURITY REQUIREMENTS.

18.1. AT Level 1 Training: This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.

18.2. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil

18.3. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

18.4. iWATCH Training. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.

19. Environmental Management System (EMS): Recycling all eligible material, including glass, paper (including magazines), plastic, aluminum, and cardboard to the maximum extent practicable;

Reducing the amount of hazardous material and/or solvent used by purchasing fewer hazardous materials and by increasing the use of products with recycled content;

Reducing the amount of solid waste from construction and demolition debris, and scrap metal sent to municipal and rubble landfills by reducing, reusing, and recycling;

Conserving energy and water usage by turning off lights and equipment when not in use and using only the necessary amount of water needed to complete the required tasks. Continuous conservation of our natural resources is a must;

20. Contamination find clause: When contaminated soil is encountered during excavation work, contractor shall report the findings to the Environmental Office immediately and contractor will segregate contaminated soil from clean soil.

21. Inadvertent find clause: When potential cultural or historic items are inadvertently found during construction activities, contractor shall cease activities in the vicinity of the discovery and report the findings to the Environmental Office immediately. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch. 12, Para 12-3 J)

22. Fuel Tank and Lines: If applicable, when underground piping associated with POL storage containers shall be tested for integrity and leaks at the time of installation, modification, construction, relocation, or replacement. New underground piping must be protected against corrosion IAW recognized industry standards. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch. 9, Para 9-3.b.(5))

23. Non-PCB transformer certification: If applicable, before contractor replace/install any transformer at USAG Daegu, contractor shall submit two copies of non-PCB transformer certification to COR for each to be installed transformer. New transformer will be installed after COR's approval for non-PCB transformer certification for each to be installed transformer.

LIST OF APPLICABLE CONTRACT DRAWINGS

PROJECT NO TITLE LOCATION

HA-00588-5J Renovate Two (2) Engine Dynamometer Test Cell, Bldg. No. S-326 Camp Carroll

GENERAL: The work shall conform to the standard detail drawings (dated 30 November 2015, issued by the Department of the Army, Installation Management Agency, Korea Region Office and located USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK), all of which form a part of the specifications.

Drawing No. Sheet No. Ref. No. Description Date

D-17-25 1 of 1 R-1 TITLE SHEET 25 Jul 17

“1 of 24AE-1EXISTING FLOOR PLAN, BLDG. #326,
GENERAL NOTES, NOTE,
LEGEND AND CODE REFERENCES“
“2 of 24AE-2REMOVAL PLAN, BLDG. #326,
ENLARGED NEW FLOORPLAN, BLDG. #326,
SCOPE OF WORK, KEY PLAN, AND LEGEND“
“3 of 24AE-3TANK DYNO ROOM SECTION, BLDG. #326,
CONTROL ROOM SECTION, BLDG. #326,
AND NOTE“
“4 of 24AE-4INTERIOR FINISH SCHEDULE,
DOOR SCHEDULE,
DOOR / WINDOW PLAN, AND NOTES“
“5 of 24AE-5WINDOW SCHEDULE, ACOUSTICAL FIXED
WINDOW DETAIL (TYP), AND NOTE“
“6 of 24AE-6ACOUSTICAL DOOR DETAIL (TYP):
HEAD, JAMB, SILL, AND
METAL SLIDING DOOR: HEAD, JAMB, SILL“
“7 of 24AE-7CONTRACTION JOINT (TYP),
PARTIAL DETAIL (TYP),
WALL PARTIAL DETAIL (TYP), AND
CEILING PARTIAL DETAIL (TYP)“
D-17-278 of 24AE-8CONCRETE DITCH DETAILS (TYP),25 Jul 17
CMU WALL OPENING DETAIL, AND
CEILING PARTIAL DETAIL (TYP)
“9 of 24M-1LEGEND, ABBREVIATIONS AND
GENERAL NOTES“
“10 of 24M-2EQUIPMENT SCHEDULE,
SCOPE OF WORK, NOTE“
“11 of 24M-3REMOVE TANK ENGINE TEST ROOMS,
NEW TANK ENGINE TEST ROOMS“
“12 of 24M-4NOTES FOR FIRE SPRINKLER SYSTEM,
REPLACE SPRINKLER HEAD PLAN“
“13 of 24M-5NEW ENGINE DYNAMOMETER
TEST CELL SYSTEM“
“14 of 24M-6NEW ABOVE THE CEILING OF ENGINE
DYNAMOMETER TEST CELL SYSTEM“

“ 15 of 24 M-7 TEST CELL VENTILATION SYSTEM “

“ 16 of 24 M-8 COMBUSTION AIR SUPPLY SYSTEM “

“ 17 of 24 M-9 ENGINE GAS EXHAUST SYSTEM “

“ 18 of 24 E-1 LEGEND, NOTES AND SCOPE OF WORK “

“ 19 of 24 E-2 REMOVAL PLAN “

“ 20 of 24 E-3 LIGHTING PLAN AND FIXTURE DETAIL “

“ 21 of 24 E-4 POWER PLAN “

“ 22 of 24 E-5 ELECTRICAL SITE PLAN “

“ 23 of 24 E-6 POWER SINGLE LINE DIAGRAM “

“ 24 of 24 E-7 PANEL SCHEDULE "DP" AND "MPC" “

PROJECT NO TITLE LOCATION

HA-00556-5J Replace Cooling Tower, Bldg. No. T-317 (MSC-K) Camp Carroll

GENERAL: The work shall conform to the standard detail drawings (dated 30 November 2015, issued by the Department of the Army, Installation Management Agency, Korea Region Office and located USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK), all of which form a part of the specifications.

Drawing No. Sheet No. Ref. No. Description Date

D-17-24 1 of 1 R-1 TITLE SHEET 25 Jul 17

“ 1 of 7 M-1 LEGEND AND ABBREVIATIONS “

“ 2 of 7 M-2 GENERAL NOTES, US ORIGIN MATERIALS “

“ 3 of 7 M-3 EQUIPMENT SCHEDULE, SCOPE OF WORK “

“4 of 7M-4REMOVE EXISTING COOLING TOWER
& PUMP ROOM PLAN“
“5 of 7M-5NEW COOLING TOWER
& PUMP ROOM PLAN,
UNIT HEATER POWER PLAN“

“ 6 of 7 M-6 NEW PUMP ROOM ISOMETRIC DIAGRAM “

“7 of 7M-7NEW COOLING SYSTEM ISOMETRIC
DIAGRAM,
SEQUENCE OF OPERATION,
PRESSURE SWITCH SCHEDULE“

SUBMITTAL REGISTER

Note 1. See the uploaded document in Federal Business Opportunities (FBO) website (https://www.fbo.gov/).

Note 2. The Submittal Register in Section J, identifies the documentation that will be made available for approval and review by the Government in the performance of this task order. It is the contractor's responsibility that this data is in compliance with the corresponding OMA specification revision 1 that is referenced.

Section F - Deliveries or Performance

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 210 calendar days including 120 calendar days for procurement of US origin materials after notice to proceed (NTP) is issued.

The time stated for completion shall include final cleanup of the premises.

(End of clause)

Section J - List of Documents, Exhibits and Other Attachments

LIST OF APPLICABLE CONTRACT DRAWINGS

PROJECT NO TITLE LOCATION

HA-00588-5J Renovate Two (2) Engine Dynamometer Test Cell, Bldg. No. S-326 Camp Carroll

GENERAL: The work shall conform to the standard detail drawings (dated 30 November 2015, issued by the Department of the Army, Installation Management Agency, Korea Region Office and located USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK), all of which form a part of the specifications.

Drawing No. Sheet No. Ref. No. Description Date

D-17-25 1 of 1 R-1 TITLE SHEET 25 Jul 17

“1 of 24AE-1EXISTING FLOOR PLAN, BLDG. #326,
GENERAL NOTES, NOTE,
LEGEND AND CODE REFERENCES“
“2 of 24AE-2REMOVAL PLAN, BLDG. #326,
ENLARGED NEW FLOORPLAN, BLDG. #326,
SCOPE OF WORK, KEY PLAN, AND LEGEND“
“3 of 24AE-3TANK DYNO ROOM SECTION, BLDG. #326,
CONTROL ROOM SECTION, BLDG. #326,
AND NOTE“
“4 of 24AE-4INTERIOR FINISH SCHEDULE,
DOOR SCHEDULE,
DOOR / WINDOW PLAN, AND NOTES“
“5 of 24AE-5WINDOW SCHEDULE, ACOUSTICAL FIXED
WINDOW DETAIL (TYP), AND NOTE“
“6 of 24AE-6ACOUSTICAL DOOR DETAIL (TYP):
HEAD, JAMB, SILL, AND
METAL SLIDING DOOR: HEAD, JAMB, SILL“
“7 of 24AE-7CONTRACTION JOINT (TYP),
PARTIAL DETAIL (TYP),
WALL PARTIAL DETAIL (TYP), AND
CEILING PARTIAL DETAIL (TYP)“
D-17-278 of 24AE-8CONCRETE DITCH DETAILS (TYP),25 Jul 17
CMU WALL OPENING DETAIL, AND
CEILING PARTIAL DETAIL (TYP)
“9 of 24M-1LEGEND, ABBREVIATIONS AND
GENERAL NOTES“
“10 of 24M-2EQUIPMENT SCHEDULE,
SCOPE OF WORK, NOTE“
“11 of 24M-3REMOVE TANK ENGINE TEST ROOMS,
NEW TANK ENGINE TEST ROOMS“
“12 of 24M-4NOTES FOR FIRE SPRINKLER SYSTEM,
REPLACE SPRINKLER HEAD PLAN“
“13 of 24M-5NEW ENGINE DYNAMOMETER
TEST CELL SYSTEM“
“14 of 24M-6NEW ABOVE THE CEILING OF ENGINE
DYNAMOMETER TEST CELL SYSTEM“

“ 15 of 24 M-7 TEST CELL VENTILATION SYSTEM “

“ 16 of 24 M-8 COMBUSTION AIR SUPPLY SYSTEM “

“ 17 of 24 M-9 ENGINE GAS EXHAUST SYSTEM “

“ 18 of 24 E-1 LEGEND, NOTES AND SCOPE OF WORK “

“ 19 of 24 E-2 REMOVAL PLAN “

“ 20 of 24 E-3 LIGHTING PLAN AND FIXTURE DETAIL “

“ 21 of 24 E-4 POWER PLAN “

“ 22 of 24 E-5 ELECTRICAL SITE PLAN “

“ 23 of 24 E-6 POWER SINGLE LINE DIAGRAM “

“ 24 of 24 E-7 PANEL SCHEDULE "DP" AND "MPC" “

PROJECT NO TITLE LOCATION

HA-00556-5J Replace Cooling Tower, Bldg. No. T-317 (MSC-K) Camp Carroll

GENERAL: The work shall conform to the standard detail drawings (dated 30 November 2015, issued by the Department of the Army, Installation Management Agency, Korea Region Office and located USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK), all of which form a part of the specifications.

Drawing No. Sheet No. Ref. No. Description Date

D-17-24 1 of 1 R-1 TITLE SHEET 25 Jul 17

“ 1 of 7 M-1 LEGEND AND ABBREVIATIONS “

“ 2 of 7 M-2 GENERAL NOTES, US ORIGIN MATERIALS “

“ 3 of 7 M-3 EQUIPMENT SCHEDULE, SCOPE OF WORK “

“4 of 7M-4REMOVE EXISTING COOLING TOWER
& PUMP ROOM PLAN“
“5 of 7M-5NEW COOLING TOWER
& PUMP ROOM PLAN,
UNIT HEATER POWER PLAN“

“ 6 of 7 M-6 NEW PUMP ROOM ISOMETRIC DIAGRAM “

“7 of 7M-7NEW COOLING SYSTEM ISOMETRIC
DIAGRAM,
SEQUENCE OF OPERATION,
PRESSURE SWITCH SCHEDULE“

SUBMITTAL REGISTER

Note 1. See the uploaded document in Federal Business Opportunities (FBO) website (https://www.fbo.gov/).

Note 2. The Submittal Register in Section J, identifies the documentation that will be made available for approval and review by the Government in the performance of this task order. It is the contractor's responsibility that this data is in compliance with the corresponding OMA specification revision 1 that is referenced.

Section K - Representations, Certifications and Other Statements of Offerors

52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)

(a) The offeror certifies that --

(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to –

(i) Those prices,

(ii) The intention to submit an offer, or

(iii) The methods of factors used to calculate the prices offered:

(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and

(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.

(b) Each signature on the offer is considered to be a certification by the signatory that the signatory --

(1) Is the person in the offeror's organization responsible for determining the prices offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision; or

(2) (i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provison ______________________________________________________ (insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization);

(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) above have not participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) above; and

(iii) As an agent, has not personally participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision.

(c) If the offeror deletes or modifies subparagraph (a)(2) of this provision, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.

(End of Provision)

252.209-7999 Representation by Corporations Regarding an Unpaid Delinquent Tax Liability or a Felony Conviction under any Federal Law REPRESENTATION BY CORPORATIONS REGARDING AN UNPAID DELINQUENT TAX LIABILTIY OR A FELONY CONVICTION UNDER ANY FEDERAL LAW (DEVIATION 2012-00004) (JAN 2012)

1. In accordance with sections 8124 and 8125 of Division A of the Consolidated Appropriations Act, 2012, (Pub. L. 112-74) none of the funds made available by that Act may be used to enter into a contract with any corporation that-

(1) Has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, where the awarding agency is aware of the unpaid tax liability, unless the agency has considered suspension or debarment of the corporation and made a determination that this further action is not necessary to protect the interests of the Government.

(2) Was convicted of a felony criminal violation under any Federal law within the preceding 24 months, where the awarding agency is aware of the conviction, unless the agency has considered suspension or debarment of the corporation and made a determination that this action is not necessary to protect the interests of the Government.

1. The Offeror represents that –

(1) It is ( ) is not ( ) a corporation that has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with authority responsible for collecting the tax liability,

(2) It is ( ) is not ( ) a corporation that was convicted of a felony criminal violation under a federal law within the preceding 24 months.

(End of provision)

5152.204-4032 REPRESENTATIONS AND CERTIFICATIONS

(a) SUBCONTRACTING:

If the offeror contemplates subcontracting, it must obtain prior written approval of subcontractor from the PCO or ACO, and list below: (1) the names and addresses of the subcontractor(s), (2) the type of subcontracting, and (3) the estimated price for each subcontract.

(b) AFFILIATED OFFERORS:

(1) Business concerns are affiliates of each other when, either directly or indirectly, one concern controls or has the power to control the other, or a third party controls or has the power to control both.

(2) Each offeror shall furnish, below, the following information:

(i) Whether the offeror has any affiliates;

(ii) The names and addresses of all affiliates of the offeror; and

(iii) The names and addresses of all persons and concerns exercising control or ownership of the offeror and any or all of its affiliates, and whether they are common officers, directors, stockholders holding controlling interest, or otherwise.

AFFILIATED CONCERNS. : (Name, location and, in detail, controlling interest in each)

(c) PRINCIPAL OWNER(S) OR STOCKHOLDER(S):

Each offeror shall list below the name(s) and address(es) of the principal owner(s) or stockholder(s) of the company and percentage of ownership. If a major portion is publicly traded and/or otherwise widely distributed, state that, with the percentage so affected.

(d) STANDARDS OF CONDUCT CERTIFICATION:

This is to certify that, to the best of my knowledge and belief, except as described below, no representative of this firm who deals with US Government employees on any aspect of this procurement is a former US Government employee, to include former US military personnel. I understand that this certification is continuing in nature and places a duty on me and my firm to notify the Contracting Officer of any additional individual(s) who fit the above description prior to the individual's assuming duties.

(i) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________

(ii) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________

(iii) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________

Firm ____________________________________________________ Name _____________________________________________________ Signature __________________________________________________

Title _____________________________________________________ Date of Execution ____________________________________________

(e) TAXES:

(1) References:

(i) Contract clause entitled "FAR 52.229-06 Taxes—Foreign Fixed-Price Contracts (Jan 1991)."

(ii) US-ROK Status of Forces Agreement (SOFA), Articles IX and XVI.

(iii) ROK Customs Law, Law No. 1976, promulgated on 29 November 1967, as amended.

(iv) ROK Value Added Tax Law, Law No. 2934, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(v) ROK Special Excise Tax Law, Law No. 2935, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(2) Contractor shall state the types and estimated amount of taxes that would normally apply to such transactions but are excluded from this proposal.

(i) Customs Tax (except for ROK MND-funded contracts or delivery orders):

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

This item will be imported specifically for this contract? Yes _____ No _____

(ii) Special Excise Tax:

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

Name of item manufacturer

(iii) Value Added Tax (VAT):

Input VAT on materials purchased for this contract. 10% _____ Input VAT on transportation leased/rented for this contract.10% _____ Input VAT on equipment leased/rented for this contract. 10% _____ Input VAT on services purchased for this contract. 10% _____ Output VAT on total contract amount. 10% _____

(iv) Special Excise (Petroleum) Tax:

No. of U/P Liters w/o Tax Tax/Unit Total Tax Amount Regular Gasoline ________ (L) ________ w________ w_____________ Premium Gasoline ________ (L) ________ w________ w_____________ Diesel ________ (L) ________ w________ w_____________ Other ________ (L) ________ w________ w_____________

(v) Education Tax.

(3) Name of the oil company from which POL products will be purchased:

Oil Company: _________________________________________ (Name only)

(4) I certify by this submission that all supplies and services to be purchased for this contract have been proposed exclusive of Value Added Tax, applicable Customs Tax (except ROK MND-funded contracts and delivery orders), Special Excise Tax, and Education Tax.

Signed (Chop)

(f) CERTIFICATIONS AND REPRESENTATIONS

By submitting an offer, each offeror agrees to be bound by all certifications and representations in this solicitation. The Government reserves the right to require any and all certifications and representations to be completed and signed in hard copy by the successful offeror prior to contract award. Failure of an offeror to complete the certifications and representations within the time directed by the Contracting Officer may result in a determination that the contractor is not a responsible offeror for this acquisition.

Section L - Instructions, Conditions and Notices to Bidders

INSTRUCTION TO OFFERORS

1. GENERAL INSTRUCTIONS FOR PREPARATION OF PROPOSAL:

a. The Government intends to award without discussion, but reserves the right to conduct discussions if deemed necessary and to establish a competitive range for efficiency in accordance with FAR 52.215-1(f)(4).

b. Offeror(s) may, at the discretion of the Government, be asked to provide more information and clarification regarding their proposals. The Government may make a final determination as to whether an offer is acceptable or unacceptable solely based on the proposals as submitted, without requesting any further information. However, if it is deemed necessary the Government may, at its sole discretion, request additional information clarifying but not substantially changing any proposal as submitted.

2. SUBMISSION OF PROPOSAL:

a. Offers shall be submitted to Federal Business Opportunities (FBO) https://www.fbo.gov/ , or if FBO is not available, email to suok.yun.ln@mail.mil with the evidence document such as screen shot. The FBO unavailability is limited to ONLY FBO server problem not individual failure/problem. All questions should be emailed to to suok.yun.ln@mail.mil within three (3) days after the site visit. The electronic offer shall be submitted by 1500 hrs on the closing date of RFP.

b. The PRICING PROPOSAL with the detailed cost breakdown shall be submitted by 1500 hours on the closing date of RFP through https://www.fbo.gov/ . The cost breakdown will be utilized to ensure the Offeror understands the requirement. The cost breakdown should clearly identify all the significant material and costs associated with the level of effort prescribed in the Statement of Work.

c. Section K : Offerors must complete all portions of Section K and submit it through https://www.fbo.gov/ by 1500 hours on the closing date of RFP. The offeror shall review all expenses to ensure that all applicable taxes are excluded from the overall price. In addition, any proposed exemption of a specific ROK tax shall be legitimate, attributable to the contract, and authorized by the applicable stated references.

Failure to submit the above requirements may be grounds for determining the proposal to be noncompliant and not eligible to be considered for award.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for--

- Date / Time: 23 Aug 2017 / 1400hrs

- Location: In front of Bldg 326, Camp Carroll.

- DPW POC: Mr. Kim, Chae Kyong at 764-4134 (DSN)

- DPW COR: Mr. Won, Ho Sik at 768-7569 (DSN)

(End of provision)

5152.236-4011 CONSTRUCTION PRICE RANGE

Pursuant to FAR 36.204 the estimated price range is between $ 1,000,000 and $5,000,000.

Section M - Evaluation Factors for Award

BASIS OF AWARD

Award shall be made to the responsible offeror submitting the lowest priced offer and completed Section K. The Government reserves the right to award without discussions with offerors. The tax exemptions stated in Section K will be reviewed by the contracting officer for reasonableness and necessity to complete the Task Order. The contracting officer may reject a proposal if the offeror appears to improperly overstate any proposed tax exemptions image1.wmf image2.wmf