View the file

Other files

File Type Posted
Amendment_0002.pdf PDF
Amendment_0001_-_Drawings.pdf PDF
Amendment_0001.pdf PDF
Plans_-_1996-ELEV-REPLACEMENT.pdf PDF
Plans.pdf PDF
Specifications.pdf PDF
Plans_-_1966-ELEVATOR-MODS.pdf PDF
W912WJ18B0009.pdf PDF
Plans_-_ALIMAK_ELEV_AS-BUILTS.pdf PDF
Plans_-_Span_Lock.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ABSTRACT OF OFFERS - CONSTRUCTION 1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES

8/23/2018 9/24/2018 1 2

4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation. SIGNATURE DATE SIGNED

9. OFFERS

5. PROJECT TITLE (IFB) 8. GOVERNMENT ESTIMATE NO. 1 NO. 2

(Check A, B, C and complete D, E, and F) A. OFFEROR A. OFFEROR

A. HIRED LABOR

B. REASONABLE CONTRACT B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT)

X (Without Profit)

6. NUMBER OF AMENDMENTS ISSUED C. REASONABLE CONTRACT C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED

(Including Profit)

7A. ITEM

NUMBER 7B. DESCRIPTION OF OFFERED ITEM

7C. EST.

QUANTITY D. UNIT E. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE E. ESTIMATED AMOUNT D. UNIT PRICE E. ESTIMATED AMOUNT

0001 Provide new elevator, north side 1 Job $533,160.00 $533,160.00 $210,000.00 $210,000.00 $285,700.00 $285,700.00

Deliver and Install New Elevator and Furnish and Install New Rack and Associated items, including replacement of FRP Panels, North Side 1 Job $1,334,960.00 $1,334,960.00 $730,000.00 $730,000.00 $115,000.00 $115,000.00

0003 Provide new elevator, south side 1 Job $382,870.00 $382,870.00 $21,000.00 $210,000.00 $278,450.00 $278,450.00

Deliver and Install New Elevator and Furnish and Install New Rack and Associated items, including replacement of FRP Panels, south side 1 Job $976,170.00 $976,170.00 $730,000.00 $730,000.00 $112,000.00 $112,000.00

*Offeror's Bid schedule did not conform to soliciation bid schedule $72,000.00

ESTIMATED TOTAL AMOUNT 3,227,160.00 $1,880,000.00 $863,150.00

W912WJ18B0009

Replace Elevator Vertical Lift Railroad Bridge, Cape Cod Canal, MA Alimak Hek

Erin E. Bradley

Bid Opening OfficerUS ARMY ENGINEER DISTRICT, NEW ENGLAND

696 VIRGINIA ROAD

CONCORD, MA 01742

2 2

Failed to Provide Bond Failed to Provide Bond

Century Elevators, Inc.

25 Sept 2018

*Mistake in Bid *Mistake in Bid

1. SOLICITATION NUMBER PAGE OF PAGES

2 2 ABSTRACT OF OFFERS - CONSTRUCTION INSTRUCTIONS - Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on

CONTINUATION SHEET a construction project. Each Continuation Sheet will accommodate 14 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 14 and attach additional

Continuation Sheets (OF 1419A) as needed.

2. PROJECT TITLE

NO. 3 NO: 4 NO: 5 NO: 6

A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR

B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT)

3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED

A. B. C.

ITEM ESTIMATED UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED

NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT

0001 1 Job $1,421,601.00 $1,421,601.00 $470,000.00 $470,000.00

0002 1 Job $1,526,171.00 $1,526,171.00 $945,540.00 $945,540.00

0003 1 Job $1,421,601.00 $1,421,601.00 $465,000.00 $465,000.00

0004 1 Job $1,526,171.00 $1,526,171.00 $745,540.00 $945,540.00

ESTIMATED TOTAL AMOUNT $5,895,544.00 $2,826,080.00

*mistake in bid

Replace Elevator Vertical Lift Railroad Bridge, Cape Cod Canal, MA

Bid Bond 20%

R. Zoppo Corp.

W912WJ18B0009

Bid Bond 20% Bid Bond 20% Bid Bond 20%

Delaware Elevator, Inc