AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment is necessary to provide responses to questions from industry and revise the Statement of Work.
Solicitation closing remains March 8, 2024 at 5:00 PM Eastern.
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 15
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 26-Feb-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ24Q0057
X 9B. DATED (SEE ITEM 11)
15-Feb-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26-Feb-2024
CODE
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
jennifer.m.samela@usace.army.milEMAIL:978-318-8324TEL:
JENNIFER M SAMELA / ADDED BY UPASS
W912WJ24Q0057
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
REQUEST FOR INFORMATION
QUESTION 1: It appears as though the sizes provided are in inches only, not feet and inches.
The way they are written, 3084 and 6084, in the door industry, translates to 3'-0" x 8'-4" and 6'- 0" x 8'-4". Looking at the pictures however, you can clearly see these doors are not those sizes.
The (11) rows of 8" block is a dead giveaway. We believe the single door is 30" x 84" and the double door is 60" x 84". Please confirm if this is correct?
RESPONSE 1: The single wide door has an approximate rough opening of 39-1/2” x 89- 1/2”. Existing single door to be removed is 36” wide with a 12” x 12” door lite. Contractor shall provide a single door that is 36" x 84" with a minimum size 24” x 30” insulated door lite with security wire. The double door has an approximate rough opening of 64” x 88-1/2”. Existing double doors to be removed are 30” wide with a 12” x 12” door lite. Contractor shall provide double doors that are each 30" x 84" with a minimum size of 16” x 30” insulated door lite with security wire. Contractor shall verify all dimensions and layout of openings prior to providing door and frame product submittal.
QUESTION 2: Due to these sizes, the 24" x 30" lite they call for in each door will simply not fit.
Instead, the exposed glass size of the lites will be 16" x 30". Please confirm if this is acceptable?
RESPONSE 2: For the single door, the Contractor shall provide a minimum size of 24” x 30” top half insulated door lite with security wire. For each of the doors on the double door, the Contractor shall provide a minimum size of 16” x 30” top half insulated door lite with security wire.
QUESTION 3: Are we to provide wire in both panes of glass in each insulated glass unit, or one pane of wire glass and one pane of tempered glass?
RESPONSE 3: The Contractor shall provide one pane of wire glass and one pane of tempered glass.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
STATEMENT OF WORK
UTILITY BUILDING REHABILITATION
CAPE COD CANAL
U.S. ARMY CORP OF ENGINEERS
BUZZARDS BAY, MASSACHUSETTS
STATEMENT OF WORK
I. General
1. Scope of work
Contractor shall furnish all equipment, tools, materials, and labor to rehabilitate an existing 22’ x 30’ utility building at the Cape Cod Canal in accordance with this statement of work.
Repair work includes scraping and painting the exterior of the building, louvers, and standalone fuel tank enclosure; mortar repointing of exterior concrete material unit (CMU) block walls, replacement of three (3) windows, two (2) doors, and roof fascia trim. Work includes minor concrete repair work on holes in existing walls. Work includes the proper handling and disposal of Asbestos, Lead, and Polychlorinated biphenyls (PCBs) hazardous materials. An Industrial Hygienist shall provide 100% onsite project monitoring/oversight during demolition activities. (See Figure 1, Photos 1-11, and attached Environmental Consulting & Management Survey Report dated 9/29/23).
*Note: This work requires the following submittals prior to commencement of work (Refer to Section II. Technical Requirements for a full list of submittals):
Accident Prevention Plan and Activity Hazard Analyses for all fieldwork.
OSHA 10 Certification First Aid/CPR Certification (If 2 or more employees on site) Schedule Paints and Coatings Window Product Data and Shop Drawings: Include construction details, material descriptions, fabrication methods, dimensions of individual components and profiles, hardware, finishes, and operating instructions for each type of aluminum window indicated. Include plans, elevations, sections, details, hardware, weatherstripping, subframe assembly details, attachments to other work, operational clearances, installation details, and the following:
o Mullion details, including reinforcement and stiffeners.
o Joinery details.
o Weather-stripping details.
o Thermal-break details.
o Glazing details.
Doors: Submit the Fabrication Drawings for door units showing construction details, material descriptions, fabrication methods, dimensions of individual components and profiles, complete door assembly including hardware, and finishes. Include plans, elevations, sections, details, hardware, weatherstripping, subframe assembly details, attachments to other work, operational clearances, and installation details.
Asbestos Compliance Plan: A site-specific Asbestos Abatement Plan is required to be submitted and accepted by the Technical Point of Contact prior to initiating asbestos abatement tasks.
Lead Compliance Plan: A site-specific Lead Compliance Plan is required to be submitted and accepted by the Technical Point of Contact prior to initiating lead abatement tasks.
Polychlorinated biphenyls (PCBs) Compliance Plan: A site-specific PCB Compliance Plan is required to be submitted and accepted by the Technical Point of Contact prior to initiating PCB abatement tasks.
Asbestos, Lead, and PCB Final Clearance Sampling.
For all materials to be used on the project, the contractor shall provide the following information:
o Manufacturer’s name.
o Catalog number.
o Specifications o Any other information necessary to approve the materials.
o Safety Data Sheets (SDS) shall be submitted along with the product data for any potentially hazardous materials such as adhesives and flux materials.
2. Locations The utility building is located at 90 Main Street, Buzzards Bay, MA 02532. The building is next to the Buzzards Bay Railroad Bridge. Contractor parking for the building is available at the Buzzards Bay Recreation Area.
3. Site Visit A scheduled site visit will be listed in the Solicitation. The project area is enclosed by a security fence. Interested vendors should attend the site visit to confirm understanding of the scope, inspect building conditions, and inspect existing utility locations prior to submitting a quote. No extra payment will be allowed for perceived additional work caused by unfamiliarity with site conditions and requirements. After contract award, the Technical Point of Contact (TPOC) for the project is Travis Germano, (978) 318-8550 or travis.j.germano@usace.army.mil.
4. Schedule The work shall be completed within 210 days from Notice to Proceed. The project area will be open to the contractor Monday through Friday, with work hours form 0700-1800. All work must be done during these hours unless additional hours are approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays. Work done on the windows and doors shall be properly sequenced to ensure the building is always weather tight.
5. Safety Requirements:
A. General: All work shall be conducted in accordance with the U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1, most recent edition), and all applicable Occupational Safety and Health Administration (OSHA), federal, state, and local safety and health requirements. Perform work in a safe manner that protects both workers and the general public from hazards. All equipment shall be in good working order with all safety features as recommended by the manufacturer. A copy of EM 385-1-1 can be accessed at the project office or electronically at the following link:
https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_ 385-1-1.pdf
Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.
B. Accident Prevention Plan: The Contractor shall prepare an Accident Prevention Plan
(APP) specific to the activities being performed, at a minimum it must meet the requirements of EM 385-1-1, Appendix A. It shall include Activity Hazard Analyses (AHAs) as described below.
A preparatory meeting shall be conducted by the prime contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing the subcontractors of the safety provisions under the terms of the contract and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. Weekly safety meetings shall be held and documented. Records shall be available to the Technical Point of Contact upon request.
C. Activity Hazard Analysis: An AHA shall be submitted for each major phase of work. A major phase of work is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subcontractor or work crew is to perform the work. The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.
D. Required Personnel: The contractor shall employ a minimum of one Competent Person
(CP) at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO shall be onsite at all times during construction. The SSHO is required to have related construction experience and have at a minimum completed a 10 Hour OSHA training. An Industrial Hygienist shall provide 100% onsite project monitoring/oversight during demolition activities.
E. Accident Reporting: All accidents and near misses shall be investigated by the contractor and reported to the Technical Point of Contact immediately.
F. Daily Reports: The contractor shall provide daily production and QC reports, employee work hours, and certified payrolls electronically to the Technical Point of Contact.
G. Asbestos-Containing Materials (ACM): All Asbestos-Containing Materials activities, training, and submittals shall comply with Occupational Health and Safety
Administration (OSHA) Class II work practices, the EM 385-1-1, Section 06.C; 29 CFR 1910.1001; 29 CFR 1926.1101; CFR 61, Subpart A and M; as well as State and local requirements.
H. Lead Based Paint (LBP): All LBP work activities, training, and submittals shall comply with EM 385-1-1, Section 06.C; 29 CFR 1910.1025; 29 CFR 1926.62; as well as State and local requirements.
I. Polychlorinated biphenyls (PCBs): All PCB activities will need to be conducted under a disposal plan in accordance with 40 CFR 761.61; as well as State and local requirements.
6. Preconstruction Conference
Prior to the start of any work, the Contractor and Technical Point of Contact will schedule and conduct a “Preconstruction Conference”. The Contractor’s Project Manager and Quality Control Personnel will be physically present to attend this meeting. This conference will be scheduled for a time and location agreeable to the government and contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the requirements in terms of safety, quality, submittals, communications, inspections, and payments. Storage areas for materials, equipment and dumpsters will also be coordinated at this meeting.
7. Permits
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.
8. Security
The contractor shall comply with all established security policies at the Cape Cod Canal Project. The Government reserves the right to close any property and reschedule work.
Excluding emergencies, the Contractor shall be given at least 24-hour notice of any such closure.
9. Contractor Conduct
The work area is located on Federal property. Contractor and employees must always act in a professional manner. Alcohol and firearms are prohibited on project grounds.
10. Payment
Payment shall be made after final inspection and acceptance by the Government, the Contractor must submit an invoice, utilizing Form ENG 93, to the Technical Point of Contact. The invoice shall include the name of contractor (as per SAM registration), invoice date, contract number, description of work completed, and total amount due. For jobs greater than 30 days the contractor may request progress payments. Invoices may be emailed to:
US Army Corps of Engineers Cape Cod Canal Field Office P.O. Box 1555
Buzzards Bay, MA 02532 Attn: Travis Germano Or emailed to Travis.J.Germano@usace.army.mil
II. Technical Requirements:
Part 1 General:
Contractor’s work includes all personnel, equipment, materials, supervision, and work necessary to rehabilitate a 22’ x 30’ utility building at the Cape Cod Canal as described herein.
1. Requests for Information:
After Contract award, requests concerning the work of this project should be directed to the Technical Point of Contact at the Cape Cod Canal Office at (978) 318-8550 or travis.j.germano@usace.army.mil.
2. Submittals:
Contractor shall provide submittals that show pertinent details of proposed materials that allows confirmation the materials are in accordance with requirements listed in the materials section of this scope of work. Although the Government technically reviews submittals, the Contractor’s work must be prosecuted using proper internal controls and review procedures.
Contractor submittals must be reviewed and accepted by the government prior to the commencement of any field activities. Contractor shall provide required submittals to the Technical Point of Contact within 45 days of Notice to Proceed.
Required submittals include:
a. Accident Prevention Plan and Activity Hazard Analyses for all fieldwork.
b. Schedule
c. Paints and Coatings
d. Window Product Data and Shop Drawings: Include construction details, material descriptions, fabrication methods, dimensions of individual components and profiles, hardware, finishes, and operating instructions for each type of aluminum window indicated. Include plans, elevations, sections, details, hardware, weatherstripping, subframe assembly details, attachments to other work, operational clearances, installation details, and the following:
1. Mullion details, including reinforcement and stiffeners.
2. Joinery details.
3. Weather-stripping details.
4. Thermal-break details.
5. Glazing details.
e. Doors: Submit the Fabrication Drawings for door units showing construction details, material descriptions, fabrication methods, dimensions of individual components and profiles, complete door assembly including hardware, and finishes. Include plans, elevations, sections, details, hardware, weatherstripping, subframe assembly details, attachments to other work, operational clearances, and installation details.
f. Asbestos Compliance Plan: A site-specific Asbestos Abatement Plan is required to be submitted and accepted by the Technical Point of Contact prior to initiating asbestos abatement tasks.
g. Lead Compliance Plan: A site-specific Lead Compliance Plan is required to be submitted and accepted by the Technical Point of Contact prior to initiating lead abatement tasks.
h. Polychlorinated biphenyls (PCBs) Compliance Plan: A site-specific PCB Compliance Plan is required to be submitted and accepted by the Technical Point of Contact prior to initiating PCB abatement tasks.
i. Asbestos, Lead, and PCB Final Clearance Sampling
j. For all materials to be used on the project, the contractor shall provide the following information:
1) Manufacturer’s name
2) Catalog number
3) Specifications
4) Any other information necessary to approve the materials.
5) Safety Data Sheets (SDS) shall be submitted along with the product data for any potentially hazardous materials such as adhesives and flux materials.
3. Government Resources:
The government will provide reasonable amounts of water and electricity for the contractor to accomplish the work. The contractor is responsible for providing all other resources to complete the project. A Medeco removable core will be provided by the Government as stated in Part 2. Section 4. “Doors” below. The Government will not provide any additional equipment or services.
4. Omissions:
This scope of work may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.
5. Quality Control and Quality Assurance:
The Contractor is responsible for the quality control of all work. The Government has the right to inspect and test all items called for by the contract, to the extent practicable at all times during the term of the contract.
6. Other Contracts:
The Government may undertake or award other contracts for additional work not related to this contract, the Contractor shall fully cooperate with other Contractors and Government employees. The contractor shall not commit or permit any act, which will interfere with the performance of work by another contractor, or by Government employees.
7. Storage and Equipment Staging Areas:
Storage and equipment staging areas shall be coordinated with TPOC. Contractor is responsible to manage all storage of materials, dumpsters, and staging inside this work area.
The contractor is responsible for receiving, unloading and movement of all materials. The contractor shall ensure that stored materials do not migrate into the waterway, roadway, or railroad track right of way. Contractor shall ensure the area adjacent the railroad track right of way is clear at all times. Any materials that migrate into the waterway, roadways, sidewalks, bike paths, or recreation areas shall be cleaned up by the contractor daily. The Government is not responsible for damage or theft of contractor equipment or materials.
8. Clean Up:
The contractor shall practice good housekeeping to maintain a safe job site. The contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials. Upon completing work, the contractor shall remove all surplus tools, equipment, and materials, etc., that are not the property of the government and shall clean up the job site to the satisfaction of the government. Contractor shall leave the entire site and areas adjacent in a neat and orderly condition. Contractor shall clean up and properly dispose of debris off-site in accordance with Federal, State and Local ordinances and regulations.
9. Sustainability:
EPA Designated: Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for a complete list of designated products and the associated recommended contents levels.
Offerors must be able to demonstrate that each offered products meets minimum content levels upon request.
Part 2 Materials:
1. All products shall be new, unused and to the satisfaction of the Technical Point of Contact prior to installation. The source of materials which will affect the appearance of the finished work shall not be changed after the work has started except with the Technical Point of Contact’s written approval. All products shall be installed in accordance with the manufacturer or supplier’s recommendations.
2. Exterior Paint:
a. Primer Coat: Block Filler Primer Coat Per Manufacturer
b. Intermediate Coat: Elastomeric, Pigmented, Exterior, Water Based, Flat, MPI 113
c. Topcoat: Elastomeric, Pigmented, Exterior, Water Based, Flat, MPI 113
d. System Dry Film Thickness (DFT): 16 mils; Apply sufficient coats to achieve a minimum dry film thickness of 16 mils.
e. Surface preparation and number of coats in accordance with manufacturer's instructions.
f. Elastomeric Sealant: TT-S-00230C, Type II, Class A, ASTM C920, Type S, Grade
NS, Class 35
3. Windows (Quantity: 3):
a. Window Type: Double Hung, Tilt In
b. Rough Opening: 45-1/2” x 49-1/2” (approximately)
c. Window Material: Aluminum
d. AAMA/WDMA Performance Grade: AW-PG70
e. Air Infiltration (cfm/ft2) @ 6.24 psf: 0.20
f. Water Resistance (psf): 15
g. Uniform Load Deflection (psf): 70
h. Uniform Load Structural (psf): 105
i. Forced Entry Resistance: 10
j. U-Factor: 0.27 Btu/sq. ft. deg F or less
k. SHGC: 0.41 or less
l. Condensation-Resistance (CRF): 57
m. Aluminum Insect Screen Frames: Manufacturer's standard aluminum alloy complying with SMA 1004. Fabricate frames with mitered or coped joints or corner extrusions, concealed fasteners, and removable polyvinyl chloride boards (PVC) spline/anchor concealing edge of frame.
n. Hurricane Windborne Debris Impact Resistance (Large Missile).
o. Fabrication of window units must comply with AAMA/WDMA/CSA
101/I.S.2/A440.
p. Fasteners: Nonmagnetic stainless steel machined screws.
q. Anchors, Clips, and Accessories: Aluminum, nonmagnetic stainless steel, or zinc-coated steel or iron complying with ASTM B 633 for SC 3 severe service conditions;
provide sufficient strength to withstand design pressure indicated.
r. Compression-Type Weather Stripping: Provide compressible weather stripping designed for permanently resilient sealing under bumper or wiper action and for complete concealment when aluminum window is closed. Comply with
AAMA/WDMA/CSA 101/I.S.2/A440-08.
s. Sliding-Type Weather Stripping: Provide woven-pile weather stripping of wool, polypropylene, or nylon pile and resin-impregnated backing fabric. Comply with
AAMA 701/702.
t. Sealant: Provide window manufacturer's standard, permanently elastic, nonshrinking, and nonmigrating type recommended by sealant manufacturer for joint size and movement.
u. Contractor shall verify all dimensions and layout of window openings.
v. Window Warranty: Ten years from date of Substantial Completion.
4. Doors:
a. Contractor shall remove existing, furnish, and install (1) 3084 36” x 84” Commercial Metal Single Door and (1) 6084 60” x 84” Commercial Metal Double Door both which swing out to open. Door and frame shall be fabricated from commercial grade galvannealed steel. Doors shall be 18-gauge galvannealed steel, stiffened, insulated and sound deadened with honeycomb, polystyrene, or polyisocyanurate core. All doors shall have a 24” x 30” insulated door lite with security wire. The Single Door shall have a minimum size of 24” x 30” top half insulated door lite with security wire. The Double Doors shall have a minimum size of 16” x 30” top half insulated door lite with security wire on each door. Welded flush door frame shall be 16-gauge galvannealed steel. Door and frame shall be painted one coat of rust inhibitive metal primer and two finish coats of pro industrial urethane alkyd enamel paint or similar.
Color to be selected by the TPOC. Contractor shall verify all dimensions and layout of openings.
i. Handle: Heavy duty commercial “Crash-bar” type opening mechanism on inside of door with heavy duty handle on the outside.
ii. Hinges: Three heavy duty commercial grade stainless steel hinges per door with non-removable hinge pins.
iii. Lock Set: Heavy Duty Commercial Type Entry Mortise Lockset, Front Door Keyed (stainless steel finish). Lockset shall be compatible to receive a Medeco removable core, coordinate with TPOC. Medeco removable core will be provided by the Government.
iv. Threshold: Raised interior, extruded aluminum bumper threshold with neoprene seal or equal.
v. Door Holder/Closer: Stainless-Steel Heavy-Duty Grade 1 with hold-open feature. ADA compliant; die cast aluminum alloy body; heavy duty forged steel main arm; full rack and pinion construction; captivated valves; capable of delayed action; provide 120° door opening and alternate mounting 180° door opening; comply with UL 10C Positive Pressure Fire Test.
vi. Door Kick Plate: Stainless Steel
vii. Drip Cap: ANSI/BHMA A156.22 Certified; composed of aluminum alloy
6063; slotted screw holes for adjustment; mechanical attachment via stainless steel screws; 2 ½” wide by 1 ½” tall.
viii. Door Swing Handing: Right Hand Reverse (RHR) – Key Outside.
ix. Door Jamb Perimeter Weather Strip Set: Aluminum alloy 6063, T5 temper, Perimeter seal black neoprene, PVC, Nitrile rubber, and Chloroprene closed cell elastomeric foam sponge seal, installed with 3/4" stainless steel sheet metal screws.
x. After installation, protect hardware from paint, stains, blemishes, and other damage until acceptance of work. Adjust hinges, locks, latches, holders, closers, and other items to operate properly. Demonstrate that keys operate locks.
5. Roof Perimeter Fascia Trim
a. All existing roof perimeter trim shall be removed and replaced in kind utilizing polyvinyl chloride boards (PVC) trim boards of same size, shape, and dimensions.
Color shall be white.
6. Polymer-Modified Cementous Repair Mortar:
a. Polymer-Modified, portland cement, fast-setting, trowel-grade mortar that is a two-component material with a migrating corrosion inhibitor used to repair horizontal surfaces.
b. Compressive strength: ASTM C109/C109M: 6000 psi minimum at 28 days.
c. Bond Strength: ASTM C882/C882M Modified: 2000 psi minimum at 28 days moist cure.
Part 3 Execution
1. The contractor shall ensure that all submittals have been approved prior to onsite work and coordinate the schedule for all onsite work with the Government TPOC.
2. The Contractor shall coordinate all activities with the TPOC to limit impact of the operations of the Railroad Bridge. The movable span of the Railroad Bridge will remain operational during this work on the utility building. The contractor shall ensure the safety of the personal working on the building and that all personnel stay clear of railroad track right of way areas for train movements. The contractor is responsible for preventing the general public from encountering hazards associated with the work.
3. Work shall be performed as required by rules, regulations, codes, and laws of local, state, and federal governments. In cases where work is not specifically shown or specified, contract shall include miscellaneous items, appurtenances, devices, and materials obviously necessary for a sound, secure and complete installation.
4. Existing Conditions: Government will move interior cabinets to provide access to windows and walls. Contractor shall be responsible for the protection of all existing structures, equipment, and areas from damage during construction. Any items not included in the Statement of Work that are damaged or altered during construction shall be restored to their pre-construction condition at the contractor’s expense and verified as such by the Government TPOC. Any disturbed areas outside of the site shall be restored to the minimum of pre-existing conditions.
5. Utilities: Government personnel will identify known subsurface utilities, conduits and structures that are near the work area. All existing utilities shall be protected from damage.
No utilities may be interrupted unless approved by the Government TPOC. Contractor shall ensure to take safety measures to work near overhead electric and communication lines in close proximity of the work area.
6. Contractor shall maintain the building to be secure and weathertight at all times. Work shall be sequenced to minimize time that the openings are without functional replacement windows and doors. The contractor shall provide temporary means to secure all openings overnight if work is not completed in one day, or during inclement weather. Contractor shall fully install new doors, windows, and roof fascia trim prior to painting the exterior of the building.
7. ASBESTOS, LEAD, AND PCB DEMOLITION: The double door window glazing, interior window glazing, interior and exterior door caulking, exterior window caulking was found to be positive for asbestos content. The building’s exterior white paint, exterior door/trim white/grey paint, window frames grey paint was found to be positive for lead based paint.
The window glazing material was found to contain PCB’s. Contractor shall provide a site-specific Asbestos Abatement Plan, Lead Compliance Plan, and PCB Compliance Plan to be submitted and accepted by the TPOC prior to initiating the demolition tasks involving any of these materials. An Industrial Hygienist shall provide 100% onsite project monitoring/oversight during demolition activities. (See attached ECM Survey Report dated 9/29/23).
8. SURFACE PREPARATION: Contractor shall remove all chipped paint and loose particles by scaping and/or wire brushing. The Contractor shall scrape and/or wire brush the exterior of the building, trim, louvers, vent pipes, electrical conduits, standalone fuel tank on the east side of the building.
9. CLEAN SURFACES: Contractor shall soft wash the exterior concrete of the building and fuel tank to remove any and all dirt, grease, oil, fungus, and mold. Contractor shall collect and capture all water runoff. Contractor shall properly test and dispose of water runoff.
10. REPAIR MORTAR JOINTS: Contractor shall repair or fill mortar joints and minor defects, including but not limited to spalls, joints, cracks, and holes prior to paint coating application.
Repointing of the block walls shall be done on the interior and exterior of the building.
Contractor shall repair any concrete wall deficiencies, fill and patch holes in the concrete block walls, and smooth sloped sills on both the interior and exterior of the building.
Contractor shall repair window and door openings as necessary to meet manufacturer’s requirements to install new units.
11. CRACK REPAIR: Contractor shall repair any gaps or cracks in the walls which are too small for mortar repair with elastomeric sealant.
12. REPLACE WINDOWS: Work includes demolition and replacement of three (3) windows.
The entire frame of each existing window shall be removed. Removal of the windows shall be done by appropriate means that will not damage the building and other equipment in proximity.
13. Examine window openings, substrates, structural support, anchorage, and conditions for compliance with requirements for installation tolerances and other conditions affecting performance of work. Verify rough opening dimensions, levelness of sill plate, and operational clearances. Proceed with installation only after unsatisfactory conditions have been corrected. Comply with manufacturer's written instructions for installing windows, hardware, accessories, flashing, and other components. Clean masonry surfaces to ensure they are visibly dry and free of excess mortar, sand, and other construction debris. Check opening for plumb and level. Repair any deficiencies of opening to accept new windows.
Prepare the opening by installing a liquid water-resistant flashing coating on all four sides of the opening. Extend the liquid water-resistant flashing coating 6” onto the exterior wall surface for continuity. Install windows level, plumb, square, true to line, and anchored securely in place. Set window sill members in bed of sealant or with gaskets, as indicated, for weathertight construction. Install windows and components to drain condensation, water penetrating joints, and moisture migrating within windows to the exterior. Adjust operating sashes, screens, hardware, and accessories for a tight fit at contact points and weather stripping for smooth operation and weathertight closure. Use a low pressure polyurethane window and door insulating foam sealant to create an interior seal. Install interior/exterior PVC trim to provide a finished system. Lubricate hardware and moving parts. Just prior to final acceptance, perform final cleaning of glass and aluminum window to remove any accumulations that may have occurred during the construction period.
14. REPLACE DOORS: Work includes demolition and replacement of two (2) doors. The entire frame of each existing door shall be removed. Removal of the doors shall be done by appropriate means that will not damage the building and other equipment in proximity. Set door frames in accordance with SDI/DOOR A250.11. Plumb, align, and brace securely until permanent anchors are set. Hang doors in accordance with clearances specified in SDI/DOOR A250.8. Comply with shop drawings and manufacturer's written instructions for installing doors, hardware, accessories, and other components. The contractor is responsible for any shims needed between the wall and frame at the location of anchors and spreaders to maintain squareness and alignment of frame, and to maintain door opening sizes. Gaps shall be sealed as part of the installation process. Use a low pressure polyurethane window and door insulating foam sealant to create an interior seal. Install interior/exterior PVC trim to provide a finished system. After erection and glazing, clean, and adjust hardware.
15. ROOF PERIMETER FASCIA TRIM: Work includes demolition and replacement of all roof perimeter fascia trim. Contractor shall remove the existing deteriorated wood fascia trim and replace with new polyvinyl chloride boards (PVC) trim boards of same size, shape, and dimensions. Color shall be white. Fasteners shall be stainless steel.
16. PAINT: Exterior building, trim, louvers, gable end vents, and fuel tank shall be primed and painted. The interior and exterior doors and frames shall be primed and painted.
17. Contractor shall provide one coat of primer. Building exterior concrete wall shall be painted one coat of a quality acrylic block fill primer. Doors and frames interior/exterior shall be painted one coat of rust inhibitive metal primer.
18. Contractor will apply a premium exterior elastomeric paint to the building exterior walls. A minimum of two coats will be applied. Each coat will be given ample time to dry per manufacturer’s instructions. Doors and frames interior/exterior and fuel tank shall be painted two coats of pro industrial urethane alkyd enamel paint or similar. Color to be selected by the
TPOC.
a. One coat of undercoat or intermediate coat.
b. One topcoat.
19. Unless otherwise specified or recommended by the paint manufacturer, paint may be applied by brush, roller, or spray.
20. Only apply paints to surfaces that are completely free of moisture as determined by sight or touch. Thoroughly work coating materials into joints, crevices, and open spaces. Pay special attention to ensure that all edges, corners, and crevices receive a film thickness equal to that of adjacent painted surfaces. Apply each coat of paint so that dry film is of uniform thickness and free from runs, drops, ridges, waves, pinholes or other voids, laps, brush marks, and variations in color, texture, and finish. Completely hide all blemishes. Allow drying time between coats, as recommended by the coating manufacturer, to permit thorough drying, but not to present topcoat adhesion problems. Provide finished surfaces free from runs, drops, ridges, waves, laps, brush marks, and variations in colors.
21. Disposal: Local regulations regarding hauling and disposal shall apply. Contractor shall dispose of all debris resulting from the construction work. Contractor shall leave the entire site of the work in a neat and orderly condition. Debris, rubbish, non-hazardous waste, and non-usable material resulting from the work under this contract shall be disposed of by the Contractor at their expense off Government property. Segregate and maximize recycling of all waste generated. Debris shall be removed and transported in such a manner that prevents damage to local roads and spillage. Prior to disposal, construction waste suspected to contain lead must undergo Toxic Characteristic Leaching Procedure (TCLP) sampling for lead. The EPA specifies that waste containing greater than 5.0 mg/l of lead be disposed of as lead waste. Asbestos, Lead, and Polychlorinated biphenyls (PCBs) hazardous materials shall be properly handled and disposal of in accordance with all local, state, and federal regulations.
22. Closeout Procedures: Contractor shall coordinate with the TPOC for the following at the completion of the project:
a. A final inspection walkthrough of the project to ensure the work is completed in accordance with the Statement of Work.
b. U.S. EPA Notification of Demolition and Renovation Form
c. Asbestos, Lead, and PCB Final Clearance Test Results
d. Hazardous Waste Manifest for all Debris
e. Warranty
f. Complete Final Payment Forms and Certifications.
(End of Summary of Changes)