Amendment W912WJ20Q0005-0002.pdf

PDF 514 KB Posted

Attached to
Mini-Split AC/Heat Pump Installations, 6 locations in CT Federal contract opportunity
Solicitation number
W912WJ20Q0005
Issued by
Department of the Army Corps of Engineers Engineering District New England

View the file

Other files for this federal contract opportunity

Other files attached to Mini-Split AC/Heat Pump Installations, 6 locations in CT, newest first.
File Type Posted
Amendment W912WJ20Q0005-0008.pdf PDF
Amendment W912WJ20Q0005-0007.pdf PDF
Amendment W912WJ20Q0005-0006.pdf PDF
Amendment W912WJ20Q0005-0005.pdf PDF
Amendment W912WJ20Q0005-0004.pdf PDF
Amendment W912WJ20Q0005-0003.pdf PDF
Amendment W912WJ20Q0005-0001.pdf PDF
Solicitation W912WJ20Q0005.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment is necessary to update the Statement of Work due to a requirements change. Closing w ill be extended until December 13, 2019 at 5:00 PM.

1. CONTRACT ID CODE PAGE OF PAGES

1 12

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 26-Nov-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ20Q0005

X 9B. DATED (SEE ITEM 11)

19-Nov-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

26-Nov-2019

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

Sheila.M.Winston@usace.army.milEMAIL:978-318-8159TEL:

SHEILA M WINSTONVINCUILLA / CONTRACT SPECIALIST

W912WJ20Q0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 06-Dec-2019 05:00 PM to 13-Dec-2019 05:00 PM.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

STATEMENT OF WORK

MINI-SPLIT AIR CONDITIONING/HEAT PUMP INSTALLATION

U.S. ARMY CORPS OF ENGINEERS

NAUGATUCK RIVER BASIN

MIDDLEBURY, STAMFORD, THOMASTON, AND COLEBROOK, CT

Statement of Work

I. General:

1. Scope of work:

Furnish all equipment, materials and labor to install a total of six (6) Energy Star rated mini-split ductless air conditioning/heat pump systems at the Hop Brook Lake Project office, five

(5) Energy Star rated mini-split ductless air conditioning/heat pump systems at the Naugatuck River Basin Office, one (1) Energy Star rated, mini-split ductless air conditioning/ heat pump system at the Stamford Hurricane Barrier Office in Stamford, CT, one (1) Energy Star rated mini-split ductless air conditioning/heat pump system at the Thomaston Dam Office, one (1) Energy Star rated mini-split ductless air conditioning/heat pump system at the Black Rock Lake Office, two (2) Energy Star rated mini-split ductless air conditioning/heat pump systems at the Colebrook River Lake Office for a total of 16 units.

2. Locations:

The Project Offices are located in Connecticut and Vermont and include the following:

Hop Brook Lake Project Office 4 Straits Turnpike, Middlebury, CT 06762 (New Haven County)

Naugatuck River Basin Office 100 Allerton Farm Road, Middlebury, CT 06762 (New Haven County)

Stamford Hurricane Barrier 230 Elmcroft Road, Stamford, CT 06905 (Fairfield County)

Thomaston Dam 331 Hill Road, Thomaston, CT 06787 (Litchfield County)

Black Rock Lake Project Office 350 Old Branch Road, Thomaston, CT 06787 (Litchfield County)

Colebrook River Lake Project Office 426 A/B Colebrook River Road, Colebrook, CT 06021 (Litchfield County)

3. Site Visit:

Site visits are strongly encouraged. Contact the Technical Point of Contact to arrange a site visit.

Hop Brook Lake Naugatuck River Basin Office Stamford Hurricane Barrier Project Manager, Diana Errico-Topolski Phone: 978.318.8370 Email: Diana.J.Errico-Topolski@usace.army.mil

Black Rock Lake Project Manager, Steve Patchkofsky Phone: 978.318.8369 Email: Steven.D.Patchkofsky@usace.army.mil

Colebrook River Lake Project Manager, John Haluchak

Email: John.A.Haluchak@usace.army.mil

4. Schedule:

The period of performance shall be 90 days from Notice to Proceed. The project area will be open to the contractor Monday through Friday 7:00 AM to 3:30 PM and all work must be done during those hours, unless additional hours are approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays.

5. Safety:

The contractor will comply with all pertinent provisions of the latest edition of the U.S. Army Corps of Engineers Safety and Health Requirements COE EM 385-1-1. A copy of COE EM 385-1-1 is available for reference at the project office or may be ordered from Superintendent of Documents, P O Box 371954 Pittsburgh, PA 15250-7954 (Tel: 202 783-3238). In addition, the manual may be viewed at the following link:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385- 1-1.pdf . The contractor shall also comply with all OSHA work safety standards. The project staff can and will order the cessation of work at any time should the safety of employees and visitors become jeopardized.

6. Preconstruction Conference:

Prior to the start of any work, the Technical Point of Contact will schedule and conduct a “Preconstruction Conference”. The Contractor’s Project Manager and Quality Control Personnel will attend this meeting. This conference will be held at the time and location agreeable to the government and contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Preconstruction conference the contractor shall provide to the name of the project superintendent with a telephone number for project coordination.

The following is a general list of items for discussion during this Preconstruction Conference:

i. Authority of the Technical Point of Contact and Quality Assurance Inspectors.

ii. Contractor’s Safety Program (including sub-contractors).

iii. Activity Prevention Plan and Activity Hazard Analysis (Submitted & accepted prior to start of work on site)

iv. Weekly Safety Meetings (Documented on NED Form 251)

v. Accident Reporting (ENG Form 3394)

vi. Safety Data Sheet (SDS) requirements

vii. Correspondence, Communication and Administrative Procedures.

viii. Invoice and payment.

7. Permits:

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

8. Security:

The contractor will comply with all established security policies at the project(s). Due to periods of heightened security that may affect the access to the areas covered under this contract, areas may be subject to periodic closures, which in turn may reduce or inhibit the Contractor’s ability to access certain areas. During periods of heightened security, the Government reserves the right, at any time, to close any property or portion of property and reschedule and/or cancel any subsequent service in an area. The Contractor shall be given at least 24 hour notice of any such closure.

9. Contractor Conduct:

Alcohol and firearms are prohibited on project grounds. Contractor and employees must comply with CFR 36 Rules and Regulations.

10. Payment:

Payment shall be made on a per job basis. After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due per line item. For jobs greater than 30 days, the contractor may request progress payment.

All invoices may be mailed or emailed to:

Hop Brook Lake Naugatuck River Basin Office Stamford Hurricane Barrier Project Manager, Diana Errico-Topolski Phone: 978.318.8370 Email: Diana.J.Errico-Topolski@usace.army.mil

Black Rock Lake Project Manager, Steve Patchkofsky

Email: Steven.D.Patchkofsky@usace.army.mil

Colebrook River Lake Project Manager, John Haluchak Phone: 978.318.8366 Email: John.A.Haluchak@usace.army.mil

II. Technical Requirements:

Part 1 General:

Summary:

Furnish all equipment, materials and labor to install ductless air conditioning/heat pump units at 6 locations in the Naugatuck River Basin in Connecticut.

Existing Conditions:

Hop Brook Lake:

The Hop Brook Lake office is a two-story, standard office with a forced air HVAC system, two exterior compressors that currently provide 30,000 BTUs each for a total of 60,000 BTUs, two air handlers and an oil-fired furnace.

Office building has one atypical area that is worth noting.

One of the upstairs offices does not have access to exterior walls. The back wall of this office ties into an attic crawlspace. The side wall of this office however, ties into a storage closet through a door, which does have exterior wall access. The main distribution panel is 480/277 with various sub-panels. (Please see informational photos).

Naugatuck River Basin Office:

The Naugatuck River Basin Office is a two-story, standard office with an existing forced air HVAC system and one exterior compressor providing 36,000BTU capacity. The Naugatuck office has a 220A electrical panel.

Stamford Hurricane Barrier:

The Stamford Hurricane Barrier is an unmanned facility that has concrete walls. The interior operating room has mineral fiber tile walls which are fashioned to a wood framework over the concrete walls. Please see informational photos for a picture of the wall structure. The ceiling is concrete and is the same construction as the wall, with mineral fiber tiles. The exact thickness of the concrete walls is unknown, but is estimated at 12” thick. There is no asbestos present in the ceiling or wall tiles and the material has been tested. The operating room at this facility currently has oil-fired forced air heat, as well as an electric baseboard. During the summer, window air conditioners are used for cooling. As far as operating room access, access is gained from a steep narrow stairway that leads from the middle level to the upper level. There are several roof access platform areas outside of the operating room, where the compressor can be mounted. The main distribution panel is 480/277V, with various sub-panels. (Please see informational photos).

Thomaston Dam:

The Thomaston Dam warm bay garage is a standard garage with no air conditioning and a Modine unit for heating. The Thomaston Dam has a 225A electrical panel that is approximately 60 feet from where the unit and compressor will be installed.

Black Rock:

The Black Rock warm bay garage is a standard garage with no air conditioning and a Modine unit for heating. The Black Rock Lake has a 220A electrical panel that is approximately 20 feet from where the unit and compressor will be installed.

Colebrook River Lake:

Office is a standard office building with a main office and an attached warm bay garage.

The main office currently has an air conditioner that has been fitted through the wall.

The warm bay garage currently has no air conditioning and a Modine unit for heating.

The electrical service is 200A and two additional sub-panels, which are within 15 feet of where the office unit and compressor will be installed, and approximately 60 feet of where the garage unit and compressor will be installed.

Site visits are highly recommended.

Clean Up:

The Contractor shall practice good housekeeping to maintain a safe job site. The contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials. Upon completing work in an area the contractor shall remove any tools, equipment, and materials that are not the property of the government. Upon completion of work, the Contractor shall clean up the job site to the satisfaction of the Government.

Government Resources:

The contractor may use the existing restroom facilities at the projects. The government will supply any electricity and water necessary for the project work from points of existing outlets. The contractor shall carefully conserve the use of electricity and water provided. The contractor shall supply their own means of communication (telephone).

Environmental Protection:

Containers for excess and/ or waste materials, rubbish, etc. shall be provided by the contractor at the site, and the site will be inspected/cleaned on a daily basis. Water, air and land resources shall not be adversely impacted during the course of the work. Contractor will take necessary steps to ensure all federal, state, and local environmental regulatory requirements are met.

Omissions:

This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.

Quality Assurance:

The contractor is responsible for the quality control of the contract work. The contractor shall establish and maintain a quality control system to assure compliance with the contract requirements. The government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.

Other Contracts:

The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees. The contractor shall not commit or permit any act, which will interfere with the performance of work by another contractor, or by Government employees.

Receiving and Storing Materials:

The Government will provide a storage area and parking for contractor personnel. The contractor is responsible for protecting any stored material until it is placed in service. The contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive material for supplies for the contractor and will not be responsible for damage to the contractor’s equipment or materials.

Requests for information:

Requests concerning the work of this project should be directed to the Technical Point of Contact, Marissa Wright at 978-318-8374 or marissa.l.wright@usace.army.mil.

Submittals:

Although the Government technically reviews submissions required by this statement of work, it is emphasized that the Contractor’s work must be completed using proper internal controls and review procedures. The documents identified below must be prepared in accordance with the applicable standards, submitted for review and accepted by the Government prior to the commencement of any field activities.

a. Accident Prevention Plan (APP) and Activity Hazard Analysis (AHA) – Prior to the start of field work

b. First Aid/CPR certifications

c. Product specification sheets, to include energy information

d. Manufacturer Warranty

e. Electrician’s license

f. Operations and Maintenance Manual and Data – Provided at completion of field work and prior to final payment.

Part 2 Products:

Sustainability:

All products must be covered by the Energy Efficiency Program set forth by the Department of Energy. Products that fall under this category will be commercial heaters, commercial coolers, etc. The list of products is periodically updated, please check the Department of Energy’s website for current accepted products:

https://energy.gov/eere/femp/find-product-categories-covered-efficiency-programs.

1. Mini split ductless air conditioning/ heat pump single zone system .

a. Quantity – 1315 Systems

b. One exterior wall mounted unit with deflector shield & one indoor wall mounted unit. Please see table under execution section for BTU heating and cooling requirements.

c. Single Phase 208/230 volt 60 Hz power requirement with outside service disconnect.

d. Insulated refrigerant lines.

e. Must include power failure mode.

f. Multi-speed with at least 4 fan speeds.

g. Wireless remote controllers for indoor wall mounted units that will allow programming of temperature setting, operation mode, fan speed and timing functions.

h. Washable permanent filters, preferred

i. Quiet operation – maximum 56 dB(A)

j. Minimum 26 SEER rating.

k. Minimum 12.0 HSPF rating.

l. CEE Tier 3 Rating.

m. Minimum 15 EER rating.

n. Energy Star rated.

2. Mini split ductless air conditioning/ heat pump dual zone system for Hop Brook Lake

Office.

a. Quantity – 1 System

b. One exterior wall mounted unit with deflector shield & two indoor wall mounted units. Please see table under execution section for BTU heating and cooling requirements.

c. Single Phase 208/230 volt 60 Hz power requirement with outside service disconnect.

d. Insulated refrigerant lines.

e. Must include power failure mode.

f. Multi-speed with at least 4 fan speeds.

g. Wireless remote controllers for indoor wall mounted units that will allow programming of temperature setting, operation mode, fan speed and timing functions.

h. Washable permanent filters, preferred

i. Quiet operation – maximum 56 dB(A)

j. Minimum 26 SEER rating.

k. Minimum 12.0 HSPF rating.

l. CEE Tier 3 Rating.

m. Minimum 15 EER rating.

n. Energy Star rated.

3. Mini split ductless air conditioning/ heat pump dual zone system for Naugatuck River

Basin Office

o. Quantity – 2 Systems

p. One exterior wall mounted unit with deflector shield & two indoor wall mounted units. Please see table under execution section for BTU heating and cooling requirements.

q. Single Phase 208/230 volt 60 Hz power requirement with outside service disconnect.

r. Insulated refrigerant lines.

s. Must include power failure mode.

t. Multi-speed with at least 4 fan speeds.

u. Wireless remote controllers for indoor wall mounted units that will allow programming of temperature setting, operation mode, fan speed and timing functions.

v. Washable permanent filters, preferred

w. Quiet operation – maximum 56 dB(A)

x. Minimum 26 SEER rating.

y. Minimum 12.0 HSPF rating.

z. CEE Tier 3 Rating.

aa. Minimum 15 EER rating.

bb. Energy Star rated.

Part 3 Execution:

Mini Split Ductless Air Condition/Heat Pumps Systems Materials & Supplies:

The Contractor shall supply, deliver, unload, and install units to satisfy the minimum requirements:

Hop Brook Lake Cooling BTUs Distance from Panel

(approximate) Ground Floor Front Office (Note ground floor front office paired with second floor main office compressor).

6,000 25

Ground Floor Back Office

6,000 25

Ground Floor Warm Bay Garage

12,000 20

Second Floor Main Office (Note second floor main office paired with ground floor front office compressor).

9,000 30

Second Floor, Second Office

6,000 30

Second Floor, Third Office

6,000 25

Naugatuck River Basin

Cooling BTUs

Ground Floor East Office (Note: Ground Floor East office paired with Second Floor East Office compressor).

6,000 20

Ground Floor Back Office (Single Compressor)

6,000 20

Ground Floor West Office (Note: Ground Floor West office paired with Second Floor West Office compressor).

6,000 20

Second Floor East Office (Note: Second Floor East

6,000 20 office paired with Ground Floor East Office compressor).

Second Floor West Office (Note: Second Floor West office paired with Ground Floor West Office compressor).

6,000 20

Stamford Hurricane Barrier

Cooling BTU’s Distance from Panel (approximate)

Operating Room 10,000 65

Thomaston Dam Cooling BTUs Distance from Panel

Warm Bay Garage 12,000 60

Black Rock Lake Cooling BTUs Distance from Panel

Warm Bay Garage 14,000 20

Colebrook River Lake

Cooling BTUs Distance from Panel (approximate)

Main Office 6,500 15 Warm Bay Garage 12,000 15

Installation:

a. Contractor shall install all products to manufacturer’s recommendations in conformance with state and local building codes and following requirements:

i. All electrical work shall be performed by a licensed electrician.

ii. Installations may require upgrading the existing electrical panel to accommodate the new systems. All work will be done to the existing State electrical code and standards.

iii. Contractor shall be responsible for running all electrical lines from the compressors and units to the panel. Distances away from panel are listed in the table above and are approximates.

iv. Compressor condensing units shall not be placed on the ground, and shall be elevated at least 20 inches off the ground, with an awning provided over the unit. Please see photo of an elevated compressor in the informational photos.

v. Cover all exposed refrigerant lines, drain lines and control wiring with a UV resistant extruded PVC line set cover & fittings that matches building colors to the highest extent practicable.

vi. Insulate all refrigerant line sets between condensing unit and cooling unit.

vii. Unit shall be purged, vacuum tested, and charged with refrigerant to manufacturer’s recommendations.

viii. Provide and install new condensate pump and pipe condensate drains to outdoors allowing for a positive drainage away from the building and foundation.

ix. Seal all penetrations made for pipes/wires in exterior building walls with waterproof expanding foam sealant.

ix. Perform one (1) functionality test. Any identified issues identified during test shall be corrected and a new test performed.

x. Provide training for control operations & system maintenance. The date and time of the training shall be coordinated with the Technical Point of Contact.

(End of Summary of Changes)

File details come from the government source that posted it. Updated .