Specifications.pdf
PDF 2 MB Posted
- Attached to
- Replacement of the Elevators at the Cape Cod Canal Railroad Bridge in Bourne, Massachusetts
- Solicitation number
- W912WJ18B0009
About this file
Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Abstract.pdf | ||
| Amendment_0002.pdf | ||
| Amendment_0001_-_Drawings.pdf | ||
| Amendment_0001.pdf | ||
| Plans_-_1996-ELEV-REPLACEMENT.pdf | ||
| Plans.pdf | ||
| Plans_-_1966-ELEVATOR-MODS.pdf | ||
| W912WJ18B0009.pdf | ||
| Plans_-_ALIMAK_ELEV_AS-BUILTS.pdf | ||
| Plans_-_Span_Lock.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912WJ18B0009
Replace Elevator Vertical Lift Railroad Bridge
Cape Cod Canal, Buzzards Bay, Massachusetts
Construction Solicitation and Specifications
August 2018
Replace Elevator, Railroad Bridge, Cape Cod Canal, MA
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 22 00 MEASUREMENT AND PAYMENT
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 01 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 20 ENVIRONMENTAL PROTECTION
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 42 14 FIBERGLASS REINFORCED PLASTIC (FRP) TRANSLUCENT PANELS
DIVISION 14 - CONVEYING EQUIPMENT
14 21 13 ELEVATORS, ELECTRIC
DIVISION 26 - ELECTRICAL
26 00 00 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 19 LOW VOLTAGE INSULATED WIRE AND CABLE
26 20 00 ELECTRICAL DISTRIBUTION SYSTEM
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Work in Railroad Right-of-Way
1.1.2 Photographs
1.2 REFERENCES
1.3 SUBMITTALS
1.4 PROTECTION OF EXISTING STRUCTURES, UTILITIES, AND WORK
1.4.1 General
1.4.2 Debris Control
1.4.3 Existing Electrical Circuits
1.4.4 Cape Cod Canal Television (CCTV) Cameras
1.4.5 Video Control Cable
1.4.6 Radio Antennae
1.4.7 Counterweight Ropes and Guides
1.4.8 Sheave Trunnion and Trunnion Bearings
1.5 SUPERINTENDENCE BY THE CONTRACTOR
1.6 COORDINATION AND DIRECTION DURING CONSTRUCTION
1.7 PROJECT/SITE CONDITIONS
1.7.1 Site Security
1.8 WORK SEQUENCE AND SCHEDULING
1.8.1 Hours of Operations
1.8.2 Coordination
1.8.3 Work Sequence
1.8.3.1 General
1.8.3.2 Initial Project Schedule
1.8.3.3 Periodic Schedule Updates
1.8.4 Organization at the Site
1.8.4.1 General
1.8.4.2 Rate of Progress
1.9 CONSTRUCTION OPERATIONAL RESTRICTIONS
1.10 CONTRACTOR'S USE OF FACILITIES AND HAULING ROUTES
1.11 CONTRACTOR USE OF PREMISES
1.11.1 Access to the Site and Storage/Staging Areas
1.11.2 Temporary Facilities and Utilities, and Storage Areas
1.11.3 Work Limits
1.11.4 Use of Lift Span
1.11.5 Protection and Security
1.11.6 Work By Other Contractors
1.11.7 Emergency Contacts
1.11.8 Damaged Property
1.11.9 Contractor's Receipt of Supplies
1.11.10 Daily Clean Up
1.11.11 Government Sanitary Facilities
1.11.12 Construction Access Plan
1.12 PRE-CONSTRUCTION SURVEY
1.13 QUALITY ASSURANCE
1.14 GENERAL SAFETY REQUIREMENTS
SECTION 01 11 00 Page 1
1.14.1 General
1.14.2 Contractor's Project Superintendent
1.15 ENVIRONMENTAL PROTECTION
1.16 PRECONSTRUCTION CONFERENCE
1.17 RECORD DRAWINGS
1.17.1 Preparation of Record Drawings
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section Table of Contents --
SECTION 01 11 00 Page 2
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
The general description below is given to indicate the approximate scope of this project only. It does not limit the work required under the project drawings and specifications.
The base bid work of this project involves the replacement of the existing 20 year old elevator and elevator related architectural, structural steel, electrical and mechanical components of the Vertical Lift Railroad Bridge at the Cape Cod Canal Facility in Buzzards Bay, Massacusetts, which has not been changed other than routine maintenance.
The Railroad Bridge shall remain fully operational for the duration of this contract. The lift span shall be in the raised position for the work of this contract. Continuous Contractor coordination with the Cape Cod Canal Marine Traffic Controller and the Massachusetts Coastal Railroad (freight operations) and the Cape Cod Central Railroad (passenger operations) is a contract requirement to accomplish this work.
During the performance of the work of theis project, at least one elevator shall be functional at all times, either an existing elevator or a new elevator.
The work of this project requires work at heights and significant fall hazards exist. The Contractor shall implement fall protection measures as specified in this document.
The Contractor is strongly encouraged to visit the project site to ascertain current conditions. Failure to complete a site visit and failure to identify obvious site conditions does not constitute a valid claim for a differing site condition once the work is executed.
1.1.1 Work in Railroad Right-of-Way
It is anticipated that the work will not require the use of rail lines and the Contractor storage and setup will be placed well clear of the railroad track. The work is not anticipated to constrain rail operations.
Therefore, the only anticipated requirement is for all the Contractors on-site employees to attend a two hour Rail Worker Safety training session at the Cape Cod Canal Field Office as part of the mobilization.
If the Contractors operation constrains rail operations beyond what is anticipated, the Contractor is responsible for providing insurance, flaggers, worker safety training, and all other requirements established by the railroad when working within the railroad right-of-way.
Attached at the end of the specification document is a "Memorandum for the Record" documenting a discussion of the Railroad Bridge elevator replacement project with officials from Cape Rail by representatives from the U.S. Army Corps of Engineers.
SECTION 01 11 00 Page 3
1.1.2 Photographs
Attached at the end of this section are photographs of the Railroad Bridge taken during a recent inspection. The photographs are intended to show the conditions of the existing elevator at that time and the general configuration of the bridge. Items shown are not generally shown in their entirety. The Government does not guarantee that the conditions shown in the photographs will exist at the time of the performance of the work, and the Contractor is advised to make his own investigation of existing conditions.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
AMERICAN RAILWAY ENGINEERING AND MAINTENANCE-OF-WAY ASSOCIATION
(AREMA)
AREMA Manual for Railway Engineering
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Initial Project Schedule; G, RO
In accordance with the contract clauses, the Contractor shall, within 5 days after receipt of Notice to Proceed (NTP) or as otherwise determined by the Contracting Officer, submit for approval a practicable project schedule. When changes are authorized that result in contract time extensions, the Contractor shall submit a revised project schedule for approval by the Contracting Officer.
Construction Access Plan; G, DO
Detail drawings indicating material thickness, type, grade, and class; dimensions; and construction details. Drawings shall include catalog cuts, erection details, alignment procedure, manufacturer's descriptive data and installation instructions, and templates. Design calculations shall also be submitted to demonstrate the structural adequacy of the proposed system and to analyze loadings that will be imposed on the Railroad Bridge superstructure.
Pre-Construction Survey; G, RO
The Contractor shall submit a pre-construction survey as described in this section.
SECTION 01 11 00 Page 4
SD-07 Certificates
Periodic Schedule Updates; G, RO
Request Application; G, RO
Request Application to work outside the hours of operation.
SD-11 Closeout Submittals
Record Drawings; G, DO
Record drawings showing all deviations which have been made from the contract drawings shall be submitted to the Contracting Officer for approval at the completion of work. See paragraph RECORD DRAWINGS for record keeping and submittal requirements.
1.4 PROTECTION OF EXISTING STRUCTURES, UTILITIES, AND WORK
1.4.1 General
The Contractor shall protect the existing bridge structure and all utilities from damage or interruption of service. Damage or any interruption of service resulting from the Contractor's operations shall be repaired or service restored promptly at the expense of the Contractor.
1.4.2 Debris Control
Care shall be taken that no railroad material, pieces of support structures, debris, or any materials whatsoever, fall into the canal or to the ground. Should debris or construction materials fall from the bridge inadvertently, prompt corrective action shall be taken to prevent further occurrences and the fallen items shall be secured and removed. The Contractor shall take all precautions practicable to prevent items from falling from the bridge. Debris deposited on horizontal surfaces of the superstructure and piers shall be collected and disposed of properly.
Sweeping of debris off the bridge to the land or water below will not be permitted. No falling debris will be tolerated as the Canal is continually open to marine traffic.
1.4.3 Existing Electrical Circuits
Electrical circuits on the bridge consist of lighting for the towers and operator's house, aerial cables run in one of two catenaries extending from each tower of the bridge, navigation lighting for marking the channel.
1.4.4 Cape Cod Canal Television (CCTV) Cameras
Two CCTV cameras on the north tower of the bridge shall not be removed and shall be protected from damage during the construction operations, if near the location of the cameras. Protective covers shall be placed over the cameras during construction in their vicinity. The Marine Traffic Controller shall be notified when the cameras are taken out of service.
Covers shall be removed at the end work in the vicinity, or at the end of the day. The Contractor shall protect the microwave reflection board on the north tower.
SECTION 01 11 00 Page 5
1.4.5 Video Control Cable
A special video control cable is attached to the north tower for operation of the cameras. A 25 pair telephone cable and a fiber optic cable are also attached to the north tower for the control of the radio base station in the tower. Use extreme care to protect these cables from damage.
1.4.6 Radio Antennae
Radio antennae for the railroads and various Federal and State agencies are located on both towers. The Contractor shall protect the antennae and helix cabling from damage at all times. Severe electrical shock and RF burn will result from touching these antennae and helix cabling during a transmission.
1.4.7 Counterweight Ropes and Guides
Protect all new counterweight ropes and guides and both elevator shafts and hoisting equipment from cleaning residue and debris attaching to or impacting the operation of these systems.
1.4.8 Sheave Trunnion and Trunnion Bearings
Protect all new counterweight rope sheaves and trunnion bearings from cleaning residue and debris attaching to or impacting the operation of these systems.
1.5 SUPERINTENDENCE BY THE CONTRACTOR
a. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent project superintendent who is satisfactory to the Contracting Officer and has the authority to act for the Contractor.
b. The project superintendent shall maintain a physical presence at the site at all times and be responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.
c. Failure to comply with these requirements shall be deemed as cause for a non-compensatory stoppage and suspension of work until the deficiency is remedied.
1.6 COORDINATION AND DIRECTION DURING CONSTRUCTION
a. The Contractor shall not take or accept any direction or instructions issued by any person, employed by the Government or otherwise, other than the Contracting Officer that changes the terms and conditions of contract actions, the scope, or any change that impacts the cost, price, or schedule. Changes authorized by the Contracting Officer will be in the form of a written, official, signed modification to the contract action received by the Contractor before the Contractor will act upon those changes. The Contractor will comply with the changes clause of this contract when the Contractor believes direction has been given from persons other than the Government Contracting Officer that equate to a change by notifying the Contracting Officer as directed by the clause. Any direction given by any Government employee or any other person outside their authority must be reported to the Contracting Officer.
SECTION 01 11 00 Page 6
b. The Contracting Officer Representative (COR) is limited to the authorities stated in the COR appointment letter. If a COR is appointed under this contract, they will be appointed by written letter from the Contracting Officer to the Contractor and COR specific to this contract only. COR appointment letters from previous contracts are not valid for this contract. See the Contracting Officer’s Representative clause of this contract.
1.7 PROJECT/SITE CONDITIONS
1.7.1 Site Security
The Contractor shall report any vandalism, suspicious activities or devices to the Contracing Officer or local police as soon as possible. The Contracting Officer will notify the Contractor of any heightened security measures and will expect vigilant monitoring of equipment, grounds and security fencing while working. At a heightened security posture, there may be work areas that are restricted. The Contracting Officer will notify the Contractor of these restricted areas, and work may be delayed or restricted or will be performed in these areas under the direct supervision of U.S. Army Corps of Engineers personnel.
1.8 WORK SEQUENCE AND SCHEDULING
1.8.1 Hours of Operations
Normal work hours are from 7:00 a.m. through 5:30 p.m., Monday through Friday. The Contractor will not be permitted to work on Saturday, Sunday, Patriots Day (a Massachusetts State holiday), or on Federal legal holidays unless otherwise authorized by the Contracting Officer. The exclusion of work on Saturday, Sunday, and legal holidays has been considered in computing the performance time of this contract. The following legal holidays are observed:
January 1st Third Monday in January Third Monday in February Last Monday of May July 4th 1st Monday of September 2nd Monday of October 11th of November Fourth Thursday of November 25th of December
When one of the above designated legal holidays falls on a Sunday, the following Monday will be observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday.
Work outside the normal hours of operation requires Contracting Officer approval. The request to work outside the hours of operation shall be made in writing to the Contracting Officer 10 calendar days prior to such work to allow arrangements to be made by the Government. The request application shall include specific dates, hours, location, type of work to be performed, contract number and project title, and names of all individuals who will be working outside the hours of operations. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.
SECTION 01 11 00 Page 7
1.8.2 Coordination
Continuous Contractor coordination with the Cape Cod Canal Marine Traffic Controller and the Massachusetts Coastal Railroad (freight operations) and the Cape Cod Central Railroad (passenger operations) is a contract requirement to accomplish this work. Both the Massachusetts Coastal Railroad and the Cape Cod Central Railroad are subsidiaries of Iowa Pacific Holdings. The Contractor's superintendent or his designated representative shall maintain radio contact with the Railroads and the Canal Marine Traffic Controller at all times during the performance of the work.
Should the Contractor utilize any railroad track based equipment, defined as the track, ties, signals or appurtances (not the bridge), or perform work in or encroaching on the railroad right-of-way, access to non US Government owned property will be required. The Contractor shall be solely responsible for coordinating with the railroad companies to determine additional railroad requirements for such work in the right-of-way, and the Contractor shall comply with all of these requirements as a condition of this contract. These requirements may include, but are not limited to, flaggers and training for Contractor employees. If the Contractor does not utilize railroad track based equipment, or performs no work in or encroaching on the railroad right-of-way, the only contract requirement will be to take the railroad worker protection training.
Contact information for the above is as follows:
Massachusetts Coastal Railroad 68 Center Street #201 Hyannis, Massachusetts 02601 Telephone: 508-771-8400
Cape Cod Central Railroad 252 Main Street Hyannis, Massachusetts 02601 508-771-3800
Cape Cod Canal Marine Traffic Controller Telephone: 978-318-8500 VHF Radio Channels 13, 14, 16
1.8.3 Work Sequence
1.8.3.1 General
There are certain essential criteria relative to the preparation of a work sequence and time schedule which the Contractor will be required to implement and follow during the prosecution of the work. Minor variations in the sequence of the items of work as specified may be made by the Contractor, provided such variations do not conflict with critical elements of the schedule. Proposed minor variations shall be noted on the progress charts submittal required by CONTRACT CLAUSE, entitled "SCHEDULES FOR CONSTRUCTION CONTRACTS". Variations shall be approved by the Contracting Officer prior to implementation.
1.8.3.2 Initial Project Schedule
The initial project schedule shall be in the form of a chart graphically indicating the sequence proposed to accomplish each work feature or
SECTION 01 11 00 Page 8 operation. The chart shall be prepared to show the starting and completion dates of all work features on a linear horizontal time scale beginning with date of Notice to Proceed and indicating calendar days to completion. The Contractor shall indicate on the chart the important work features or operations that are critical to the timely overall completion of the project. Key dates for such important work features and portions of work features are milestone dates and shall be so indicated on the chart. This schedule will be the medium through which the timeliness of the Contractor's construction effort is appraised. Anticipated adverse weather delay days shall be included and clearly indicated in the schedule.
The initial schedule shall be cost and resource loaded for contract monitoring and control purposes. Schedules shall be established using a standard critical path method (CPM), or other industry approved standard.
Each activity shall have an early start/finish date, late start/finish date, task duration, and total float clearly indicated.
1.8.3.3 Periodic Schedule Updates
An updated schedule showing actual progress shall be submitted monthly or with each pay request. Changes to the base-line schedule shall be outlined in a narrative describing the reason for the change.
1.8.4 Organization at the Site
1.8.4.1 General
The Contractor shall employ ample personnel and sufficient equipment to accomplish the work of this contract in the least amount of time, within the prosecution period specified in SPECIAL CONTRACT REQUIREMENTS, Clause 1.
1.8.4.2 Rate of Progress
Should the Contractor fail to maintain a satisfactory rate of progress in accordance with the Contractor's approved progress schedule, the Contracting Officer may require that additional personnel and equipment be placed on the work and weekend and overtime work be performed, in order that the work be brought up to schedule and maintained.
1.9 CONSTRUCTION OPERATIONAL RESTRICTIONS
a. The lift span is normally in the up position. The span is lowered for all Railroad traffic and maintenance work.
b. The Contractor shall accommodate railroad traffic across the Bridge at all times. Railroad traffic across the Bridge will not be suspended during the work of this contract. Railroad traffic will generally occur close to the times shown on the "Train Schedule" listing below. However, deviations from the schedule as listed are expected. Therefore, daily coordination with the Bridge Operators is required to ensure that the Bridge is operational for the passage of trains. Typically the Contractor should expect not more than a continuous 8 hour period during the workday in which to perform work without railroad traffic. However, the Contractor can also expect some days to have more frequent Railroad traffic, which will reduce the amount of continuous work time on the Bridge. All work that limits the operation of the Bridge or the passage of trains shall be completed or removed a minimum of 30 minutes prior to train passage. Equipment, materials, and all work shall be setup to allow the Bridge to move up and down freely and to allow the passage of rail traffic without interference.
SECTION 01 11 00 Page 9
All Contractor personnel shall be off of the Bridge during the passage of rail traffic.
c. All work shall be scheduled and performed in a manner to ensure that no restriction will be placed on the normal flow of marine navigation. The only exception is rigging and scaffolding needed below the span that reduces the vertical clearance under the Bridge. The minimum clearance at mean high water shall be 130 feet to the bottom of all temporary equipment. All reductions in the clearance under the Bridge requires coordination with the U.S. Coast Guard for a "Notice to Mariners".
d. The Contractor shall ensure that the bridge is properly balanced at all times. All use of tools or equipment that may affect the balance of the span will require the Contractor to furnish and install balance blocks on the Bridge counterweights.
e. Provide key personnel hand-held VHF radios. The radios shall be capable of communicating with the bridge operating personnel when bridge movements are being made. Appoint one person to be sure workers are in a safe position during bridge moves and to communicate, as necessary, with the bridge operators before, during, and after a bridge move. A minimum 30 minute time period is required to clear all personnel to safety before the bridge moves.
f. During the performance of the work of this project, at least one elevator shall be functional at all times, either an existing elevator or a new elevator.
Train Schedule and Required Bridge Movements
Use of the Railroad Bridge and operation of the lift span for the passage of trains will be required during the construction period of this contract. Required time frames for anticipated bridge movements are listed below. These times, and the number of required movements, are subject to change.
Note: A "bridge movement" is defined as the lift span moving from the raised position to the lowered position and then back to the raised position again after the passage of a train. The entire movement process typically requires between 15 and 30 minutes to complete.
A. Monday through Friday, all year:
1 to 2 bridge movements between 0700 and 1100 1 bridge movement between 1630 and 1900
B. Additional Seasonal Movements; the Friday before Memorial Day through Labor Day (25 May 2018 through 3 September 2018 and 24 May 2019 through 2 September 2019):
Fridays:
1 additional bridge movement between 0700 and 0800.
1 bridge movement between 2130 and 2230
Saturdays and Sundays:
1 bridge movement between 0900 and 1000.
1 bridge movement between 1900 and 2000.
SECTION 01 11 00 Page 10
C. 3 July, any year: same as Friday in "B" above.
D. Memorial Day, July 4th, and Labor Day: same as Saturday and Sunday in "B" above.
E. 17 May through 13 October, any year (these are in addition to movements described above):
Thursdays and Saturdays: 1 bridge movement between 1830 and 1930 Fridays:
1 bridge movement between 1730 and 1800 1 bridge movement between 2015 and 2045
1.10 CONTRACTOR'S USE OF FACILITIES AND HAULING ROUTES
The Contractor shall be responsible for the following:
(1) Determining the trucking and hauling routes and associated restrictions to and from the work, to include the coordination for the use of such routes with local, State, and Federal authorities.
(3) Complying with all local, State, and Federal regulations and restrictions when using any facilities or hauling routes.
1.11 CONTRACTOR USE OF PREMISES
1.11.1 Access to the Site and Storage/Staging Areas
Access to the project site is available for construction traffic. The Contractor is responsible for maintaining access necessary for its equipment, material, and plant to and from the work area.
Access to temporary facilities and storage/staging areas shall be as specified in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS.
1.11.2 Temporary Facilities and Utilities, and Storage Areas
The Contractor shall conform to Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS regarding temporary facilities, temporary utilities, and storage areas. Confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
1.11.3 Work Limits
Work shall be restricted to the Federal Property associated with the Railroad Bridge and Cape Cod Canal Facilities, storage areas as indicated in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, and as indicated by the Contracting Officer.
1.11.4 Use of Lift Span
The lift span may be used by the Contractor up to once per week, when the lift span is operational, and only for the purpose of delivering materials and equipment to the lift span and towers. No additional use of the lift
SECTION 01 11 00 Page 11 span will be permitted. The lift span may not be used by the Contractor to transport Contractor personnel on and off of the Bridge.
All Contractor use of the lift span will be subject to the approval of the Contracting Officer and dependent on the passage of scheduled or unscheduled train and marine traffic. All Bridge movements shall be scheduled in advance with the Contracting Officer. All Contractor requests for use of the lift span shall be submitted to the Contracting Officer for approval a minimum of 7 calendar days prior to the desired bridge movement.
1.11.5 Protection and Security
a. Protection to Contractor personnel or their equipment cannot be provided at the worksite by the Government.
b. The Contractor shall protect all its personnel, Government personnel, and the general public from injury.
c. The Contractor shall conduct all its work so as to prevent injury or unsafe conditions during construction.
1.11.6 Work By Other Contractors
During the performance period of this contract, no other work is anticipated to occur by other contractors.
1.11.7 Emergency Contacts
The Contractor shall provide a list of emergency contacts in the event of an emergency. The list shall include the contact names, addresses, and telephone numbers. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.11.8 Damaged Property
Work shall proceed in a manner which will minimize disturbance or risk of damage to structures and surrounding lands. The Contractor shall repair such items damaged in the course of carrying out the work at no additional cost to the Government. All repairs shall match similar existing items in all aspects. All replacements shall be in kind.
1.11.9 Contractor's Receipt of Supplies
The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.
1.11.10 Daily Clean Up
The Contractor shall at all times keep rubbish from entering surrounding lands and water. Rubbish accumulated at the temporary facilities shall be removed from the premises daily.
1.11.11 Government Sanitary Facilities
Toilet facilities are not available on site for Contractor's use. The Contractor shall provide portable toilets for its personnel and subcontractors as specified in Section 01 50 00 TEMPORARY CONSTRUCTION
FACILITIES AND CONTROLS.
SECTION 01 11 00 Page 12
1.11.12 Construction Access Plan
Access to the project site is limited as specified above. The Contractor shall devise its own means of accessing the lift span and towers for the transport of personnel, equipment, and materials, as necessary to accomplish the work within the specified time period. The plan for accessing the Bridge shall be submitted to the Contracting Officer for review and approval. No obstacles shall encroach upon the railroad clearances prescribed in the American Railway Engineering and Maintenance -of Way Association (AREMA) "Manual for Railway Engineering," Chapter 28.
1.12 PRE-CONSTRUCTION SURVEY
The Contractor shall perform a pre-construction survey at the project site. This pre-construction survey shall include still photographs and/or videos in sufficient quantity to fully document the existing condition of all features of the Railroad Bridge within the work area which may be impacted by construction activities, such as steel structure, elevator components, utilities, and other pertinent features. A written narrative shall be prepared by the Contractor which organizes and summarizes the findings of the pre-construction survey photographs and/or videos. Each item shall be identified as "to remain", "to be removed and reset", "to be removed and replaced", or "to be demolished or discarded". The condition of each item shall also be documented. The written narrative, together with the photographs and/or videos, shall constitute a "Pre-construction Survey Report", which shall be submitted to the Contracting Officer for approval. No on-site work shall be performed until this "Pre-construction Survey Report" has been approved. Damage to items remaining or to be reused caused by the Contractor's operations shall be repaired by the Contractor at no additional expense to the Government.
1.13 QUALITY ASSURANCE
a. All items of work not addressed in the contract documents shall be completed in strict accordance with the manufacturers’ specifications.
b. The Government is not obligated to inspect the Contractor’s work, or to protect the Contractor from the consequences of its work. Government inspections are a general examination of the Contractor’s conduct and workmanship and are solely for the purpose of the Government.
Government-designated Quality Assurance Representatives (QARs) do not have the authority to accept work, nor is a Government inspection to be construed as conclusive.
c. Government agents including QARs and project engineers are not authorized to change the contract without the written approval of the Contracting Officer; this lack of authority extends to all situations in which the action of these agents could be construed as constituting a change.
d. The quality of workmanship is subject to audit by Government or Government-designated QARs at any time during the contract. The Contractor shall cooperate fully and provide all information necessary for this audit.
e. The Contractor shall submit all requests for changes in writing to the Contracting Officer. Do not proceed with changes without possession of written authorization of the Contracting Officer.
SECTION 01 11 00 Page 13
f. The Contractor shall not conceal any work unless the Contracting Officer has approved all items of work which are to be concealed. The Contractor shall notify the Contracting Officer of its intention to conceal work at least 24 hours in advance of concealment.
1.14 GENERAL SAFETY REQUIREMENTS
1.14.1 General
The Contractor shall take all necessary precautions in observing safety regulations in accordance with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, and shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government property. The Contractor shall perform the work in a manner consistent with security and with fire safety regulations especially with regards to ingress and egress. Temporary closures shall not compromise life safety, security or fire safety.
1.14.2 Contractor's Project Superintendent
The Contractor's project superintendent shall take an active role in enforcing the safety requirements by participation in safety conferences, hazard analysis, tool box meetings, walk-through inspections, correction of violations, etc., and including that of any subcontractor's work.
1.15 ENVIRONMENTAL PROTECTION
To provide for control of all environmental pollution arising from construction activities, the Contractor and its subcontractors, in the performance of this contract, shall comply with Section 01 57 20 ENVIRONMENTAL PROTECTION, and all applicable federal, state, and local laws and regulations concerning environmental protection pollution control and abatement.
1.16 PRECONSTRUCTION CONFERENCE
The Contracting Officer will conduct a preconstruction conference with key Contractor personnel. The purpose of the conference is to review contract requirements and to establish a working relationship between the Contractor's Staff and the U.S. Army Corps of Engineers personnel who will be closely associated with the project. During the conference, the Contracting Officer will inform the Contractor concerning Job Safety, Quality Control, Labor Relations, and Environmental Protection. The Contractor's Superintendent, Quality Control Representative, and Site Safety and Health Officer (SSHO) shall attend this conference.
1.17 RECORD DRAWINGS
Maintain at the jobsite one set of full-size contract drawings marked to show all deviations which have been made from the contract drawings, including buried or concealed construction and utility features revealed during the course of construction. Record the horizontal and vertical location of all buried utilities that differ from the contract drawings.
These drawings shall be available for review by the Contracting Officer at all times. Upon completion of the work, submit the original marked set of prints to the Contracting Officer for approval. Requests for partial payments will not be approved if the marked prints are not current, and request for final payment will not be approved until the marked prints are submitted to and approved by the Contracting Officer.
SECTION 01 11 00 Page 14
1.17.1 Preparation of Record Drawings
The entries shall be made in the jobsite set of prints at the time field changes are made, pertinent information collected, or need for corrections established, as a continuing process during the life of the contract. As revised drawings are issued by the Contracting Officer, revised prints shall be introduced into the set to replace the superseded drawings and all applicable notations previously made on the superseded drawings transferred to the current prints. Carefully prepared sketches, not less than 8-1/2" x 11", may be used to depict changes or added information in lieu of notations on the actual prints. Staple sketches to the prints affected by the change. All plan views, sections, elevations, profiles, diagrams, details, or schedules affected by a change shall be marked up as required to reflect the change. All notations or changes made on the prints shall be in sufficient detail to clearly depict the change. Colored pens or pencils shall be used to make notations on the record prints as follows:
Red pen or pencil shall be employed to indicate added or corrected work or information.
Green pen or pencil shall be used to show the deleted or incorrectly depicted work or information.
Blue or black pen or pencil shall be used to show information not to be recorded on the drawings but included on the marked-up prints for explanatory or clarification purposes for the benefit of the Contracting Officer.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
SECTION 01 11 00 Page 15
North Tower elevator’s enclosure panels. Typical minor to moderate corrosion on fasteners (panels to be replaced).
Elevator shaft, looking down. Typical condition of topside of bracing members. Typical minor corrosion and paint failure.
Elevator shaft, typical condition of underside of bracing members. Minor corrosion and paint failure on rivet heads.
Elevator shaft, has areas of minor corrosion and paint failure on topside of the bracing connection plates.
Elevator shaft, typical condition of bracing members.
Elevator shaft, typical configuration of shaft and panels. Panels to be replaced.
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 JOB PAYMENT ITEMS
1.2 BIDDING SCHEDULE - PAYMENT ITEMS
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00 Page 1
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. The job price and payment made the job item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.2 BIDDING SCHEDULE - PAYMENT ITEMS
Payment items for the work of this contract on which the contract progress payments will be based are listed in the BIDDING SCHEDULE and are described below. All costs for items of work, which are not specifically mentioned to be included in a particular Bidding Schedule job or unit price payment item, shall be included in the listed item most closely associated with the work involved.
a. Item Number 0001, "Provide New Elevator, North Side".
All costs for labor, equipment, and materials to provide a new elevator on the north side of the Railroad Bridge, as shown on the contract drawings and in accordance with the specifications. This item includes only the material and purchase cost for the new elevator. Delivery and installation of the new elevator is included in Item 0002.
Unit of Measure: Job.
b. Item Number 0002, "Deliver and Install New Elevator and Furnish and Install New Rack and Associated Items, including Replacement of FRP Panels, North Side".
All costs for labor, equipment, and materials to deliver and install a new elevator and to furnish and install a new rack and associated items, including replacement of FRP panels and warranty inspection and service at 4 months and 9 months from Government acceptance, on the north side of the Railroad Bridge, as shown on the contract drawings and in accordance with the specifications. The material and purchase cost for the new elevator must be included in Item 0001.
Unit of Measure: Job.
c. Item Number 0003, "Provide New Elevator, South Side".
All costs for labor, equipment, and materials to provide a new elevator on the south side of the Railroad Bridge, as shown on the contract drawings and in accordance with the specifications. This item includes
SECTION 01 22 00 Page 2 only the material and purchase cost for the new elevator. Delivery and installation of the new elevator is included in Item 0004.
Unit of Measure: Job.
d. Item Number 0004, "Deliver and Install New Elevator and Furnish and Install New Rack and Associated Items, including Replacement of FRP Panels, South Side".
All costs for labor, equipment, and materials to deliver and install a new elevator, and to furnish and install a new rack and associated items, including replacement of FRP panels and warranty inspection and service at 4 months and 9 months from Government acceptance, on the south side of the Railroad Bridge, as shown on the contract drawings and in accordance with the specifications. The material and purchase cost for the new elevator must be included in Item 0003.
Unit of Measure: Job.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00 Page 3
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
1.2.2 Approving Authority
1.2.3 Work
1.3 SUBMITTALS
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved (G)
1.4.1.1 Approval Codes
1.4.2 Information Only
1.5 PREPARATION
1.5.1 Transmittal Form
1.6 QUANTITY OF SUBMITTALS
1.6.1 Number of Copies of SD-02 Shop Drawings
1.6.2 Number of Copies of SD-03 Product Data and SD-08
Manufacturer's Instructions
1.6.3 Number of Samples SD-04 Samples
1.6.4 Number of Copies SD-05 Design Data and SD-07 Certificates
1.6.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's
Field Reports
1.6.6 Number of Copies of SD-10 Operation and Maintenance Data
1.6.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11
Closeout Submittals
1.7 INFORMATION ONLY SUBMITTALS
1.8 VARIATIONS
1.8.1 Considering Variations
1.8.2 Proposing Variations
1.8.3 Warranting That Variations Are Compatible
1.8.4 Review Schedule Is Modified
1.9 SUBMITTAL REGISTER
1.9.1 Use of Submittal Register
1.9.2 Contractor Use of Submittal Register
1.9.3 Approving Authority Use of Submittal Register
1.9.4 Copies Delivered to the Government
1.10 SCHEDULING
1.11 GOVERNMENT APPROVING AUTHORITY
1.11.1 Review Notations
1.12 DISAPPROVED SUBMITTALS
1.13 APPROVED SUBMITTALS
1.14 APPROVED SAMPLES
1.15 WITHHOLDING OF PAYMENT
1.16 STAMPS
PART 2 PRODUCTS
SECTION 01 33 00 Page 1
PART 3 EXECUTION
SECTION 01 33 00 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Contractor's Quality Control (CQC) System Manager to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to start of construction (work) or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates of insurance
Surety bonds
List of proposed Subcontractors
SECTION 01 33 00 Page 3
List of proposed products
Construction Progress Schedule
Network Analysis Schedule (NAS)
Submittal register
Schedule of prices
Accident Prevention Plan
Work plan
Quality Control(QC) plan
Environmental protection plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Include assemblies or portions of assemblies that are to be incorporated into the project and those that will be removed at conclusion of the work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a
SECTION 01 33 00 Page 4 material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within two years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements shall be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further qualify the orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and (SDS) concerning impedances, hazards and safety precautions.
SD-09 Manufacturer's Field Reports
Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and must state the test results; and indicate whether the material, product, or system has passed or failed the test.
Factory test reports.
SD-10 Operation and Maintenance Data
Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
SECTION 01 33 00 Page 5
This data is intended to be incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2.2 Approving Authority
Office or designated person authorized to approve submittal.
1.2.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G, RO
1.4 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.4.1 Government Approved (G)
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.
Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction," they are considered to be "shop drawings."
1.4.1.1 Approval Codes
a. Construction Division "RO"…