Amendment 0003.pdf
PDF 169 KB Posted
- Attached to
- Littleville Electrical Service Upgrades
- Solicitation number
- W912WJ21B0005
About this file
This amendment modifies a solicitation for the Littleville Electrical Service Upgrades project. The scope involves installing new utility poles, overhead electrical lines, and underground electrical and communication conduits at the Littleville site. The amendment provides responses to offeror questions, clarifying that the same installer is not required for pole and overhead line work versus underground conduit work due to differing standards. Precast manholes and horizontal conduit placement with 12-inch separation are confirmed to meet specifications. It is the offeror's responsibility to coordinate the required electrical service upgrade with the local utility, Eversource. Site visit attendees from various contractor firms are also noted.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Abstract.pdf | ||
| Amendment 0004.pdf | ||
| Site Photos.pdf | ||
| Rev1_Specifications Section _01 22 00.pdf | ||
| Rev1_Bid Schedule _ 00 41 00.docx | DOCX document | |
| Amendment 0002.pdf | ||
| Amendment 0001.pdf | ||
| Drawings_Final.pdf | ||
| Specifications.pdf | ||
| Solicitation W912WJ21B0005.pdf | ||
| Drawings_Information.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provide responses to RFI's. All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 27-Apr-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912WJ21B0005
X 9B. DATED (SEE ITEM 11)
02-Apr-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
28-Apr-2021
CODE
US ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA ROAD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912WJ21B0005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0003
1. Does the Contractor have to be local to qualify for this IFB, or can they be from another state? There appears to be conflicting specs on this subject.
SECTION 33 71 01 Page 7 “1.4.2 Installer Qualifications Contractor or sub-contractor hired to install poles and aerial conductors shall be a contractor regularly engaged in the installation of utility poles in the local area and in accordance with the local utility, Eversource, specifications.”
-And-
SECTION 33 71 02 Page 8
” 1.4.2 Cable Installer Qualifications Provide at least one onsite person in a supervisory position with a documentable level of competency and experience to supervise all cable pulling operations. Provide a resume showing the cable installers' experience in the last three years, including a list of references complete with points of contact, addresses and telephone numbers. Cable installer must demonstrate experience with a minimum of three medium voltage cable installations. The Contracting Officer reserves the right to require additional proof of competency or to reject the individual and call for an alternate qualified cable installer.”
Government Response: Installation of the new Poles and OH lines will need to meet Eversource standards, therefore 33 71 01 page 7. Cable installation refers to the underground conduits which are Government Owned, thus the slightly different requirement. The same installer is not required for both tasks.
2. In reference to the above solicitation, we are hereby requesting a clarification, determination and/or information concerning the following:
Specification Section No(s): 33 71 01 – Underground Electrical Distribution Reference Drawing No(s): ES-503
Request: In reference to EMH-2 and CMH-2 are precast electrical and communication manholes acceptable?
Government Response: Precast manholes are acceptable.
3. In reference to the above solicitation, we are hereby requesting a clarification, determination and/or
W912WJ21B0005
Specification Section No(s): 33 71 01 – Underground Electrical Distribution Reference Drawing No(s): ES-503
Request: Can the duct bank be installed with the electrical conduits running side by side horizontally next to the communication conduits in lieu of running on top of vertically? Reference attached sketch keeping the required 12” spacing as well as providing both electric and communication warning tapes.
Note: Sketch attached to email.
Government Response: Conduits may run side by side with the required 12” separation between power and communication.
4. In reference to the above solicitation, we are hereby requesting a clarification, determination and/or
Specification Section No(s): N/A Reference Drawing No(s): ES-101
Request: Please provide the point of contact for the Utility modification.
Government Response: It is the Contractor’s responsibility to prepare an Eversource work request for the electrical service upgrade. The project doesn’t have a specific point of contact and the Contractor can start the utility coordination effort by calling 888-633-3797 or via contacting eversource.com.
The following have been modified:
AMENDMENT 0002
Site Visit Attendees
Name Company Dean Lackay Midwest Electrical Construction Jay Harris Colony Construction Tom Collins Springfield Electrical Co.
Tucker Schmitt M.L.Schmitt Electrical Sara J. Torres Contract Specialist, USACE Henry Phillip Tech Lead, USACE Coleman, Matthew Project Manager, USACE
(End of Summary of Changes)