This document is a Collateral Equipment (CEQ) Summary List prepared by Naval Facilities Engineering Command for Project NA311 Transportation/Admin Building at U.S. Naval Air Facility Atsugi, Japan, dated April 28, 2026.
The procurement consists of two packages of furnishings, fixtures, and equipment (FF&E) required to outfit the transportation and administrative building. Base CLIN Package 1 includes approximately 59 line items totaling 267 individual pieces of equipment, such as workstations and desks (21 units), various chairs (84 units), file cabinets (24 units), tables, storage units, blinds, and operational equipment including welding booths, microwave ovens, washers, dryers, refrigerators, and television sets. Numerous items are marked "Source locally for correct power" due to the overseas location in Japan. The Option CLIN Package 2 contains 12 additional line items with 96 pieces, including specialized equipment such as welding machines (arc and argon), tire changers, plasma cutting machines, hydraulic press, sheet metal cutter, spot air-conditioners, and diagnostic equipment like noise meters and opacimeters. Both packages include line items for CONUS/OCONUS shipping and freight, installation, and project administration with three site visits. The Option CLIN may be exercised within 90 calendar days from award without extending the period of performance. All unit costs and total costs are shown as "$ -" indicating this is a planning document with costs to be determined during solicitation and pricing phase.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought Market Survey FFE Japan 10 Nov 26.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAVAL FACILITIES ENGINEERING COMMAND
COLLATERAL EQUIPMENT (CEQ) SUMMARY LIST
BASE: U.S. Naval Air Facility Atsugi, Japan PROJECT: NA311 TRANSPORTATION / ADMIN BUILDING DATE: 28-Apr-26
CODE QTY ITEM CATEGORY &
DESCRIPTION
CAT
CODE
UNIT COST TOTAL COST REMARKS
3 1 bandsaw, rotary A1 $ - $ - Source locally for correct power
8A 1 blind (24X60) A-139 $ - $ -
8B 3 blind (52X60) A-139 $ - $ -
8C 10 blind (70X60) A-139 $ - $ -
21 11 chair, customer guest A $ - $ -
22A 32 chair, unit (task) A-132 $ - $ -
22B 24 chair, unit (break) A-132 $ - $ - 22C 28 chair, unit (side) A-132 $ - $ -
23 2 coffee maker A1 $ - $ - Source locally for correct power
30A 15 desk, workstation (60X24) A-131 $ - $ -
30B 2 desk, workstation (72X24) A-131 $ - $ -
30C 1 desk, workstation (48X24) A-131 $ - $ -
30D 3 desk, workstation (54X24) A-131 $ - $ -
32 2 bench drilling machine A1 $ - $ - Source locally for correct power
33 1 dryer, front load A1 $ - $ - Source locally for correct power
37 3 entrance mat A $ - $ -
41 22 file cabinet (vertical) A-126 $ - $ -
45 1 fixed type hot water- steam cleaner B1 $ - $ - Source locally for correct power
46 1 fixed type - ice maker B1 $ - $ - Source locally for correct power
47 3 metal storage A $ - $ -
48 6 folding table A-127 $ - $ -
50 2 grinder (bench) A1 $ - $ - Source locally for correct power
51 5 hazmat locker A $ - $ -
55 8 light, work, portable A $ - $ -
64A 4 table (corner) A $ - $ -
64B 1 table (center) A $ - $ - 67 6 paper towel dispenser B-204 $ - $ - Do not include labor to install. GOJ will install.
72A 2 refrigerator (narrow) A1 $ - $ - Source locally for correct power
72B 1 refrigerator (wide) A1 $ - $ - Source locally for correct power
74 2 file cabinet (sliding) A $ - $ - 80 3 shower curtain A $ - $ -
95A 1 television set (32") A1 $ - $ - Source locally for correct power
95B 2 television set (55") A1 $ - $ - Source locally for correct power
98 26 trash can A $ - $ -
100 2 umbrella stand A $ - $ -
104 2 washer, front load A1 $ - $ - Source locally for correct power
105 1 welding booth A-182 $ - $ -
126 1 oil pump (waste oil) A $ - $ -
127 2 microwave oven A1 $ - $ - Source locally for correct power
Base CLIN - PACKAGE 1 PRODUCT TOTAL -$
Base CLIN - PACKAGE 1 TOTAL -$
6 5 battery charger A1 $ - $ - Source locally for correct power
9 12 book shelf A $ - $ -
20 23 microwave oven, household A1 $ - $ - Source locally for correct power
Base CLIN - FFE Package 1
Option CLIN - FFE Package 2
CONUS/ OCONUS Shipping/Freight
Installation
Project Administration (including three visits)
NAVAL FACILITIES ENGINEERING COMMAND
COLLATERAL EQUIPMENT (CEQ) SUMMARY LIST
BASE: U.S. Naval Air Facility Atsugi, Japan PROJECT: NA311 TRANSPORTATION / ADMIN BUILDING DATE: 28-Apr-26
CODE QTY ITEM CATEGORY &
DESCRIPTION
CAT
CODE
UNIT COST TOTAL COST REMARKS
25 2 conference table A $ - $ -
60 5 circulating fan A1 $ - $ - Source locally for correct power
62 3 oil drain A $ - $ -
68 1 plasma cutting machine A $ - $ - Source locally for correct power
69 1 press, hydraulic, 60-ton A $ - $ - Source locally for correct power
77 1 sheet metal cutter A1 $ - $ -
81 1 shredder A1 $ - $ - Source locally for correct power
85 1 parts cleaner A1 $ - $ - Source locally for correct power
88 10 spot air-conditioner A1 $ - $ - Source locally for correct power
89 1 spot welding machine A1 $ - $ - Source locally for correct power
96 1 tire changer (small) B1 $ - $ - Source locally for correct power
97 1 tire changer (large) B1 $ - $ - Source locally for correct power
102 17 vise A $ - $ -
106 2 welding machine A1 $ - $ - Source locally for correct power
107 1 welding machine (arc welding) A1 $ - $ - Source locally for correct power
108 1 welding machine (argon) A1 $ - $ - Source locally for correct power
110 1 wheel balancer A1 $ - $ - Source locally for correct power
123 1 co / ch detector A1 $ - $ - Source locally for correct power
124 1 opacimeter A $ - $ - 125 1 noise meter A $ - $ -
128 4 tank (new oil) A $ - $ -
129 2 drain cabinet (waste oil & llc) A $ - $ -
Option CLIN - PACKAGE 2 PRODUCT TOTAL -$
Option CLIN - PACKAGE 2 TOTAL -$
*NOTE: The Option CLIN (FF&E Package 2) may be exercised within ninety (90) calendar days from the date of award.
Exercising this option does not extend the period of performance.
OVERALL GRAND TOTAL (BOTH PACKAGES)
CONUS/ OCONUS Shipping/Freight
Installation
Project Administration (including three visits)