Letcher County FEIS Appendix J - Air Emission Calculations (2017).pdf

PDF 162 KB Posted

Attached to
AE Services for Federal Bureau of Prisons Federal Correctional Institution (FCI) and minimum-security Federal Prison Camp (FPC)
Solicitation number
W912QR-25-FBP-FCIFPC
Issued by

About this file

This document is an Appendix J Air Emission Calculations (2017) report for a proposed federal correctional facility project, detailing comprehensive air emission estimates for two alternative site locations: Payne Gap/Larson and Roxana. The calculations break down emissions across multiple construction phases and operational activities, including clearing, site preparation, gravel work, concrete work, building construction, paving, and fugitive dust emissions.

The emissions calculations cover key pollutants including VOC, CO, NOx, SO2, PM10, PM2.5, and CO2, with detailed metrics for both construction and operational stages. For Alternative 1 (Payne Gap/Larson), the total annual emissions range from 7.81 tons of VOC to 217.60 tons of PM10 in the first year, with 11,232 metric tons of CO2. The Modified Alternative 2 (Roxana) shows similar patterns, with annual emissions of 3.48 tons of VOC to 158.82 tons of PM10, and 4,644 metric tons of CO2. The document also includes calculations for emergency generators, boilers, wastewater treatment plant operations, and staff commuting emissions, providing a comprehensive environmental impact assessment for the proposed facility.

View the file

Other files

File Type Posted
Letcher County FEIS Appendix H (Part 1.1) - USFWS Endangered Species Act Consultation (2017).pdf PDF
Letcher County FEIS Appendix H (Part 3) - USFWS Endangered Species Act Consultation (2017).pdf PDF
Letcher County FEIS Appendix H (Part 1.3) - USFWS Endangered Species Act Consultation (2017).pdf PDF
Letcher County FEIS Appendix H (Part 2) - USFWS Endangered Species Act Consultation (2017).pdf PDF
Letcher County FEIS Appendix H (Part 1.2) - USFWS Endangered Species Act Consultation (2017).pdf PDF
Letcher County FEIS Appendix B - Agency Consultation and Coordination.pdf PDF
Letcher County FEIS Appendix E - Phase I Environmental Site Assessment.pdf PDF
Letcher County FEIS Appendix F - Additional Geotechnical Study Roxanna Site (2016).pdf PDF
Letcher County FEIS Appendix I - Traffic Impact Study (2015).pdf PDF
Letcher County FEIS Appendix G - Results of Investigation of Materials to be Excavated (2016).pdf PDF
Letcher County FEIS Appendix D - Wetland Delineation Report.pdf PDF
Letcher County FEIS Appendix C - Cultural Resources Survey Reports.pdf PDF
Letcher County FEIS Appendix A - Public Scoping.pdf PDF
Copy of Industry Day Registration Spreadsheet - BOP Prison Project For Meeting.xlsx XLSX spreadsheet
Letcher County FEIS_July52024.pdf PDF
Copy of Industry Day Registration Spreadsheet - BOP Prison Project For Meeting.xlsx XLSX spreadsheet
FBOP SATOC Industry Day - Draft 20 May 2025.pptx PPTX presentation
FEIS Public Notice of Availability 071024.pdf PDF
Federal Bureau of Prisons Louisville Industry Day - Registration Form.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX J

AIR EMISSION CALCULATIONS (2017)

TAB A. SUMMARY

Alternative 1 Payne Gap/Larson Site

VOC CO NOx SO2 PM10 PM2.5 CO2

Activity Year Tons Tons Tons Tons Tons Tons Metric Tons

Construction 1 7.81 32.40 108.78 1.90 217.60 27.06 11,232

Construction 2 7.81 32.40 108.78 1.90 147.10 20.01 11,232

Operations Yearly 0.70 29.33 21.36 0.18 1.16 0.58 1,288

Modified Alternative 2 Roxana Site

VOC CO NOx SO2 PM10 PM2.5 CO2

Activity Year Tons Tons Tons Tons Tons Tons Metric Tons

Construction 1 3.48 14.06 43.62 0.95 158.82 18.16 4,644

Construction 2 3.48 14.06 43.62 0.95 158.82 18.16 4,644

Construction 3 3.48 14.06 43.62 0.95 158.82 18.16 4,644

Operations Yearly 0.70 29.33 21.36 0.18 1.16 0.58 1,288

TAB B. CONSTRUCTION EMISSIONS

Alternative 1 Payne Gap/Larson

Table 1.1 Clearing

218 acres

VOC CO NOx SO2 PM10 PM2.5 CO2 g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr

Dozer 2,529 145 0.58 0.38 1.41 4.17 0.12 0.30 0.29 536

Loader/Backhoe 2,529 87 0.21 1.43 7.35 6.35 0.15 1.06 1.03 692

Small Backhoe 2,529 55 0.21 1.43 7.35 6.35 0.15 1.06 1.03 692

VOC CO NOx SO2 PM10 PM2.5 CO2 lb lb lb lb lb lb lb

Dozer 176.60 663.13 1,956.81 54.03 138.78 134.61 251,166

Loader w/ integral Backhoe 145.84 748.63 646.67 15.15 108.29 105.04 70,450

Small backhoe 92.20 473.27 408.81 9.58 68.46 66.41 44,538

VOC CO NOx SO2 PM10 PM2.5 CO2 lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile Dump Truck 1,158 230 16 0.0015 0.0080 0.0361 0.0000 0.0015 0.0015 3.4385

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Dump Truck 28.56 150.98 677.18 0.34 28.24 27.37 64,555

Subtotal in lbs 443 2036 3689 79 344 333 430709

Clearing Grand Total in Tons 0.22 1.02 1.84 0.04 0.17 0.17

Clearing Grand Total in Metric Tons 195.4

Table 1.2 Site Prep

Site Prep Excavate/Fill (CY) 25,760,829 CY

Grading (SY) 1,055,120 SY Assume compact 0.5 feet (0.166 yards) = 175,150 CY

VOC CO NOx SO2 PM10 PM2.5 CO2 g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr

Excavator 85,869 243 0.59 0.34 1.21 4.03 0.12 0.22 0.22 536

Skid Steer Loader 103,043 160 0.23 0.38 1.47 4.34 0.12 0.31 0.30 536

Dozer (Rubber Tired) 93,336 145 0.59 0.38 1.41 4.17 0.12 0.30 0.29 536

Compactor 1,297 103 0.58 0.40 1.57 4.57 0.12 0.32 0.31 536

Grader 375 285 0.58 0.34 1.21 4.07 0.12 0.23 0.22 536

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Excavator 9,334.40 32,820.31 109,366.82 3,128.13 6,047.26 5,865.84 14,542,105

Skid Steer Loader 3,203.99 12,288.30 36,268.76 963.29 2,553.02 2,476.43 4,478,179

Dozer (Rubber Tired) 6,630.48 24,897.59 73,469.64 2,028.50 5,210.52 5,054.20 9,430,197

Compactor 67.51 268.33 780.18 19.69 54.53 52.89 91,526

Grader 46.94 164.93 555.75 15.74 30.80 29.87 73,160

VOC CO NOx SO2 PM10 PM2.5 CO2

MPH lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile

Dump Truck (14 CY) 85,869 5 230 0.0015 0.0080 0.0361 0.0000 0.0015 0.0015 3.4385

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Dump Truck (12 CY) 4,990.66 26,381.47 118,326.87 59.19 4,935.37 4,782.13 11,280,045

Subtotal in lb: 24,274 96,821 338,768 6,215 18,832 18,261 39,895,212

Site Prep Grand Total in Tons 12.14 48.41 169.38 3.11 9.42 9.13

Site Prep Grand Total in Metric Tons 18,096

Table 1.3 Gravel Work 12,257 CY

VOC CO NOx SO2 PM10 PM2.5 CO2 g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr

Dozer 125 185 0.59 0.34 1.21 4.08 0.12 0.23 0.22 536

Wheel Loader for Spreading 157 87 0.59 0.35 1.25 4.23 0.12 0.24 0.23 536

Compactor 346 103 0.43 0.36 1.34 4.45 0.12 0.26 0.25 536

VOC CO NOx SO2 PM10 PM2.5 CO2 lb lb lb lb lb lb lb

Dozer 7.42 26.07 88.11 2.49 4.88 4.74 11,570

Wheel Loader for Spreading 4.43 15.85 53.74 1.46 3.03 2.94 6,801

Compactor 8.69 32.35 107.58 2.78 6.21 6.03 12,947

Offroad Equipment Hours Engine HP Load Factor

Onroad Equipment Miles Engine HP

Offroad Equipment Hours Engine HP Load Factor

Offroad Equipment

Hours of

Operation Engine HP Load Factor

Onroad Equipment

Hours of

Operation Engine HP Speed (mph)

VOC CO NOx SO2 PM10 PM2.5 CO2 lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile

Dump Truck 44,754 230 0.0015 0.0080 0.0361 0.0000 0.0015 0.0015 3.4385

VOC CO NOx SO2 PM10 PM2.5 CO2 lb lb lb lb lb lb lb

Dump Truck 68.09 359.91 1614.28 0.81 67.33 65.24 153,888

Subtotal (lbs): 89 434 1,864 8 81 79 185,207

Gravel Work Grand Total in Tons 0.04 0.22 0.93 0.00 0.04 0.04

Gravel Work Grand Total in Metric Tons 84

Table 1.4 Concrete Work

Foundation Work 6,532 CY

Sidewalks, etc. 435 CY

Total 6,967 CY Note: Assume all excavated soil is accounted for in Excavate/Fill and Trenching

VOC CO NOx SO2 PM10 PM2.5 CO2 g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr

Concrete Mixer 382 3.5 0.43 0.69 3.04 6.17 0.13 0.54 0.52 588 Concrete Truck 346 300 0.43 0.38 1.75 6.18 0.11 0.27 0.26 530

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Concrete Mixer 0.87 3.86 7.83 0.16 0.69 0.66 746

Concrete Truck 37.31 171.62 607.77 11.21 26.41 25.62 52,092

Subtotal (lbs): 38 175 616 11 27 26 52,838

Concrete Work Grand Total in Tons 0.02 0.09 0.31 0.01 0.01 0.01

Concrete Work Grand Total in Metric Tons 24

Table 1.5 Building Construction

352,726 SF Foundation

795,151 SF Total

VOC CO NOx SO2 PM10 PM2.5 CO2 g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr

Crane 4,050 330 0.58 0.25 1.22 5.26 0.11 0.21 0.20 530

Concrete Truck 4,050 300 0.43 0.19 1.45 4.32 0.12 0.21 0.20 536

Diesel Generator 3,240 40 0.43 0.26 1.41 3.51 0.11 0.23 0.22 536

Telehandler 8,100 99 0.59 0.51 3.94 4.93 0.13 0.52 0.51 595

Scissors Lift 6,480 83 0.59 0.51 3.94 4.93 0.13 0.52 0.51 595

Skid Steer Loader 4,050 67 0.59 1.69 7.97 6.70 0.15 1.19 1.15 691

Pile Driver 18,951 260 0.43 0.46 1.55 5.90 0.11 0.31 0.30 530 All Terrain Forklift 162 84 0.59 0.51 3.94 4.93 0.13 0.52 0.51 595

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Crane 419.87 2083.97 8988.25 194.94 354.97 344.32 906,208

Concrete Truck 216.07 1675.27 4976.34 132.86 241.94 234.69 617,636

Diesel Generator 32.25 173.08 430.99 13.26 28.49 27.63 65,873

Telehandler 531.45 4109.13 5140.90 133.40 543.53 527.22 620,179

Scissors Lift 356.45 2756.02 3448.04 89.47 364.55 353.61 415,959

Skid Steer Loader 597.30 2812.06 2363.91 52.44 419.69 407.10 243,832

Pile Driver 2167.58 7248.75 27568.82 532.17 1466.10 1422.12 2,474,001

All Terrain Forklift 9.02 69.73 87.24 2.26 9.22 8.95 10,524

VOC CO NOx SO2 PM PM2.5 CO2 lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile

Delivery Truck 19,439 265 45 0.0015 0.0080 0.0361 0.0000 0.0015 0.0015 3.4385

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Delivery Truck 1330.77 7034.69 31552.17 15.78 1316.03 1275.17 3,007,854

Subtotal (lbs): 5,661 27,963 84,557 1,167 4,745 4,601 8,362,065

Building Construction Grand Total in Tons 2.83 13.98 42.28 0.58 2.37 2.30

Building Construction Grand Total in Metric Tons 3,793

Annual Emissions

Onroad Equipment

Hours of

Operation Engine HP Speed (mph)

Offroad Equipment

Hours of

Operation Engine HP Load Factor

Emission Factors

Annual Emissions

Onroad Equipment Miles Engine HP

Offroad Equipment

Hours of

Operation Engine HP Load Factor

Emission Factors

Table 1.6 Paving

Pavement Surface Area 234,173 SF 5,725 CY

Paving HMA 155,959 CF

VOC CO NOx SO2 PM PM2.5 CO2 g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr

Grader 717 145 0.59 0.38 1.41 4.16 0.12 0.30 0.29 536

Roller 1,076 401 0.59 0.34 2.46 5.53 0.12 0.34 0.33 536

Paving Machine 1,434 164 0.59 0.38 1.44 4.25 0.12 0.30 0.29 536 Asphalt Curbing Machine 143 130 0.59 0.40 1.57 4.57 0.12 0.32 0.31 536

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Grader 50.91 191.01 562.86 15.59 40.00 38.80 72,458

Roller 191.53 1,381.86 3,105.60 64.67 190.04 184.34 300,633

Paving Machine 116.27 441.36 1,301.01 35.26 91.79 89.04 163,901

Asphalt Curbing Machine 9.58 38.09 110.74 2.79 7.74 7.51 12,991

VOC CO NOx SO2 PM PM2.5 CO2 lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile

Dump Truck 1,142 230 0 0.001521 0.008042 0.036070 1.80E05 0.001504 0.001458 3.438541 Water Truck 23 230 10 0.001521 0.008042 0.036070 1.80E05 0.001504 0.001458 3.438541

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Dump Truck 21.99 116.26 521.44 0.26 21.75 21.07 49,709

Water Truck 0.35 1.85 8.28 0.00 0.35 0.33 789

Weight of

HMA (tons) VOC VOC CO NOx SO2 PM10 PM2.5 CO2 lb/ton lb lb lb lb lb lb lb Standard Hot Mix Asphalt 155,959 8,489 0.04 339.55

Subtotal (lbs): 730 2,170 5,610 119 352 341 600,480

Paving Grand Total in Tons 0.37 1.09 2.80 0.06 0.18 0.17

Paving Grand Total in Metric Tons 272

Table 1.7 Fugitive Dust Emissions

PM 10 days of PM2.5/

Year tons/acre/ mo acres disturbance PM10 Total PM10 Ratio PM2.5 Total

Year 1 0.42 65.40 154 211.5 0.1 21.2

Year 2 0.42 43.60 154 141.0 0.1 14.1

Table 1.8 Total Emissions

VOC CO NOx SO2 PM10 PM2.5 CO2

Year Tons Tons Tons Tons Tons Tons Metric Tons

Year 1 7.81 32.40 108.78 1.90 217.60 27.06 11,232

Year 2 7.81 32.40 108.78 1.90 147.10 20.01 11,232

Modified Alternative 2 Roxana

Table 2.1 Clearing

181 acres

VOC CO NOx SO2 PM10 PM2.5 CO2 g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr

Dozer 2,100 145 0.58 0.38 1.41 4.17 0.12 0.30 0.29 536

Loader/Backhoe 2,100 87 0.21 1.43 7.35 6.35 0.15 1.06 1.03 692

Small Backhoe 2,100 55 0.21 1.43 7.35 6.35 0.15 1.06 1.03 692

VOC CO NOx SO2 PM10 PM2.5 CO2 lb lb lb lb lb lb lb

Dozer 146.65 550.67 1,624.96 44.87 115.24 111.79 208,572

Loader w/ integral Backhoe 121.10 621.67 537.00 12.58 89.93 87.23 58,503

Small backhoe 76.56 393.01 339.48 7.95 56.85 55.14 36,985

Load Factor

Hot Mix Asphalt (HMA)

Volume of

HMA

(ft3)

Offroad Equipment

Hours of

Operation Engine HP

Offroad Equipment

Hours of

Operation Engine HP Load Factor

Onroad Equipment

Hours of

Operation Engine HP

Productivity based Speed

(miles/hour)

VOC CO NOx SO2 PM10 PM2.5 CO2 lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile Dump Truck 961 230 16 0.0015 0.0080 0.0361 0.0000 0.0015 0.0015 3.4385

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Dump Truck 23.71 125.32 562.11 0.28 23.45 22.72 53,585

Subtotal in lbs 368 1691 3064 66 285 277 357,645

Clearing Grand Total in Tons 0.18 0.85 1.53 0.03 0.14 0.14

Clearing Grand Total in Metric Tons 162.2

Table 2.2 Site Prep

Site Prep Excavate/Fill (CY) 18,084,992 CY

Grading (SY) 876,040 SY Assume compact 0.5 feet (0.166 yards) = 145,423 CY

VOC CO NOx SO2 PM10 PM2.5 CO2 g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr

Excavator 60,283 243 0.59 0.34 1.21 4.03 0.12 0.22 0.22 536

Skid Steer Loader 72,340 160 0.23 0.38 1.47 4.34 0.12 0.31 0.30 536

Dozer (Rubber Tired) 65,525 145 0.59 0.38 1.41 4.17 0.12 0.30 0.29 536

Compactor 673 103 0.58 0.40 1.57 4.57 0.12 0.32 0.31 536

Grader 311 285 0.58 0.34 1.21 4.07 0.12 0.23 0.22 536

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Excavator 6,552.89 23,040.37 76,777.20 2,195.99 4,245.27 4,117.91 10,208,783

Skid Steer Loader 2,249.26 8,626.62 25,461.37 676.25 1,792.27 1,738.50 3,143,769

Dozer (Rubber Tired) 4,654.70 17,478.49 51,576.83 1,424.04 3,657.86 3,548.13 6,620,145

Compactor 35.02 139.19 404.69 10.21 28.28 27.44 47,476

Grader 38.96 136.90 461.28 13.06 25.56 24.80 60,723

VOC CO NOx SO2 PM10 PM2.5 CO2

MPH lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile

Dump Truck (14 CY) 60,283 5 230 0.0015 0.0080 0.0361 0.0000 0.0015 0.0015 3.4385

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Dump Truck (12 CY) 458.55 2,423.97 10,872.05 5.44 453.47 439.39 1,036,428

Subtotal in lb: 13,989 51,846 165,553 4,325 10,203 9,896 21,117,323

Site Prep Grand Total in Tons 6.99 25.92 82.78 2.16 5.10 4.95

Site Prep Grand Total in Metric Tons 9,579

Table 2.3 Gravel Work 11,535 CY

VOC CO NOx SO2 PM10 PM2.5 CO2 g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr

Dozer 116 185 0.59 0.34 1.21 4.08 0.12 0.23 0.22 536

Wheel Loader for Spreading 148 87 0.59 0.35 1.25 4.23 0.12 0.24 0.23 536

Compactor 326 103 0.43 0.36 1.34 4.45 0.12 0.26 0.25 536

VOC CO NOx SO2 PM10 PM2.5 CO2 lb lb lb lb lb lb lb

Dozer 7.20 25.28 85.43 2.41 4.73 4.59 11,218

Wheel Loader for Spreading 4.29 15.36 52.10 1.42 2.94 2.85 6,594

Compactor 8.43 31.37 104.31 2.70 6.02 5.84 12,553

VOC CO NOx SO2 PM10 PM2.5 CO2 lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile

Dump Truck 59,045 230 0.0015 0.0080 0.0361 0.0000 0.0015 0.0015 3.4385

VOC CO NOx SO2 PM10 PM2.5 CO2 lb lb lb lb lb lb lb

Dump Truck 89.83 474.84 2129.76 1.07 88.83 86.07 203,029

Subtotal (lbs): 110 547 2,372 8 103 99 233,394

Gravel Work Grand Total in Tons 0.05 0.27 1.19 0.00 0.05 0.05

Gravel Work Grand Total in Metric Tons 106

Offroad Equipment Hours Engine HP Load Factor

Onroad Equipment Miles Engine HP

Offroad Equipment Hours Engine HP Load Factor

Onroad Equipment Hours Engine HP

Onroad Equipment

Hours of

Operation Engine HP Speed (mph)

Table 2.4 Concrete Work

Foundation Work 6,532 CY

Sidewalks, etc. 435 CY

Total 6,967 CY Note: Assume all excavated soil is accounted for in Excavate/Fill and Trenching

VOC CO NOx SO2 PM10 PM2.5 CO2 g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr

Concrete Mixer 382 3.5 0.43 0.69 3.04 6.17 0.13 0.54 0.52 588 Concrete Truck 346 300 0.43 0.38 1.75 6.18 0.11 0.27 0.26 530

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Concrete Mixer 0.87 3.86 7.83 0.16 0.69 0.66 746

Concrete Truck 37.31 171.62 607.77 11.21 26.41 25.62 52,092

Subtotal (lbs): 38 175 616 11 27 26 52,838

Concrete Work Grand Total in Tons 0.02 0.09 0.31 0.01 0.01 0.01

Concrete Work Grand Total in Metric Tons 24

Table 2.5 Building Construction

352,726 SF Foundation

795,151 SF Total

VOC CO NOx SO2 PM10 PM2.5 CO2 g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr

Crane 4,050 330 0.58 0.25 1.22 5.26 0.11 0.21 0.20 530

Concrete Truck 4,050 300 0.43 0.19 1.45 4.32 0.12 0.21 0.20 536

Diesel Generator 3,240 40 0.43 0.26 1.41 3.51 0.11 0.23 0.22 536

Telehandler 8,100 99 0.59 0.51 3.94 4.93 0.13 0.52 0.51 595

Scissors Lift 6,480 83 0.59 0.51 3.94 4.93 0.13 0.52 0.51 595

Skid Steer Loader 4,050 67 0.59 1.69 7.97 6.70 0.15 1.19 1.15 691

Pile Driver 18,951 260 0.43 0.46 1.55 5.90 0.11 0.31 0.30 530 All Terrain Forklift 162 84 0.59 0.51 3.94 4.93 0.13 0.52 0.51 595

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Crane 419.87 2083.97 8988.25 194.94 354.97 344.32 906,208

Concrete Truck 216.07 1675.27 4976.34 132.86 241.94 234.69 617,636

Diesel Generator 32.25 173.08 430.99 13.26 28.49 27.63 65,873

Telehandler 531.45 4109.13 5140.90 133.40 543.53 527.22 620,179

Scissors Lift 356.45 2756.02 3448.04 89.47 364.55 353.61 415,959

Skid Steer Loader 597.30 2812.06 2363.91 52.44 419.69 407.10 243,832

Pile Driver 2167.58 7248.75 27568.82 532.17 1466.10 1422.12 2,474,001

All Terrain Forklift 9.02 69.73 87.24 2.26 9.22 8.95 10,524

VOC CO NOx SO2 PM PM2.5 CO2 lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile

Delivery Truck 19,439 265 45 0.0015 0.0080 0.0361 0.0000 0.0015 0.0015 3.4385

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Delivery Truck 1330.77 7034.69 31552.17 15.78 1316.03 1275.17 3,007,854

Subtotal (lbs): 5,661 27,963 84,557 1,167 4,745 4,601 8,362,065

Building Construction Grand Total in Tons 2.83 13.98 42.28 0.58 2.37 2.30

Building Construction Grand Total in Metric Tons 3,793

Annual Emissions

Onroad Equipment

Hours of

Operation Engine HP Speed (mph)

Annual Emissions

Offroad Equipment

Hours of

Operation Engine HP Load Factor

Emission Factors

Offroad Equipment

Hours of

Operation Engine HP Load Factor

Emission Factors

Table 2.6 Paving

Pavement Surface Area 204,645 SF 5,003 CY

Paving HMA 135,066 CF

VOC CO NOx SO2 PM PM2.5 CO2 g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr g/hphr

Grader 627 145 0.59 0.38 1.41 4.16 0.12 0.30 0.29 536

Roller 940 401 0.59 0.34 2.46 5.53 0.12 0.34 0.33 536

Paving Machine 1,253 164 0.59 0.38 1.44 4.25 0.12 0.30 0.29 536 Asphalt Curbing Machine 125 130 0.59 0.40 1.57 4.57 0.12 0.32 0.31 536

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Grader 50.91 191.01 562.86 15.59 40.00 38.80 72,458

Roller 191.53 1,381.86 3,105.60 64.67 190.04 184.34 300,633

Paving Machine 116.27 441.36 1,301.01 35.26 91.79 89.04 163,901

Asphalt Curbing Machine 9.58 38.09 110.74 2.79 7.74 7.51 12,991

VOC CO NOx SO2 PM PM2.5 CO2 lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile lb/mile

Dump Truck 998 230 17 0.001521 0.008042 0.036070 1.80E05 0.001504 0.001458 3.438541 Water Truck 20 230 10 0.001521 0.008042 0.036070 1.80E05 0.001504 0.001458 3.438541

VOC CO NOx SO2 PM PM2.5 CO2 lb lb lb lb lb lb lb

Dump Truck 19.22 101.60 455.69 0.23 19.01 18.42 43,441

Water Truck 0.31 1.61 7.23 0.00 0.30 0.29 690

Weight of

HMA (tons) VOC VOC CO NOx SO2 PM10 PM2.5 CO2 lb/ton lb lb lb lb lb lb lb Standard Hot Mix Asphalt 136,294 7,418 0.04 296.74

Subtotal (lbs): 685 2,156 5,543 119 349 338 594,113

Paving Grand Total in Tons 0.34 1.08 2.77 0.06 0.17 0.17

Paving Grand Total in Metric Tons 269.48

Table 2.7. Fugitive Dust Emissions

PM 10 days of PM2.5/

Year tons/acre/ mo acres disturbance PM10 Total PM10 Ratio PM2.5 Total

Year 1 0.42 48.30 154 156.2 0.1 15.6

Year 2 0.42 48.30 154 156.2 0.1 15.6

Year 3 0.42 48.30 154 156.2 0.1 15.6

Table 2.8 Total Emissions

VOC CO NOx SO2 PM10 PM2.5 CO2

Year Tons Tons Tons Tons Tons Tons Metric Tons

Year 1 3.48 14.06 43.62 0.95 158.82 18.16 4,644

Year 2 3.48 14.06 43.62 0.95 158.82 18.16 4,644

Year 3 3.48 14.06 43.62 0.95 158.82 18.16 4,644

Hot Mix Asphalt (HMA)

Volume of

HMA

(ft 3)

Offroad Equipment

Hours of

Operation Engine HP Load Factor

Onroad Equipment

Hours of

Operation Engine HP

Productivity based Speed

(miles/hour)

TAB C. OPERATIONAL EMISSIONS

Factoryfabricated and assembled watertube flexible tube boilers, dual fired natural gas and fuel oil.

Two diesel Emergency Generators 2 megawatts each or 2682 HP each

Table 1. Operational Emissions Emergency Generators

Assume the IC engines are typically operated 0.5 hours per week for testing and maintenance = 26 hr/yr

Assume additional five 24hour periods for total power outages per year = 120 hr/yr Pollutant Emission Factors

146 Total Hours Diesel Fuel a, b

> 447 kW

VOC CO NOx SO2 PM CO2 lb/hphr kW # lb/yr lb/yr lb/yr lb/yr lb/yr lb/yr CO 0.0055

2000 2 503 4,307 10,181 10 548 908,447 NOx 0.013

Tons/yr 0.25 2.15 5.09 0.00 0.27 454 PM 0.0007 metric tons/yr 412 SO2 c 0.00809 S

S 0.0015

VOC

d

0.000642

CO2 1.16

b Emission factors from U.S. EPA. Compilation of Air Pollutant

Emission Factors Volume I (AP42), Section 3.4, 5th Edition; .

factors based upon power output c The variable S in the emissions factor equals the sulfur content of the fuel expressed as percent weight.

dVOC = TOC methane (9%)

SO2 factor was assumed to equal 0.0015 for diesel fuel.

Generator

Table 2. Operational Parameters Boilers

10200502/03, 10300Distillate oil fired Boilers <100 Million Btu/hr

Example boiler that is < 100 MM Btu:

Pollutant (lb/10 gal) a,b

Heat Input

(MMBtu/hr) a

Fuel Type

Annual

Hours of

Operation

Est. Qty Oil consumed

Annually

(gal) CO 5

15 Oil 5100 759,900 NOx 20

15 Oil 5100 759,900 PM10 1

PM2.5 0.25

Total est. quantity of oil consumed annually 1,519,800 gal SO2 0.213 0.0015 Percent Sulfur content in fuel

VOC 0.34

140,000 btu/gal fuel oil 149 gal/hour fuel consumption @ CO2 22,300

80 % efficiency N2O 0.26

Assume heat 10/15 to 4/14 CH4 0.216

182 heating days a Emission factors from U.S. Environmental Protection Agency. Compilation

183 non heating days of Air Pollutant Emission Factors Volume I (AP42), Section 1.3, 5th Edition.

b Emission factors based on burning fuel oil with a heating value of 140 MMBtu/103 gal

Table 3. Annual Emissions for Boilers

VOC CO NOx SO2 PM10 PM2.5 CO2 N2O CH4

258 3800 15198 162 760 190 3800 198 164

258 3800 15198 162 760 190 3800 198 164

Total in Tons/yr 0.26 3.80 15.20 0.16 0.76 0.19 3.80 0.20 0.16

CO2e = 62 metric tons/yr

Table 4. Wastewater Treatment Plant Operations

Aerobic treatment

Anticipated flow = 300,000 Gallons per day

Assumed BOD 25 mg/l effluent 9.46353E05 kg/gal

GHG EF = 1.6 kg CO2e/kg BOD

Daily GHG emissions 45.42 kg CO2e/day

Annual 16.58 metric tons per year

Assumed BOD from Table 2 of EPA 832F00016, Wastewater Technology Fact Sheet, Package Plants

GHG EF from Contribution of Onsite and Offsite Processes to GHG Emissions by Wastewater Treatment Plants, Yerushalmi, L. et al., 2009

Emission Factor

Boiler 1

Boiler 2

Emission Source

Annual Emissions in lbs

Table 5. Total Annual Emissions for All Equipment

Stationary Source VOC t/yr CO t/yr NOx t/yr SO2 t/yr PM10 t/yr PM2.5 t/yr CO2e MT/yr

Generators 0.25 2.15 5.09 0.00 0.27 0.27 412

Boilers 0.26 3.80 15.20 0.16 0.76 0.19 62

WWTP 17

Total 0.51 5.95 20.29 0.17 1.03 0.46 491

Table 6. Commuting Staff 300 per day

3VOCs 3CO 3NOx 3

SO2

PM10

PM2.5

4,5

CO2

Vehicles # vehicles # days mi/day lb/mi lb/mi lb/mi lb/mi lb/mi lb/mi g/mi passenger vehicles 300 365 40 8.593E05 1.067E02 4.873E04 7.357E06 5.68927E05 5.19227E05 182.00

VOCs CO NOx SO2 PM10 PM2.5 CO2 lb lb lb lb lb lb g

376.36 46755.73 2134.28 32.23 249.19 227.42 797,160,000

Tons per Year 0.19 23.38 1.07 0.02 0.12 0.11

Metric Tons per Year 797

CO2e in metric tons/year 797

Table 7. Total Annual Operating Emissions from Stationary Sources and Commuters

VOC t/yr CO t/yr NOx t/yr SO2 t/yr PM10 t/yr PM2.5 t/yr CO2e MT/yr

Operating Emissions 0.70 29.33 21.36 0.18 1.16 0.58 1,288

TAB D. CONSTRUCTION ASSUMPTIONS

Buildings Common to both Alternatives

Clearing (AC)

Grading

(SY)

Site Prep

Excavate/Fill

(CY)

Building

Construction

Total Size

(sm)

Building

Construction

Total Size (sf)

Foundation footprint (sm)

Foundation footprint

(sf) # Stories Paving (CY)

Gravel

Work (CY)

Concrete

Work sidewalks, etc (CY)

Concrete

Work foundation

(CY)

Central Utility Plant 1,217 13,100 1,217 13,100 1 243 16 243

Firing Range 96 1,033 96 1,033 1 19 1 19

Outside Warehouse 3,279 35,295 3,279 35,295 1 654 44 654

Staff Training Bldg 910 9,795 910 9,795 1 181 12 181

Penitentiary 61,654 663,637 20,551 221,212 3 4,097 273 4,097

Prison Camp 6,063 65,262 6,063 65,262 1 1,209 80 1,209

Garage/Landscape 653 7,029 653 7,029 1 130 9 130

5,725 5,725

Fill/Excavate Payne Gap 25,760,829

Grading Payne Gap 1,055,120

Clearing Payne Gap 218

Payne Gap Total 218 1,055,120 25,760,829 73,872 795,151 32,769 352,726 5,725 12,257 435 6,532

5,003 5,003

Fill/Excavate Roxana 18,084,992

Grading Roxana 876,040

Clearing Roxana 181

Roxana Total 181 876,040 18,084,992 73,219 32,769 5,003 11,535 435 6,532

300 fulltime staff

Alternative 1 Payne Gap/Larson 753 acres

218 acres cleared

2,794,660 CY soil excavation 10,912,130 CY total excavation Total excavation + fill= 25,760,829

8,117,470 CY rock excavation

1,540,797 CY structural fill 14,848,699 CY total fill

13,307,902 CY spoil fill

Road Estimates Assume road width of 18 feet

Entry road/to warehouses 900 m 2,953 ft

USP access 600 m 1,969 ft

Camp access 2000 m 6,562 ft

11,483 ft total

206,693 SF total

Parking/paved areas Require parking for 100 vehicles per shift; overlap; visitors; deliveries

27,480 sf total

Project Name

Roads/Parking Payne Gap

Roads/Parking Roxana

Modified Alternative 2 Roxana 570 acres

181 acres cleared

8,612,966 CY soil excavated 9,342,682 CY total excavation Total excavation + fill= 18,084,992

729,716 CY rock excavated

8,742,310 CY structural fill

25 ac dynamic compaction

Road Estimates Assume road width of 18 feet

Total length 3000 m

9,843 ft total

177,165 SF total

Parking/paved areas Require parking for 100 vehicles per shift; overlap; visitors; deliveries

27,480 sf total