Update_to_Question_9_on_Q_&_A_sheet_posted_27_Jul.docx

DOCX document 12 KB Posted

Attached to
Construction Materials
Solicitation number
W91B4N-18-A-8002
Issued by

About this file

Update to Q&A dtd, 27 July for #9

View the file

Other files

File Type Posted
NEW_BPA_Materials_Price_List-dtd_28_July_2018.xlsx XLSX spreadsheet
Revised_BPA_Materials_Price_List_Attachment_1.xlsx XLSX spreadsheet
Questions_and_Answers_for_BPA_Material.pdf PDF
BPA_Materials_Price_List_-_Attachment_1.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Previous Question and Revised Answer - 28 July 2018

9. Q. Is it obligatory for contractors to quote complete requirement or we can quote portions of the requirement i.e. Electrical & Lighting, Plumbing, Hardware etc…(Not All Portions)?

9. Answer: The contractors shall submit pricing for all commodities identified on the NEW BPA Materials Price List dated 28 July 2018