Amendment 0001.pdf

PDF 373 KB Posted

Attached to
Bourne Bridge Painting Federal contract opportunity
Solicitation number
W912WJ24B0009
Issued by
Department of the Army Corps of Engineers Engineering District New England

About this file

This document is an Amendment 0001 to a federal solicitation for the Bourne Bridge Painting project. The amendment provides responses to Requests for Information (RFIs) and releases the site visit sign-in sheet. The key details are:

The solicitation is for a maintenance painting project on the Bourne Bridge over the Cape Cod Canal in Massachusetts. The bridge is a seven-span structural steel truss bridge carrying four lanes of vehicular traffic. The amendment addresses questions about the bridge's suicide fence, whether pressure washing is required, use of the railroad tracks during performance, and use of parking areas for manlift access. It confirms the railroad tracks will remain active, and Contractors must manage work to avoid impacting rail operations unless they coordinate additional requirements with MassDOT. The ground areas below the bridge can be used for manlift access, with the Contractor responsible for providing traffic control. All other aspects of the solicitation remain unchanged.

View the file

Other files for this federal contract opportunity

Other files attached to Bourne Bridge Painting, newest first.
File Type Posted
Bid Abstract.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004.pdf PDF
Amendment 0002.pdf PDF
Amendment 0003.pdf PDF
Specifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment is to provide responses to requests for information (RFIs) and release the site visit sign in sheet. All oher aspects remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 01-May-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ24B0009

X 9B. DATED (SEE ITEM 11)

12-Apr-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

01-May-2024

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ24B0009

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0001

Site Visit Attendees Emaneuel Fraugos – Liberty Maintenance, Inc. – (917) 709-0742 Andreas Troumouliaris – Legend Painting, Inc. – (330) 509-5154 Donnie Dursin – Atlas Painting – (804) 922-7690 Emmanuel Chrysakis – Royal Bridge – (305) 989-9200 John Savidakis – Omega Coatings – (727) 940-7423 Angelo Danapas – Omega Coatings – (727) 272-4673 Gierry Rancourt – TSI – (603) 581-5332 Himesh Patel – Vealant Construction – (978) 805-8253

RFI 0001

1. Will the suicide fence need to be removed?

The project does not require the removal of the bridge suicide fence. However, should a portion of the fence removal be necessary to accommodate the Contractor’s means and methods in carrying out certain tasks of painting the bridge, the Contractor must submit for review his/her means of removing and re-installing the fence to ensure that its functionality and strength are maintained. Please note that no part of the fence can be removed without temporary provisions for protection of traveling public and pedestrians.

2. Is pressure washing of the bridge anticipated?

Pressure washing of the bridge is not anticipated.

3. Will the railroad tracks be in use during the project Period of Performance and will the contractor be required to have any sort of insurance?

The railroad tracks are owned by MassDOT and will remain active during the entire period of performance.

Railroad tracks are only on the south side of the Canal. It is expected that Contractors will manage positioning of equipment and tools to keep clear of the railroad tracks right of way and not constrain rail operations to require any special insurance. However, the Contractors on-site employees shall be required to attend a two hour Rail Worker Safety training session at the Cape Cod Canal Field Office as part of the mobilization.

If Contractors propose to constrain rail operations by working within the railroad right-of-way, Contractors shall be solely responsible for coordinating with MassDOT and the railroad operator to determine additional railroad requirements and shall comply with all railroad requirements as a condition of this contract.

4. If manlifts are chosen to access work locations on the bridge, can the parking areas below the bridge be used?

Yes, the ground surface areas below the bridge can be used for manlift access to the bridge. Contractors are responsible to provide all traffic control devices, barriers, cones, and signs to provide safe work areas for manlifts and provide a marked detour path for personnel and vehicles on the service roads, recreation area and within the campground. Equipment shall not be left on the service roads, in recreation parking areas or campground activity areas when not in use.

W912WJ24B0009

(End of Summary of Changes)

File details come from the government source that posted it. Updated .