About this file
Salient Characteristics
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| CST_Salient_Characteristics_TEMP_BLDG_(rev_21_Aug_17).pdf | ||
| Temp_Facility_Specs.pptx | PPTX presentation | |
| Salient_Characteristics-_Revised.docx | DOCX document | |
| Cost_Proposal_Template.xls | XLS spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Template last updated 02/27/2015
Salient Characteristics
CST TEMPORARY FABRIC COVERED STRUCTURE WITH POWER/DATA SUPPLY AT
DC ARMORY FOR CFMO
Availability for manufacturing, shipping, handling, and installing a fabric covered structure, so as to provide a complete turnkey product ready for use and fully functional with the following characteristics, but not limited to:
Finish interior dimensions need to be 42’ length, 40’ width, and 20’ height.
(see layout)
18 oz. cover, white, flame retardant PVC vinyl fabric with polyester scrim in accordance with UFC 3-600-01.
Flame retardant fabric -NFP 701 and UVA treated in accordance with UFC 3- 600-01.
Frame members with 18” bi-beam galvanized tubular steel truss design at 8’ truss spacing in accordance with UFC 3-301-01.
All connections via plate to plate junction with A-325 structural bolts in accordance with UFC 3-301-01 and Industry Standards.
Fabric 100% waterproofing in accordance with Industry standards for fabric covered structures.
Anchor supports to secure the temp structure to the asphalt surface, to accommodate snow, wind, ponding and drift loads, but not limited to) in accordance with UFC 3-301-01 and Industry Standards
Two (2) Main access end panels need to be 34’ wide x14’ high fabric access panels- to be located over at each side over the 40’ width. (see layout)
Two (2) (3’x7’) man doors –aluminum man door with frame- located at each side over the 42’ length with hardware and anchors.
LED light kit including six (6) 12,000 Lumen LED lights, with a Reloc connectors light system, LED high bay fixtures, switches, and a 100 amp panel box in accordance with UFC 3-520-01
Ventilation kit including a 24” exhaust fan with frame and a 24” louvered vents with frame in accordance with UFC 3-410-01.
HVAC 10 ton AC system with 24kW strip heater including all wiring, hardware, and duct work in accordance with UFC 3-410-01.
Heater kit including four (4) 30kW fan forced heaters suspended form ceiling in accordance with UFC 3-410-01.
Availability for running required underground data and power to supply the temporary structure load demands in accordance with UFC 3-580-01 & UFC 3-
Template last updated 02/27/2015
501-01.
Availability for installing eight (8) VAC 14 A electrical outlets; and two (2) 50A twist lock power, 125V/250V, 3 pole, 4 wire, each one with its one breaker; each one with power feed of 120/240V 1PH 50A or 120/208V 3PH 50A; and four wire connection (L1, L2, N, G) (see layout) in accordance with UFC 3-520-01.
Temporary site drainage for the fabric covered structure in accordance with UFC 3-201-01.
Conceptual layout for the proposed temp fabric structure below