Amendment W912WJ21Q0009-0003.pdf
PDF 584 KB Posted
- Solicitation number
- W912WJ21Q0009
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment W912WJ21Q0009-0005.pdf | ||
| Amendment W912WJ21Q0009-0004.pdf | ||
| Amendment W912WJ21Q0009-0002.pdf | ||
| As Built.pdf | ||
| Amendment W912WJ21Q0009-0001.pdf | ||
| Solicitation W912WJ21Q0009.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W13G86028304920001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment is necessary to provide a response to a question from industry. Question and answ er #6 is applicable to this amendment.
Closing remains December 7, 2020 at 5:00 PM Eastern.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 01-Dec-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ21Q0009
X 9B. DATED (SEE ITEM 11)
17-Nov-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
01-Dec-2020
CODE
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
Sheila.M.Winston@usace.army.milEMAIL:978-318-8159TEL:
SHEILA M WINSTONVINCUILLA / CHIEF, CONTRACTING DIVISION
W912WJ21Q0009
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been modified:
REQUEST FOR INFORMATION
QUESTIONS AND ANSWERS:
1. Please confirm the grade of the new HMA pavement will match the grade of the existing pavement. With the 4” new pavement section, there will be several hundred cubic yards of material removed and stockpiled on-site. Does the Government have room to store this quantity of material on-site as stated in 3.B on page 13 of 38?
Answer: The grade of the new HMA pavement will match the grade of the existing pavement. Yes, the Government has room to store this quantity of material on-site as stated in section 3.B.
2. Is any survey required to verify the pre- and post-construction locations of the settlement monuments?
Answer: No, a settlement survey will not be necessary as the monuments are on the other side of the guardrail and outside of the paving area.
3. Are wattles or other erosion conrol measures required?
Answer: No erosion control measures are required unless conditions exist or would be created that meet the language as included in II. Technical Requirements, Part 1: General, Section 5. Environmental Protection.
4. SOW indicates depth of reclamation to be 12 inches. Could you please confirm the existing subsurface utilities are deep enough to achieve this depth of reclamation?
Answer: The depth of reclamation will be changed to 9 inches as indicated by the revised Statement of Work.
5. Could you please provide a specific product for the crush gravel shoulders?
Answer: The product for the crushed gravel shoulders shall be ¾” processed gravel.
6. Can you confirm that only the asphalt pavement mix for the base and wearing (top) courses as specified in the Statement of Work will accepted? Is this mix available?
Answer: The mix as specified in the Statement of Work has been confirmed as available, therefore, only mixes that meet these requirements will be accepted. The mixes shall not contain any recycled asphalt products, only new material. The awarded vendor will be required to submit products that meet these specifications for acceptance by the Government. Products that do not meet these specifications will not be accepted for use and shall be replaced by those that do at no additional expense to the Government.
(End of Summary of Changes)