Attachment 6 – Con’t
Question 43. Are subcontractors allowed to submit their pricing and compensation plans separately from the prime contractor as a sealed package sent directly to the Government or is the prime required to submit the prime as well as the subcontractors' response?
Answer: The subcontractors are permitted to submit their proposals separately to the Government
POC's listed on the solicitation.
Question 44.
We have made a concerted effort to include the fully burden rate on our offer letters.
Will they still be accepted or compliant with section L of the RFP since the release of the amendment?
Answer: Yes, those letters of intent will still be accepted.
Question 45: On the workload Data revised spread sheet, line 14 – does not reference PWS task area in the Reference PWS Paragraph – I think it should be Paragraph 3.0 thru 3.4 and 3.5.6.
Answer: Workload Data spreadsheet was updated to reflect PWS paragraph number for Line 14. It will read Paragraph 3.0 thru 3.4 and 3.5.6.