This document is a portion of the specifications for Solicitation No. W912QR24R0015, which is a Request for Proposal (RFP) issued by the U.S. Army Corps of Engineers Engineering District Louisville for the Design-Bid-Build construction of a collocated Area Maintenance Support Activity (AMSA) and Vehicle Maintenance Shop (VMS) at Camp Pendleton, CA for the U.S. Army Reserves. The project requires constructing a 15,000 square foot facility, supporting site work, and demolishing four existing buildings totaling 6,774 square feet. The contract duration is 900 calendar days from contract award. The solicitation specifies that the facilities must be designed to a minimum 40-year lifespan and meet energy efficiency and accessibility requirements in accordance with Unified Facilities Criteria. No specific pricing terms, set-asides, or incumbent information is provided in this document.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PN#: 89783, P2: 481866
Camp Pendleton Area Maintenance Support Activity (AMSA)
DOCUMENT PROJECT Page 1 Amendment 0003 - CERTIFIED FINAL
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 10 00 SOLICITATION CONTRACT FORM
00 80 00.00 06 04/21 SPECIAL PROVISIONS
00 80 00.00 06 CONSTRUCTION PROJECT SIGN DETAILS
DIVISION 01 - GENERAL REQUIREMENTS
01 32 01.00 06 07/18 PROJECT SCHEDULE
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29.00 06 11/17 SUSTAINABILITY REPORTING
AM0001*******************************************************************************
01 33 29.00 06 HIGH PERFORMANCE AND SUSTAINABLE
BUILDING CHECKLIST
01 33 29.00 06 LEED PROJECT CHECKLIST
******************************************************************************AM0001
01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
00.15
04.10
11/16, CHG 2: 08/19 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
CONTRACTOR QUALITY CONTROL
01 45 35 11/20 SPECIAL INSPECTIONS
AM0002*******************************************************************************
01 45 35 STATEMENT OF SPECIAL INSPECTIONS
01 45 35 SCHEDULE OF SPECIAL INSPECTIONS
******************************************************************************AM0002
01 46 00.00 06 04/20 TOTAL BUILDING COMMISSIONING
19.00 06
11/20, 04/20
CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
TEMPORARY ENVIRONMENTAL CONTROLS AND
PERMITS
AM0003******************************************************************************* 01 57 19.00 06 Stormwater Pollution Prevention Plan *****************************************************************************AM0003
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
01 78 23 05/23
DISPOSAL
OPERATION AND MAINTENANCE DATA
01 91 19 05/23 BUILDING ENCLOSURE COMMISSIONING
AM0002*******************************************************************************
01 91 19 APPENDIX A: AIR LEAKAGE TEST FORM
******************************************************************************AM0002
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
02 81 00 11/18 TRANSPORTATION AND DISPOSAL OF
HAZARDOUS MATERIALS
02 82 00 11/18, CHG 1: 11/19 ASBESTOS REMEDIATION
02 83 00 11/18 LEAD REMEDIATION
02 84 16 11/22 HANDLING OF LIGHTING BALLASTS AND
LAMPS CONTAINING PCBs AND MERCURY
02 84 33 11/22 REMOVAL AND DISPOSAL OF
POLYCHLORINATED BIPHENYLS (PCBs)
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 4: 08/22 CAST-IN-PLACE CONCRETE
03 42 13.00 10 05/16 PLANT-PRECAST CONCRETE PRODUCTS FOR
W912QR24R0015_Specs_Vol2-0003
DOCUMENT PROJECT Page 2 Amendment 0003 - CERTIFIED FINAL
BELOW GRADE CONSTRUCTION
03 45 00 05/16, CHG 2: 11/21 PRECAST ARCHITECTURAL CONCRETE
DIVISION 04 - MASONRY
04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY
DIVISION 05 - METALS
05 05 20
05 05 23.16
05/22
08/18
POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
STRUCTURAL WELDING
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING
05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS
05 51 33 02/16, CHG 2: 02/18 METAL LADDERS
05 52 00 02/18, CHG 1: 02/20 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY
06 41 16.00 10 08/10, CHG 1: 11/18 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABIN
ETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 08/19 PRESSURE TESTING AN AIR BARRIER
SYSTEM FOR AIR TIGHTNESS
07 21 13 02/16, CHG 2: 08/20 BOARD AND BLOCK INSULATION
07 21 16 11/11, CHG 4: 08/18 MINERAL FIBER BLANKET INSULATION
07 22 00 02/16, CHG 3: 11/18 ROOF AND DECK INSULATION
07 27 10.00 10 08/19, CHG 1: 02/20 BUILDING AIR BARRIER SYSTEM
07 27 19.01 05/17, CHG 2: 08/20 SELF-ADHERING AIR BARRIERS
07 27 26 05/17, CHG 2: 08/20 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 53 23 05/12, CHG 2: 08/18 ETHYLENE-PROPYLENE-DIENE-MONOMER
ROOFIN
G
07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 36 19 08/20 VERTICAL LIFT DOORS
08 51 13 05/19 ALUMINUM WINDOWS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 08/20 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD
09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING
DOCUMENT PROJECT Page 3
09 67 23.14 08/16, CHG 1: 08/18 CHEMICAL RESISTANT RESINOUS FLOORING
09 90 00 02/21 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 11 00 08/20 VISUAL DISPLAY UNITS
10 14 00.20 08/20 INTERIOR SIGNAGE
10 21 13 08/20 TOILET COMPARTMENTS
10 26 00 08/20 WALL PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
10 51 13 05/11 PLASTIC LOCKERS
10 56 13 04/06 STEEL SHELVING
10 90 00.00 48 04/06 MISCELLANEOUS SPECIALTIES (PARTIAL
OMAR FUNDED)
DIVISION 12 - FURNISHINGS
12 24 13 08/20 ROLLER WINDOW SHADES
12 48 00.00 48 11/04 WALK-OFF MAT
DIVISION 13 - SPECIAL CONSTRUCTION
13 34 19 08/20, CHG 1: 02/21 METAL BUILDING SYSTEMS
13 48 73 05/22 SEISMIC CONTROL FOR MISCELLANEOUS
EQUIPMENT
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS,
FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE
22 05 48.00 20 04/06, CHG 1: 05/15 MECHANICAL SOUND, VIBRATION, AND
SEISMIC CONTROL
22 15 14.00 40 11/17 GENERAL SERVICE COMPRESSED-AIR
SYSTEMS, LOW PRESSURE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 48.19 05/18, CHG 2: 08/20 SEISMIC BRACING FOR HVAC
23 05 93.00 06 08/16 TESTING, ADJUSTING, AND BALANCING
(TAB) OF HVAC
23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 11 14 04/06 VEHICLE FLUID PIPING AND EQUIPMENT
23 11 20 05/20 FACILITY GAS PIPING
23 23 00 08/21 REFRIGERANT PIPING
23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION
AM0003*******************************************************************************
23 35 16.17 10 05/20 MECHANICAL ENGINE AND WELDING FUME
EXHAUST SYSTEMS
******************************************************************************AM0003
DOCUMENT PROJECT Page 4
23 80 20.00 10 05/20 GAS-FIRED HEATING EQUIPMENT
23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.01 05/21 CYBERSECURITY FOR HVAC
FACILITY-RELATED CONTROL SYSTEMS
25 05 11.02 05/21 CYBERSECURITY FOR FIRE LIFE SAFETY
FACILITY-RELATED CONTROL SYSTEMS
25 05 11.03 05/21 CYBERSECURITY FOR ELECTRICAL
FACILITY-RELATED CONTROL SYSTEMS
25 08 10 05/21 UTILITY MONITORING AND CONTROL SYSTEM
TESTING
25 10 10 02/19, CHG 1: 05/21 UTILITY MONITORING AND CONTROL SYSTEM
(UMCS) FRONT END AND INTEGRATION
DIVISION 26 - ELECTRICAL
AM0002*******************************************************************************
26 05 48 11/23 SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT
26 05 48.00 10 10/07 SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT
******************************************************************************AM0002
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 12 19.10 05/19, CHG 1: 11/19 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED
TRANSFORMERS
26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM
26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION
26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS
UNDER 600 VOLTS
26 41 00 11/13 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 05 28.36 48 04/20 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
27 10 00.00 48 10/20 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 13 00.00 48 01/11 Physical Access Control System
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00.00 06 07/18 EARTHWORK
31 62 50 11/20, CHG 1: 05/22 DENSIFIED AGGREGATE PIERS
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT
32 11 23 05/22 AGGREGATE BASE COURSE FOR FLEXIBLE
PAVING
32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
DOCUMENT PROJECT Page 5
32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 15 00 05/17 AGGREGATE SURFACING
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 31 13 11/21 CHAIN LINK FENCES AND GATES
DIVISION 33 - UTILITIES
33 11 00 02/18, CHG 1: 02/22 WATER UTILITY DISTRIBUTION PIPING
33 11 23 11/09, CHG 1: 08/17 NATURAL GAS AND LIQUID PETROLEUM PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00.00 48 04/20 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 13.15 11/22, CHG 1: 02/23 BRIDGE CRANES, OVERHEAD ELECTRIC,
UNDER RUNNING TROLLEY
DIVISION 46 - WATER AND WASTEWATER EQUIPMENT
46 25 14 02/11, CHG 1: 11/13 COALESCING OIL-WATER SEPARATORS
-- End of Project Table of Contents --
AMDT #0003
Stormwater Pollution Prevention Plan
STORMWATER POLLUTION PREVENTION PLAN
for
Project Location:
WDID:
RISK LEVEL: 1
Legally Responsible Person (LRP):
Carmen Call
Whitetail Environmental
Carmen.a.call.ctr@army.mil
614 N Main St, Jay, OK 74346
510-326-6912
Project Address:
Camp Pendleton South, California 92058
CASQA Traditional SWPPP Template ii August 2023 for the 2022 CGP
Site Operating Hours:
Estimated Project Dates:
Start of Construction: April 1, 2024
Completion of Construction: September 18, 2026
SWPPP Prepared by:
Michael Baker International
9635 Granite Ridge Dr., Unit 300
San Diego, CA 92123
SWPPP Preparation Date:
11/06/2023
QSD Name and Signature:
Jay Sullivan, PE, CFM, QSD
CASQA Traditional SWPPP Template iii August 2023
Contact Information Role Name Phone Number License or Certification
Number, if Applicable
Qualified SWPPP Developer (QSD)
Jay Sullivan 858-614-5000 QSD # 20574, RCE # 77445
Qualified SWPPP Practitioner (QSP)
Qualified SWPPP Practitioner (QSP)
QSP Delegate
Index of Appendices
Appendix Title Page
A Site Maps and Drawings A-1
B Permit Registration Documents B-1
C SWPPP Amendment QSD Certifications C-1
D Submitted Changes of Information D-1
E Construction Schedule E-1
F Construction Activities, Materials Used, and Associated Pollutants
F-1
G CASQA Stormwater BMP Handbook: Construction Fact Sheets
G-1
H BMP Inspection Form H-1
I Training Forms I-1
J Responsible Parties J-1
K Contractors and Subcontractors K-1
L Calculations L-1
M Weather Reports M-1
N Monitoring Records N-1
O Example Storm Event Monitoring Forms O-1
P Field Meter Instructions P-1
Q Supplemental Information Q-1
R Active Treatment System and Passive Treatment Plans
R-1
S Construction General Permit S-1
CASQA Traditional SWPPP Template iv August 2023
Table of Contents
Table of Contents ...................................................................................................iv
Qualified SWPPP Developer ................................................................................ vii
Amendment Log ................................................................................................. viii
Section 1 SWPPP Requirements .................................................................. 1-1
1.1 Introduction ................................................................................................................... 1-1
1.2 Permit Registration Documents .................................................................................... 1-1
1.3 SWPPP Availability and Implementation ..................................................................... 1-2
1.4 SWPPP Amendments.................................................................................................... 1-2
1.5 Retention of Records .................................................................................................... 1-4
1.6 Reporting ...................................................................................................................... 1-4
1.7 Changes to Permit Coverage ......................................................................................... 1-6
1.8 Notice of Termination ................................................................................................... 1-6
Section 2 Project Information ...................................................................... 2-1
2.1 Project and Site Description ......................................................................................... 2-1
2.1.1 Site Description ........................................................................................................ 2-1
2.1.2 Existing Conditions .................................................................................................. 2-1
2.1.3 Existing Drainage..................................................................................................... 2-1
2.1.4 Geology and Groundwater ....................................................................................... 2-1
2.1.5 Project Description .................................................................................................. 2-1
2.1.6 Developed Condition ............................................................................................... 2-2
2.2 Permits and Governing Documents .............................................................................. 2-2
2.3 Stormwater Run-On from Offsite Areas ....................................................................... 2-2
2.4 Findings of the Construction Site Sediment and Receiving Water Risk Determination 2-
2.5 Construction Schedule .................................................................................................. 2-4
2.6 Potential Construction Activity and Pollutant Sources ................................................ 2-5
2.7 TMDL Requirements .................................................................................................... 2-5
2.8 Identification of Non-Stormwater Discharges ............................................................. 2-5
2.9 Required Site Map Information .................................................................................... 2-6
Section 3 Best Management Practices .......................................................... 3-1
3.1 Schedule for BMP Implementation .............................................................................. 3-1
3.2 Erosion and Sediment Control ..................................................................................... 3-3
3.2.1 Erosion Control ........................................................................................................ 3-3
3.2.2 Sediment Controls ................................................................................................... 3-8
CASQA Traditional SWPPP Template v August 2023
3.3 Non-Stormwater Controls and Waste and Materials Management ........................... 3-12
3.3.1 Non-Stormwater Controls ..................................................................................... 3-12
3.3.2 Materials Management and Waste Management .................................................. 3-15
3.4 TMDL-Related BMPs .................................................................................................. 3-20
3.5 Post Construction Stormwater Management Measures ............................................. 3-21
Section 4 BMP Inspection and Maintenance ................................................ 4-1
4.1 BMP Inspection and Maintenance ............................................................................... 4-1
Section 5 Training ........................................................................................ 5-1
Section 6 Responsible Parties and Operators............................................... 6-1
6.1 Responsible Parties ....................................................................................................... 6-1
6.2 Contractor List .............................................................................................................. 6-3
Section 7 Construction Site Monitoring Program ........................................ 7-1
7.1 Purpose ..................................................................................................................... 7-1
7.2 Applicability of Permit Requirements ...................................................................... 7-1
7.3. Weather and Precipitation Event Tracking .............................................................. 7-1
7.4 Monitoring Locations .............................................................................................. 7-2
7.5 Safety and Monitoring Exemptions ......................................................................... 7-2
7.6 Visual Monitoring .................................................................................................... 7-2
7.7 Water Quality Sampling and Analysis ..................................................................... 7-6
7.8 Active Treatment System Monitoring.................................................................... 7-16
7.9 Passive Treatment Monitoring .............................................................................. 7-16
7.10 Watershed Monitoring Option .............................................................................. 7-16
7.11 Quality Assurance and Quality Control ................................................................. 7-16
7.12 Records Retention ................................................................................................. 7-19
Section 8 References .................................................................................... 8-1
CASQA Traditional SWPPP Template vi August 2023
Appendices
Appendix A: Site Maps and Drawings
Appendix B: Permit Registration Documents
Appendix C: SWPPP Amendment QSD Certifications
Appendix D: Submitted Changes of Information
Appendix E: Construction Schedule
Appendix F: Construction Activities, Materials Used, and Associated Pollutants
Appendix G: CASQA Stormwater BMP Handbook: Construction Fact Sheets
Appendix H: BMP Inspection Form
Appendix I: Training Forms
Appendix J: Responsible Parties
Appendix K: Contractors and Subcontractors
Appendix L: Calculations
Appendix M: Weather Reports
Appendix N: Monitoring Records
Appendix O: Example Storm Event Monitoring Forms
Appendix P: Field Meter Instructions
Appendix Q: Supplemental Information
Appendix R: Active Treatment System and Passive Treatment Plans
Appendix S: Construction General Permit
CASQA Traditional SWPPP Template vii August 2023
Qualified SWPPP Developer
Approval and Certification of the Stormwater Pollution Prevention Plan
Project Name: Camp Pendleton AMSA
Project Number/ID:
“This Stormwater Pollution Prevention Plan and its appendices were prepared under my direction to meet the requirements of the California Construction Stormwater General Permit (Order No. 2022- 0057-DWQ). I certify that I am a Qualified SWPPP Developer in good standing as of the date signed below and will maintain up to date credentials for the duration of the project.”
QSD Signature
Jay Sullivan
Date
20574
QSD Name
Technical Manager – Surface Water
QSD Certificate Number
858-614-5031
Title and Affiliation
Jay.Sullivan@mbakerintl.com
Telephone Number
11-6-2023
CASQA Traditional SWPPP Template for the 2022 CGP viii August 2023
Amendment Log
Project Name: Camp Pendleton AMSA
Project Number/ID:
Amendment No.
Date Brief Description of Amendment
(include section and page number) Prepared and Approved By
Name:
QSD#
The SWPPP will be revised when:
• There is a 2022 CGP violation (2022 CGP Section VI.Q.1);
• There is a reduction or increase in total disturbed acreage (2022 CGP Section III.F.2. and F.4);
• BMPs are not effective and are not resulting in a reduction or elimination of pollutants in stormwater discharges and authorized non-stormwater discharges (2022 CGP Section VI.Q.1 and Attachment E Section III.C.5);
• There is a change in the project duration that changes the project Risk Type (2022 CGP Section III.F.1);
• Dischargers with projects where all construction activities (including passive treatment, active treatment systems, and/or active equipment) will be suspended for 30 days or more (2022 CGP Section III.G);
• There is a change in construction or operations that may affect the discharge of pollutants to surface waters, groundwater(s), or a municipal separate storm sewer system (MS4) (2022 CGP Sections IV.O. and VI.Q.1); or
When deemed necessary by the QSD. The QSD has determined that the changes listed in Table 1-1 can be field determined by the QSP. All other changes will be made by the QSD as formal amendments to the SWPPP. Note that the 2022 CGP requires that the QSD “revise the SWPPP to address potential problems identified by visual inspections, sampling data, comments from a QSP, or their own site observations (2022 CGP Section V.C.2.).
SWPPP Amendment QSD Certifications are located in Appendix C.
CASQA Traditional SWPPP Template 1-1 August 2023
Section 1 SWPPP Requirements
1.1 INTRODUCTION
This Stormwater Pollution Prevention Plan (SWPPP) is designed to comply with California’s General Permit for Stormwater Discharges Associated with Construction and Land Disturbance Activities (2022 CGP), State Water Resources Control Board (State Water Board) Order No. 2022-0057-DWQ (NPDES No. CAS000002) (Appendix S). This SWPPP has been prepared following the 2022 CGP SWPPP Template for Traditional Projects provided in the California Stormwater Quality Association (CASQA) Stormwater Best Management Practice (BMP) Handbook: Construction (CASQA 2023).
This project is considered a traditional construction project.
In accordance with the 2022 CGP, Section IV.O, this SWPPP is designed to address the following:
• Identification of all pollutants, their sources, and control mechanisms, including sources of sediment associated with all construction activities (e.g., sediment, paint, cement, stucco, cleaners, site erosion);
• Pollutant source assessments, including a list of potential pollutant sources and identification of site areas where additional BMPs are necessary to reduce or prevent pollutants in stormwater and authorized non-stormwater discharges, per the minimum requirements when developing the pollutant source assessment;
• Description of site-specific BMPs implemented to reduce or eliminate stormwater pollution;
• Where not otherwise required to be under a Regional Water Quality Control Board (Regional Water Board) permit, all non-stormwater discharges are identified and either eliminated, controlled, or treated;
• Site BMPs are effective and result in the reduction or elimination of pollutants in stormwater discharges and authorized non-stormwater discharges from construction activity to the Best Available Technology/Best Control Technology (BAT/BCT) standard;
and;
• Stabilization BMPs are installed to reduce or eliminate pollutants after construction is completed are effective and maintained; and
• Calculations and design details, as well as BMP controls, are complete and correct.
The Camp Pendleton AMSA project comprises approximately of 6.56 acres. The Project is located at Camp Pendleton South, California 92058. The property is owned and being developed by the US Army Corps of Engineers. The project’s location is shown on the Site Maps in Appendix A.
1.2 PERMIT REGISTRATION DOCUMENTS
Required Permit Registration Documents (PRDs) shall be submitted to the State Water Board via the Stormwater Multi Application and Report Tracking System (SMARTS) by the LRP or DAR. The project-specific PRDs include (2022 CGP Section III.A):
1. Notice of Intent (NOI);
CASQA Traditional SWPPP Template 1-2 August 2023
2. Risk Level Determination (Construction Site Sediment and Receiving Water Risk Determination);
3. Site Drawings and Map;
4. SWPPP;
5. Applicable plans, calculations, and other supporting documentation for compliance with the Phase I or Phase II municipal separate storm sewer system (MS4) post construction requirements or the post-construction standards of the 2022 CGP:
• Attachment or web-source containing the applicable Phase I or Phase II MS4 post construction requirements;
• The post construction plans and calculations submitted to or approved by the applicable Phase I or Phase II MS4; and/or
• Post-construction water balance calculation;
6. Dischargers proposing an alternate K-factor or LS-factor must submit documentation to support the site-specific factors, if applicable;
7. Active Treatment System (ATS) Plan, if applicable;
8. Passive Treatment Plan, if applicable;
9. Dewatering Plan, if applicable;
10. Annual Fee per the current 23 California Code of Regulations Chapter 9 fee schedule for National Pollutant Discharge Elimination System (NPDES) stormwater permits; and
11. Signed Certification Statement (LRP Certification is provided electronically with SMARTS PRD submittal).
Site Maps can be found in Appendix A. A copy of the submitted PRDs shall also be kept in Appendix B along with the Waste Discharge Identification (WDID) confirmation.
1.3 SWPPP AVAILABILITY AND IMPLEMENTATION
The SWPPP will be available at the construction site during working hours list on the title sheet and Section 7.5, while construction is occurring and shall be made available upon request by a federal, state, or municipal inspector. A current copy of the site-specific SWPPP and any site inspection reports required by the 2022 CGP may be kept in electronic format at the site so long as the information requested by a federal, state, or municipal inspector can be made available during an inspection. Legible maps in hard copy must be available at the site (2022 CGP Section
IV.O.1.).
The SWPPP must be implemented at the appropriate level to protect water quality at all times throughout the life of the project. The SWPPP must remain on the site during construction activities, commencing with the initial mobilization and ending with the termination of coverage under the 2022 CGP.
1.4 SWPPP AMENDMENTS
SWPPP changes or amendments will be uploaded through SMARTS within 30 calendar days.
The SWPPP will be revised when:
• If there is a 2022 CGP violation (2022 CGP Section VI.Q.1);
CASQA Traditional SWPPP Template 1-3 August 2023
• There is a reduction or increase in total disturbed acreage (2022 CGP Section III.F.2 and F.4.);
• BMPs are not effective and are not resulting in a reduction or elimination of pollutants in stormwater discharges and authorized non-stormwater discharges (2022 CGP Section VI.Q.1 and Attachment D Section III.C.5);
• There is a change in the project duration that changes the project’s risk level (2022 CGP Section III.F.1); or
• Dischargers with projects where all construction activities (including passive treatment, active treatment systems, and/or active equipment) will be suspended for 30 days or more (2022 CGP Section III.G.).
Additionally, the SWPPP will be amended when:
• There is a change in construction or operations that may affect the discharge of pollutants to surface waters, groundwater(s), or a municipal separate storm sewer system (MS4) (2022 CGP Sections IV.O. and VI.Q.1); or
When deemed necessary by the QSD. The QSD has determined that the changes listed in Table 1-1 can be field determined by the QSP. All other changes will be made by the QSD as formal amendments to the SWPPP. Note that the 2022 CGP requires that the QSD revise the SWPPP to address potential problems identified by visual inspections, sampling data, comments from a QSP, or their own site observations (2022 CGP Section V.C.2.).
The following items shall be included in each amendment:
• Who requested the amendment;
• The location of proposed change;
• The reason for change;
• The original BMP(s) proposed, if any;
• The new BMP(s) proposed; and
• QSD certification.
SWPPP amendments will be logged at the front of the SWPPP and SWPPP Amendment QSD certifications will be located in Appendix C. The SWPPP text will be revised, replaced and/or hand annotated as necessary to properly convey the amendment. SWPPP amendments must be made by a QSD. The following changes have been designated by the QSD as “to be field determined” and constitute minor changes that the QSP may implement based on field conditions.
Table 1-1 List of Changes to be Field Determined
Candidate changes for field location or determination by QSP (1)
Check changes that can be field located, or field determined by
QSP
Increase quantity of an Erosion or Sediment Control Measure
Relocate/add stockpiles or stored materials
Relocate or add toilets
CASQA Traditional SWPPP Template 1-4 August 2023
Table 1-1 List of Changes to be Field Determined
Candidate changes for field location or determination by QSP (1)
Check changes that can be field located, or field determined by
QSP
Relocate vehicle storage and/or fueling locations
Relocate areas for waste storage
Relocate water storage and/or water transfer location
Changes to access points (entrance/exits)
Change type or location of Erosion or Sediment Control Measure
Minor changes to schedule or phases
Changes in construction materials
(1) Any field changes not identified for field location or field determination by the QSP must be made as an amendment by the QSD.
1.5 RETENTION OF RECORDS
Paper or electronic records of documents required by this SWPPP will be retained for a minimum of three years from the date generated or date submitted, whichever is later, for the following items:
• SWPPP;
• Visual monitoring reports;
• Sampling equipment calibration records;
• pH and turbidity sampling field sheets;
• Analytical laboratory reports; and
These records will be available at the Site until construction is complete. Records assisting in the determination of compliance with the 2022 CGP will be made available within a reasonable time to the Regional Water Board, State Water Board, or U.S. Environmental Protection Agency (EPA) upon request. Requests by the Regional Water Board for retention of records for a period longer than three years will be adhered to.
1.6 REPORTING
Completed inspection checklists are not required to be submitted to the Regional Water Board.
However, completed inspection checklists will be kept with the SWPPP on-site or electronically.
The 2022 CGP requires that permittees prepare, certify, and electronically submit an Annual Report no later than September 1 of each year. Reporting requirements are identified in 2022 CGP Section VI.P. Annual reports will be filed in SMARTS and in accordance with information required by the online forms.
Planned changes in site construction activities that may result in non-compliance with the 2022 CGP are required to be provided in writing to the Regional Water Board and local stormwater agency in advance of the changes.
CASQA Traditional SWPPP Template 1-5 August 2023
If a 2022 CGP discharge violation occurs, the QSP will immediately notify the LRP. The LRP will include information on the violation with the Annual Report. Corrective measures will be implemented immediately following identification of the discharge or written notice of non-compliance from the Regional Board. Discharges and corrective actions must be documented and include the following items:
• The date, time, location, nature of operation, and type of unauthorized discharge;
• The cause or nature of the notice or order;
• The BMPs deployed before the discharge event, or prior to receiving notice or order; and
• The date of deployment and type of BMPs deployed after the discharge event, or after receiving the notice or order, including additional measures installed or planned to reduce or prevent re-occurrence.
Results of (pH and turbidity, etc.) monitoring will be electronically submitted through SMARTS for all field sampling results within 30 days of the completion of the precipitation event or within 10 days if the field sampling results demonstrate the exceedance of the pH and/or turbidity NALs. See Section 7.7.2.7 for additional discussion of the reporting requirements.
Reporting requirements for pH and turbidity Receiving Water Monitoring Triggers are discussed in Section 7.7.2.7.
Results of non-visible pollutant monitoring, and corrective actions will be electronically submitted within 30 days after obtaining analytical results or within 10 days if the analytical results demonstrate the exceedance of an applicable TMDL-related NAL or NEL or Basin Plan parameter. See Section 7.7.1.7 for additional discussion of the reporting requirements.
A NAL exceedance report will be prepared when requested, in writing, by the Regional Water Board.
In the event of a TMDL NEL exceedance, by the end of each reporting year the project will submit and certify, in SMARTS, documentation of the site assessment, SWPPP evaluation, and implementation of the corrective actions.
Results of monitoring (pH, turbidity, flowrate, volume discharged, and freeboard storage) will be electronically submitted monthly during the project. See the ATS Plan for additional discussion of the reporting requirements.
In the event of an ATS NEL exceedance results will be electronically certified and submitted to SMARTS within 24-hours of obtaining the results.
The Regional Water Board will be notified via email 24 hours prior to the beginning of a planned dewatering discharge.
In the event of an emergency dewatering, the Regional Water Board and applicable MS4 are to be notified within 24 hours of a discharge occurring. An emergency is defined as the need to protect human life and health or prevent severe property damage.
Results of (pH and turbidity, etc.) monitoring will be electronically submitted through SMARTS for all field sampling results within 30 days of the completion of the precipitation event or within 10 days if the field sampling results demonstrate the exceedance of the pH and/or turbidity NALs.
See Section 7.7.4.5 for additional discussion of the reporting requirements including contacts for Regional Water Board and MS4 notifications.
CASQA Traditional SWPPP Template 1-6 August 2023
A Passive Treatment Plan will be submitted electronically 14 days before passive treatment chemicals are used on site. See the Passive Treatment Plan for additional discussion of the reporting requirements.
1.7 CHANGES TO PERMIT COVERAGE
The 2022 CGP allows for the reduction or increase of the total acreage covered under the 2022 CGP when: a portion of the project is complete and/or conditions for termination of coverage have been met; when ownership of a portion of the project is purchased by a different entity; or when new acreage is added to the project.
Modified PRDs will be filed electronically through a Change of Information (COI) within 30 days of a reduction or increase in total disturbed area if a change in permit-covered acreage is to be sought. The SWPPP will be modified appropriately and will be logged at the front of the SWPPP. SWPPP Amendments QSD Certifications will be located in Appendix C. COIs submitted electronically via SMARTS can be found in Appendix D.
1.8 NOTICE OF TERMINATION
A Notice of Termination (NOT) must be submitted electronically by the LRP or DAR via SMARTS to terminate coverage under the 2022 CGP.
According to the requirements of 2022 CGP Section III.H.4., the following final stabilization method will be used to satisfy final stabilization condition requirements:
70 percent final cover method supported by pre- and post-project photographs demonstrating stabilization.
RUSLE or RUSLE2 method with computation proof supported by pre- and post-project photographs demonstrating stabilization.
Custom method for which Regional Water Board approval has been obtained, supported by documentation required by the Regional Water Board and pre- and pos- project photographs demonstrating stabilization.
The Regional Water Board will consider a construction site complete when the conditions of the 2022 CGP Section III.H., have been met.
The discharger is required to submit the following in SMARTS:
• NOT SMARTS Form;
• QSP-prepared final NOT inspection which includes the QSP name and valid QSP certificate number;
• Final site map with photo orientation references;
• Photos demonstrating final stabilization and the applicable post-construction BMPs and/or low impact development; and
• A long-term maintenance plan for the post-construction stormwater runoff BMPs and/or low impact development features being implemented.
According to the 2022 CGP, the NOT will be automatically approved within 30 calendar days after the date the NOT was submitted, unless, within the 30 calendar days the Regional Water Board notifies the discharger through SMARTS that the Notice of Termination has been denied, returned, or accepted for review (2022 CGP Section III.H.7).
CASQA Traditional SWPPP Template 1-7 August 2023
Note: If an Annual Report has not been filed in the current reporting year, an Annual Report will need to be submitted prior to the NOT.
CASQA Traditional SWPPP Template 2-1 August 2023
Section 2 Project Information
2.1 PROJECT AND SITE DESCRIPTION
2.1.1 Site Description
The Camp Pendleton AMSA project site is Risk Level 1 that comprises approximately 6.56 acres and is located at Camp Pendleton South, California 92058. The project site is located approximately 0.5 miles west of interstate 5 and adjacent to Oceanside Harbor. The project is located at latitude 33°12'48.40"N, and longitude 117°23'49.21"W and is identified on the Site Map in Appendix A.
2.1.2 Existing Conditions
As of the initial date of this SWPPP, the project site is fully developed. Most of the existing site is a building, parking lot and storage yard. The project site was previously developed with a public land use. There are no known historic sources of contamination at the site. Soil sampling and analysis is required when soil contamination is found or suspected. The results of this analysis are in Appendix Q.
2.1.3 Existing Drainage
The project site elevation is relatively flat. The elevation of the project site ranges from 25 to 13 feet above mean sea level (msl). Surface drainage at the site currently flows north to southwest and southeast. Stormwater is conveyed through surface runoff. Existing site topography, drainage patterns, and stormwater conveyance systems are shown on Site Maps in Appendix A.
The project discharges to the Oceanside. Oceanside Harbor eventually discharges into the Pacific Ocean. The water quality impairments (303 (d) list and TMDLs identified in the 2022 CGP Table H-1 for the receiving waters are identified in the Table 2-1.
Table 2-1 Applicable 303(d) List Impairments and TMDLs
Receiving Water Water Quality Impairment
303(d) list TMDL (2022 CGP Table H-1)
Oceanside Harbor Copper
Toxicity
None
2.1.4 Geology and Groundwater
The site is underlain with undocumented artificial fill overlying Quaternary-aged Young Alluvium. See soils reports titled “Geotechnical Investigation Army Support Facility Camp Pendleton, California” dated July 14, 2023. Groundwater was encountered approximately 14 feet below ground surface during the geotechnical investigation.
2.1.5 Project Description
Project grading will occur on approximately 6.56 acres of the project. The limits of grading are shown on Site Maps in Appendix A. Soil will be stockpiled as shown on Site Maps in Appendix A.
CASQA Traditional SWPPP Template 2-2 August 2023
2.1.6 Developed Condition
Post-construction surface drainage will mimic the existing condition and sheet flow towards Oceanside Harbor.
Post-construction drainage patterns and conveyance systems are presented on Site Maps in Appendix A.
2.2 PERMITS AND GOVERNING DOCUMENTS
In addition to the 2022 CGP, the following documents have been taken into account while preparing this SWPPP:
• Regional Water Board requirements
• Basin Plan requirements
• Contract Documents
• Air Quality regulations and permits.
• Federal Endangered Species Act
• National Historic Preservation Act/Requirements of the State Historic Preservation Office
• State of California Endangered Species Act
• Clean Water Act Section 401 Water Quality Certifications and 404 Permits
• CA Department of Fish and Game 1600 Streambed Alteration Agreement
• California Ocean Plan
• State Water Board GeoTracker database (GeoTracker)
2.3 STORMWATER RUN-ON FROM OFFSITE AREAS
There is no anticipated offsite run-on to this construction site because existing BMPs or stormwater conveyance system prevent onsite flow from upstream areas.
Table 2-2 Construction Site Estimates
Construction site area 6.56 acres
Total area of disturbance 6.56 acres
Percent impervious before construction 86 %
Runoff coefficient before construction 0.80
Percent impervious after construction 96 %
Runoff coefficient after construction 0.87
CASQA Traditional SWPPP Template 2-3 August 2023
2.4 FINDINGS OF THE CONSTRUCTION SITE SEDIMENT AND
RECEIVING WATER RISK DETERMINATION
A construction site risk assessment has been performed for the project and the resultant risk level is Risk Level 1.
The risk level was determined through the use of the R-value determined from EPA’s Rainfall Erosivity Factor Calculator for Small Construction Sites at: https://lew.epa.gov/ in accordance with the State Water Board Guidance for multi-year projects at:
https://www.waterboards.ca.gov/water_issues/programs/stormwater/smarts/construction/do cs/rfactor_guide.pdf, and K and LS via a site-specific analysis. The risk level is based on project duration, location, proximity to impaired receiving waters, and soil conditions. A copy of the Risk Level determination submitted on SMARTS with the PRDs is included in Appendix B.
Table 2-3 and Table 2-4 summarize the sediment and receiving water risk factors and document the sources of information used to derive the factors.
Table 2-3 Summary of Sediment Risk
RUSLE
Factor
Value Method for Establishing Value
R 67.63 NPDES Rainfall Erosivity Factor Calculator
K 0.07 NRCS Web Soil Survey, K Factor, Whole Soil
LS 1.92 Caltrans Water Quality Planning Tool
Total Predicted Sediment Loss (tons/acre) 9.09
Overall Sediment Risk Low Sediment Risk < 15 tons/ acre Medium Sediment Risk >= 15 and < 75 tons/acre High Sediment Risk >= 75 tons/acre
☒ Low
☐ Medium
☐ High
Runoff from the project site discharges into an unnamed tributary below Hodges Dam that discharge into the San Dieguito River, and eventually the Pacific Ocean.
Table 2-4 Summary of Receiving Water Risk
Receiving Water Name
303(d) Listed for Sediment Related Pollutant (1)
TMDL for Sediment Related Pollutant (1)
Beneficial Uses of
COLD, SPAWN,
and MIGRATORY
(1)
Oceanside Harbor ☐ Yes ☒ No ☐ Yes ☒ No ☐ Yes ☒ No
Overall Receiving Water Risk ☒ Low
☐ High
(1) If yes is selected for any option the Receiving Water Risk is High
Risk Level 1 sites are subject to the narrative effluent limitations specified in the 2022 CGP, and may be subject to numeric effluent limits for applicable TMDLs, dewatering activities, active treatment systems and passive treatment systems used on site. The narrative effluent
CASQA Traditional SWPPP Template 2-4 August 2023 limitations require stormwater discharges associated with construction activity to minimize or prevent pollutants in stormwater and authorized non-stormwater through the use of controls, structures, and best management practices (BMPs). This SWPPP has been prepared to address Risk Level 1 requirements (2022 CGP Attachment D).
Table 2-5 Numeric Action Levels and Numeric Effluent Limits
Parameter Unit Numeric Action Level Numeric Effluent
Limit pH pH units Lower NAL < 6.5 Upper NAL > 8.5
Not Applicable
Turbidity NTU > 250 NTU Not Applicable
2.5 CONSTRUCTION SCHEDULE
The site sediment risk was determined based on construction taking place between April 1, 2024 to September 18, 2026. Modification or extension of the schedule (start and end dates) may affect risk determination and permit requirements. The LRP shall contact the QSD if the schedule changes during construction to address potential impact to the SWPPP. The estimated schedule for planned work can be found in Appendix E.
CASQA Traditional SWPPP Template 2-5 August 2023
2.6 POTENTIAL CONSTRUCTION ACTIVITY AND POLLUTANT
SOURCES
Appendix F includes a list of construction activities and associated materials that are anticipated to be used onsite as well as the pollutant source assessment form that was completed for the project. These activities and associated materials will or could potentially contribute pollutants, other than sediment, to stormwater runoff.
The anticipated activities and associated pollutants were used in Section 3 to select the BMPs for the project. Locations of anticipated pollutants and associated BMPs are shown on the Site Map in Appendix A.
Additionally, proper measures will be taken to ensure that trench spoils or any other soils disturbed during construction activities that are contaminated are not discharged with stormwater or non-stormwater discharges into storm drains or water bodies (except pursuant to a separate NPDES Permit). If contaminated soils are found on site, and the responsible party cannot be identified or fails to take action, soils will be sampled to determine proper handling and protect public safety. The appropriate local, State, and federal agencies along with the appropriate Regional Water Board will be notified when contaminated soils are observed.
For sampling requirements for non-visible pollutants associated with construction activity, please refer to Section 7.7.1. For a full and complete list of onsite pollutants, refer to the Safety Data Sheets (SDS), which are retained onsite at the construction trailer or are available electronically at the site.
2.7 TMDL REQUIREMENTS
Based on the project’s receiving water and the pollutant source assessment, the following TMDLs are applicable to the project (See 2022 CGP Attachment H).
Table 2-8 Project TMDLs
TMDL Applicable Water Body/ Watershed
Pollutants Additional TMDL-Related
NAL or NEL
Compliance Actions
Indicator Bacteria
San Dieguito River
Benthic Community Effects, Indicator Bacteria, Nitrogen, Phosphorus, Total Dissolved Solids, Toxicity
These TMDLs are also identified in Section 2.1.3. The applicable NALs and NELs are also identified in Section 2.4. BMP requirements related to TMDLs are discussed in Section 3.4.
Monitoring requirements related to TMDLs are discussed further in Section 7.7.
2.8 IDENTIFICATION OF NON-STORMWATER DISCHARGES
Non-stormwater discharges into storm drainage systems or waterways, which are not authorized under the 2022 CGP and listed in the SWPPP, or authorized under a separate NPDES permit, are prohibited.
Non-stormwater discharges that are authorized from this project site include the following:
CASQA Traditional SWPPP Template 2-6 August 2023
• Discharges from fire-fighting activities.
• Fire hydrant flushing.
• Waters used to wash vehicles where detergents are not used.
• Water used to control dust.
• Potable water including uncontaminated water line flushing.
• Routine external building wash down that does not use detergents.
• Uncontaminated air conditioning or compressor condensate.
• Uncontaminated excavation dewatering.
• Landscape irrigation.
These authorized non-stormwater discharges will be managed with the stormwater and non-stormwater BMPs described in Section 3 of this SWPPP and will be minimized under the direction of the QSP. Additionally, the non-stormwater discharges not applicable to this project are still allowable granted they do not contact potential pollutant sources.
Activities at this site that may result in unauthorized non-stormwater discharges include:
• None
Steps will be taken, including the implementation of appropriate BMPs, to ensure that unauthorized discharges are eliminated, controlled, disposed, or treated on-site.
Discharges of construction materials and wastes, such as fuel or paint, resulting from dumping, spills, or direct contact with rainwater or stormwater runoff, are also prohibited.
The following discharge(s) have been authorized by (a) regional NPDES permit(s):
• None
2.9 REQUIRED SITE MAP INFORMATION
The construction project’s Site Map(s) showing the project location, surface water boundaries, geographic features, construction site perimeter and general topography, locations of storm drain inlets that receive runoff from the project, and other requirements identified in 2022 CGP Sections IV.O.2. k. and l are located in Appendix A. Table 2-9 identifies Maps or Sheet Nos.
where required elements are illustrated.
Table 2-9 Required Map Information
Included on Map/Plan
Sheet No. (1) Required Element
Pre-Earthwork Drawings
CE101, 102 & 501 Site and project boundaries
CASQA Traditional SWPPP Template 2-7 August 2023
Table 2-9 Required Map Information
Included on Map/Plan
Sheet No. (1) Required Element
CE101, 102 & 501
Areas disturbed during geotechnical or other preconstruction investigation work
CE101, 102 & 501 Existing roads and trails
CE101, 102 & 501 Drainage areas
CE101, 102 & 501 Discharge locations
CE101, 102 & 501 Existing storms drain system if applicable
CE101, 102 & 501 Proposed locations of storage areas for waste
CE101, 102 & 501 Proposed locations of construction materials
CE101, 102 & 501 Proposed locations of project staging areas
CE101, 102 & 501 Proposed locations of stockpiles
CE101, 102 & 501 Proposed locations of vehicles, equipment staging and vehicle maintenance
CE101, 102 & 501 Proposed locations of loading/unloading materials
CE101, 102 & 501 Proposed locations of site access (entrance/exits)
CE101, 102 & 501 Proposed locations of fueling, water storage, water transfer for dust control
CE101, 102 & 501 Proposed locations of demolition
CE101, 102 & 501 Proposed locations of other construction support activities
Construction and Earthwork Drawing(s)
CE101, 102 & 501 Site layout (grading plans) including roads
CE101, 102 & 501 Site and project boundaries
CE101, 102 & 501 Drainage areas
CE101, 102 & 501 Discharge locations
CE101, 102 & 501 Sampling locations
CE101, 102 & 501 Areas of soil disturbance (temporary or permanent)
CE101, 102 & 501 Proposed active areas of soil disturbance (cut or fill)