About this file

This document is an amendment to a solicitation for wire rope replacement services at the Woonsocket Falls Dam in Woonsocket, Rhode Island. The U.S. Army Corps of Engineers Engineering District New England is seeking to replace approximately 50 feet of wire rope on Tainter Gate 2. The amendment provides responses to six questions from industry. Magnetic flux leakage testing is no longer required but pre-stretching and tension testing of the new wire rope must be performed. The public boat ramp 1 mile upstream may be used for small boat access but is not suitable for large boats. Any remaining trees can be removed under the tree removal option. Manhole covers on the service bridge can provide overhead access to the catwalk platform when reseated with approved sealant. Existing materials used in a temporary repair on the gate must remain on site and be returned to the contracting officer once removed. The closing date for proposals remains October 31, 2023 at 5:00 PM Eastern time.

View the file

Other files for this federal contract opportunity

Other files attached to Wire Rope Replacement, Woonsocket Falls Dam, Woonsocket, RI, newest first.
File Type Posted
Photographs_Plans_Drawings.pdf PDF
Specifications_Revised 25 Oct.pdf PDF
Amendment W912WJ24Q0001-0004.pdf PDF
Specifications and Plans_Revised 16 Oct.pdf PDF
Amendment W912WJ24Q0001-0003.pdf PDF
Bid Schedule_Revised.pdf PDF
Specifications and Plans_Revised.pdf PDF
Amendment W912WJ24Q0001-0002.pdf PDF
Amendment W912WJ24Q0001-0001.pdf PDF
Specifications and Plans.pdf PDF
Solicitation W912WJ24Q0001.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment is necessary to provide a response to questions from industry.

Question/Response #6 is applicable to this amendment.

Solicitation closing remains October 31, 2023 at 5:00 PM Eastern.

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 26-Oct-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ24Q0001

X 9B. DATED (SEE ITEM 11)

13-Sep-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

26-Oct-2023

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

jennifer.m.samela@usace.army.milEMAIL:978-318-8324TEL:

JENNIFER M SAMELA / ADDED BY UPASS

W912WJ24Q0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been modified:

REQUEST FOR INFORMATION

QUESTION 1: Can the wire rope testing requirements in Specification 35 01 70.13 sections

2.1.3 Pre-Stretching, 2.1.6 Magnetic Flux Leakage Testing, and 2.1.13 Tension Testing be removed from the requirements?

RESPONSE 1: The Magnetic Flux Leakage Testing requirement has been removed from the specifications. The requirements for Pre-Stretching and Tension Testing of the wire rope remain.

Please see revised specifications for further details.

QUESTION 2: Is there a public boat ramp for boat access?

RESPONSE 2: Yes, there is public boat launch 1 mile upstream at Cold Springs Park. The Government has launched small boats from this launch (see photos included in this amendment), however, Contractors should consider that this launch may not be suitable for the launch of larger boats.

QUESTION 3: Is the tree that is currently lodged in Gate 1 included in the work for the Gate 1 Option or with the Option for the Tree Removal also be exercised to cover tree removal costs?

RESPONSE 3: If any trees remain once on-site work is in progress, then the Government would consider the exercise of the included option for tree removal.

QUESTION 4: Can the 4 manhole covers/hatches that are above each gate operator, on top of the service bridge, be used as overhead access to the catwalk platform?

RESPONSE 4: Yes, the manhole covers/hatches can be used as overhead access from the service bridge to the catwalk platform (see photos included in this amendment and drawing BE-1-1138 of the Plans, Drawings, and Photos attachment), but must be re-seated and requires replacement with a sealant approved for use by the COR (contracting office representative). Sealant shall be ASTM C920, Type M, Grade NS, use T, NT.

QUESTION 5: What length of wire rope is required?

RESPONSE 5: Approximate length of existing wire rope is 50 feet. Contractor shall field verify required lengths of rope prior to fabrication and installation. See revised specifications for further details.

W912WJ24Q0001

QUESTION 6: Are the new materials (wire rope with eye splices, shackles, etc.) on tainter Gate #2 to be removed off site and disposed of by the Contractor after installation of new wire rope that meets the requirements of this solicitation?

RESPONSE 6: No, all new materials that have been used by the Government in a temporary repair on tainer gate #2 shall remain on site and remain property of the Government during and after the installation of the new wire rope. These materials are to be returned to the COR or Project Manger once removed. All materials other than those used in the temporary repair are to be removed off-site and disposed of in accordance with federal, state, and local regulations by the Contractor.

(End of Summary of Changes)