This document is an Amendment to a federal solicitation. The amendment provides responses to requests for information (RFIs) related to the Bourne Bridge Painting project, which involves maintenance painting of below-deck structural steel members on the Bourne Bridge over the Cape Cod Canal in Buzzards Bay, Massachusetts. The RFI responses address details such as the elevation height from the ground to certain structural elements, train traffic frequency, power line information, work area and access requirements, traffic control measures, and work schedule flexibility. The solicitation is being administered by the U.S. Army Corps of Engineers, New England District, under Solicitation Number W912WJ24B0009. All other aspects of the solicitation remain the same.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Abstract.pdf | ||
| Amendment 0005.pdf | ||
| Amendment 0004.pdf | ||
| Amendment 0002.pdf | ||
| Specifications.pdf | ||
| Amendment 0001.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This amendment is to provide responses to requests for information (RFI's). All other aspects remain the same.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 14-May-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ24B0009
X 9B. DATED (SEE ITEM 11)
12-Apr-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
14-May-2024
CODE
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912WJ24B0009
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0003
RFI 0002
1. What is the elevation height from the ground to EJ-3 & EJ-4?
As-Built drawings in Appendix D show approximate contour lines of the ground below the bridge at time of bridge construction that provide information on the approximate height and reach to the bridge. Please note that further developments have occurred to the surrounding ground around the bridge that might alter some or all of these grades. Contractor is encouraged to visit the site to be familiar with the current condition for the bid.
2. How frequent is the train traffic?
It is up to the contractor to investigate train frequency.
3. What is the Amperage of the power lines over the roadway & going up to the pier and next to EJ-3 work area & will USAC take care of power company protection of wires?
South and North side of Bourne Bridge – There are two power cables with 2,100 volts and another cable with 120 volts that run from the bridge pier over the service road to utility poles adjacent to the service road. There is also a power cable with 4,160 volts that runs on poles along the service roads. Contractors are expected to maintain appropriate standoff distances between the cables and all equipment/personnel. In the vicinity of EJ-3 and EJ-4 on the bridge, all cables are within conduits.
4. How large an area will the contractor have for large manlift use?
Work area and duration required to work under each particular span of the bridge shall be incorporated in the Work Plan and be coordinated with the COR. See also response to Question #4 on Amendment 0001.
5. How will traffic control be taken care of? Are there specific dates that the contractor will not be allowed on the bridge roadway for work due to traffic concerns?
All work is under the bridge. No work is required at or above the road surface as stipulated in Specification Section 01 11 00, Para 1.1. See provisions stated in Specification Section 01 11 00, Para 1.1.6 for Temporary Short Term Lane Restrictions.
6. Will there be any variance in durations of 8 HR workdays or schedule for longer days or additional days?
See provisions stated in Specification Section 01 11 00, Para 1.7.1 for Hours of Operations and Work outside the normal hours of operations.
7. It was mentioned that the jump fence could be removed to access the underside of the bridge as long as it was replaced, will replacement be required by the end of every shift?
The intent of the project is for all work to be accessed and performed from under the bridge. Temporary Short Term Lane Restrictions provisions stated in Specification Section 01 11 00, Para 1.1.6 is intended only for limited duration for equipment and material delivery only. See Amendment 0001 on requirements for protection of traveling public and pedestrians.
(End of Summary of Changes)