5 - Bid Sheet w-Coefficient Concrete_Reqmts.xlsx
XLSX spreadsheet 62 KB Posted
- Attached to
- Installation Concrete Requirements Federal contract opportunity
- Solicitation number
- W91QF4-21-B-0002
About this file
This document contains a bid sheet for a federal contract solicitation for installation concrete requirements. The solicitation seeks bids for various concrete construction and repair items such as new or replaced pavement, curbs, sidewalks, slabs, and pavers. The bid sheet includes over 200 line items with detailed specifications, quantities, and unit pricing for concrete-related work. Pricing is provided by the government for estimates and contractors will submit their own adjusted pricing coefficients. The solicitation number is W91QF4-21-B-0002 and was issued by the Department of the Army Materiel Command Mission and Installation Contracting Command at Fort Eustis. The pre-proposal conference will be held on January 7, 2021 to review instructions and award criteria. The deadline to register is January 5, 2021.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 6 - W91QF4-21-B-0002 - Q and A Amendment.pdf | ||
| SOL_Amend 01_W91QF4-21-B-0002 -Q and A.pdf | ||
| W91QF4-21-B-0002_DPW_Installation_Concrete_Reqmts.pdf | ||
| 3 - Specs - Concrete Requirement 2020.pdf | ||
| 2 - Drawing Concr Reqmnts (Rev) - 2020.pdf | ||
| 4 - WD-KS20200141-Highway-29 May 20.pdf | ||
| 1 - Quality of Workmanship and Stds.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Year
| MISCELLANEOUS CONCRETE REPAIRS - BIDDING SCHEDULE | |||||||
| BASE YEAR | |||||||
| BID ITEM | DESCRIPTION | Unified Facilities Guide Specification | UNIT OF MEASURE | DPW - Cost Estimate | ESTIMATED QUANTITY | TOTAL COST | |
| 1 | New PCCP 6" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $141.36 | 20 | $ 2,827.20 |
| 2 | New PCCP 6" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $70.35 | 50 | $ 3,517.50 |
| 3 | New PCCP 6" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $60.50 | 200 | $ 12,100.00 |
| 4 | New PCCP 8" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $155.10 | 20 | $ 3,102.00 |
| 5 | New PCCP 8" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $90.72 | 50 | $ 4,536.00 |
| 6 | New PCCP 8" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $70.35 | 200 | $ 14,070.00 |
| 7 | New PCCP 10" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $181.26 | 20 | $ 3,625.20 |
| 8 | New PCCP 10" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $100.57 | 50 | $ 5,028.50 |
| 9 | New PCCP 10" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $65.10 | 200 | $ 13,020.00 |
| 10 | Replace PCCP 6" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $203.75 | 20 | $ 4,075.00 |
| 11 | Replace PCCP 6" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $115.00 | 50 | $ 5,750.00 |
| 12 | Replace PCCP 6" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $72.68 | 200 | $ 14,536.00 |
| 13 | Replace PCCP 8" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $225.53 | 20 | $ 4,510.60 |
| 14 | Replace PCCP 8" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $130.96 | 50 | $ 6,548.00 |
| 15 | Replace PCCP 8" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $90.88 | 200 | $ 18,176.00 |
| 16 | Replace PCCP 10" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $230.61 | 20 | $ 4,612.20 |
| 17 | Replace PCCP 10" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $135.35 | 50 | $ 6,767.50 |
| 18 | Replace PCCP 10" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $95.77 | 200 | $ 19,154.00 |
| 19 | New Curb & Gutter | 32 16 19 | Concrete Curbs Gutters and Sidewalks | LNFT | $35.22 | 250 | $ 8,805.00 |
| 20 | Replace Curb & Gutter | 32 16 19 | Concrete Curbs Gutters and Sidewalks | LNFT | $59.50 | 300 | $ 17,850.00 |
| 21 | New Concrete Sidewalk | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $39.85 | 250 | $ 9,962.50 |
| 22 | Replace Concrete Sidewalk | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $80.15 | 300 | $ 24,045.00 |
| 23 | New Sidewalk Ramp | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $86.50 | 40 | $ 3,460.00 |
| 24 | Replace Sidewalk Ramp | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $165.74 | 40 | $ 6,629.60 |
| 25 | New Sidewalk Ramp (Detectable Warning) | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $104.00 | 40 | $ 4,160.00 |
| 26 | Replace Sidewalk Ramp (Detectable Warning) | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $189.25 | 40 | $ 7,570.00 |
| 27 | New Concrete Slab | 03 30 00 | Cast-in-Place Concrete | CUYD | $192.95 | 150 | $ 28,942.50 |
| 28 | Replace Concrete Slab | 03 30 00 | Cast-in-Place Concrete | CUYD | $401.55 | 150 | $ 60,232.50 |
| 29 | New Elevated Concrete Slab | 03 30 00 | Cast-in-Place Concrete | CUYD | $1,058.34 | 5 | $ 5,291.70 |
| 30 | Replace Elevated Concrete Slab | 03 30 00 | Cast-in-Place Concrete | CUYD | $1,555.65 | 20 | $ 31,113.00 |
| 31 | Falsework for Elevated Slab | N/A | N/A | SQFT | $25.25 | 200 | $ 5,050.00 |
| 32 | Concrete Wall | 03 30 00 | Cast-in-Place Concrete | CUYD | $805.78 | 100 | $ 80,578.00 |
| 33 | Concrete Footer | 03 30 00 | Cast-in-Place Concrete | CUYD | $322.13 | 50 | $ 16,106.50 |
| 34 | New On-Grade Steps | 03 30 00 | Cast-in-Place Concrete | LF Nose | $81.00 | 75 | $ 6,075.00 |
| 35 | Replace On-Grade Steps | 03 30 00 | Cast-in-Place Concrete | LF Nose | $184.83 | 100 | $ 18,483.00 |
| 36 | New Above-Grade Steps | 03 30 00 | Cast-in-Place Concrete | CUYD | $881.77 | 5 | $ 4,408.85 |
| 37 | Replace Above-Grade Steps | 03 30 00 | Cast-in-Place Concrete | CUYD | $1,602.50 | 10 | $ 16,025.00 |
| 38 | Capillary Water Barrier (4") | 03 30 00 31 00 00 | Cast-in-Place Concrete Earthwork | SQYD | $12.00 | 200 | $ 2,400.00 |
| 39 | Vaper Barrier | 03 30 00 31 00 00 | Cast-in-Place Concrete Earthwork | SQYD | $2.75 | 200 | $ 550.00 |
| 40 | Flowable Fill Concrete | N/A | N/A | CUYD | $201.45 | 30 | $ 6,043.50 |
| 41 | Reinforcing Steel | 03 20 00.10 | Concrete Reinforcing | LBS | $1.51 | 10,000 | $ 15,100.00 |
| 42 | Reinforcing Steel (Epoxy Coated) | 03 20 00.10 | Concrete Reinforcing | LBS | $1.75 | 500 | $ 875.00 |
| 43 | Woven Wire Steel Fabric 4 X 4 | 03 20 00.10 | Concrete Reinforcing | SQYD | $5.98 | 1,000 | $ 5,980.00 |
| 44 | Dowel Bars, Epoxy Coated and Baskets for Roadway 3/4" | 03 20 00.10 | Concrete Reinforcing | LNFT | $15.11 | 300 | $ 4,533.00 |
| 45 | Colored Concrete (Material Cost Dye) | N/A | NO BID | CUYD | 100 | $ - 0 | |
| 46 | Stamp Pattern in Concrete (Additional Labor Costs) | N/A | N/A | SQYD | $10.27 | 500 | $ 5,135.00 |
| 47 | Saw Cut Concrete or Asphalt 4" Thick | N/A | N/A | LNFT | $3.72 | 300 | $ 1,116.00 |
| 48 | Saw Cut Concrete or Asphalt 6" Thick | N/A | N/A | LNFT | $5.26 | 200 | $ 1,052.00 |
| 49 | Saw Cut Concrete or Asphalt 8" Thick | N/A | N/A | LNFT | $6.62 | 200 | $ 1,324.00 |
| 50 | Sealing PCCP Joints (>1/8" to 1/2") | 32 01 19.61 | Sealing Cracks in Rigid Pavement | LNFT | $3.35 | 500 | $ 1,675.00 |
| 51 | Sealing PCCP Cracks (>1/2" to 1") | 32 01 19.61 | Sealing Cracks in Rigid Pavement | LNFT | $7.01 | 500 | $ 3,505.00 |
| 52 | Sealing PCCP Cracks (>1" to 2") | 32 01 19.61 | Sealing Cracks in Rigid Pavement | LNFT | $14.98 | 50 | $ 749.00 |
| 53 | New handrail (<30" above ground) | 05 52 00 | Metal Railings | LNFT | $97.00 | 100 | $ 9,700.00 |
| 54 | Replace handrail (<30" above ground) | 05 52 00 | Metal Railings | LNFT | $166.34 | 50 | $ 8,317.00 |
| 55 | New Guardrail/Handrail (≥ 30" above ground) | 05 52 00 | Metal Railings | LNFT | $185.65 | 200 | $ 37,130.00 |
| 56 | Replace Guardrail/Handrail (≥ 30" above ground) | 05 52 00 | Metal Railings | LNFT | $262.38 | 50 | $ 13,119.00 |
| 57 | Construct Sub-base Less than 5 CY | 32 11 23 | Aggregate Base Courses | CUYD | $125.81 | 100 | $ 12,581.00 |
| 58 | Construct Sub-base 5 to 50 cubic yards | 32 11 23 | Aggregate Base Courses | CUYD | $112.20 | 100 | $ 11,220.00 |
| 59 | Construct Sub-base over 50 cubic yards | 32 11 23 | Aggregate Base Courses | CUYD | $99.98 | 175 | $ 17,496.50 |
| 60 | Common Excavation | 31 00 00 | Earthwork | CUYD | $11.00 | 1,500 | $ 16,500.00 |
| 61 | Common Excavation (Government Furnished) | 31 00 00 | Earthwork | CUYD | $13.25 | 1,500 | $ 19,875.00 |
| 62 | Common Excavation (Contractor Furnished) | 31 00 00 | Earthwork | CUYD | $25.00 | 1,500 | $ 37,500.00 |
| 63 | Embankment | 31 00 00 | Earthwork | CUYD | $32.94 | 500 | $ 16,470.00 |
| 64 | Embankment (Contractor Furnished) | 31 00 00 | Earthwork | CUYD | $41.77 | 100 | $ 4,177.00 |
| 65 | Salvage Topsoil | 31 00 00 | Earthwork | SQYD | $1.01 | 1,000 | $ 1,010.00 |
| 66 | Topsoil (Government Furnished) | 31 00 00 | Earthwork | CUYD | $11.43 | 1,500 | $ 17,145.00 |
| 67 | Rock Excavation | 31 00 00 | Earthwork | CUYD | $59.63 | 1,500 | $ 89,445.00 |
| 68 | Rip-Rap (D50)(4") | 31 00 00 | Earthwork | CUYD | $68.00 | 50 | $ 3,400.00 |
| 69 | Rip-Rap (D50)(6") | 31 00 00 | Earthwork | CUYD | $73.00 | 50 | $ 3,650.00 |
| 70 | Manipulation for Treated Subgrade | 32 11 30 | Lime Treated Subgrades | SQYD | $24.45 | 1,500 | $ 36,675.00 |
| 71 | Quicklime for Treated Subgrade | 32 11 30 | Lime Treated Subgrades | TONS | $330.46 | 20 | $ 6,609.20 |
| 72 | Hydrated Lime for Treated Subgrade | 32 11 30 | Lime Treated Subgrades | TONS | $485.76 | 20 | $ 9,715.20 |
| 73 | Geotextile Separation Fabric | 31 05 19 | Geosynthetics | SQYD | $2.75 | 1,000 | $ 2,750.00 |
| 74 | Core Drill (4”) Pavement Sampling | N/A | N/A | EACH | $100.33 | 20 | $ 2,006.60 |
| 75 | In-Situ Soil Sampling and Testing for soil classification | 32 11 13.13 | Lime Treated Subgrades | EACH | $800.51 | 5 | $ 4,002.55 |
| 76 | Replace Asphalt Incidental to Work | 32 12 16 | HMA | CUFT | $50.35 | 100 | $ 5,035.00 |
| 77 | Pavement Marking (Paint)(4")(Yellow)(Without Glass Beads) | 32 17 23 | Pavement Markings | LNFT | $0.52 | 3,000 | $ 1,560.00 |
| 78 | Pavement Marking (Paint)(4")(White)(Without Glass Beads) | 32 17 23 | Pavement Markings | LNFT | $0.52 | 5,000 | $ 2,600.00 |
| 79 | Pavement Marking (Paint)(4")(Yellow) | 32 17 23 | Pavement Markings | LNFT | $0.52 | 10,000 | $ 5,200.00 |
| 80 | Pavement Marking (Paint)(4")(White) | 32 17 23 | Pavement Markings | LNFT | $0.52 | 2,000 | $ 1,040.00 |
| 81 | Pavement Marking (Paint)(12")(White) | 32 17 23 | Pavement Markings | LNFT | $2.60 | 500 | $ 1,300.00 |
| 82 | Pavement Marking (Paint)(18")(White) | 32 17 23 | Pavement Markings | LNFT | $3.50 | 500 | $ 1,750.00 |
| 83 | Pavement Marking (Paint)(24")(White) | 32 17 23 | Pavement Markings | LNFT | $4.44 | 500 | $ 2,220.00 |
| 84 | Pavement Marking (Paint)(Symbol: Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $60.59 | 10 | $ 605.90 |
| 85 | Pavement Marking (Paint)(Symbol: Turn Arrow) | 32 17 23 | Pavement Markings | EACH | $55.82 | 20 | $ 1,116.40 |
| 86 | Pavement Marking (Paint)(Symbol: Turn and Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $65.99 | 5 | $ 329.95 |
| 87 | Pavement Marking (Paint)(Symbol: Bicycle) | 32 17 23 | Pavement Markings | EACH | $150.13 | 15 | $ 2,251.95 |
| 88 | Pavement Marking (Paint)(Symbol: Sharrow) | 32 17 23 | Pavement Markings | EACH | $150.13 | 15 | $ 2,251.95 |
| 89 | Pavement Marking (Paint)(Symbol: Handicap) | 32 17 23 | Pavement Markings | EACH | $52.41 | 30 | $ 1,572.30 |
| 90 | Pavement Marking (Paint)(Symbol: RR Crossing) | 32 17 23 | Pavement Markings | EACH | $300.71 | 2 | $ 601.42 |
| 91 | Pavement Marking (Paint)(Word "ONLY") | 32 17 23 | Pavement Markings | EACH | $97.00 | 6 | $ 582.00 |
| 92 | Pavement Marking (Epoxy)(4")(Yellow) | 32 17 23 | Pavement Markings | LNFT | $1.10 | 10,000 | $ 11,000.00 |
| 93 | Pavement Marking (Epoxy)(4")(White) | 32 17 23 | Pavement Markings | LNFT | $1.10 | 2,000 | $ 2,200.00 |
| 94 | Pavement Marking (Epoxy)(12")(White) | 32 17 23 | Pavement Markings | LNFT | $4.10 | 500 | $ 2,050.00 |
| 95 | Pavement Marking (Epoxy)(18")(White) | 32 17 23 | Pavement Markings | LNFT | $6.10 | 500 | $ 3,050.00 |
| 96 | Pavement Marking (Epoxy)(24")(White) | 32 17 23 | Pavement Markings | LNFT | $8.10 | 500 | $ 4,050.00 |
| 97 | Pavement Marking (Epoxy)(Symbol: Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $250.45 | 10 | $ 2,504.50 |
| 98 | Pavement Marking (Epoxy)(Symbol: Turn Arrow) | 32 17 23 | Pavement Markings | EACH | $250.45 | 20 | $ 5,009.00 |
| 99 | Pavement Marking (Epoxy)(Symbol: Turn and Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $275.68 | 5 | $ 1,378.40 |
| 100 | Pavement Marking (Epoxy)(Symbol: RR Crossing) | 32 17 23 | Pavement Markings | EACH | $350.72 | 2 | $ 701.44 |
| 101 | Pavement Marking (Epoxy)(Word "ONLY") | 32 17 23 | Pavement Markings | EACH | $250.45 | 5 | $ 1,252.25 |
| 102 | Pavement Marking (Thermoplastic)(12")(White) | 32 17 23 | Pavement Markings | LNFT | $10.00 | 500 | $ 5,000.00 |
| 103 | Pavement Marking (Thermoplastic)(18")(White) | 32 17 23 | Pavement Markings | LNFT | $15.82 | 500 | $ 7,910.00 |
| 104 | Pavement Marking (Thermoplastic)(24")(White) | 32 17 23 | Pavement Markings | LNFT | $20.05 | 500 | $ 10,025.00 |
| 105 | Pavement Marking (Thermoplastic)(Symbol: Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $150.45 | 10 | $ 1,504.50 |
| 106 | Pavement Marking (Thermoplastic)(Symbol: Turn Arrow) | 32 17 23 | Pavement Markings | EACH | $150.45 | 20 | $ 3,009.00 |
| 107 | Pavement Marking (Thermoplastic)(Symbol: Turn and Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $200.22 | 5 | $ 1,001.10 |
| 108 | Pavement Marking (Thermoplastic)(Symbol: Bicycle) | 32 17 23 | Pavement Markings | EACH | $175.68 | 15 | $ 2,635.20 |
| 109 | Pavement Marking (Thermoplastic)(Symbol: Sharrow) | 32 17 23 | Pavement Markings | EACH | $150.55 | 15 | $ 2,258.25 |
| 110 | Pavement Marking (Thermoplastic)(Symbol: RR Crossing) | 32 17 23 | Pavement Markings | EACH | $150.85 | 30 | $ 4,525.50 |
| 111 | Pavement Marking (Thermoplastic)(Word "ONLY") | 32 17 23 | Pavement Markings | EACH | $125.57 | 2 | $ 251.14 |
| 112 | Inset Pavement Markings | 33 17 23 | Pavement Markings | SQFT | $8.15 | 1,000 | $ 8,150.00 |
| 113 | Pavement Marking Removal | 33 17 23 | Pavement Markings | SQFT | $5.85 | 1,000 | $ 5,850.00 |
| 114 | Install Curb Inlet 2' X 3' X 5 | 33 40 00 | Storm Drainage Utilities | EACH | $4,250.85 | 4 | $ 17,003.40 |
| 115 | Install Curb Inlet 5' X 5' X 5' | 33 40 00 | Storm Drainage Utilities | EACH | $4,285.85 | 4 | $ 17,143.40 |
| 116 | Install Junction Box 5’ X 5’ X 5” | 33 40 00 | Storm Drainage Utilities | EACH | $8,100.82 | 2 | $ 16,201.64 |
| 117 | Install additional depth of drainage structure | 33 40 00 | Storm Drainage Utilities | LNFT | $390.67 | 30 | $ 11,720.10 |
| 118 | Raise Manhole Lid | 33 40 00 | Storm Drainage Utilities | EACH | $1,250.50 | 5 | $ 6,252.50 |
| 119 | Construct 12" Corrugated HDPE | 33 40 00 | Storm Drainage Utilities | LNFT | $54.00 | 50 | $ 2,700.00 |
| 120 | Construct 15" Corrugated HDPE | 33 40 00 | Storm Drainage Utilities | LNFT | $62.45 | 50 | $ 3,122.50 |
| 121 | Construct 18" Corrugated HDPE | 33 40 00 | Storm Drainage Utilities | LNFT | $71.93 | 50 | $ 3,596.50 |
| 122 | Construct 24" Corrugated HDPE | 33 40 00 | Storm Drainage Utilities | LNFT | $83.71 | 50 | $ 4,185.50 |
| 123 | Construct 30" Corrugated HDPE | 33 40 00 | Storm Drainage Utilities | LNFT | $92.57 | 50 | $ 4,628.50 |
| 124 | Construct 18" RCP | 33 40 00 | Storm Drainage Utilities | LNFT | $81.16 | 50 | $ 4,058.00 |
| 125 | Construct 24" RCP | 33 40 00 | Storm Drainage Utilities | LNFT | $93.94 | 50 | $ 4,697.00 |
| 126 | Construct 30" RCP | 33 40 00 | Storm Drainage Utilities | LNFT | $104.33 | 50 | $ 5,216.50 |
| 127 | Construct 36" RCP | 33 40 00 | Storm Drainage Utilities | LNFT | $155.95 | 50 | $ 7,797.50 |
| 128 | Construct 42" RCP | 33 40 00 | Storm Drainage Utilities | LNFT | $198.61 | 50 | $ 9,930.50 |
| 129 | Construct 48" RCP | 33 40 00 | Storm Drainage Utilities | LNFT | $225.35 | 50 | $ 11,267.50 |
| 130 | Construct 18" Flared End Section | 33 40 00 | Storm Drainage Utilities | EACH | $1,225.59 | 4 | $ 4,902.36 |
| 131 | Construct 24" Flared End Section | 33 40 00 | Storm Drainage Utilities | EACH | $1,402.61 | 4 | $ 5,610.44 |
| 132 | Construct 30" Flared End Section | 33 40 00 | Storm Drainage Utilities | EACH | $1,601.38 | 4 | $ 6,405.52 |
| 133 | Construct 36" Flared End Section | 33 40 00 | Storm Drainage Utilities | EACH | $1,650.93 | 4 | $ 6,603.72 |
| 134 | Construct 42" Flared End Section | 33 40 00 | Storm Drainage Utilities | EACH | $2,350.61 | 2 | $ 4,701.22 |
| 135 | Construct 48" Flared End Section | 33 40 00 | Storm Drainage Utilities | EACH | $2,608.96 | 2 | $ 5,217.92 |
| 136 | Trench Excavation (Trenches 5 feet of less in depth) | 31 00 00 | Earthwork | CUYD | $37.21 | 300 | $ 11,163.00 |
| 137 | Trench Excavation (Trenches exceeding 5 feet in depth) | 31 00 00 | Earthwork | CUYD | $41.00 | 150 | $ 6,150.00 |
| 138 | Trench Box (8' Tall) | 31 00 00 | Earthwork | WKLY | $1,000.55 | 4 | $ 4,002.20 |
| 139 | Construct 12" Trench Drain | 33 40 00 | Storm Drainage Utilities | LNFT | $237.75 | 30 | $ 7,132.50 |
| 140 | Down Spout Boot Cast Iron 4" | 33 40 00 | Storm Drainage Utilities | EACH | $475.88 | 5 | $ 2,379.40 |
| 141 | Down Spout Boot Cast Iron 6" | 33 40 00 | Storm Drainage Utilities | EACH | $701.83 | 5 | $ 3,509.15 |
| 142 | Down Spout Boot Cast Iron 8" | 33 40 00 | Storm Drainage Utilities | EACH | $1,100.77 | 5 | $ 5,503.85 |
| 143 | Down Spout Boot Steel 4" | 33 40 00 | Storm Drainage Utilities | EACH | $695.99 | 5 | $ 3,479.95 |
| 144 | Down Spout Boot Steel 6" | 33 40 00 | Storm Drainage Utilities | EACH | $975.29 | 5 | $ 4,876.45 |
| 145 | Down Spout Boot Steel 8" | 33 40 00 | Storm Drainage Utilities | EACH | $1,225.37 | 5 | $ 6,126.85 |
| 146 | Down Spout Lines PVC 6" | 33 40 00 | Storm Drainage Utilities | LNFT | $35.24 | 40 | $ 1,409.60 |
| 147 | Down Spout Lines PVC 8" | 33 40 00 | Storm Drainage Utilities | LNFT | $42.21 | 40 | $ 1,688.40 |
| 148 | Pipe Cleaning, Hydraulically Propelled Cleaning | 33 01 30.16 | TV Inspection and Cleaning of Sewer Pipelines | HOUR | $398.46 | 40 | $ 15,938.40 |
| 149 | Pipe Cleaning, Combination Hydraulically Propelled Cleaning and Vac Truck | 33 01 30.16 | TV Inspection and Cleaning of Sewer Pipelines | HOUR | $501.61 | 40 | $ 20,064.40 |
| 150 | TV Camera Inspection of Sewer Pipelines | 33 01 30.16 | TV Inspection and Cleaning of Sewer Pipelines | HOUR | $360.96 | 40 | $ 14,438.40 |
| 151 | Fence Posts (Metal)(2")(End, Corner, and Pull Posts)(Concrete Filled) | 32 31 13 | Fencing | EACH | $198.00 | 10 | $ 1,980.00 |
| 152 | Fence Posts (Metal)(2") | 32 31 13 | Fencing | EACH | $185.87 | 20 | $ 3,717.40 |
| 153 | Fence Fabric, Chain-Link | 32 31 13 | Fencing | SQYD | $60.33 | 1,400 | $ 84,462.00 |
| 154 | 3 Strand Barbed-Wire on Extension Arms | 32 31 13 | Fencing | LNFT | $5.99 | 200 | $ 1,198.00 |
| 155 | Fence Gate, Singe Swing (4' Width) with Gate Posts | 32 31 13 | Fencing | EACH | $889.00 | 3 | $ 2,667.00 |
| 156 | Fence Gate, Singe Swing (6' Width) with Gate Posts | 32 31 13 | Fencing | EACH | $1,025.00 | 1 | $ 1,025.00 |
| 157 | Fence Gate, Double Swing (12' width) with Gate Posts | 32 31 13 | Fencing | EACH | $1,945.00 | 1 | $ 1,945.00 |
| 158 | Concrete Mow Strip (24" wide x 4" deep) | 32 13 13.06 | Concrete Pavement | LNFT | $68.25 | 200 | $ 13,650.00 |
| 159 | Bollard (Steel Pipe)(Concrete Filled) | 32 31 13 | Fencing | EACH | $748.92 | 5 | $ 3,744.60 |
| 160 | Replace Isolated Bricks (Group < 50 Bricks) | 04 20 00 | Unit Masonry | EACH | $60.00 | 10 | $ 600.00 |
| 161 | Replace Bricks (Group ≥ 50 Bricks) | 04 20 00 | Unit Masonry | EACH | $20.33 | 500 | $ 10,165.00 |
| 162 | New CMU (8"x8"x16") Block Wall | 04 20 00 | Unit Masonry | SQFT | $22.77 | 2,000 | $ 45,540.00 |
| 163 | Replace CMU | 04 20 00 | Unit Masonry | EACH | $55.91 | 100 | $ 5,591.00 |
| 164 | Repointing Brick Masonry | 04 20 00 | Unit Masonry | LNFT | $12.75 | 100 | $ 1,275.00 |
| 165 | Repointing Stone Masonry | 04 20 00 | Unit Masonry | LNFT | $18.10 | 100 | $ 1,810.00 |
| 166 | Repointing Concrete Masonry | 04 20 00 | Unit Masonry | LNFT | $8.80 | 5,000 | $ 44,000.00 |
| 167 | Mortar Analysis | 04 03 00 | Conservation Treatement for Period Masonry | EACH | $1,600.00 | 50 | $ 80,000.00 |
| 168 | Replace Isolated Bricks (Group < 50 Bricks)(Historical) | 04 03 00 | Conservation Treatement for Period Masonry | EACH | $60.00 | 5,000 | $ 300,000.00 |
| 169 | Replace Bricks (Group ≥ 50 Bricks)(Historical) | 04 03 00 | Conservation Treatement for Period Masonry | EACH | $20.97 | 5,000 | $ 104,850.00 |
| 170 | Replace Stone Masonry (Rough Field)(Historical) | 04 03 00 | Conservation Treatement for Period Masonry | SQFT | $81.00 | 500 | $ 40,500.00 |
| 171 | Replace Stone Masonry (Dressed)(Historical) | 04 03 00 | Conservation Treatement for Period Masonry | SQFT | $81.00 | 500 | $ 40,500.00 |
| 172 | Repointing Masonry(Historical) | 04 03 00 | Conservation Treatement for Period Masonry | LNFT | $15.96 | 500 | $ 7,980.00 |
| 173 | Repointing Stone Masonry (Historical) | 04 03 00 | Conservation Treatement for Period Masonry | LNFT | $23.91 | 50 | $ 1,195.50 |
| 174 | Joint Sealant, Masonry Joints (width < 1/2") | 04 20 00 | Unit Masonry | LNFT | $7.75 | 50 | $ 387.50 |
| 175 | Joint Sealant, Masonry Joints (1/2" ≤ width < 3/4") | 04 20 00 | Unit Masonry | LNFT | $8.75 | 50 | $ 437.50 |
| 176 | Joint Sealant, Masonry Joints (3/4" ≤ width < 1") | 04 20 00 | Unit Masonry | LNFT | $9.75 | 50 | $ 487.50 |
| 177 | Joint Sealant, Masonry Joints (Width > 1") | 04 20 00 | Unit Masonry | LNFT | $15.76 | 250 | $ 3,940.00 |
| 178 | Concrete Chimney Crown | 04 20 00 | Unit Masonry | CUFT | $1,125.85 | 10 | $ 11,258.50 |
| 179 | Man Lift | 01 35 26 | Government Safety Requirements | DAY | $350.50 | 5 | $ 1,752.50 |
| 180 | Scaffolding (errected to 30 feet in height) | 01 35 26 | Government Safety Requirements | CSF | $1,250.75 | 100 | $ 125,075.00 |
| 181 | Scaffolding (errected over 30 feet in height to 60 feet) | 01 35 26 | Government Safety Requirements | CSF | $1,350.75 | 300 | $ 405,225.00 |
| 182 | Scaffolding (errected over 60 feet in elevation) | 01 35 26 | Government Safety Requirements | CSF | $1,500.55 | 100 | $ 150,055.00 |
| 183 | Flashing EPDM | 04 03 00 | Conservation Treatement for Period Masonry | SQFT | $14.75 | 100 | $ 1,475.00 |
| 184 | Remove and Replace Brick Paver Pedestrian/Light Vehicle 1 to 100 SF | 32 16 15 | Unit Pavers | SQFT | $35.66 | 200 | $ 7,132.00 |
| 185 | Remove and Replace Brick Pavers Pedestrian/Light Vehicle over 100 SF | 32 16 15 | Unit Pavers | SQFT | $38.98 | 700 | $ 27,286.00 |
| 186 | Remove and Replace Concrete Paver Pedestrian/Light Vehicle 1 to 100 SF | 32 16 15 | Unit Pavers | SQFT | $31.11 | 200 | $ 6,222.00 |
| 187 | Remove and Replace Concrete Pavers Pedestrian/Light Vehicle over 100 SF | 32 16 15 | Unit Pavers | SQFT | $26.38 | 700 | $ 18,466.00 |
| 188 | Remove and Replace Concrete Pavers Vehicle 1 to 100 SF | 32 16 15 | Unit Pavers | SQFT | $34.61 | 200 | $ 6,922.00 |
| 189 | Remove and Replace Concrete Pavers Vehicle Over 100 SF | 32 16 15 | Unit Pavers | SQFT | $30.00 | 700 | $ 21,000.00 |
| 190 | New Concrete Paver Pedestrian/Light Vehicle 1 to 100 SF | 32 16 15 | Unit Pavers | SQFT | $25.00 | 100 | $ 2,500.00 |
| 191 | New Concrete Pavers Pedestrian/Light Vehicle over 100 SF | 32 16 15 | Unit Pavers | SQFT | $23.00 | 500 | $ 11,500.00 |
| 192 | New Concrete Pavers Vehicle 1 to 100 SF | 32 16 15 | Unit Pavers | SQFT | $29.78 | 100 | $ 2,978.00 |
| 193 | New Concrete Pavers Vehicle Over 100 SF | 32 16 15 | Unit Pavers | SQFT | $26.15 | 300 | $ 7,845.00 |
| 194 | Concrete Pole Base | 03 30 00 | Cast-in-Place Concrete | EACH | $1,700.50 | 4 | $ 6,802.00 |
| 195 | Conduit, galvanized, 1" diameter | N/A | N/A | LNFT | $19.90 | 200 | $ 3,980.00 |
| 196 | Clearing Vegetation | 31 11 00 | Clearing and Grubbing | ACRE | $650.50 | 30 | $ 19,515.00 |
| 197 | Clearing and Grubbing Vegetation | 31 11 00 | Clearing and Grubbing | ACRE | $10,000.50 | 2 | $ 20,001.00 |
| 198 | Silt Fence | 01 57 19 | Temporary Environmental Controls | LNFT | $7.65 | 200 | $ 1,530.00 |
| 199 | Biodegrable Log | 01 57 19 | Temporary Environmental Controls | LNFT | $8.79 | 200 | $ 1,758.00 |
| 200 | Filter Sock | 01 57 19 | Temporary Environmental Controls | LNFT | $14.83 | 100 | $ 1,483.00 |
| 201 | Erosion Control Material (Class I) | 01 57 19 | Temporary Environmental Controls | SQYD | $5.50 | 200 | $ 1,100.00 |
| 202 | Erosion Control Material (Class II) | 01 57 19 | Temporary Environmental Controls | SQYD | $7.55 | 50 | $ 377.50 |
| 203 | Seeding (Tall Fescue application rate 0.1 LBS./SQYD) | 32 92 19 | Seeding | SQYD | $50.53 | 500 | $ 25,265.00 |
| 204 | Sodding | 32 92 23 | Sodding | SQYD | $145.57 | 300 | $ 43,671.00 |
| 205 | Hazarduous Material Handling | N/A | NO BID | TBD | 1 | $ - 0 |
SUBTOTAL $81,016.25 $3,053,254.82
Contractor Co-Efficient 0.00
Concrete Line Items Sub-Total (Pre-Bond) $0.00
| 206 | Payment & Performance Bond - On Task Order at or over $35,000.00 | % | 3% | $ - 0 | $ - 0 |
| 207 | Payment & Performance Bond - On Task Order at or over $150,000.00 | % | 3% | $ - 0 | $ - 0 |
TOTAL $0.00
Fort Leavenworth, Kansas
&P of &N
Option Year #1
| MISCELLANEOUS CONCRETE REPAIRS - BIDDING SCHEDULE | |||||||
| OPTION YEAR #1 | |||||||
| BID ITEM | DESCRIPTION | Unified Facilities Guide Specification | UNIT OF MEASURE | DPW - Cost Estimate | ESTIMATED QUANTITY | TOTAL COST | |
| 1 | New PCCP 6" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $141.36 | 20 | $ 2,827.20 |
| 2 | New PCCP 6" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $70.35 | 50 | $ 3,517.50 |
| 3 | New PCCP 6" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $60.50 | 200 | $ 12,100.00 |
| 4 | New PCCP 8" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $155.10 | 20 | $ 3,102.00 |
| 5 | New PCCP 8" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $90.72 | 50 | $ 4,536.00 |
| 6 | New PCCP 8" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $70.35 | 200 | $ 14,070.00 |
| 7 | New PCCP 10" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $181.26 | 20 | $ 3,625.20 |
| 8 | New PCCP 10" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $100.57 | 50 | $ 5,028.50 |
| 9 | New PCCP 10" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $65.10 | 200 | $ 13,020.00 |
| 10 | Replace PCCP 6" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $203.75 | 20 | $ 4,075.00 |
| 11 | Replace PCCP 6" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $115.00 | 50 | $ 5,750.00 |
| 12 | Replace PCCP 6" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $72.68 | 200 | $ 14,536.00 |
| 13 | Replace PCCP 8" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $225.53 | 20 | $ 4,510.60 |
| 14 | Replace PCCP 8" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $130.96 | 50 | $ 6,548.00 |
| 15 | Replace PCCP 8" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $90.88 | 200 | $ 18,176.00 |
| 16 | Replace PCCP 10" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $230.61 | 20 | $ 4,612.20 |
| 17 | Replace PCCP 10" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $135.35 | 50 | $ 6,767.50 |
| 18 | Replace PCCP 10" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $95.77 | 200 | $ 19,154.00 |
| 19 | New Curb & Gutter | 32 16 19 | Concrete Curbs Gutters and Sidewalks | LNFT | $35.22 | 250 | $ 8,805.00 |
| 20 | Replace Curb & Gutter | 32 16 19 | Concrete Curbs Gutters and Sidewalks | LNFT | $59.50 | 300 | $ 17,850.00 |
| 21 | New Concrete Sidewalk | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $39.85 | 250 | $ 9,962.50 |
| 22 | Replace Concrete Sidewalk | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $80.15 | 300 | $ 24,045.00 |
| 23 | New Sidewalk Ramp | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $86.50 | 40 | $ 3,460.00 |
| 24 | Replace Sidewalk Ramp | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $165.74 | 40 | $ 6,629.60 |
| 25 | New Sidewalk Ramp (Detectable Warning) | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $104.00 | 40 | $ 4,160.00 |
| 26 | Replace Sidewalk Ramp (Detectable Warning) | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $189.25 | 40 | $ 7,570.00 |
| 27 | New Concrete Slab | 03 30 00 | Cast-in-Place Concrete | CUYD | $192.95 | 150 | $ 28,942.50 |
| 28 | Replace Concrete Slab | 03 30 00 | Cast-in-Place Concrete | CUYD | $401.55 | 150 | $ 60,232.50 |
| 29 | New Elevated Concrete Slab | 03 30 00 | Cast-in-Place Concrete | CUYD | $1,058.34 | 5 | $ 5,291.70 |
| 30 | Replace Elevated Concrete Slab | 03 30 00 | Cast-in-Place Concrete | CUYD | $1,555.65 | 20 | $ 31,113.00 |
| 31 | Falsework for Elevated Slab | N/A | N/A | SQFT | $25.25 | 200 | $ 5,050.00 |
| 32 | Concrete Wall | 03 30 00 | Cast-in-Place Concrete | CUYD | $805.78 | 100 | $ 80,578.00 |
| 33 | Concrete Footer | 03 30 00 | Cast-in-Place Concrete | CUYD | $322.13 | 50 | $ 16,106.50 |
| 34 | New On-Grade Steps | 03 30 00 | Cast-in-Place Concrete | LF Nose | $81.00 | 75 | $ 6,075.00 |
| 35 | Replace On-Grade Steps | 03 30 00 | Cast-in-Place Concrete | LF Nose | $184.83 | 100 | $ 18,483.00 |
| 36 | New Above-Grade Steps | 03 30 00 | Cast-in-Place Concrete | CUYD | $881.77 | 5 | $ 4,408.85 |
| 37 | Replace Above-Grade Steps | 03 30 00 | Cast-in-Place Concrete | CUYD | $1,602.50 | 10 | $ 16,025.00 |
| 38 | Capillary Water Barrier (4") | 03 30 00 31 00 00 | Cast-in-Place Concrete Earthwork | SQYD | $12.00 | 200 | $ 2,400.00 |
| 39 | Vaper Barrier | 03 30 00 31 00 00 | Cast-in-Place Concrete Earthwork | SQYD | $2.75 | 200 | $ 550.00 |
| 40 | Flowable Fill Concrete | N/A | N/A | CUYD | $201.45 | 30 | $ 6,043.50 |
| 41 | Reinforcing Steel | 03 20 00.10 | Concrete Reinforcing | LBS | $1.51 | 10,000 | $ 15,100.00 |
| 42 | Reinforcing Steel (Epoxy Coated) | 03 20 00.10 | Concrete Reinforcing | LBS | $1.75 | 500 | $ 875.00 |
| 43 | Woven Wire Steel Fabric 4 X 4 | 03 20 00.10 | Concrete Reinforcing | SQYD | $5.98 | 1,000 | $ 5,980.00 |
| 44 | Dowel Bars, Epoxy Coated and Baskets for Roadway 3/4" | 03 20 00.10 | Concrete Reinforcing | LNFT | $15.11 | 300 | $ 4,533.00 |
| 45 | Colored Concrete (Material Cost Dye) | N/A | NO BID | CUYD | 100 | $ - 0 | |
| 46 | Stamp Pattern in Concrete (Additional Labor Costs) | N/A | N/A | SQYD | $10.27 | 500 | $ 5,135.00 |
| 47 | Saw Cut Concrete or Asphalt 4" Thick | N/A | N/A | LNFT | $3.72 | 300 | $ 1,116.00 |
| 48 | Saw Cut Concrete or Asphalt 6" Thick | N/A | N/A | LNFT | $5.26 | 200 | $ 1,052.00 |
| 49 | Saw Cut Concrete or Asphalt 8" Thick | N/A | N/A | LNFT | $6.62 | 200 | $ 1,324.00 |
| 50 | Sealing PCCP Joints (>1/8" to 1/2") | 32 01 19.61 | Sealing Cracks in Rigid Pavement | LNFT | $3.35 | 500 | $ 1,675.00 |
| 51 | Sealing PCCP Cracks (>1/2" to 1") | 32 01 19.61 | Sealing Cracks in Rigid Pavement | LNFT | $7.01 | 500 | $ 3,505.00 |
| 52 | Sealing PCCP Cracks (>1" to 2") | 32 01 19.61 | Sealing Cracks in Rigid Pavement | LNFT | $14.98 | 50 | $ 749.00 |
| 53 | New handrail (<30" above ground) | 05 52 00 | Metal Railings | LNFT | $97.00 | 100 | $ 9,700.00 |
| 54 | Replace handrail (<30" above ground) | 05 52 00 | Metal Railings | LNFT | $166.34 | 50 | $ 8,317.00 |
| 55 | New Guardrail/Handrail (≥ 30" above ground) | 05 52 00 | Metal Railings | LNFT | $185.65 | 200 | $ 37,130.00 |
| 56 | Replace Guardrail/Handrail (≥ 30" above ground) | 05 52 00 | Metal Railings | LNFT | $262.38 | 50 | $ 13,119.00 |
| 57 | Construct Sub-base Less than 5 CY | 32 11 23 | Aggregate Base Courses | CUYD | $125.81 | 100 | $ 12,581.00 |
| 58 | Construct Sub-base 5 to 50 cubic yards | 32 11 23 | Aggregate Base Courses | CUYD | $112.20 | 100 | $ 11,220.00 |
| 59 | Construct Sub-base over 50 cubic yards | 32 11 23 | Aggregate Base Courses | CUYD | $99.98 | 175 | $ 17,496.50 |
| 60 | Common Excavation | 31 00 00 | Earthwork | CUYD | $11.00 | 1,500 | $ 16,500.00 |
| 61 | Common Excavation (Government Furnished) | 31 00 00 | Earthwork | CUYD | $13.25 | 1,500 | $ 19,875.00 |
| 62 | Common Excavation (Contractor Furnished) | 31 00 00 | Earthwork | CUYD | $25.00 | 1,500 | $ 37,500.00 |
| 63 | Embankment | 31 00 00 | Earthwork | CUYD | $32.94 | 500 | $ 16,470.00 |
| 64 | Embankment (Contractor Furnished) | 31 00 00 | Earthwork | CUYD | $41.77 | 100 | $ 4,177.00 |
| 65 | Salvage Topsoil | 31 00 00 | Earthwork | SQYD | $1.01 | 1,000 | $ 1,010.00 |
| 66 | Topsoil (Government Furnished) | 31 00 00 | Earthwork | CUYD | $11.43 | 1,500 | $ 17,145.00 |
| 67 | Rock Excavation | 31 00 00 | Earthwork | CUYD | $59.63 | 1,500 | $ 89,445.00 |
| 68 | Rip-Rap (D50)(4") | 31 00 00 | Earthwork | CUYD | $68.00 | 50 | $ 3,400.00 |
| 69 | Rip-Rap (D50)(6") | 31 00 00 | Earthwork | CUYD | $73.00 | 50 | $ 3,650.00 |
| 70 | Manipulation for Treated Subgrade | 32 11 30 | Lime Treated Subgrades | SQYD | $24.45 | 1,500 | $ 36,675.00 |
| 71 | Quicklime for Treated Subgrade | 32 11 30 | Lime Treated Subgrades | TONS | $330.46 | 20 | $ 6,609.20 |
| 72 | Hydrated Lime for Treated Subgrade | 32 11 30 | Lime Treated Subgrades | TONS | $485.76 | 20 | $ 9,715.20 |
| 73 | Geotextile Separation Fabric | 31 05 19 | Geosynthetics | SQYD | $2.75 | 1,000 | $ 2,750.00 |
| 74 | Core Drill (4”) Pavement Sampling | N/A | N/A | EACH | $100.33 | 20 | $ 2,006.60 |
| 75 | In-Situ Soil Sampling and Testing for soil classification | 32 11 13.13 | Lime Treated Subgrades | EACH | $800.51 | 5 | $ 4,002.55 |
| 76 | Replace Asphalt Incidental to Work | 32 12 16 | HMA | CUFT | $50.35 | 100 | $ 5,035.00 |
| 77 | Pavement Marking (Paint)(4")(Yellow)(Without Glass Beads) | 32 17 23 | Pavement Markings | LNFT | $0.52 | 3,000 | $ 1,560.00 |
| 78 | Pavement Marking (Paint)(4")(White)(Without Glass Beads) | 32 17 23 | Pavement Markings | LNFT | $0.52 | 5,000 | $ 2,600.00 |
| 79 | Pavement Marking (Paint)(4")(Yellow) | 32 17 23 | Pavement Markings | LNFT | $0.52 | 10,000 | $ 5,200.00 |
| 80 | Pavement Marking (Paint)(4")(White) | 32 17 23 | Pavement Markings | LNFT | $0.52 | 2,000 | $ 1,040.00 |
| 81 | Pavement Marking (Paint)(12")(White) | 32 17 23 | Pavement Markings | LNFT | $2.60 | 500 | $ 1,300.00 |
| 82 | Pavement Marking (Paint)(18")(White) | 32 17 23 | Pavement Markings | LNFT | $3.50 | 500 | $ 1,750.00 |
| 83 | Pavement Marking (Paint)(24")(White) | 32 17 23 | Pavement Markings | LNFT | $4.44 | 500 | $ 2,220.00 |
| 84 | Pavement Marking (Paint)(Symbol: Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $60.59 | 10 | $ 605.90 |
| 85 | Pavement Marking (Paint)(Symbol: Turn Arrow) | 32 17 23 | Pavement Markings | EACH | $55.82 | 20 | $ 1,116.40 |
| 86 | Pavement Marking (Paint)(Symbol: Turn and Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $65.99 | 5 | $ 329.95 |
| 87 | Pavement Marking (Paint)(Symbol: Bicycle) | 32 17 23 | Pavement Markings | EACH | $150.13 | 15 | $ 2,251.95 |
| 88 | Pavement Marking (Paint)(Symbol: Sharrow) | 32 17 23 | Pavement Markings | EACH | $150.13 | 15 | $ 2,251.95 |
| 89 | Pavement Marking (Paint)(Symbol: Handicap) | 32 17 23 | Pavement Markings | EACH | $52.41 | 30 | $ 1,572.30 |
| 90 | Pavement Marking (Paint)(Symbol: RR Crossing) | 32 17 23 | Pavement Markings | EACH | $300.71 | 2 | $ 601.42 |
| 91 | Pavement Marking (Paint)(Word "ONLY") | 32 17 23 | Pavement Markings | EACH | $97.00 | 6 | $ 582.00 |
| 92 | Pavement Marking (Epoxy)(4")(Yellow) | 32 17 23 | Pavement Markings | LNFT | $1.10 | 10,000 | $ 11,000.00 |
| 93 | Pavement Marking (Epoxy)(4")(White) | 32 17 23 | Pavement Markings | LNFT | $1.10 | 2,000 | $ 2,200.00 |
| 94 | Pavement Marking (Epoxy)(12")(White) | 32 17 23 | Pavement Markings | LNFT | $4.10 | 500 | $ 2,050.00 |
| 95 | Pavement Marking (Epoxy)(18")(White) | 32 17 23 | Pavement Markings | LNFT | $6.10 | 500 | $ 3,050.00 |
| 96 | Pavement Marking (Epoxy)(24")(White) | 32 17 23 | Pavement Markings | LNFT | $8.10 | 500 | $ 4,050.00 |
| 97 | Pavement Marking (Epoxy)(Symbol: Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $250.45 | 10 | $ 2,504.50 |
| 98 | Pavement Marking (Epoxy)(Symbol: Turn Arrow) | 32 17 23 | Pavement Markings | EACH | $250.45 | 20 | $ 5,009.00 |
| 99 | Pavement Marking (Epoxy)(Symbol: Turn and Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $275.68 | 5 | $ 1,378.40 |
| 100 | Pavement Marking (Epoxy)(Symbol: RR Crossing) | 32 17 23 | Pavement Markings | EACH | $350.72 | 2 | $ 701.44 |
| 101 | Pavement Marking (Epoxy)(Word "ONLY") | 32 17 23 | Pavement Markings | EACH | $250.45 | 5 | $ 1,252.25 |
| 102 | Pavement Marking (Thermoplastic)(12")(White) | 32 17 23 | Pavement Markings | LNFT | $10.00 | 500 | $ 5,000.00 |
| 103 | Pavement Marking (Thermoplastic)(18")(White) | 32 17 23 | Pavement Markings | LNFT | $15.82 | 500 | $ 7,910.00 |
| 104 | Pavement Marking (Thermoplastic)(24")(White) | 32 17 23 | Pavement Markings | LNFT | $20.05 | 500 | $ 10,025.00 |
| 105 | Pavement Marking (Thermoplastic)(Symbol: Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $150.45 | 10 | $ 1,504.50 |
| 106 | Pavement Marking (Thermoplastic)(Symbol: Turn Arrow) | 32 17 23 | Pavement Markings | EACH | $150.45 | 20 | $ 3,009.00 |
| 107 | Pavement Marking (Thermoplastic)(Symbol: Turn and Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $200.22 | 5 | $ 1,001.10 |
| 108 | Pavement Marking (Thermoplastic)(Symbol: Bicycle) | 32 17 23 | Pavement Markings | EACH | $175.68 | 15 | $ 2,635.20 |
| 109 | Pavement Marking (Thermoplastic)(Symbol: Sharrow) | 32 17 23 | Pavement Markings | EACH | $150.55 | 15 | $ 2,258.25 |
| 110 | Pavement Marking (Thermoplastic)(Symbol: RR Crossing) | 32 17 23 | Pavement Markings | EACH | $150.85 | 30 | $ 4,525.50 |
| 111 | Pavement Marking (Thermoplastic)(Word "ONLY") | 32 17 23 | Pavement Markings | EACH | $125.57 | 2 | $ 251.14 |
| 112 | Inset Pavement Markings | 33 17 23 | Pavement Markings | SQFT | $8.15 | 1,000 | $ 8,150.00 |
| 113 | Pavement Marking Removal | 33 17 23 | Pavement Markings | SQFT | $5.85 | 1,000 | $ 5,850.00 |
| 114 | Install Curb Inlet 2' X 3' X 5 | 33 40 00 | Storm Drainage Utilities | EACH | $4,250.85 | 4 | $ 17,003.40 |
| 115 | Install Curb Inlet 5' X 5' X 5' | 33 40 00 | Storm Drainage Utilities | EACH | $4,285.85 | 4 | $ 17,143.40 |
| 116 | Install Junction Box 5’ X 5’ X 5” | 33 40 00 | Storm Drainage Utilities | EACH | $8,100.82 | 2 | $ 16,201.64 |
| 117 | Install additional depth of drainage structure | 33 40 00 | Storm Drainage Utilities | LNFT | $390.67 | 30 | $ 11,720.10 |
| 118 | Raise Manhole Lid | 33 40 00 | Storm Drainage Utilities | EACH | $1,250.50 | 5 | $ 6,252.50 |
| 119 | Construct 12" Corrugated HDPE | 33 40 00 | Storm Drainage Utilities | LNFT | $54.00 | 50 | $ 2,700.00 |
| 120 | Construct 15" Corrugated HDPE | 33 40 00 | Storm Drainage Utilities | LNFT | $62.45 | 50 | $ 3,122.50 |
| 121 | Construct 18" Corrugated HDPE | 33 40 00 | Storm Drainage Utilities | LNFT | $71.93 | 50 | $ 3,596.50 |
| 122 | Construct 24" Corrugated HDPE | 33 40 00 | Storm Drainage Utilities | LNFT | $83.71 | 50 | $ 4,185.50 |
| 123 | Construct 30" Corrugated HDPE | 33 40 00 | Storm Drainage Utilities | LNFT | $92.57 | 50 | $ 4,628.50 |
| 124 | Construct 18" RCP | 33 40 00 | Storm Drainage Utilities | LNFT | $81.16 | 50 | $ 4,058.00 |
| 125 | Construct 24" RCP | 33 40 00 | Storm Drainage Utilities | LNFT | $93.94 | 50 | $ 4,697.00 |
| 126 | Construct 30" RCP | 33 40 00 | Storm Drainage Utilities | LNFT | $104.33 | 50 | $ 5,216.50 |
| 127 | Construct 36" RCP | 33 40 00 | Storm Drainage Utilities | LNFT | $155.95 | 50 | $ 7,797.50 |
| 128 | Construct 42" RCP | 33 40 00 | Storm Drainage Utilities | LNFT | $198.61 | 50 | $ 9,930.50 |
| 129 | Construct 48" RCP | 33 40 00 | Storm Drainage Utilities | LNFT | $225.35 | 50 | $ 11,267.50 |
| 130 | Construct 18" Flared End Section | 33 40 00 | Storm Drainage Utilities | EACH | $1,225.59 | 4 | $ 4,902.36 |
| 131 | Construct 24" Flared End Section | 33 40 00 | Storm Drainage Utilities | EACH | $1,402.61 | 4 | $ 5,610.44 |
| 132 | Construct 30" Flared End Section | 33 40 00 | Storm Drainage Utilities | EACH | $1,601.38 | 4 | $ 6,405.52 |
| 133 | Construct 36" Flared End Section | 33 40 00 | Storm Drainage Utilities | EACH | $1,650.93 | 4 | $ 6,603.72 |
| 134 | Construct 42" Flared End Section | 33 40 00 | Storm Drainage Utilities | EACH | $2,350.61 | 2 | $ 4,701.22 |
| 135 | Construct 48" Flared End Section | 33 40 00 | Storm Drainage Utilities | EACH | $2,608.96 | 2 | $ 5,217.92 |
| 136 | Trench Excavation (Trenches 5 feet of less in depth) | 31 00 00 | Earthwork | CUYD | $37.21 | 300 | $ 11,163.00 |
| 137 | Trench Excavation (Trenches exceeding 5 feet in depth) | 31 00 00 | Earthwork | CUYD | $41.00 | 150 | $ 6,150.00 |
| 138 | Trench Box (8' Tall) | 31 00 00 | Earthwork | WKLY | $1,000.55 | 4 | $ 4,002.20 |
| 139 | Construct 12" Trench Drain | 33 40 00 | Storm Drainage Utilities | LNFT | $237.75 | 30 | $ 7,132.50 |
| 140 | Down Spout Boot Cast Iron 4" | 33 40 00 | Storm Drainage Utilities | EACH | $475.88 | 5 | $ 2,379.40 |
| 141 | Down Spout Boot Cast Iron 6" | 33 40 00 | Storm Drainage Utilities | EACH | $701.83 | 5 | $ 3,509.15 |
| 142 | Down Spout Boot Cast Iron 8" | 33 40 00 | Storm Drainage Utilities | EACH | $1,100.77 | 5 | $ 5,503.85 |
| 143 | Down Spout Boot Steel 4" | 33 40 00 | Storm Drainage Utilities | EACH | $695.99 | 5 | $ 3,479.95 |
| 144 | Down Spout Boot Steel 6" | 33 40 00 | Storm Drainage Utilities | EACH | $975.29 | 5 | $ 4,876.45 |
| 145 | Down Spout Boot Steel 8" | 33 40 00 | Storm Drainage Utilities | EACH | $1,225.37 | 5 | $ 6,126.85 |
| 146 | Down Spout Lines PVC 6" | 33 40 00 | Storm Drainage Utilities | LNFT | $35.24 | 40 | $ 1,409.60 |
| 147 | Down Spout Lines PVC 8" | 33 40 00 | Storm Drainage Utilities | LNFT | $42.21 | 40 | $ 1,688.40 |
| 148 | Pipe Cleaning, Hydraulically Propelled Cleaning | 33 01 30.16 | TV Inspection and Cleaning of Sewer Pipelines | HOUR | $398.46 | 40 | $ 15,938.40 |
| 149 | Pipe Cleaning, Combination Hydraulically Propelled Cleaning and Vac Truck | 33 01 30.16 | TV Inspection and Cleaning of Sewer Pipelines | HOUR | $501.61 | 40 | $ 20,064.40 |
| 150 | TV Camera Inspection of Sewer Pipelines | 33 01 30.16 | TV Inspection and Cleaning of Sewer Pipelines | HOUR | $360.96 | 40 | $ 14,438.40 |
| 151 | Fence Posts (Metal)(2")(End, Corner, and Pull Posts)(Concrete Filled) | 32 31 13 | Fencing | EACH | $198.00 | 10 | $ 1,980.00 |
| 152 | Fence Posts (Metal)(2") | 32 31 13 | Fencing | EACH | $185.87 | 20 | $ 3,717.40 |
| 153 | Fence Fabric, Chain-Link | 32 31 13 | Fencing | SQYD | $60.33 | 1,400 | $ 84,462.00 |
| 154 | 3 Strand Barbed-Wire on Extension Arms | 32 31 13 | Fencing | LNFT | $5.99 | 200 | $ 1,198.00 |
| 155 | Fence Gate, Singe Swing (4' Width) with Gate Posts | 32 31 13 | Fencing | EACH | $889.00 | 3 | $ 2,667.00 |
| 156 | Fence Gate, Singe Swing (6' Width) with Gate Posts | 32 31 13 | Fencing | EACH | $1,025.00 | 1 | $ 1,025.00 |
| 157 | Fence Gate, Double Swing (12' width) with Gate Posts | 32 31 13 | Fencing | EACH | $1,945.00 | 1 | $ 1,945.00 |
| 158 | Concrete Mow Strip (24" wide x 4" deep) | 32 13 13.06 | Concrete Pavement | LNFT | $68.25 | 200 | $ 13,650.00 |
| 159 | Bollard (Steel Pipe)(Concrete Filled) | 32 31 13 | Fencing | EACH | $748.92 | 5 | $ 3,744.60 |
| 160 | Replace Isolated Bricks (Group < 50 Bricks) | 04 20 00 | Unit Masonry | EACH | $60.00 | 10 | $ 600.00 |
| 161 | Replace Bricks (Group ≥ 50 Bricks) | 04 20 00 | Unit Masonry | EACH | $20.33 | 500 | $ 10,165.00 |
| 162 | New CMU (8"x8"x16") Block Wall | 04 20 00 | Unit Masonry | SQFT | $22.77 | 2,000 | $ 45,540.00 |
| 163 | Replace CMU | 04 20 00 | Unit Masonry | EACH | $55.91 | 100 | $ 5,591.00 |
| 164 | Repointing Brick Masonry | 04 20 00 | Unit Masonry | LNFT | $12.75 | 100 | $ 1,275.00 |
| 165 | Repointing Stone Masonry | 04 20 00 | Unit Masonry | LNFT | $18.10 | 100 | $ 1,810.00 |
| 166 | Repointing Concrete Masonry | 04 20 00 | Unit Masonry | LNFT | $8.80 | 5,000 | $ 44,000.00 |
| 167 | Mortar Analysis | 04 03 00 | Conservation Treatement for Period Masonry | EACH | $1,600.00 | 50 | $ 80,000.00 |
| 168 | Replace Isolated Bricks (Group < 50 Bricks)(Historical) | 04 03 00 | Conservation Treatement for Period Masonry | EACH | $60.00 | 5,000 | $ 300,000.00 |
| 169 | Replace Bricks (Group ≥ 50 Bricks)(Historical) | 04 03 00 | Conservation Treatement for Period Masonry | EACH | $20.97 | 5,000 | $ 104,850.00 |
| 170 | Replace Stone Masonry (Rough Field)(Historical) | 04 03 00 | Conservation Treatement for Period Masonry | SQFT | $81.00 | 500 | $ 40,500.00 |
| 171 | Replace Stone Masonry (Dressed)(Historical) | 04 03 00 | Conservation Treatement for Period Masonry | SQFT | $81.00 | 500 | $ 40,500.00 |
| 172 | Repointing Masonry(Historical) | 04 03 00 | Conservation Treatement for Period Masonry | LNFT | $15.96 | 500 | $ 7,980.00 |
| 173 | Repointing Stone Masonry (Historical) | 04 03 00 | Conservation Treatement for Period Masonry | LNFT | $23.91 | 50 | $ 1,195.50 |
| 174 | Joint Sealant, Masonry Joints (width < 1/2") | 04 20 00 | Unit Masonry | LNFT | $7.75 | 50 | $ 387.50 |
| 175 | Joint Sealant, Masonry Joints (1/2" ≤ width < 3/4") | 04 20 00 | Unit Masonry | LNFT | $8.75 | 50 | $ 437.50 |
| 176 | Joint Sealant, Masonry Joints (3/4" ≤ width < 1") | 04 20 00 | Unit Masonry | LNFT | $9.75 | 50 | $ 487.50 |
| 177 | Joint Sealant, Masonry Joints (Width > 1") | 04 20 00 | Unit Masonry | LNFT | $15.76 | 250 | $ 3,940.00 |
| 178 | Concrete Chimney Crown | 04 20 00 | Unit Masonry | CUFT | $1,125.85 | 10 | $ 11,258.50 |
| 179 | Man Lift | 01 35 26 | Government Safety Requirements | DAY | $350.50 | 5 | $ 1,752.50 |
| 180 | Scaffolding (errected to 30 feet in height) | 01 35 26 | Government Safety Requirements | CSF | $1,250.75 | 100 | $ 125,075.00 |
| 181 | Scaffolding (errected over 30 feet in height to 60 feet) | 01 35 26 | Government Safety Requirements | CSF | $1,350.75 | 300 | $ 405,225.00 |
| 182 | Scaffolding (errected over 60 feet in elevation) | 01 35 26 | Government Safety Requirements | CSF | $1,500.55 | 100 | $ 150,055.00 |
| 183 | Flashing EPDM | 04 03 00 | Conservation Treatement for Period Masonry | SQFT | $14.75 | 100 | $ 1,475.00 |
| 184 | Remove and Replace Brick Paver Pedestrian/Light Vehicle 1 to 100 SF | 32 16 15 | Unit Pavers | SQFT | $35.66 | 200 | $ 7,132.00 |
| 185 | Remove and Replace Brick Pavers Pedestrian/Light Vehicle over 100 SF | 32 16 15 | Unit Pavers | SQFT | $38.98 | 700 | $ 27,286.00 |
| 186 | Remove and Replace Concrete Paver Pedestrian/Light Vehicle 1 to 100 SF | 32 16 15 | Unit Pavers | SQFT | $31.11 | 200 | $ 6,222.00 |
| 187 | Remove and Replace Concrete Pavers Pedestrian/Light Vehicle over 100 SF | 32 16 15 | Unit Pavers | SQFT | $26.38 | 700 | $ 18,466.00 |
| 188 | Remove and Replace Concrete Pavers Vehicle 1 to 100 SF | 32 16 15 | Unit Pavers | SQFT | $34.61 | 200 | $ 6,922.00 |
| 189 | Remove and Replace Concrete Pavers Vehicle Over 100 SF | 32 16 15 | Unit Pavers | SQFT | $30.00 | 700 | $ 21,000.00 |
| 190 | New Concrete Paver Pedestrian/Light Vehicle 1 to 100 SF | 32 16 15 | Unit Pavers | SQFT | $25.00 | 100 | $ 2,500.00 |
| 191 | New Concrete Pavers Pedestrian/Light Vehicle over 100 SF | 32 16 15 | Unit Pavers | SQFT | $23.00 | 500 | $ 11,500.00 |
| 192 | New Concrete Pavers Vehicle 1 to 100 SF | 32 16 15 | Unit Pavers | SQFT | $29.78 | 100 | $ 2,978.00 |
| 193 | New Concrete Pavers Vehicle Over 100 SF | 32 16 15 | Unit Pavers | SQFT | $26.15 | 300 | $ 7,845.00 |
| 194 | Concrete Pole Base | 03 30 00 | Cast-in-Place Concrete | EACH | $1,700.50 | 4 | $ 6,802.00 |
| 195 | Conduit, galvanized, 1" diameter | N/A | N/A | LNFT | $19.90 | 200 | $ 3,980.00 |
| 196 | Clearing Vegetation | 31 11 00 | Clearing and Grubbing | ACRE | $650.50 | 30 | $ 19,515.00 |
| 197 | Clearing and Grubbing Vegetation | 31 11 00 | Clearing and Grubbing | ACRE | $10,000.50 | 2 | $ 20,001.00 |
| 198 | Silt Fence | 01 57 19 | Temporary Environmental Controls | LNFT | $7.65 | 200 | $ 1,530.00 |
| 199 | Biodegrable Log | 01 57 19 | Temporary Environmental Controls | LNFT | $8.79 | 200 | $ 1,758.00 |
| 200 | Filter Sock | 01 57 19 | Temporary Environmental Controls | LNFT | $14.83 | 100 | $ 1,483.00 |
| 201 | Erosion Control Material (Class I) | 01 57 19 | Temporary Environmental Controls | SQYD | $5.50 | 200 | $ 1,100.00 |
| 202 | Erosion Control Material (Class II) | 01 57 19 | Temporary Environmental Controls | SQYD | $7.55 | 50 | $ 377.50 |
| 203 | Seeding (Tall Fescue application rate 0.1 LBS./SQYD) | 32 92 19 | Seeding | SQYD | $50.53 | 500 | $ 25,265.00 |
| 204 | Sodding | 32 92 23 | Sodding | SQYD | $145.57 | 300 | $ 43,671.00 |
| 205 | Hazarduous Material Handling | N/A | NO BID | TBD | 1 | $ - 0 |
SUBTOTAL $81,016.25 $3,053,254.82
Contractor Co-Efficient 0.00
Concrete Line Items Sub-Total (Pre-Bond) $0.00
| 206 | Payment & Performance Bond - On Task Order at or over $35,000.00 | % | 3% | $ - 0 | $ - 0 |
| 207 | Payment & Performance Bond - On Task Order at or over $150,000.00 | % | 3% | $ - 0 | $ - 0 |
TOTAL $0.00
Fort Leavenworth, Kansas
&P of &N
Option Year #2
| MISCELLANEOUS CONCRETE REPAIRS - BIDDING SCHEDULE | |||||||
| BASE YEAR | |||||||
| BID ITEM | DESCRIPTION | Unified Facilities Guide Specification | UNIT OF MEASURE | DPW - Cost Estimate | ESTIMATED QUANTITY | TOTAL COST | |
| 1 | New PCCP 6" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $141.36 | 20 | $ 2,827.20 |
| 2 | New PCCP 6" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $70.35 | 50 | $ 3,517.50 |
| 3 | New PCCP 6" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $60.50 | 200 | $ 12,100.00 |
| 4 | New PCCP 8" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $155.10 | 20 | $ 3,102.00 |
| 5 | New PCCP 8" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $90.72 | 50 | $ 4,536.00 |
| 6 | New PCCP 8" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $70.35 | 200 | $ 14,070.00 |
| 7 | New PCCP 10" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $181.26 | 20 | $ 3,625.20 |
| 8 | New PCCP 10" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $100.57 | 50 | $ 5,028.50 |
| 9 | New PCCP 10" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $65.10 | 200 | $ 13,020.00 |
| 10 | Replace PCCP 6" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $203.75 | 20 | $ 4,075.00 |
| 11 | Replace PCCP 6" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $115.00 | 50 | $ 5,750.00 |
| 12 | Replace PCCP 6" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $72.68 | 200 | $ 14,536.00 |
| 13 | Replace PCCP 8" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $225.53 | 20 | $ 4,510.60 |
| 14 | Replace PCCP 8" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $130.96 | 50 | $ 6,548.00 |
| 15 | Replace PCCP 8" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $90.88 | 200 | $ 18,176.00 |
| 16 | Replace PCCP 10" Thick 1 to 25 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $230.61 | 20 | $ 4,612.20 |
| 17 | Replace PCCP 10" Thick 25 to 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $135.35 | 50 | $ 6,767.50 |
| 18 | Replace PCCP 10" Thick over 100 Square Yards | 32 13 13.06 | Concrete Pavement | SQYD | $95.77 | 200 | $ 19,154.00 |
| 19 | New Curb & Gutter | 32 16 19 | Concrete Curbs Gutters and Sidewalks | LNFT | $35.22 | 250 | $ 8,805.00 |
| 20 | Replace Curb & Gutter | 32 16 19 | Concrete Curbs Gutters and Sidewalks | LNFT | $59.50 | 300 | $ 17,850.00 |
| 21 | New Concrete Sidewalk | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $39.85 | 250 | $ 9,962.50 |
| 22 | Replace Concrete Sidewalk | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $80.15 | 300 | $ 24,045.00 |
| 23 | New Sidewalk Ramp | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $86.50 | 40 | $ 3,460.00 |
| 24 | Replace Sidewalk Ramp | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $165.74 | 40 | $ 6,629.60 |
| 25 | New Sidewalk Ramp (Detectable Warning) | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $104.00 | 40 | $ 4,160.00 |
| 26 | Replace Sidewalk Ramp (Detectable Warning) | 32 16 19 | Concrete Curbs Gutters and Sidewalks | SQYD | $189.25 | 40 | $ 7,570.00 |
| 27 | New Concrete Slab | 03 30 00 | Cast-in-Place Concrete | CUYD | $192.95 | 150 | $ 28,942.50 |
| 28 | Replace Concrete Slab | 03 30 00 | Cast-in-Place Concrete | CUYD | $401.55 | 150 | $ 60,232.50 |
| 29 | New Elevated Concrete Slab | 03 30 00 | Cast-in-Place Concrete | CUYD | $1,058.34 | 5 | $ 5,291.70 |
| 30 | Replace Elevated Concrete Slab | 03 30 00 | Cast-in-Place Concrete | CUYD | $1,555.65 | 20 | $ 31,113.00 |
| 31 | Falsework for Elevated Slab | N/A | N/A | SQFT | $25.25 | 200 | $ 5,050.00 |
| 32 | Concrete Wall | 03 30 00 | Cast-in-Place Concrete | CUYD | $805.78 | 100 | $ 80,578.00 |
| 33 | Concrete Footer | 03 30 00 | Cast-in-Place Concrete | CUYD | $322.13 | 50 | $ 16,106.50 |
| 34 | New On-Grade Steps | 03 30 00 | Cast-in-Place Concrete | LF Nose | $81.00 | 75 | $ 6,075.00 |
| 35 | Replace On-Grade Steps | 03 30 00 | Cast-in-Place Concrete | LF Nose | $184.83 | 100 | $ 18,483.00 |
| 36 | New Above-Grade Steps | 03 30 00 | Cast-in-Place Concrete | CUYD | $881.77 | 5 | $ 4,408.85 |
| 37 | Replace Above-Grade Steps | 03 30 00 | Cast-in-Place Concrete | CUYD | $1,602.50 | 10 | $ 16,025.00 |
| 38 | Capillary Water Barrier (4") | 03 30 00 31 00 00 | Cast-in-Place Concrete Earthwork | SQYD | $12.00 | 200 | $ 2,400.00 |
| 39 | Vaper Barrier | 03 30 00 31 00 00 | Cast-in-Place Concrete Earthwork | SQYD | $2.75 | 200 | $ 550.00 |
| 40 | Flowable Fill Concrete | N/A | N/A | CUYD | $201.45 | 30 | $ 6,043.50 |
| 41 | Reinforcing Steel | 03 20 00.10 | Concrete Reinforcing | LBS | $1.51 | 10,000 | $ 15,100.00 |
| 42 | Reinforcing Steel (Epoxy Coated) | 03 20 00.10 | Concrete Reinforcing | LBS | $1.75 | 500 | $ 875.00 |
| 43 | Woven Wire Steel Fabric 4 X 4 | 03 20 00.10 | Concrete Reinforcing | SQYD | $5.98 | 1,000 | $ 5,980.00 |
| 44 | Dowel Bars, Epoxy Coated and Baskets for Roadway 3/4" | 03 20 00.10 | Concrete Reinforcing | LNFT | $15.11 | 300 | $ 4,533.00 |
| 45 | Colored Concrete (Material Cost Dye) | N/A | NO BID | CUYD | 100 | $ - 0 | |
| 46 | Stamp Pattern in Concrete (Additional Labor Costs) | N/A | N/A | SQYD | $10.27 | 500 | $ 5,135.00 |
| 47 | Saw Cut Concrete or Asphalt 4" Thick | N/A | N/A | LNFT | $3.72 | 300 | $ 1,116.00 |
| 48 | Saw Cut Concrete or Asphalt 6" Thick | N/A | N/A | LNFT | $5.26 | 200 | $ 1,052.00 |
| 49 | Saw Cut Concrete or Asphalt 8" Thick | N/A | N/A | LNFT | $6.62 | 200 | $ 1,324.00 |
| 50 | Sealing PCCP Joints (>1/8" to 1/2") | 32 01 19.61 | Sealing Cracks in Rigid Pavement | LNFT | $3.35 | 500 | $ 1,675.00 |
| 51 | Sealing PCCP Cracks (>1/2" to 1") | 32 01 19.61 | Sealing Cracks in Rigid Pavement | LNFT | $7.01 | 500 | $ 3,505.00 |
| 52 | Sealing PCCP Cracks (>1" to 2") | 32 01 19.61 | Sealing Cracks in Rigid Pavement | LNFT | $14.98 | 50 | $ 749.00 |
| 53 | New handrail (<30" above ground) | 05 52 00 | Metal Railings | LNFT | $97.00 | 100 | $ 9,700.00 |
| 54 | Replace handrail (<30" above ground) | 05 52 00 | Metal Railings | LNFT | $166.34 | 50 | $ 8,317.00 |
| 55 | New Guardrail/Handrail (≥ 30" above ground) | 05 52 00 | Metal Railings | LNFT | $185.65 | 200 | $ 37,130.00 |
| 56 | Replace Guardrail/Handrail (≥ 30" above ground) | 05 52 00 | Metal Railings | LNFT | $262.38 | 50 | $ 13,119.00 |
| 57 | Construct Sub-base Less than 5 CY | 32 11 23 | Aggregate Base Courses | CUYD | $125.81 | 100 | $ 12,581.00 |
| 58 | Construct Sub-base 5 to 50 cubic yards | 32 11 23 | Aggregate Base Courses | CUYD | $112.20 | 100 | $ 11,220.00 |
| 59 | Construct Sub-base over 50 cubic yards | 32 11 23 | Aggregate Base Courses | CUYD | $99.98 | 175 | $ 17,496.50 |
| 60 | Common Excavation | 31 00 00 | Earthwork | CUYD | $11.00 | 1,500 | $ 16,500.00 |
| 61 | Common Excavation (Government Furnished) | 31 00 00 | Earthwork | CUYD | $13.25 | 1,500 | $ 19,875.00 |
| 62 | Common Excavation (Contractor Furnished) | 31 00 00 | Earthwork | CUYD | $25.00 | 1,500 | $ 37,500.00 |
| 63 | Embankment | 31 00 00 | Earthwork | CUYD | $32.94 | 500 | $ 16,470.00 |
| 64 | Embankment (Contractor Furnished) | 31 00 00 | Earthwork | CUYD | $41.77 | 100 | $ 4,177.00 |
| 65 | Salvage Topsoil | 31 00 00 | Earthwork | SQYD | $1.01 | 1,000 | $ 1,010.00 |
| 66 | Topsoil (Government Furnished) | 31 00 00 | Earthwork | CUYD | $11.43 | 1,500 | $ 17,145.00 |
| 67 | Rock Excavation | 31 00 00 | Earthwork | CUYD | $59.63 | 1,500 | $ 89,445.00 |
| 68 | Rip-Rap (D50)(4") | 31 00 00 | Earthwork | CUYD | $68.00 | 50 | $ 3,400.00 |
| 69 | Rip-Rap (D50)(6") | 31 00 00 | Earthwork | CUYD | $73.00 | 50 | $ 3,650.00 |
| 70 | Manipulation for Treated Subgrade | 32 11 30 | Lime Treated Subgrades | SQYD | $24.45 | 1,500 | $ 36,675.00 |
| 71 | Quicklime for Treated Subgrade | 32 11 30 | Lime Treated Subgrades | TONS | $330.46 | 20 | $ 6,609.20 |
| 72 | Hydrated Lime for Treated Subgrade | 32 11 30 | Lime Treated Subgrades | TONS | $485.76 | 20 | $ 9,715.20 |
| 73 | Geotextile Separation Fabric | 31 05 19 | Geosynthetics | SQYD | $2.75 | 1,000 | $ 2,750.00 |
| 74 | Core Drill (4”) Pavement Sampling | N/A | N/A | EACH | $100.33 | 20 | $ 2,006.60 |
| 75 | In-Situ Soil Sampling and Testing for soil classification | 32 11 13.13 | Lime Treated Subgrades | EACH | $800.51 | 5 | $ 4,002.55 |
| 76 | Replace Asphalt Incidental to Work | 32 12 16 | HMA | CUFT | $50.35 | 100 | $ 5,035.00 |
| 77 | Pavement Marking (Paint)(4")(Yellow)(Without Glass Beads) | 32 17 23 | Pavement Markings | LNFT | $0.52 | 3,000 | $ 1,560.00 |
| 78 | Pavement Marking (Paint)(4")(White)(Without Glass Beads) | 32 17 23 | Pavement Markings | LNFT | $0.52 | 5,000 | $ 2,600.00 |
| 79 | Pavement Marking (Paint)(4")(Yellow) | 32 17 23 | Pavement Markings | LNFT | $0.52 | 10,000 | $ 5,200.00 |
| 80 | Pavement Marking (Paint)(4")(White) | 32 17 23 | Pavement Markings | LNFT | $0.52 | 2,000 | $ 1,040.00 |
| 81 | Pavement Marking (Paint)(12")(White) | 32 17 23 | Pavement Markings | LNFT | $2.60 | 500 | $ 1,300.00 |
| 82 | Pavement Marking (Paint)(18")(White) | 32 17 23 | Pavement Markings | LNFT | $3.50 | 500 | $ 1,750.00 |
| 83 | Pavement Marking (Paint)(24")(White) | 32 17 23 | Pavement Markings | LNFT | $4.44 | 500 | $ 2,220.00 |
| 84 | Pavement Marking (Paint)(Symbol: Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $60.59 | 10 | $ 605.90 |
| 85 | Pavement Marking (Paint)(Symbol: Turn Arrow) | 32 17 23 | Pavement Markings | EACH | $55.82 | 20 | $ 1,116.40 |
| 86 | Pavement Marking (Paint)(Symbol: Turn and Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $65.99 | 5 | $ 329.95 |
| 87 | Pavement Marking (Paint)(Symbol: Bicycle) | 32 17 23 | Pavement Markings | EACH | $150.13 | 15 | $ 2,251.95 |
| 88 | Pavement Marking (Paint)(Symbol: Sharrow) | 32 17 23 | Pavement Markings | EACH | $150.13 | 15 | $ 2,251.95 |
| 89 | Pavement Marking (Paint)(Symbol: Handicap) | 32 17 23 | Pavement Markings | EACH | $52.41 | 30 | $ 1,572.30 |
| 90 | Pavement Marking (Paint)(Symbol: RR Crossing) | 32 17 23 | Pavement Markings | EACH | $300.71 | 2 | $ 601.42 |
| 91 | Pavement Marking (Paint)(Word "ONLY") | 32 17 23 | Pavement Markings | EACH | $97.00 | 6 | $ 582.00 |
| 92 | Pavement Marking (Epoxy)(4")(Yellow) | 32 17 23 | Pavement Markings | LNFT | $1.10 | 10,000 | $ 11,000.00 |
| 93 | Pavement Marking (Epoxy)(4")(White) | 32 17 23 | Pavement Markings | LNFT | $1.10 | 2,000 | $ 2,200.00 |
| 94 | Pavement Marking (Epoxy)(12")(White) | 32 17 23 | Pavement Markings | LNFT | $4.10 | 500 | $ 2,050.00 |
| 95 | Pavement Marking (Epoxy)(18")(White) | 32 17 23 | Pavement Markings | LNFT | $6.10 | 500 | $ 3,050.00 |
| 96 | Pavement Marking (Epoxy)(24")(White) | 32 17 23 | Pavement Markings | LNFT | $8.10 | 500 | $ 4,050.00 |
| 97 | Pavement Marking (Epoxy)(Symbol: Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $250.45 | 10 | $ 2,504.50 |
| 98 | Pavement Marking (Epoxy)(Symbol: Turn Arrow) | 32 17 23 | Pavement Markings | EACH | $250.45 | 20 | $ 5,009.00 |
| 99 | Pavement Marking (Epoxy)(Symbol: Turn and Thru Arrow) | 32 17 23 | Pavement Markings | EACH | $275.68 | 5 | $ 1,378.40 |
| 100 | Pavement Marking (Epoxy)(Symbol: RR Crossing) | 32 17 23 | Pavement Markings | EACH | $350.72 | 2 | $ 701.44 |
| 101 | Pavement Marking (Epoxy)(Word "ONLY") | 32 17 23 | Pavement Markings | EACH | $250.45 | 5 | $ 1,252.25 |
| 102 | Pavement Marking (Thermoplastic)(12")(White) | 32 17 23 | Pavement Markings | LNFT | $10.00 | 500 | $ 5,000.00 |
| 103 | Pavement Marking (Thermoplastic)(18")(White) | 32 17 23 | Pavement Markings | LNFT | $15.82 | 500 | $ 7,910.00 |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .