Update_to_Question_9_on_Q_&_A_sheet_posted_27_Jul.docx
DOCX document 12 KB Posted
- Attached to
- Construction Materials
- Solicitation number
- W91B4N-18-A-8002
About this file
Update to Q&A dtd, 27 July for #9
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NEW_BPA_Materials_Price_List-dtd_28_July_2018.xlsx | XLSX spreadsheet | |
| Revised_BPA_Materials_Price_List_Attachment_1.xlsx | XLSX spreadsheet | |
| Questions_and_Answers_for_BPA_Material.pdf | ||
| BPA_Materials_Price_List_-_Attachment_1.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Previous Question and Revised Answer - 28 July 2018
9. Q. Is it obligatory for contractors to quote complete requirement or we can quote portions of the requirement i.e. Electrical & Lighting, Plumbing, Hardware etc…(Not All Portions)?
9. Answer: The contractors shall submit pricing for all commodities identified on the NEW BPA Materials Price List dated 28 July 2018