Amendment W912WJ25Q0022-0003.pdf
PDF 614 KB Posted
- Solicitation number
- W912WJ25Q0022
About this file
This is Amendment 0003 to solicitation W912WJ25Q0022, issued by the US Army Corps of Engineers New England District, which extends the response deadline to January 22, 2025 at 5:00 PM Eastern and provides responses to industry questions about trough specifications and revised Statement of Work requirements.
The amendment clarifies that the drainage troughs shall be 18" wide (rather than 2 feet) and must be installed in three sections with watertight seals between sections, rather than as continuous lengths. The work involves installing four new stainless steel rain troughs at the Woonsocket Falls Dam Service Bridge in Woonsocket, RI, along with sealing four manhole access hatches and applying concrete deck/curb sealer to approximately 4,500 square feet of surface area. The period of performance is 180 days from Notice to Proceed, with work to be performed Monday-Friday 7:00 AM to 3:30 PM. This remains a small business set-aside under NAICS 238190 with an estimated value between $25,000-$100,000.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Drainage Holes.pdf | ||
| Amendment W912WJ25Q0022-0002.pdf | ||
| BE-1-1138.044.pdf | ||
| BE-1-1123.029.pdf | ||
| BE-1-1120.026.pdf | ||
| Amendment W912WJ25Q0022-0001.pdf | ||
| Solicitation W912WJ25Q0022.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W13G86429544740001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment is necessary to provide responses to questions from industry. Questions/responses #3 and #4 are applicable to this amendment.
The Statement of Work has been revised.
Closing is extended until January 22, 2025 at 5:00 PM Eastern.
1. CONTRACT ID CODE PAGE OF PAGES
1 11
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 14-Jan-2025
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ25Q0022
X 9B. DATED (SEE ITEM 11)
30-Dec-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
14-Jan-2025
CODE
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
jennifer.m.samela@usace.army.milEMAIL:978-318-8324TEL:
JENNIFER M SAMELA / ADDED BY UPASS
W912WJ25Q0022
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been modified:
REQUEST FOR INFORMATION
QUESTION 1: Solicitation states that rain troughs shall be approximately two (2) ft wide to catch water from additional one (1) inch drainage holes along deck expansion joints and bridge curb. Are the holes shown in information photo #4 the drainage holes? If not, where are the drainage holes located and can you provide pictures?
RESPONSE 1: Please see the additional photo included as an attachments with this amendment for the location of the drainage holes.
QUESTION 2: Since the As-Builts are pdf images embedded in a pdf, it is not possible to zoom in or expand the As-Builts to read the measurements. Can you provide copies of the As-Builts that will permit enlargement of the images?
RESPONSE 2: Larger scale As Builts are included as attachments with this amendment.
QUESTION 3: What width are the troughs required to be? Currently there is no minimum width or drawings that provide information on the width of the expansion joints and drainage holes.
RESPONSE 3: Please refer to the revised Statement of Work. Troughs shall be 18” wide.
QUESTION 4: Stainless steel can only be milled to a length of 10 ft. maximum. This makes a “continuous length” rain trough of 17 ft. not feasible as required per the specifications provided. What is acceptable?
RESPONSE 4: Please refer to the revised Statement of Work. The troughs will consist of three (3) sections, with one span in the middle and two spans on each end. The Contractor must ensure a watertight seal between all sections.
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 17-Jan-2025 05:00 PM to 22-Jan-2025 05:00 PM.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
STATEMENT OF WORK
Woonsocket Falls Dam Service Bridge Drainage Troughs and Sealing U.S. Army Corps of Engineers
Woonsocket Flood Reduction Project Woonsocket, RI
Statement of Work
REVISED
I. General
1. Scope of Work
Contractor shall provide all labor, equipment, materials, transportation, and permits for the installation and sealing of new drainage troughs, and manhole access hatch, concrete deck, and curb sealing at the Woonsocket Falls Dam Service Bridge. Note: See separately attached informational photos and documents for more information.
All work shall be completed in accordance with the following Statement of Work. Work shall be performed in a timely manner and to the satisfaction of the Technical Point of Contact (TPOC).
Note: This work requires the following submittals prior to the commencement of work:
ENG Form 6293 (Accident Prevention Plan Worksheet) Activity Hazard Analysis (AHA) ENG Form 6282 (Site Safety and Health Officer Designation Letter) First Aid/CPR Certifications Safety Data Sheets (SDS) for all chemicals and/or products to be used on-site.
Applicable license and permits.
2. Location
The required services shall be performed at the following project site location:
121 S Main Street, Woonsocket, Rhode Island.
3. Site Visit Contact the TPOC, Jason Monteiro (978) 318-8312 or Jason.T.Monteiro@usace.army.mil to arrange a site visit.
4. Schedule The period of performance shall be 180 days from Notice to Proceed. The project area will be open to the contractor Monday through Friday 7:00 AM to 3:30 PM and all work must be done during those hours unless additional hours are approved by the TPOC. No work shall be done on weekends or Government holidays.
All preconstruction submittals shall be submitted within 30 days of Notice to Proceed.
The Government reserves up to 21 days for review and acceptance on each submittal/ resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall be resubmitted to the Government in an acceptable form within 14 days of the Government’s response, unless additional time is granted by the Government in writing. No field work may proceed prior to the acceptance of preconstruction submittals.
5. Safety Requirements
a. General:
All work shall be conducted in accordance with the U.S. Army Corps of Engineers (USACE) Safety and Occupational Health Requirements (EM 385-1-1, most recent edition), and all applicable Occupational Safety and Health Administration (OSHA), federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed electronically at the following link:
https://www.publications.usace.army.mil/Portals/76/EM%20385-1- 1%20_EFFECTIVE%2015March2024.pdf
Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.
b. Accident Prevention Plan (APP):
The contractor shall prepare a site-specific Accident Prevention Plan. The APP must be written by a Competent Person (CP) and document the specific work processes, equipment, materials to be used, hazards and applicable control measures.
The mandatory ENG Form 6293 (Accident Prevention Plan Worksheet) must be submitted and accepted prior to beginning on site work:
https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_Aug%202024 %20-%20FINAL.pdf
A preparatory meeting shall be conducted by the prime contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing the subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.
Daily safety meetings shall be held and documented. Records shall be available to the TPOC upon request.
c. Activity Hazard Analysis (AHA):
An AHA shall be submitted and accepted for each definable feature of work (DFOW) in accordance with EM 385-1-1, Chapter 2-6. A DFOW is defined as any task, which is separate and distinct from other tasks, has separate control requirements, or is identified as different trades or disciplines. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.
For a non-mandatory formatted outline of an AHA, see ENG Form 6206 (Activity Hazard Analysis) https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2023Aug24.pdf
d. Site Safety and Health Officer (SSHO) Requirements:
The contractor shall employ a minimum of one person to function as a Level 3, SSHO. A Level 3 SSHO is a designated employee with collateral duty safety and occupational health (SOH) responsibilities that meets the requirements of EM 385-1- 1, Chapter 2-3.b and 2-4.b.
Level 3 SSHOs must possess:
Training, knowledge, and/or experience identifying hazards and implementing controls for the work being performed.
The SSHO shall be present at the project site and be responsible for overseeing the implementation of the prime contractor’s SOH program. Contractor shall designate all SSHOs on a mandatory ENG Form 6282 (Site Safety and Health Officer Designation Letter):
https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2023Aug28.pdf
e. First-Aid and CPR Personnel Requirements:
For shifts with multiple employees, provide at least two employees that are certified to administer First Aid and CPR. When employees work alone, they must be certified in First Aid and be provided an effective means of communication to call for assistance in the event of an emergency. Minimum First Aid and CPR qualifications are outlined in EM 385-1-1, Chapter 3-3.
f. Additional Personnel Requirements:
Other Competent or Qualified Persons may be required per EM 385-1-1 and/or other sections of this scope of work, based on the definable features of work for this project.
g. Accident Reporting:
All accidents and near misses shall be investigated by the contractor and reported to the TPOC in accordance with EM 385-1-1, Table 2-1.
The mandatory ENG Form 3394 shall be completed and submitted to the TPOC within seven (7) days of an incident:
https://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/Eng_ Form_3394_2021Aug.pdf
h. Employee Exposure Data:
The contractor shall electronically report total employee work hours (including subcontractors) to the TPOC by close of business on the 10th calendar day of the following month.
6. Preconstruction Conference
Prior to the start of any work, the TPOC will schedule and conduct a “Preconstruction Conference”. The Contractor’s Project Manager and Quality Control Personnel shall be physically present at this meeting. The Contractor shall directly oversee all work on the project and the Project Manager and Quality Control Personnel shall have the authority to act on behalf of the Contractor. This conference will be held at the time and location agreeable to the Government and Contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the TPOC to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor.
This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Preconstruction Conference the Contractor shall provide the name of the Project Superintendent with a telephone number for project coordination.
The following is a general list of items for discussion during this Preconstruction Conference:
Authority of the TPOC and Quality Assurance Inspectors Contractor’s Safety Program (including sub-contractors).
Activity Hazard Analysis.
Accident Prevention Plan (ENG Form 6293) SSHO Requirements Safety Meetings (Documented on NED Form 251) Accident Reporting (ENG Form 3394) Safety Data Sheet (SDS) requirements Correspondence, Communication and Administrative Procedures.
Invoice and payment.
7. Permits The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.
8. Security The Contractor will comply with all established security policies at the Project. Due to periods of heightened security that may affect the access to the areas covered under this contract, areas may be subject to periodic closures, which in turn may reduce or inhibit the Contractor’s ability to access certain areas. During periods of heightened security, the Government reserves the right, at any time, to close any property or portion of property and reschedule and/or cancel any subsequent service in an area. The Contractor shall be given at least 24-hour notice of any such closure.
9. Payment Payment shall be made on a per job basis. After final inspection and acceptance by the Government, the Contractor must submit an invoice and a completed, signed US Army Corps of Engineers ENG93 form to the TPOC. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due per line item. For jobs greater than 30 days the Contractor may request progress payments.
Invoice/Forms shall be mailed to:
US Army Corps of Engineers 518 East Hartford Ave., Uxbridge, MA 01569-1209 or emailed to Jason.T.Monteiro@usace.army.mil or faxed to the office at (508) 278-4234.
10. Damage to Government and Private Property The Contractor shall be responsible for restoring any Government facilities or structures damaged because of the firm’s operation. The Contractor shall also be responsible for any damage to private property or injury to any person because of the firm’s operations. The Contractor shall notify the TPOC immediately of damage to Government and private property and injury to any person resulting from the firms’ operation.
11. Point of Contact Requirements The Contractor shall provide to the TPOC a telephone number and a point of contact for discussion of any contractual matters.
II. Technical
1. Submittals:
Although the Government reviews submissions required by this Statement of Work, it is emphasized that the Contractor’s work must be completed using proper internal controls and review procedures. The Government reserves up to twenty-one (21) days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall resubmit to the Government in acceptable form within fourteen (14) days of the Government’s response, unless additional time is granted by the Government in writing.
The documents identified below must be prepared in accordance with the applicable standards, submitted to the TPOC for review and accepted by the Government.
Preconstruction Submittals: Submitted within thirty (30) days of Notice to Proceed. Submittals must be accepted prior to the commencement of any field work.
ENG Form 6293 (Accident Prevention Plan Worksheet) ENG Form 6282 (Site Safety and Health Officer Designation Letter) Appropriate licenses and certifications First Aid and CPR Certificates Activity Hazard Analysis (AHA) Material/Product Specification Sheets Safety Data Sheets (SDS) sheets for any products used
2. Clean Up:
The Contractor shall practice good housekeeping to maintain a safe job site. The contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials. Upon completing work in an area, the contractor shall remove any tools, equipment, and materials that are not the property of the Government.
Upon completion of work, the Contractor shall clean up the job site to the satisfaction of the Government.
3. Government Resources:
The Contractor is responsible for providing all materials to complete the project. Unless specified in the contract, the Government will not provide any equipment, telephone services or other resources.
4. Omissions:
This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.
5. Quality Assurance:
The Contractor is responsible for the quality control of the contract work. The Government has the right to inspect and test all items called for by the contract, to the extent practicable always and at all places during the term of the contract.
6. Other Contracts:
The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees. The Contractor shall not commit or permit any act, which will interfere with the performance of work by another contractor, or by Government employees.
7. Environmental Protection:
Containers for excess and/ or waste materials, rubbish, etc. shall be provided by the contractor at the site, and the site will be inspected/ cleaned daily. No burning is permissible. Water, air, and land resources shall not be adversely impacted during the work. Contractor will take necessary steps to ensure all federal, state, and local environmental regulatory requirements are met.
8. Sustainability All products provided by the contractor must meet the recycled content requirements set forth by the Environmental Protection Agency. Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for a complete list of designated products and the associated recommended contents levels. Offerors must be able to demonstrate that each offered products meets minimum content levels upon request.
Furthermore, the contractor should also meet the BioPreferred Program requirements.
The United States Department of Agriculture (USDA) designates certain bio-based products for federal procurement and specifies minimum bio-based content levels for those products. Any designated product that is being offered or supplied under this contract shall meet USDA BioPreferred's minimum bio-based content level. Visit the BioPreferred web site https://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml for the complete list of designated products and the associated minimum bio-based content level requirements.
9. Receiving and Storing Materials:
The Contractor is responsible for protecting any stored material until it is placed in service. The contractor is responsible for receiving and unloading of delivered goods.
Government employees will not receive material or supplies for the Contractor and will not be responsible for damage to contractor equipment or material.
General:
10. Existing Conditions:
Woonsocket Falls Service Bridge requires new rain troughs or gutters to be supplied and installed. During each rain event or snow melt event, water pours thru the bridge expansion joints, onto the catwalk and equipment below the bridge. New troughs and rain gutters will be installed to protect the equipment and personnel below.
Woonsocket Falls Service Bridge currently has four manhole/ access hatches installed in the bridge deck. The existing sealant, that seals out the water from the catwalk below, is beginning to fail and needs to be removed and replaced.
11. Products:
Rain Troughs, hardware and sealers shall meet or exceed the specifications listed below.
Application of products shall follow manufacturer’s recommendations and final measurements are the responsibility of the contractor.
a. Rain Troughs:
i. Quantity: 4
ii. Shall be designed to be compatible with existing bridge expansion joints which are approximately fourteen feet long.
iii. Seamless V-Shaped design, continuous length.
iv. Shall be designed to be installed as three (3) individual sections, one span in the center and two spans, one on each end, with a watertight connection/seal between each section.
v. Shall extend an additional minimum of eighteen inches (18”) beyond the edge of the bridge on both sides to ensure water does not splash on to the bridge.
vi. Shall be approximately two feet 18” wide, enough to capture water from additional one inch drainage holes along deck expansion joints and Bridge curb.
vii. Shall be pitched from a high point from the center of the deck to both sides, to allow water to flow away from the center.
viii. Trough and hardware shall be 316 Stainless Steel Construction.
ix. Trough shall be a minimum of 16-gauge thickness.
x. Shall use Stainless Steel Fasteners with Rubber Gaskets
xi. Rubber gaskets to run the length of the troughs, to provide a seal between the troughs and concrete deck.
xii. Shall be able to flex with bridge deck expansion joint.
b. Rain Trough (quantity 4) and Manhole/Access Hatch (quantity 4) Sealer
i. Four Rain Troughs, each trough approximately fourteen feet long with twenty-eight linear feet to be sealed.
ii. Four Manhole/Access Hatches, each hatch approximately four-foot square opening with sixteen liner feet to be sealed.
iii. Shall meet or exceed ASTM C 920, Type M, Grade NS, use T.
iv. Shall be a polyurethane elastomeric sealant.
v. Must be capable of a +/- 25% joint movement when cured.
vi. Non sag, tough, durable, and flexible consistency.
vii. Grey in color.
c. Concrete Bridge Deck and Curb Sealer
i. Approximately 4,500 square feet of Concrete surface to be sealed.
ii. Clear penetrating water repellent silane sealer.
iii. Composed of a minimum of 40% of active solids.
iv. For use on existing concrete surfaces.
v. Water based with reduced evaporation rate.
vi. For use on horizontal and vertical surfaces.
vii. Does not alter the existing surface after application.
viii. Long term protection against salt corrosion, mildew, water, wind driven rain, and surface spalling.
ix. Extends life of concrete.
x. Department of Transportation application use.
xi. Application of product shall follow manufacturer’s recommendations.
d. Surface Preparation
i. Prepare surfaces in accordance with product manufacturer recommendations for the trough and manhole/access hatch sealer.
ii. Prepare surfaces in accordance with product manufacturer recommendations for concrete and curb sealer.
12. Execution:
Installation of products shall occur in accordance with the scope of work and local and federal laws and the National Building Code.
a) Before the start of work, the schedule must be approved by the TPOC
b) Work area shall be restricted to contractors and USACE Employees
c) All products installed shall be properly tested by the contractor with the TPOC present
d) The equipment in the work area shall be protected from damage during the duration of the contract
e) Remove and dispose of exisitng sealer from Manhole/Access Hatches.
f) Clean surface and prepare for new Manhole/Access Hatches sealer
g) Clean concrete bridge deck and curb to prepare for new concrete sealer
h) Install new sealer around four (4) Manhole/Access Hatches.
i) Install new concrete sealer on the entirety of the bridge deck and the curbs
j) Remove and dispose of existing rain trough, any existing seals and any unused bolts that may prevent a watertight seal once new troughs are installed
k) Properly dispose of existing troughs/gutters, old sealant and associated material off site
l) Install the new gaskets for the new rain troughs.
m) Install the new rain troughs.
n) Install sealant in a manner that prevents any water leakage from the rain troughs.
o) Cleanup site and dispose of any construction debris off site.
p) Test all troughs with water onto each bridge deck expansion joint (4) and
Manhole/Access Hatches (4) with TPOC present, to ensure proper water flow and no observable leakage.
(End of Summary of Changes)