Spec_01_22_00_A0002.pdf
PDF 1 MB Posted
- Solicitation number
- W912WJ-16-B-0011
About this file
Revised Spec
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BidAbstract.pdf | ||
| Bid_Snapsheet.pdf | ||
| W912WJ-16-B-0011_-_Amendment_0003.pdf | ||
| Plans_PLY-507_C-303_A0002.pdf | ||
| Amendment_W912WJ-16-B-0011-0002.pdf | ||
| Spec_35_31_19_A0002.pdf | ||
| Spec_01_50_00_A0002.pdf | ||
| SPECS_Revised_August.pdf | ||
| PLANS.pdf | ||
| Amendment_W912WJ-16-B-0011-0001.pdf | ||
| PLANS.pdf | ||
| SPECS.pdf | ||
| Solicitation_W912WJ-16-B-0011.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPAIRS TO STONE DIKE, PLYMOUTH LONG BEACH,
PLYMOUTH, MASSACHUSETTS
AMENDMENT 0002
AUGUST 2016
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 JOB PAYMENT ITEMS
1.2 BIDDING SCHEDULE - PAYMENT ITEMS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 22 00 Page 1
AMENDMENT 0002
AUGUST 2016
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.2 BIDDING SCHEDULE - PAYMENT ITEMS
Payment items for the work of this contract on which the contract progress payments will be based are listed in the BIDDING SCHEDULE and are described below. All costs for items of work that are not specifically mentioned to be included in a particular Bidding Schedule job payment item, shall be included in the listed job item most closely associated with the work involved.
BASE BID ITEMS
a. Item No. 0001, "Mobilization and Demobilization."
Payment will be made for costs associated with mobilization and demobilization for construction operations, as defined in Special Contract Requirements clause "PAYMENT FOR MOBILIZATION AND
DEMOBILIZATION".
Unit of measure: Job.
b. Item No. 0002, "Major Repair Work."
This work will be paid for at the contract job sum for the removal, handling, and rehandling of existing armor stone, and the rebuilding of the existing stone dike at five (5) separate major repair areas as shown on the contract drawings, and as specified in Section 35 31 19 STONE DIKE REPAIRS and other appropriate sections of the specifications. The price shall include all plant, supervision, labor, new armor stones, materials, quality control, safety, and equipment incidental to the completion of this item.
(AMENDMENT 0002) No additional payment will be made for the rehandling of new or existing stone required to repair the stone dike in accordance with the contract documents. This inlcudes necessary rehandling to interlock stones between repair and non-repair areas, and transition areas. All costs associated with the rehandling of new or existing stone for major repairs shall be included under this item.
Unit of measure: Job.
SECTION 01 22 00 Page 2
AMENDMENT 0002
AUGUST 2016
c. Item No. 0003, "Minor Repair Work."
(AMENDMENT 0002) This work will be paid for at the contract job sum to complete minor repairs to the existing stone dike at five (5) separate locations. The repair work shall be as specified under the "Minor Repair Area Notes" shown on contract drawing Sheet C-303. The price shall include all plant, supervision, labor, new armor stones, materials, quality control, safety, and equipment incidental to the completion of this item.
(AMENDMENT 0002) No additional payment will be made for the rehandling of new or existing stone required to repair the stone dike in accordance with the contract documents. This inlcudes necessary rehandling to interlock stones between repair and non-repair areas, and transition areas. All costs associated with the rehandling of new or existing stone for minor repairs shall be included under this item.
Unit of measure: Job.
OPTIONAL BID ITEM
d. Item Number 0004, "Additional Minor Repair Work #1."
(AMENDMENT 0002) This work will be paid for at the contract job sum to complete minor repairs to the existing stone dike at five (5) separate locations. The repair work shall be as specified under the "Minor Repair Area Notes" shown on contract drawing Sheet C-303. The price shall include all plant, supervision, labor, new armor stones, materials, quality control, safety, and equipment incidental to the completion of this item. Refer to Bid Notes under Section 00 41 00, Bidding Schedule.
(AMENDMENT 0002) No additional payment will be made for the rehandling of new or existing stone required to repair the stone dike in accordance with the contract documents. This inlcudes necessary rehandling to interlock stones between repair and non-repair areas, and transition areas. All costs associated with the rehandling of new or existing stone for minor repairs shall be included under this item.
Unit of Measure: Job.
e. Item Number 0005, "Additional Minor Repair Work #2."
(AMENDMENT 0002) This work will be paid for at the contract job sum to complete minor repairs to the existing stone dike at five (5) separate locations. The repair work shall be as specified under the "Minor Repair Area Notes" shown on contract drawing Sheet C-303. The price shall include all plant, supervision, labor, new armor stones, materials, quality control, safety, and equipment incidental to the completion of this item. Refer to Bid Notes under Section 00 41 00, Bidding Schedule.
(AMENDMENT 0002) No additional payment will be made for the rehandling of new or existing stone required to repair the stone dike in accordance with the contract documents. This inlcudes necessary rehandling to interlock stones between repair and non-repair areas, and transition areas. All costs associated with the rehandling of new or existing stone for minor repairs shall be included under this item.
SECTION 01 22 00 Page 3
AMENDMENT 0002
AUGUST 2016
Unit of Measure: Job.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 22 00 Page 4