Attachment_6_con't.pdf

PDF 354 KB Posted

Attached to
Force Development Federal contract opportunity
Solicitation number
W91CRB-17-R-0030
Issued by
Department of the Army Materiel Command Army Contracting Command Aberdeen Proving Ground

About this file

Q&A's updated

View the file

Other files for this federal contract opportunity

Other files attached to Force Development, newest first.
File Type Posted
Attachment_6_con't.pdf PDF
W91CRB-17-R-0030-P0006.pdf PDF
A01_-_Cost_Model_-_FOrce_Development_-_12617.xlsx XLSX spreadsheet
W91CRB-17-R-0030-P0005.pdf PDF
A01_Workload_Data_Force_Development_12617.xlsx XLSX spreadsheet
Attachment_6_con't.pdf PDF
W91CRB-17-R-0030-P0004.pdf PDF
A07_Solicitation_Amendment_03_Conformed_Force_Development.pdf PDF
A07_Solicitation_Questions_W91CRB-17-R-0030.pdf PDF
A07_Solicitation_Amendment_03_Force_Development.pdf PDF
A07_Solicitation_Amendment_02_Force_Development.pdf PDF
A07_Solicitation_Questions_Amendment_02_W91CRB-17-R-0030.pdf PDF
A07_Solicitation_Amendment_02_Conformed_Force_Development.pdf PDF
A01_Cost_Model_Force_Development_Revised.xlsx XLSX spreadsheet
A07_Solicitation_Questions_W91CRB-17-R-0030.pdf PDF
A07_Solicitation_Amendment_01_Force_Development.pdf PDF
A07_Solicitation_Amendment_01_Conformed_Force_Development.pdf PDF
A01_Workload_Data_Force_Development_Revised.xlsx XLSX spreadsheet
A07_Solicitation_Draft_25Sep17_Force_Development.pdf PDF
A01_Workload_Data_Force_Development_25Sep17.xlsx XLSX spreadsheet
A01_CDRL_1_4May17.pdf PDF
A01_QASP_Final_Force_Development.pdf PDF
A01_Cost_Model_Force_Development_22Sep17.xlsx XLSX spreadsheet
A01_CDRL_2_4May17.pdf PDF
A01_DD254_Force_Development.pdf PDF
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 6 – Con’t

Question 43. Are subcontractors allowed to submit their pricing and compensation plans separately from the prime contractor as a sealed package sent directly to the Government or is the prime required to submit the prime as well as the subcontractors' response?

Answer: The subcontractors are permitted to submit their proposals separately to the Government

POC's listed on the solicitation.

Question 44.

We have made a concerted effort to include the fully burden rate on our offer letters.

Will they still be accepted or compliant with section L of the RFP since the release of the amendment?

Answer: Yes, those letters of intent will still be accepted.

Question 45: On the workload Data revised spread sheet, line 14 – does not reference PWS task area in the Reference PWS Paragraph – I think it should be Paragraph 3.0 thru 3.4 and 3.5.6.

Answer: Workload Data spreadsheet was updated to reflect PWS paragraph number for Line 14. It will read Paragraph 3.0 thru 3.4 and 3.5.6.