Updated CST Salient Characteristics as 21 August 2017

View the file

Other files

File Type Posted
Temp_Facility_Specs.pptx PPTX presentation
Salient_Characteristics-_Revised.docx DOCX document
Salient_Characteristics_TEMP_BLDG_R.pdf PDF
Cost_Proposal_Template.xls XLS spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Salient Characteristics

DC ARMORY CST TEMPORARY FABRIC STRUCTURE WITH POWER/DATA

SUPPLY

August 21, 2017

Commercial Availability Certification:

I have evaluated the commercial marketplace and determined that all of the salient characteristics documented below are available in products/services offered in the commercial marketplace.

Availability for manufacturing, shipping, handling, and installing a fabric covered structure, so as to provide a complete turnkey product ready for use and fully functional with the following characteristics, but not limited to:

• Finish interior dimensions need to be 42’ length, 40’ width, and 20’ height.

(see layout)

• Provide 18 oz. cover white flame retardant PVC vinyl fabric with polyester scrim.

Flame retardant fabric per NFP 70, UVA treated, and 100% waterproof in accordance with UFC 3-600-01.

• Provide frame members with 18” bi-beam galvanized tubular steel truss design at 8’ truss spacing in accordance with UFC 3-301-01.

• Provide all connections via plate to plate junction with A-325 structural bolts in accordance with UFC 3-301-01 and Industry Standards.

• Provide design and installation of foundation in accordance with the United Facilities Criteria (UFC-3-301) and International Building Code (IBC) requirements. The fabric structure shall be anchored to the foundation to resist wind, snow, and other applicable loads.

• Provide two (2) end panels –main acces vehicles doors- roll up manually operated 34’ wide x14’ high fabric access panel, to be located at each side over the 40’ width. (see layout)

• Provide two (2) 3’x7’ aluminum man doors with frames to be located at each side over the 42’ length with hardware and anchors.

• Provide LED light kit to include six (6) 12,000 lumen LED interior lights, with a

Reloc connectors light system, LED high bay fixtures, switches, and a 400A electrical panel to accommodate the circuits required for the power, to be located within the structure in accordance with UFC 3-530-01.

• Provide a ventilation system to include a 24” exhaust fan with frame and two (2)

24” louvered vents with frame in accordance with UFC 3-410-01.

• Provide HVAC system including a 10Ton carrier with 24Kw strip heater system, including all wiring, hardware, and duct work in accordance with UFC 3-410-01.

• Provide heater kit including four (4) fan forced heaters suspended from ceiling in accordance with UFC 3-410-01.

• Provide the fabric structure with the manufacturer recommended insulation in order to contain the required indoor temperature, and to avoid condensation.

• Provide the fabric structure with power through underground conduit drawn from a suitable location at the D. C. Armory. If the existing power supply is not enough to feed the fabric structure, the contractor shall provide the available power plus additional spare conduits in trench for future use.

• Provide the fabric structure with data through underground 2” conduit drawn from the 114W Telecomunication Room. The contractor shall be responsible for the underground waterproof conduit, and 2 ½ “ core drill perforation through the building exterior wall.

• The underground trench for the underground conduits shall be 3ft deep.

• Provide two (2) 50A twist lock power, 125V/250V, 3 pole, 4 wire, each one with its one breaker; each one with power feed of 120/240V 1PH 50A or 120/208V 3PH 50A; and four wire connection (L1, L2, N, G) (see layout) in accordance with

UFC 3-520-01.

• Provide upon acceptable completion, one year warranty/guarantee on all workmanship and materials.

Conceptual Layout for the Fabric Structure

DC ARMORY CST TEMPORARY FABRIC STRUCTURE WITH POWER/DATA SUPPLY
Finish interior dimensions need to be 42’ length, 40’ width, and 20’ height. (see layout)