HAMPTON_MAINT_DREDGE_Final_1_July_2019.pdf
PDF 32 MB Posted
- Solicitation number
- W912WJ19B0011
About this file
Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Abstract_W912WJ19B0011.pdf | ||
| W912WJ19B0011_0004.pdf | ||
| HAM_2018_03_cond_sort20.xyz | XYZ file | |
| W912WJ19B0011_0003.pdf | ||
| HAM_2018_03_cond_vol.xyz | XYZ file | |
| HAM_20181010_CS_2018_058_03avg.xyz | XYZ file | |
| HAM_20181010_CS_2018_058_20min.xyz | XYZ file | |
| Revised_Army_Permit.pdf | ||
| W912WJ19B0011_0002.pdf | ||
| W912WJ19B0011_0001.pdf | ||
| Site_Visit_Attendance_List.pdf | ||
| Solicitation_W912WJ19B0011.pdf | ||
| Drawings.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Number:
W912WJ19B0011
Maintenance Dredging
Hampton Harbor, Hampton and Seabrook, New Hampshire
Construction Solicitation and Specifications
July 2019
Maintenance Dredging, Hampton Harbor, Hampton and Seabrook, NH
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 32 00 GEOTECHNICAL DATA
00 41 00 BIDDING SCHEDULE
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 22 00 MEASUREMENT AND PAYMENT
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 01 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 54 50 DREDGING PLANT AND EQUIPMENT
01 57 20 ENVIRONMENTAL PROTECTION
01 58 00 PROJECT IDENTIFICATION
01 71 23 FIELD ENGINEERING
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 23 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM - PIPELINE
HYDRAULIC DREDGE
35 20 25 DREDGING AND DREDGED MATERIAL PLACEMENT
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
DOCUMENT 00 32 00
GEOTECHNICAL DATA
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 EXAMINATION OF SAMPLES
1.4 EXISTING REPORTS AND HISTORICAL DATA
1.5 SOIL CLASSIFICATION
1.6 INTERPRETATION
1.7 LABORATORY TESTS
-- End of Section Table of Contents --
DOCUMENT 00 32 00 Page 1
DOCUMENT 00 32 00
GEOTECHNICAL DATA
PART 1 GENERAL
1.1 SUMMARY
The surface conditions indicated on the contract drawings and in the specifications are the result of site surveys, borings, and laboratory tests. Copies of the logs of explorations, laboratory test results, and locations at the site where subsurface investigations were performed are located at the end of the specifications. A summary of the subsurface materials expected to be encountered during dredging is contained in Section 35 20 25 DREDGING AND DREDGED MATERIAL PLACEMENT, Subpart "Character of Materials".
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referenced to in the text by basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D421 (1985; 2002) Practice for Dry Preparation of Soil Samples for Particle-Size Analysis and Determination of Soil Constants
ASTM D422 (1963; R 2002 e1) Particle-Size Analysis of Soils
ASTM D2216 (2005)Test Method for Laboratory Determination of Water (Moisture) Content of Soil and Rock
ASTM D2487 (2006) Classification of Soils for Engineering Purposes (Unified Soil Classification System)
ASTM D2488 (2006) Description and Identification of Soils (Visual-Manual Procedure)
ASTM D2850 (2003a) Unconsolidated - Undrained Triaxial Compression Test on Cohesive Soils
ASTM D2974 (2000) Test method for Moisture, Ash and Organic Matter of Peat and Organic Soil
1.3 EXAMINATION OF SAMPLES
Subsurface explorations were performed by the U.S. Army Corps of Engineers. Pertinent subsurface information in the Appendix attached to the specifications.
DOCUMENT 00 32 00 Page 2
1.4 EXISTING REPORTS AND HISTORICAL DATA
Existing reports and historical data, relative to the dredging of Boston Harbor are available for viewing at the U.S. Army Corps of Engineers New England District, 696 Virginia Road, Concord, MA. Advance arrangements to view the reports may be made with Ms. Coral Siligato, Project Manager, (coral.e.siligato@usace.army.mil), telephone 978-318-8012.
1.5 SOIL CLASSIFICATION
The soil classification of the U.S. Army Corps of Engineers soil samples was done in accordance with ASTM D2488 in the field and ASTM D2487 in the laboratory.
1.6 INTERPRETATION
Subsurface investigation data are provided only for information purposes and for the convenience of the Contractor. The data shown on the boring logs is for the specific locations indicated only and no assurance is given that these conditions are representative of conditions between borings or areas adjacent thereto. The responsibility lies with the Contractor to interpret subsurface conditions that may affect his work.
1.7 LABORATORY TESTS
Laboratory tests were generally performed in accordance with the following test methods:
a. Moisture Content: ASTM D2216.
b. Organic Content: ASTM D2974.
c. Particle-Size Analysis: ASTM D422, ASTM D421.
d. Unconsolidated-Undrained Triaxial Testing: ASTM D2850.
Note: Not all samples were tested in the laboratory using all the methods described above.
-- End of Document --
DOCUMENT 00 32 00 Page 3
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 No Dredge Seasons
1.2 PHOTOGRAPHS
1.3 SUBMITTALS
1.4 PROJECT/SITE CONDITIONS
1.4.1 Physical Data
1.5 SUPERINTENDENCE BY THE CONTRACTOR
1.6 COORDINATION AND DIRECTION DURING CONSTRUCTION
1.7 SEQUENCING AND SCHEDULING
1.7.1 Operational Period, Restrictions, and Hours
1.7.2 Work Sequence
1.7.2.1 General
1.7.2.2 Progress Schedule
1.7.3 Organization at the Site
1.7.3.1 General
1.7.3.2 Rate of Progress
1.8 CONTRACTOR USE OF PREMISES
1.8.1 Storage Areas
1.8.1.1 Work Limits
1.8.2 Contractor's Receipt of Supplies
1.8.3 Access to Work Site
1.8.4 Protection and Security
1.8.5 Work By Other Contractors
1.8.6 Emergency Contacts
1.8.7 Damaged Property
1.8.8 Contractor's Receipt of Supplies
1.8.9 Daily Clean Up
1.8.10 Government Sanitary Facilities
1.9 QUALITY ASSURANCE
1.10 COORDINATION
1.10.1 Daily Dredge Operations Location Map (DOLM)
1.10.2 Public Notice
1.10.3 Notice to Mariners
1.10.4 Aids to Navigation
1.10.5 Moorings
1.10.6 Points of Contact
1.11 PRE-DREDGING PHOTOGRAPHIC AND VIDEO SURVEY
1.12 GENERAL SAFETY REQUIREMENTS
1.12.1 General
1.12.2 Contractor's Project Superintendent
1.13 ENVIRONMENTAL PROTECTION
1.14 PRECONSTRUCTION CONFERENCE
PART 2 PRODUCTS
SECTION 01 11 00 Page 1
PART 3 EXECUTION
SECTION 01 11 00 Page 2
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
The general description below is given to indicate the approximate scope of this project only. It does not limit the work required under the project drawings and specifications.
The work of this project shall include the following work in the Entrance Channel and in the Inner Harbor:
Entrance Channel
1. dredging of the 8-foot deep entrance channel to its authorized depth of -8 feet Mean Lower Low Water (MLLW) with a 1 foot allowable overdepth to -9 feet MLLW (Optional Work).
Inner Harbor
1. Dredging of the 8-foot deep Hampton channel to its authorized depth of -8 feet MLLW with a 1 foot allowable overdepth to -9 feet MLLW.
2. Dredging of the 8-foot deep cross channel to its authorized depth of -8 feet MLLW with a 1 foot allowable overdepth to -9 feet MLLW.
3. Dredging of the 8-foot deep Hampton anchorage to its authorized depth of -8 feet MLLW with a 1 foot allowable overdepth to -9 feet MLLW.
4. Dredging of the 6-foot deep Hampton anchorage to its authorized depth of -6 feet MLLW with a 1 foot allowable overdepth to -7 feet MLLW.
5. Dredging of 8-foot deep Seabrook channel to its authorized depth of -8 feet MLLW with a 1 foot allowable overdepth to -9 feet MLLW.
6. Dredging of the 8-foot deep Seabrook anchorage to its authorized depth of -8 feet MLLW with a 1 foot allowable overdepth to -9 feet MLLW.
7. Dredging of the 6-foot deep state maintained anchorage to a depth of -6 feet MLLW with a 1 foot allowable overdepth to -7 feet MLLW (Optional Work).
The dredged material shall be removed by hydraulic dredging and transported via hydraulic pipeline to four dredged material placement areas; Hampton Beach, Seabrook Beach, South Bridge Abutment, and between the double sheet pile wall adjacent to the middle ground sand flats. The dredged material, once pumped to each land placement area, shall be shaped and graded to the specified berm width and slopes as indicated on the contract drawings.
Placement at the double sheet pile wall shall consist of pumping dredged material directly into the annular space between the double sheet pile walls until the material reaches the top of the wall.
SECTION 01 11 00 Page 3
1.1.1 No Dredge Seasons
(a) Operational Restrictions:
To avoid impacts to local environmental resources and due to environmental restrictions, the work required under this contract will only be permitted between 1 October 2019 and 15 March 2020.
Environmental windows of permitted dredging, placement of dredged material, and other work shall be as follows:
(1) Dredging of the Inner Harbor: 15 October 2019 through 15 January 2020.
(2) Dredging of the Federal Entrance Channel: 15 October 2019 through 1 March 2020.
(3) All other work and work on receiving beaches: 1 October 2019 through 1 March 2020.
"All other work" shall include, but not be limited to, preparation of and work on receiving beaches, pipeline installation and removal, sand fence installation, placement of dredged material within the West Bulkhead, and placement and grading of beachfill.
(b) Notice to Proceed (NTP) Received after September 1, 2019:
The Contractor shall be required to:
(1) Commence on preliminary work by promptly placing all orders, awarding subcontracts, processing required submittals and details under this contract within 15 calendar days after the NTP to ensure immediate readiness to commence dredging; and
(2) Commence dredging at the site within 30 calendar days after the date the Contractor receives the NTP, provided that the dates are within the permitted dredging and disposal windows as specified above in subpart "Operational Restrictions."
1.2 PHOTOGRAPHS
Photographs showing the existing conditions of the project site and adjacent areas are attached at the end of the specification document. The photographs are attached for informational purposes only. The Contractor shall make his own investigations of existing conditions in the field prior to the start of work.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Pre-Dredging Photographic and Video Survey; G, RO
The Contractor shall submit a pre-dredging photographic and
SECTION 01 11 00 Page 4 video survey as described in this section.
Notice to Mariners
Submit a copy of Notice to Mariners to the Contracting Officer.
Aids to Navigation
Submit proof of coordination with the USCG for any necessary relocation or movement of aids to navigation.
Safe Harbor Plan; G, RO
The Contractor shall submit a Safe Harbor Plan to the Contracting Officer for approval prior to the start of on-site work. The Safe Harbor Plan shall include a written description of the Contractor's plan to provide for the safety and security of floating plant, equipment, and personnel in the event of a storm or other site emergency. The location for the docking of floating plant and the off-loading of equipment and crews shall be clearly indicated.
1.4 PROJECT/SITE CONDITIONS
1.4.1 Physical Data
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
a. Site Conditions: The indications of physical conditions on the drawings and in the specifications are the result of site investigations and surveys. The conditions represented prevailed at the time the investigations and surveys were made. A pre-dredge survey may be performed by the Government prior to the start of Contractor dredging operations at the site. Before commencing work at the site, the Contractor shall verify the existing conditions indicated on the drawings and in the specifications. See CONTRACT CLAUSE entitled "SITE
INVESTIGATION AND CONDITIONS AFFECTING THE WORK".
b. Weather Conditions: The monthly normal mean temperature and the monthly normal mean precipitation for the site may be obtained by the Contractor from the nearest U.S. National Weather Service Office.
c. Conditions of Channel at Inner Harbor Channels and Anchorages:
Under most weather conditions, the inner harbor is calm to relatively calm with swells typically less than 1 foot. Inner harbor channels and anchorages were last dredged by the State between 2012 and 2013 and have experienced considerable shoaling since that time resulting in controling depths above Mean Lower Low Water (MLLW) in some locations.
d. Channel Traffic: The 8-foot channel is used primarily by a recreation fleet and commercial vessels, which may cause interference with contract operations. The Government will not undertake to keep the channel free from vessels or other obstructions, except to the extent of applicable regulations. The Contractor will be required to conduct the work in such a manner as to obstruct navigation as little as possible, and in the event the Contractor's plant so obstructs the
SECTION 01 11 00 Page 5 channel as to make difficult or endanger the passage of any vessels, the plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage.
e. Conditions at Entrance Channel to Harbor: The tidal currents at the entrance to the Harbor can be substantial (up to 5 knots during maximum flood and ebb tidal periods), creating a potentially dangerous condition. Under optimum weather conditions, the sea swell is typically 1-2 feet in a southerly direction. In normal weather, the sea swell can range from 2-4 feet.
1.5 SUPERINTENDENCE BY THE CONTRACTOR
a. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent project superintendent who is satisfactory to the Contracting Officer and has the authority to act for the Contractor.
b. The project superintendent shall maintain a physical presence at the site at all times and be responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.
c. Failure to comply with these requirements shall be deemed as cause for a non-compensatory stoppage and suspension of work until the deficiency is remedied.
1.6 COORDINATION AND DIRECTION DURING CONSTRUCTION
a. The Contractor shall not take or accept any direction or instructions issued by any person, employed by the Government or otherwise, other than the Contracting Officer that changes the terms and conditions of contract actions, the scope, or any change that impacts the cost, price, or schedule. Changes authorized by the Contracting Officer will be in the form of a written, official, signed modification to the contract action received by the Contractor before the Contractor will act upon those changes. The Contractor will comply with the changes clause of this contract when the Contractor believes direction has been given from persons other than the Government Contracting Officer that equate to a change by notifying the Contracting Officer as directed by the clause. Any direction given by any Government employee or any other person outside their authority must be reported to the Contracting Officer.
b. The Contracting Officer Representative (COR) is limited to the authorities stated in the COR appointment letter. If a COR is appointed under this contract, they will be appointed by written letter from the Contracting Officer to the Contractor and COR specific to this contract only. COR appointment letters from previous contracts are not valid for this contract. See the Contracting Officer’s Representative clause of this contract.
1.7 SEQUENCING AND SCHEDULING
1.7.1 Operational Period, Restrictions, and Hours
a. The work shall be performed within the permitted environmental window as noted in Subpart "No Dredge Seasons" of this section of the specifications."
SECTION 01 11 00 Page 6
b. Operational Hours: The Contractor will be allowed to perform work 24 hours per day, 7 days per week, including holidays, for the entire contract performance period.
1.7.2 Work Sequence
1.7.2.1 General
There are certain essential criteria relative to the preparation of a work sequence and time schedule which the Contractor will be required to implement and follow during the prosecution of the work. See Section 35 20 25 DREDGING for the required order of work. Minor variations in the sequence of the items of work as approved may be made by the Contractor, provided such variations do not conflict with critical elements of the schedule. Proposed minor variations shall be noted on the progress charts submittal required by CONTRACT CLAUSE, entitled "SCHEDULES FOR CONSTRUCTION CONTRACTS." Variations shall be approved by the Contracting Officer prior to implementation.
1.7.2.2 Progress Schedule
See requirements for a project Progress Schedule in Section 01 32 01
PROGRESS SCHEDULE.
1.7.3 Organization at the Site
1.7.3.1 General
The Contractor shall employ ample personnel and sufficient equipment to accomplish the work of this contract in the least amount of time, within the prosecution period specified in the SPECIAL CONTRACT REQUIREMENTS, Subpart COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984) FAR 52.211-10.
1.7.3.2 Rate of Progress
Should the Contractor fail to maintain a satisfactory rate of progress, the Contracting Officer may require that additional personnel and equipment be placed on the work and weekend and overtime work be performed, in order that the work be brought up to schedule and maintained.
1.8 CONTRACTOR USE OF PREMISES
1.8.1 Storage Areas
See Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS.
1.8.1.1 Work Limits
The limits of work consist of the shoaled areas of the channel and anchorage as shown on the contract drawings, and the side slope areas (assumed 1V:3H) which shall be dredged to obtain the required depth with allowable overdepth, and the four on-shore placement sites (Hampton Beach, Seabrook Beach, South Bridge Abutment, and between the double sheet pile wall adjacent to the middle ground sand flats) as shown on the contract drawings.
SECTION 01 11 00 Page 7
1.8.2 Contractor's Receipt of Supplies
The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.
1.8.3 Access to Work Site
Access to the project site will be discussed at the Preconstruction Conference.
1.8.4 Protection and Security
a. Protection to Contractor personnel or their equipment cannot be provided at the worksite by the Government.
b. The Contractor shall protect all its personnel, Government personnel, and the general public from injury.
c. The Contractor shall conduct all its work so as to prevent injury or unsafe conditions during construction.
1.8.5 Work By Other Contractors
During the performance period of this contract, no other work is anticipated to occur by other contractors.
1.8.6 Emergency Contacts
The Contractor shall provide a list of emergency contacts in the event of an emergency. The list shall include the contact names, addresses, and telephone numbers. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.8.7 Damaged Property
Work shall proceed in a manner which will minimize disturbance or risk of damage to boats, structures, and surrounding lands. The Contractor shall repair such items damaged in the course of carrying out the work at no additional cost to the Government. All repairs shall match similar existing items in all aspects. All replacements shall be in kind.
1.8.8 Contractor's Receipt of Supplies
The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.
1.8.9 Daily Clean Up
The Contractor shall at all times keep rubbish from entering surrounding lands and water. Rubbish accumulated at the temporary facilities shall be removed from the premises daily.
1.8.10 Government Sanitary Facilities
Toilet facilities are not available on site for Contractor's use. The Contractor shall provide portable toilets for its personnel and subcontractors as specified in Section 01 50 00 TEMPORARY CONSTRUCTION
SECTION 01 11 00 Page 8
FACILITIES AND CONTROLS.
1.9 QUALITY ASSURANCE
a. All items of work not addressed in the contract documents shall be completed in strict accordance with the manufacturers’ specifications.
b. The Government is not obligated to inspect the Contractor’s work, or to protect the Contractor from the consequences of its work. Government inspections are a general examination of the Contractor’s conduct and workmanship and are solely for the purpose of the Government.
Government-designated Quality Assurance Representatives (QARs) do not have the authority to accept work, nor is a Government inspection to be construed as conclusive.
c. Government agents including QARs and project engineers are not authorized to change the contract without the written approval of the Contracting Officer; this lack of authority extends to all situations in which the action of these agents could be construed as constituting a change.
d. The quality of workmanship is subject to audit by Government or Government-designated QARs at any time during the contract. The Contractor shall cooperate fully and provide all information necessary for this audit.
e. The Contractor shall submit all requests for changes in writing to the CONTRACTING OFFICER. Do not proceed with changes without possession of written authorization of the Contracting Officer.
f. The Contractor shall not conceal any work unless the Contracting Officer has approved all items of work which are to be concealed. The Contractor shall notify the Contracting Officer of its intention to conceal work at least 24 hours in advance of concealment.
1.10 COORDINATION
1.10.1 Daily Dredge Operations Location Map (DOLM)
The Contractor shall prepare a Dredge Operations Location Map (DOLM) for each day that dredging activities are planned for this project. The DOLM shall indicate the locations where dredge(s) shall be working during a specific 24 hour period, planned disposal activity, and other significant activities planned. The DOLM shall be prepared in PDF format and forwarded to the parties indicated on a distribution list that will be provided to the Contractor after receipt of the Notice to Proceed. An example of a DOLM is attached at the end of this specification section. All information shown on the example is required for each DOLM prepared, including vessel information, location, maps, channel stations, etc. The DOLM's shall be prepared and distributed a minimum of 24 hours prior to the start of the period addressed in the specific DOLM.
1.10.2 Public Notice
The public shall be notified of this dredging project approximately two weeks before commencement of dredging operations at the site. A brief description of the work to be performed and the intended schedule of dredging and disposal operations shall be published in a newspaper of general circulation in the area adjacent to the dredging. The notice shall include the locations where the work is to be performed, the time sequence
SECTION 01 11 00 Page 9 of events, a map of the the disposal site, the location and limits of the disposal site, and the procedure the Contractor will use to respond to claims of loss of fishing gear during the dredging work. The notice shall include the Contractor's point of contact and telephone number.
1.10.3 Notice to Mariners
Before beginning dredging operations, the Contractor shall coordinate with the U.S. Coast Guard (USCG) to issue a "Notice to Mariners" regarding the work to be performed and the Contractor's proposed operations.
The Corps of Engineers and the USCG have agreed to phraseology when issuing navigational bulletins and notices. The information furnished shall be consistent with USCG Broadcast Notice to Mariners and Local Notice to Mariners. When requesting local USCG offices to issue navigational information for Corps of Engineers work involving marine construction, the following terminology shall be used, as applicable:
For cautionary areas: "Mariners are urged to use extreme caution in the area."
For dredging and work operations: "Mariners are urged to transit at their slowest safe speed to minimize wake and proceed with caution after passing arrangements have been made."
1.10.4 Aids to Navigation
Aids to navigation (beacons, buoys, markers, etc.) have been placed by the USCG in the vicinity of the project area. The Contractor shall not remove, change the location of, obstruct, willfully damage, make fast to, or interfere with these aids to navigation. If the work of this project requires the temporary movement or relocation of any aid to navigation, the Contractor shall notify the USCG and the Contracting Officer of the requirement 30 days in advance, in writing. USCG personnel will then move or relocate the aid to navigation as appropriate for the progress of the work. Under no circumstances shall the Contractor move or relocate an aid to navigation under his own authority with his own personnel. The Contractor shall also contact the USCG at the completion of all work and the removal of all marine plant.
1.10.5 Moorings
Refer to Subpart MOORINGS in Section 35 20 25 DREDGING AND DREDGED MATERIAL
PLACEMENT.
1.10.6 Points of Contact
Coast Guard (Notice to Mariners and Aids to Navigation):
Lt. Megan Drewniak, Division Chief, Waterways Management Coast Guard Sector Northern New England Contact Phone Number: (207) 741-5421
Mary Swanson, 1st Coast Guard District Contact Phone Number: (617) 223-8356
New Hampshire Harbor Masters:
Tracy Shattuck, Chief Harbor Master NH Division of Ports and Harbors
SECTION 01 11 00 Page 10
Contact Phone Number: 603-365-0505 Contact Email: tshattuck@peasedev.org
Don Barnard, Hampton Harbor Master Contact Phone Numbers: 603-929-1064 or 603-365-0511 Contact Email: retcap2@comcast.net
Mike Pike, Seabrook Harbor Master Contact Phone Number: 603-365-6345 Contact Email: happyhunters@comcast.net
1.11 PRE-DREDGING PHOTOGRAPHIC AND VIDEO SURVEY
The Contractor shall perform a pre-dredging photographic and video survey at the project site to with the Contracting Officer. This pre-dredging photographic and video survey shall include still photographs and videos in sufficient quantity to fully document the existing condition of all bulkheads, piers, piles, fenders, and other shorefront features, including parking lots and other paved areas, within and adjacent to areas to be dredged as part of this contract. The survey shall provide full coverage of all access and staging areas and material placement areas. A written narrative shall be prepared by the Contractor which organizes and summarizes the findings of the pre-dredging survey photographs and videos.
The narrative shall separately organize all items by individual owners.
The condition of each item shall also be documented in writing. The written narrative, together with the photographs and videos, shall constitute a "Pre-Dredging Photographic and Video Survey Report", which shall be submitted to the Contracting Officer for approval. No on-site dredging work shall be performed until this "Pre-Dredging Photographic and Video Survey Report" has been approved. Damage to features caused by the Contractor's operations shall be repaired by the Contractor at no additional expense to the Government.
1.12 GENERAL SAFETY REQUIREMENTS
1.12.1 General
The Contractor shall take all necessary precautions in observing safety regulations in accordance with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, and shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government property. The Contractor shall perform the work in a manner consistent with security and with fire safety regulations especially with regards to ingress and egress. Temporary closures shall not compromise life safety, security or fire safety.
1.12.2 Contractor's Project Superintendent
The Contractor's project superintendent shall take an active role in enforcing the safety requirements by participation in safety conferences, hazard analysis, tool box meetings, walk-through inspections, correction of violations, etc., and including that of any subcontractor's work.
1.13 ENVIRONMENTAL PROTECTION
To provide for control of all environmental pollution arising from construction activities, the Contractor and its subcontractors, in the performance of this contract, shall comply with Section 01 57 20 ENVIRONMENTAL PROTECTION, and all applicable federal, state, and local laws
SECTION 01 11 00 Page 11 and regulations concerning environmental protection pollution control and abatement.
1.14 PRECONSTRUCTION CONFERENCE
The Contracting Officer will conduct a preconstruction conference with key Contractor personnel. The purpose of the conference is to review contract requirements and to establish a working relationship between the Contractor's Staff and the U.S. Army Corps of Engineers personnel who will be closely associated with the project. During the conference, the Contracting Officer will inform the Contractor concerning Job Safety, Quality Control, Labor Relations, and Environmental Protection. The Contracting Officer will also review the contract requirements relative to the conditions contained in the "Water Quality Certification" and other environmental permits issued for this project. The Contractor's Superintendent, Quality Control Representative, and Site Safety and Health Officer (SSHO) shall attend this conference..
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 11 00 Page 12
FILE NAME:
DRAWING DATE:
DRAWN BY:
USACE JOB NO:
GLDD JOB N0.
APPROVED BY:
SCALE:
PAGE OF
EE
BOSTON GLDD TRAFFIC MAP
ALX
OCT 17, 2017
W912WJ-16-C-0036
1AJB 1
EQUIPMENT TRAFFIC MAP
15666 TO FIT
E6EPGTJM
Text Box Daily Dredge Operations Location Map Example
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
1.2 JOB PAYMENT ITEMS
1.3 UNIT PRICE PAYMENT ITEMS
1.3.1 Variation in Estimated Quantities - Subdivided Items
1.4 BIDDING SCHEDULE - PAYMENT ITEMS
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 22 00 Page 1
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-05 Design Data
Quantity Surveys
Submit originals of all field notes and all other records relating to quantity surveys for progress payments.
1.2 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.3 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items. Submit originals of all field notes and all other records relating to Quantity Surveys.
1.3.1 Variation in Estimated Quantities - Subdivided Items
The following variation in estimated quantities - subdivided items applies only to Items Numbers 0002, 0003, and 0004.
(a) Variation from the estimated quantity in the actual work performed under any second or subsequent sub-item or elimination of all work under such a second or subsequent sub-item will not be the basis for an adjustment in contract unit price.
(b) Where the actual quantity of work performed for Items Numbers 0002, 0003, and 0004 is less than 85% of the quantity of the first sub-item listed under such item, the Contractor will be paid at the contract
SECTION 01 22 00 Page 2 unit price for that sub-item for the actual quantity of work performed and, in addition, an equitable adjustment shall be made in accordance with the clause FAR 52.212-11, Variation in Estimated Quantities.
(c) If the actual quantity of work performed under Items Numbers 0002, 0003, and 0004 exceeds 115% or is less than 85% of the total estimated quantity of the sub-item under that item and/or if the quantity of the work performed under the second sub-item or any subsequent sub-item under Items Numbers 0002, 0003, and 0004 exceeds 115% or is less than 85% of the estimated quantity of any such sub-item, and if such variation causes an increase or a decrease in the time required for performance of this contract the contract completion time will be adjusted in accordance with the clause FAR 52.211-18, Variation in Estimated Quantities.
1.4 BIDDING SCHEDULE - PAYMENT ITEMS
Payment items for the work of this contract on which the contract progress payments will be based are listed in the BIDDING SCHEDULE and are described below. All costs for items of work, which are not specifically mentioned to be included in a particular Bidding Schedule payment item shall be included in the listed lump sum or unit price item most closely associated with the work involved.
Base Bid Items
a. Item No. 0001, "Mobilization and Demobilization."
Payment will be made for costs associated with mobilization and demobilization for mechanical dredging operations and disposal operations as defined in Special Contract Requirements clause "PAYMENT
FOR MOBILIZATION AND DEMOBILIZATION".
Unit of Measure: Job.
b. Item Number 0002, "Maintenance Dredging and Disposal, Inner Harbor;
Channels and Anchorages".
The contract price per cubic yard for Payment Item Number 0002 shall include all costs of removal to the specified depth, as indicated on the contract drawings, of all materials encountered from the Inner Harbor Channels and Anchorages (including the 8-foot deep Hampton Channel, the 8-foot deep Cross Channel, the 8-foot deep Hampton Anchorage, the 6-foot deep Hampton Anchorage, the 8-foot deep Seabrook Channel, and the 8-foot deep Seabrook Anchorage), and all costs associated with transferring the removed material via hydraulic pipeline, placing it at the designated beach locations, the Route 1A bridge abutment location, and/or the sheet pile wall location, and grading the fill to the lines and grades specified in the contract documents.
The total amount of material removed and placed and graded at the placement locations, and paid for under the contract for Item 0002, will be measured by the cubic yard in place by computing the volume between the bottom surface shown by soundings of the last pre-dredge survey made before dredging begins and the bottom surface shown by the soundings of a post-dredge survey made as soon as practicable after the removal of the material. Dredged material will be included that is within the limits of the side slopes and specified channel overdepth as
SECTION 01 22 00 Page 3 described in Section 35 20 25 DREDGING, Subpart "Overdepth and Side Slope," less any deductions that may be required for misplaced material described in Subpart "Disposal of Excavated Material."
The contract drawings listed in Special Contract Requirements clause, "Contract Drawings and Specifications" are believed to accurately represent conditions existing on the date of the survey shown on the drawings, but the depths and the specific areas to be dredged shown thereon may be verified and corrected by soundings taken by the Government before dredging begins. Determination of quantities removed and the deductions made to determine quantities after having once been made by the Contracting Officer, will not be reopened, except on evidence of collusion, fraud, or obvious error.
Monthly partial payments will be based on approximate quantities determined by Contractor quality control surveys. The pre-dredge survey made immediately before dredging, and the post-dredge survey made as soon as practicable after the removal of the material, will be performed by the Government at no cost to the Contractor.
Unit of Measure: Cubic Yard (CD).
Optional Bid Items
c. Item Number 0003, "Maintenance Dredging and Disposal, Entrance Channel".
d. Item Number 0004, "Maintenance Dredging and Disposal, State Maintained Anchorage".
The contract price per cubic yard for Payment Item Numbers 0003 and 0004 shall include all costs of removal to the specified depth, as indicated on the contract drawings, of all materials encountered from the Entrance Channel and from the State Maintained Anchorage, and all costs associated with transferring the removed material via hydraulic pipeline, placing it at the designated beach locations, the Route 1A bridge abutment location, and/or the sheet pile wall location, and grading the fill to the lines and grades specified in the contract documents.
The total amount of material removed and placed and graded at the disposal locations, and paid for under the contract for Item Numbers 0003 and 0004, will be measured by the cubic yard in place by computing the volume between the bottom surface shown by soundings of the last pre-dredge survey made before dredging begins and the bottom surface shown by the soundings of a post-dredge survey made as soon as practicable after the removal of the material. Dredged material will be included that is within the limits of the side slopes and specified channel overdepth as described in Section 35 20 25 DREDGING, Subpart "Overdepth and Side Slope," less any deductions that may be required for misplaced material described in Subpart "Disposal of Excavated Material."
The contract drawings listed in Special Contract Requirements clause "Contract Drawings and Specifications" are believed to accurately represent conditions existing on the date of the survey shown on the drawings, but the depths and the specific areas to be dredged shown thereon may be verified and corrected by soundings taken by the Government before dredging begins. Determination of quantities removed
SECTION 01 22 00 Page 4 and the deductions made to determine quantities after having once been made by the Contracting Officer, will not be reopened, except on evidence of collusion, fraud, or obvious error.
Monthly partial payments will be based on approximate quantities determined by Contractor quality control surveys. The pre-dredge survey made immediately before dredging, and the post-dredge survey made as soon as practicable after the removal of the material, will be performed by the Government at no cost to the Contractor.
Unit of Measure: Cubic Yard (CD).
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 22 00 Page 5
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 PROJECT SCHEDULER QUALIFICATIONS
PART 2 PRODUCTS
2.1 SOFTWARE
2.1.1 Government Default Software
2.1.2 Contractor Software
2.1.2.1 Primavera
2.1.2.2 Other Than Primavera
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 BASIS FOR PAYMENT AND COST LOADING
3.2.1 Activity Cost Loading
3.2.2 Withholdings / Payment Rejection
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
3.3.2 Activity Durations
3.3.3 Procurement Activities
3.3.4 Mandatory Tasks
3.3.5 Government Activities
3.3.6 Standard Activity Coding Dictionary
3.3.6.1 Workers Per Day (WRKP)
3.3.6.2 Responsible Party Coding (RESP)
3.3.6.3 Area of Work Coding (AREA)
3.3.6.4 Modification Number (MODF)
3.3.6.5 Bid Item Coding (BIDI)
3.3.6.6 Phase of Work Coding (PHAS)
3.3.6.7 Category of Work Coding (CATW)
3.3.6.8 Feature of Work Coding (FOW)
3.3.7 Contract Milestones and Constraints
3.3.7.1 Project Start Date Milestone and Constraint
3.3.7.2 End Project Finish Milestone and Constraint
3.3.7.3 Interim Completion Dates and Constraints
3.3.7.3.1 Start Phase
3.3.7.3.2 End Phase
3.3.8 Calendars
3.3.9 Open Ended Logic
3.3.10 Default Progress Data Disallowed
3.3.11 Out-of-Sequence Progress
3.3.12 Added and Deleted Activities
SECTION 01 32 01 Page 1
3.3.13 Original Durations
3.3.14 Leads, Lags, and Start to Finish Relationships
3.3.15 Retained Logic
3.3.16 Percent Complete
3.3.17 Remaining Duration
3.3.18 Cost Loading of Closeout Activities
3.3.18.1 As-Built Drawings
3.3.18.2 O & M Manuals
3.3.19 Early Completion Schedule and the Right to Finish Early
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Preliminary Project Schedule Submission
3.4.2 Initial Project Schedule Submission
3.4.3 Periodic Schedule Updates
3.5 SUBMISSION REQUIREMENTS
3.5.1 Data CD/DVDs
3.5.2 Narrative Report
3.5.3 Schedule Reports
3.5.3.1 Activity Report
3.5.3.2 Logic Report
3.5.3.3 Total Float Report
3.5.3.4 Earnings Report by CLIN
3.5.3.5 Schedule Log
3.5.4 Network Diagram
3.5.4.1 Continuous Flow
3.5.4.2 Project Milestone Dates
3.5.4.3 Critical Path
3.5.4.4 Banding
3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram
3.6 PERIODIC SCHEDULE UPDATE
3.6.1 Periodic Schedule Update Meetings
3.6.2 Update Submission Following Progress Meeting
3.7 WEEKLY PROGRESS MEETINGS
3.8 REQUESTS FOR TIME EXTENSIONS
3.8.1 Justification of Delay
3.8.2 Time Impact Analysis (Prospective Analysis)
3.8.3 Forensic Schedule Analysis (Retrospective Analysis)
3.8.4 Fragmentary Network (Fragnet)
3.8.5 Time Extension
3.8.6 Impact to Early Completion Schedule
3.9 FAILURE TO ACHIEVE PROGRESS
3.9.1 Artificially Improving Progress
3.9.2 Failure to Perform
3.9.3 Recovery Schedule
3.10 OWNERSHIP OF FLOAT
3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS
3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS
SECTION 01 32 01 Page 2
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G, RO
Preliminary Project Schedule; G, RO
Initial Project Schedule; G, RO
Periodic Schedule Update; G, RO
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
SECTION 01 32 01 Page 3
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
2.1.1 Government Default Software
The Government intends to use Primavera P6.
2.1.2 Contractor Software
Scheduling software used by the Contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.
2.1.2.1 Primavera
If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.
2.1.2.2 Other Than Primavera
If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
SECTION 01 32 01 Page 4
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates, as appropriate to the work.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission, review and acceptance of features require design completion
c. Submission of mechanical/electrical/information systems layout drawings.
d. Long procurement activities
SECTION 01 32 01 Page 5
e. Submission and approval of O & M manuals.
f. Submission and approval of as-built drawings.
g. Submission and approval of DD1354 data and installed equipment lists.
h. Submission and approval of testing and air balance (TAB).
i. Submission of TAB specialist design review report.
j. Submission and approval of fire protection specialist.
k. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.
l. Air and water balancing.
m. Building commissioning - Functional Performance Testing.
n. Controls testing plan submission.
o. Controls testing.
p. Performance Verification testing.
q. Other systems testing, if required.
r. Contractor's pre-final inspection.
s. Correction of punch list from Contractor's pre-final inspection.
t. Government's pre-final inspection.
u. Correction of punch list from Government's pre-final inspection.
v. Final inspection.
3.3.5 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard…
This is the start of the file's text. The full file is on GovTribe.