W912QR23R0034_SPECS-0001.pdf

PDF 1 MB Posted

Attached to
Alpena ANG Hangar and Maintenance Shops, MI
Solicitation number
W912QR23R0034
Issued by

About this file

This document provides details for a federal construction contract opportunity. The solicitation is for design-build-build services for a new aircraft hangar and maintenance shops at Alpena Air National Guard Base in Michigan. The estimated construction cost is between $10-20 million. The NAICS code is 236220 and size determination is $45 million. This is a full and open competition requiring compliance with HUBZone price evaluation preferences. The point of contact is provided for any questions. Site visit information is available in the solicitation.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Design/Bid/Build for the new construction of Alpena ANG Aircraft Hangar and Maintenance Shops at Alpena, MI has hereby been amended as follow s:

SEE SUMMARY OF CHANGES

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912QR23R0034

X 9B. DATED (SEE ITEM 11)

18-May-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

28-Jun-2023

CODE

U. S. ARMY ENGINEER DISTRICT, LOUISVILLE

600 DR. MARTIN LUTHER KING, JR. PLACE

ROOM 821

LOUISVILLE KY 40202-2239

W912QR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912QR23R0034_SPECS-0001

W912QR23R0034

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMDT 0001 SUMMARY OF CHANGES

Aircraft Maintenance Hangar Alpena ANG, Michigan

W912QR23R0034

Amendment 0001

SUMMARY OF CHANGES

1. The following SPECIFICATION SECTIONS have been added in their entirety:

09 54 60 LINEAR METAL CEILING SYSTEM

13 31 34 BIRD NETTING

2. The following SPECIFICATION SECTIONS have been replaced in their entirety:

TABLE OF CONTENTS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

3. The following PLAN SHEETS have been revised and replaced in their entirety:

Sheet No TITLE

EL601 LIGHTING FIXTURE SCHEDULE

EP101 POWER PLAN -AREA A

EP102 POWER PLAN -AREA B

4. The proposal due date has been extended from 6 July 2023 at 11am Eastern to 27 July 2023 at 11am Eastern.

5. FAR Clause 52.204-27 Prohibition on a ByteDance Covered Application (June 2023) has been added in it’s entirety by reference.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 06-Jul-2023 11:00 AM to 27-Jul-2023 11:00 AM.

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

W912QR23R0034

The following have been added by reference:

52.204-27 Prohibition on a ByteDance Covered Application JUN 2023

(End of Summary of Changes)

P2 504941 Replace Alpena Aircraft Maintenance Hangar/Shops Alpena County Regional Airport, Michigan

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 80 00.00 06 04/21 SPECIAL PROVISIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 32 01.00 06 07/18 PROJECT SCHEDULE

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 33 29.00 06 11/17 SUSTAINABILITY REPORTING

01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS

01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.15 10 11/16, CHG 2: 08/19 RESIDENT MANAGEMENT SYSTEM CONTRACTOR

MODE (RMS CM)

01 45 04.10 06 CONTRACTOR QUALITY CONTROL

01 45 35 02/15 SPECIAL INSPECTIONS

01 46 00.00 06 04/20 TOTAL BUILDING COMMISSIONING

01 50 00 11/20, CHG 1: 08/21 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS

01 57 19.00 06 04/20 TEMPORARY ENVIRONMENTAL CONTROLS AND

PERMITS

01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

DIVISION 02 - EXISTING CONDITIONS

02 41 00 05/10 DEMOLITION

02 61 13 02/10 EXCAVATION AND HANDLING OF

CONTAMINATED MATERIAL

02 81 00 11/18 TRANSPORTATION AND DISPOSAL OF

HAZARDOUS MATERIALS

DIVISION 03 - CONCRETE

03 30 00 02/19 CAST-IN-PLACE CONCRETE

03 53 14.00 20 02/10 LIGHT REFLECTIVE NONFERROUS METALLIC

AGGREGATE FLOOR SYSTEM

DIVISION 04 - MASONRY

04 20 00 11/15 UNIT MASONRY

04 72 00 10/18 VIBRANT DRY TAMPED CAST STONE

DIVISION 05 - METALS

05 05 20 05/22 POST-INSTALLED CONCRETE AND MASONRY

ANCHORS

05 05 23.16 08/18 STRUCTURAL WELDING

05 12 00 08/18 STRUCTURAL STEEL

05 30 00 05/15 STEEL DECKS

05 40 00 05/15 COLD-FORMED METAL FRAMING

05 50 13 05/17 MISCELLANEOUS METAL FABRICATIONS

05 51 33 02/16 METAL LADDERS

05 52 00 02/18 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 08/16 ROUGH CARPENTRY

PROJECT TABLE OF CONTENTS Page 1

CERTIFIED FINAL AMENDMENT 0001

06 41 16.00 10 08/10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL

CABINETS

06 61 16 08/20 SOLID SURFACING FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 11 13 08/11 BITUMINOUS DAMPPROOFING

07 21 13 02/16 BOARD AND BLOCK INSULATION

07 21 16 11/11 MINERAL FIBER BLANKET INSULATION

07 22 00 02/16 ROOF AND DECK INSULATION

07 27 10.00 10 08/19 BUILDING AIR BARRIER SYSTEM

07 27 19.01 05/17 SELF-ADHERING AIR BARRIERS

07 27 26 05/17 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 27 36 05/17 SPRAY FOAM AIR BARRIERS

07 42 13 05/11 METAL WALL PANELS

07 42 63 05/11 FABRICATED WALL PANEL ASSEMBLIES

07 60 00 05/17 FLASHING AND SHEET METAL

07 61 14.00 20 08/16 STEEL STANDING SEAM ROOFING

07 72 13 12/16 PREFABRICATED ROOF CURBS

07 84 00 05/10 FIRESTOPPING

07 92 00 08/16 JOINT SEALANTS

07 95 00 EXPANSION CONTROL

DIVISION 08 - OPENINGS

08 11 13 08/20 STEEL DOORS AND FRAMES

08 31 00 05/17 ACCESS DOORS AND PANELS

08 34 16.10 11/21 HORIZONTAL ROLLING STEEL DOORS

08 34 19.10 20 02/12 ROLLING SERVICE AND FIRE DOORS

08 34 73 11/19, CHG 1: 02/21 SOUND CONTROL DOOR ASSEMBLIES

08 44 00 05/19 CURTAIN WALL AND GLAZED ASSEMBLIES

08 60 45 08/20 TRANSLUCENT PANELS

08 71 00 02/16 DOOR HARDWARE

08 81 00 05/19 GLAZING

08 91 00 08/20 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 06 00 08/22 SCHEDULES FOR FINISHES

09 22 00 02/10 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 08/16 GYPSUM BOARD

09 54 60 LINEAR METAL CEILING SYSTEM

09 65 00 08/10 RESILIENT FLOORING

09 67 23.13 11/19 STANDARD RESINOUS FLOORING

09 90 00 05/11 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 11 00 08/20 VISUAL DISPLAY UNITS

10 14 00.10 08/17 EXTERIOR SIGNAGE

10 14 00.20 08/20 INTERIOR SIGNAGE

10 21 13 08/20 TOILET COMPARTMENTS

10 26 00 08/20 WALL AND DOOR PROTECTION

10 28 13 08/20 TOILET ACCESSORIES

10 44 16 11/19 FIRE EXTINGUISHERS

DIVISION 11 - EQUIPMENT

11 01 50 08/08 FALL PROTECTION SYSTEMS

PROJECT TABLE OF CONTENTS Page 2

CERTIFIED FINAL AMENDMENT 0001

Amendment 0001

DIVISION 12 - FURNISHINGS

12 21 00 08/17 WINDOW BLINDS

12 48 13 08/17 ENTRANCE FLOOR MATS AND FRAMES

DIVISION 13 - SPECIAL CONSTRUCTION

13 31 34 BIRD NETTING

13 34 19 08/20, CHG 1: 02/21 METAL BUILDING SYSTEMS

13 48 00 05/18 BRACING FOR MISCELLANEOUS EQUIPMENT

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 10 05/09 WET PIPE SPRINKLER SYSTEMS, FIRE

PROTECTION

21 13 18.00 10 05/09 PREACTION SPRINKLER SYSTEMS, FIRE

PROTECTION

21 30 00 04/08 FIRE PUMPS

DIVISION 22 - PLUMBING

22 00 00 11/15 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 08/18 AIR SUPPLY, DISTRIBUTION, VENTILATION,

AND EXHAUST SYSTEMS

23 05 48.19 05/18 BRACING FOR HVAC

23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR

HVAC

23 07 00 02/13 THERMAL INSULATION FOR MECHANICAL

SYSTEMS

23 09 00 02/19 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 11/15 INSTRUMENTATION AND CONTROL DEVICES

FOR HVAC

23 09 23.02 02/19 BACNET DIRECT DIGITAL CONTROL FOR HVAC

AND OTHER BUILDING CONTROL SYSTEMS

23 11 25 11/08 FACILITY GAS PIPING

23 23 00 10/07 REFRIGERANT PIPING

23 52 00 04/08 HEATING BOILERS

23 81 00 05/18 DECENTRALIZED UNITARY HVAC EQUIPMENT

23 82 00.00 20 02/16 TERMINAL HEATING UNITS

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11.01 11/17 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS ENERGY MANAGEMENT

CONTROL SYSTEM (EMCS) BUILDING LEVEL

ONLY

25 05 11.02 11/17 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS FIRE ALARM REPORTING

SYSTEM/MASS NOTIFICATION SYSTEM

BUILDING LEVEL ONLY

25 08 10 04/06 UTILITY MONITORING AND CONTROL SYSTEM

TESTING

25 10 10 02/19 UTILITY MONITORING AND CONTROL SYSTEM

(UMCS) FRONT END AND INTEGRATION

PROJECT TABLE OF CONTENTS Page 3

CERTIFIED FINAL AMENDMENT 0001

Amendment 0001

DIVISION 26 - ELECTRICAL

26 00 00.00 20 07/06 BASIC ELECTRICAL MATERIALS AND METHODS

26 08 00 11/22 APPARATUS INSPECTION AND TESTING

26 12 19.10 05/19 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED

TRANSFORMERS

26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM

26 24 13 08/21 SWITCHBOARDS

26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION

26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS

UNDER 600 VOLTS

26 35 43 08/21 400-HERTZ (HZ) SOLID STATE FREQUENCY

CONVERTER

26 35 44 08/21 270 VDC SOLID STATE CONVERTER

26 35 44.00 20 02/18 270 VDC SOLID STATE GROUND POWER UNIT

26 41 00 11/13 LIGHTNING PROTECTION SYSTEM

26 51 00 5/20, CHG 2: 11/21 INTERIOR LIGHTING

26 56 00 8/21 EXTERIOR LIGHTING

26 56 20 02/19 AIRFIELD AND HELIPORT LIGHTING AND

VISUAL NAVIGATION AIDS

DIVISION 27 - COMMUNICATIONS

27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING

SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 76 08/11 INTERIOR FIRE ALARM AND MASS

NOTIFICATION SYSTEM

DIVISION 31 - EARTHWORK

31 00 00.00 06 07/18 EARTHWORK

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT

32 11 23 05/22 GRADED CRUSHED AGGREGATE AND AGGREGATE

BASE COURSES

32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS

32 12 15.13 11/20 ASPHALT PAVING FOR AIRFIELDS

32 12 16.16 11/20 HOT-MIX ASPHALT (HMA) FOR ROADS

32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR

ROADS AND SITE FACILITIES

32 13 14.13 08/19 CONCRETE PAVING FOR AIRFIELDS AND

OTHER HEAVY DUTY PAVEMENTS

32 13 73.19 04/08 COMPRESSION CONCRETE PAVING JOINT

SEALANT

32 16 19 05/18 CONCRETE SIDEWALKS

32 17 23 08/16 PAVEMENT MARKINGS

32 31 13.53 11/21 ORNAMENTAL PICKET FENCES AND GATES

32 92 19 08/17 SEEDING

DIVISION 33 - UTILITIES

33 11 00 02/18 WATER UTILITY DISTRIBUTION PIPING

33 16 15 04/08 WATER STORAGE STEEL TANKS

33 30 00 05/18 SANITARY SEWERAGE

PROJECT TABLE OF CONTENTS Page 4

33 40 00 11/21 STORMWATER UTILITIES

33 51 15 08/19 NATURAL-GAS / LIQUEFIED PETROLEUM GAS

DISTRIBUTION PIPELINES

33 71 02 02/15 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

DIVISION 34 - TRANSPORTATION

34 73 16 11/19 AIRFIELD GROUNDING

DIVISION 46 - WATER AND WASTEWATER EQUIPMENT

46 25 14 02/11 COALESCING OIL-WATER SEPARATORS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 5

Amendment 0001***********************************************************

SECTION 09 54 60

Amendment 0001

LINEAR METAL CEILING SYSTEM

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C636/C636M (2013) Standard Practice for Installation of Metal Ceiling Suspension Systems for Acoustical Tile and Lay-In Panels

ASTM E580/E580M (2022) Standard Practice for Installation of Ceiling Suspension Systems for Acoustical Tile and Lay-in Panels in Areas Subject to Earthquake Ground Motions

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-02 Shop Drawings

Drawings; G RO

SD-03 Product Data

Ceiling Systems; G RO

Manufacturer's Published Literature, Including Specifications; G RO

Recycled Content; S

SD-04 Samples

Ceiling Tile; G RO

1.3 QUALITY ASSURANCE

1.3.1 Manufacturer/Installer Qualifications

Provide metal ceiling system components produced by a single manufacturer with a minimum 5 years' experience in actual production of specified

SECTION 09 54 60 Page 1 products and with resources to provide consistent quality in appearance and physical properties, without delaying the work.

Provide suspension system components produced by a single manufacturer to provide compatible components for a complete metal ceiling system installation.

Perform installations using a firm with installers having no less than 3 years of successful experience on projects of similar size and requirements.

1.4 CERTIFICATIONS

1.4.1 Product Certification

Manufacturer's certifications that products comply with specified requirements and governing codes including product data, laboratory test reports and research reports showing compliance with specified standards.

1.4.2 Qualification Data

1.4.2.1 Test Reports

Certified reports from independent agency substantiating structural compliance to wind loads and other governing requirements.

1.4.2.2 Certificates

Data substantiating manufacturer and installer qualifications.

Certified data attesting fire rated materials comply with specifications.

1.4.2.3 Manufacturer's Instructions

Detailed installation instructions and maintenance data.

1.4.3 Recycled Content

Product shall contain a minimum recycled content of 30 percent pre-consumer, 40 percent post-consumer.

1.5 SHOP DRAWINGS

Submit shop drawings for reflected ceiling plans (RCPs), drawn to scale, and indicating penetrations and ceiling mounted items. Show the following details:

a. Reflected ceiling plan(s): Indicating metal ceiling layout, ceiling mounted items and penetrations.

b. Suspension system, carrier and component layout.

c. Details of system assembly and connections to building components.

1.6 DELIVERY, STORAGE, AND HANDLING

Deliver materials to the site in the manufacturer's original unopened containers with brand name and type clearly marked. Carefully handle and store materials in dry, watertight enclosures. Carefully place on skids, SECTION 09 54 60 Page 2 to damage from moisture and other construction activities. Handle components to prevent damage to surfaces and edges, and to prevent distortion and other physical damage.

1.7 WARRANTY

Provide manufacturer's warranty to repair or replace defective materials and workmanship including but not limited to, sagging and warping of panels and rusting and of grid systems, for a period of 1 year from date of final acceptance of the work.

1.8 MAINTENANCE AND EXTRA MATERIAL

1.8.1 Maintenance Instructions

Provide manufacturers standard maintenance and cleaning instructions for finishes provided.

1.8.2 Extra Materials

Furnish extra materials described below that match products installed, are packaged with protective covering for storage, and are identified with labels describing contents. Only typical system components are included with attic stock.

a. Acoustical metal ceiling pan units: Full-size units equal to 2 percent of amount installed.

b. Ceiling suspension system components: Quantity of each grid and exposed component equal to 2 percent of amount installed.

PART 2 PRODUCTS

2.1 LINEAR METAL CEILING SYSTEM

2.1.1 Samples for Verification

Full-size units (or as specified below) of each type of ceiling assembly indicated; in sets for each color, texture, and pattern specified, showing the full range of variations expected in these characteristics. Submit ceiling tile samples for each type specified:

a. 11-inch square metal panel units.

b. 11-inch long samples of each exposed molding or trim.

c. 11-inch long samples of each suspension component.

2.1.2 Materials

Linear panels for exterior installations.

a. Panel Profile Type: Box 4, roll formed, 0.032 inch, exterior inch thick aluminum with square edges; 3-5/32 inch wide, 5/8 inch deep with 27/32-inch reveal to form a 4-inch module.

(1) Panel length: As indicated on drawings.

(2) Closure:

SECTION 09 54 60 Page 3

(a) Flat recessed closure: 5/8-inch wide roll-formed aluminum hat-shaped closure panel to snap-fit between ceiling panels; black finish.

(3) Perforation: Non-perforated.

b. Panel Finish:

(1) Paint: Powder coat (0.025- or 0.032-inch exterior). Color to match Faux Wood Columns.

2.2 METAL SUSPENSION SYSTEM

a. Carrier:

(1) Universal hat-shaped.

(2) 0.038-inch roll-formed aluminum section with hook-shaped tabs spaced to receive ceiling panels at 2 inches on center and 27/32 inch apart.

(3) Support holes spaced 4 inches on center.

(4) Finish: Factory applied black enamel.

b. Hanger Wire: 12-gage galvanized carbon steel hanger wire.

c. Seismic/wind uplift compression struts.

2.3 ACCESSORY MATERIALS

2.3.1 Panel Splice

Formed aluminum insert designed to snap-fit between ends of two ceiling panels. Finish: Black.

2.4 FINISHES

Use manufacturer's full range textures, patterns and finishes as specified for panel units and suspension system members. Treat ceiling suspension system components to inhibit corrosion.

PART 3 EXECUTION

3.1 EXAMINATION

Examine substrates and structural framing to which acoustical metal panels attach or abut, with Installer present, for compliance with requirements specified in this and other sections that affect installation and anchorage, and other conditions affecting performance of metal panel ceilings.

Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

Furnish layouts for anchors, clips, and other ceiling anchors whose

SECTION 09 54 60 Page 4 installation is specified in other sections.

Measure each ceiling area and establish layout of acoustical metal pan units to balance border widths at opposite edges of each ceiling. Avoid using less than half-width units at borders, and comply with layout shown on reflected ceiling plans.

Survey substrate for wall attachment to assure squareness and proper elevation for wall panel installation.

3.3 INSTALLATION

Install acoustical metal pan ceilings, per manufacturers shop drawings provided, per manufacturer's written instructions and to comply with publications referenced below:

a. CISCA: Ceiling Systems Handbook.

b. Standard for Ceiling Suspension System Installations: ASTM C636/C636M.

c. Standard for Ceiling Suspension Systems Requiring Seismic Restraint:

ASTM E580/E580M .

d. IBC (International Building Code) standard for seismic zone for local area.

Suspend ceiling hangers from building's approved structural substrates and as follows:

a. Install hangers plumb and free from contact with insulation or other objects within ceiling plenum that are not part of supporting structure or of ceiling suspension system.

b. Splay hangers only where required to miss obstructions; offset resulting horizontal forces by bracing, counter-splaying, or other equally effective means.

c. Where width of ducts and other construction within ceiling plenum produce hanger spacings that interfere with location of hangers at spacing required to support standard suspension system members, install supplemental suspension members and hangers in form of trapezes or equivalent devices. Size supplemental suspension members and hangers to support ceiling loads within performance limits established by referenced standards and publications.

d. Where used secure wire hangers to ceiling suspension members and to supports above with a minimum of three tight turns. Connect hangers directly either to structures or to inserts, eye screws, or other devices that are secure; that are appropriate for substrate; and that will not deteriorate or otherwise fail due to age, corrosion, or elevated temperatures.

e. Space hangers not more than 48 inches on center, along each member supported directly from hangers, unless otherwise indicated; and provide hangers not more than 8 inches from ends of each member.

Supply supporting calculations from licensed Structural Engineer verifying hanger spacing meets all requirements, when spacing exceed those recommended.

SECTION 09 54 60 Page 5

f. Fine level grid to 1/8 inch in 10 feet from specified elevation(s), square and true.

g. Adjust suspension system runners so they are square (within 0.5 degree from 90 degrees) and securely interlocked with one another. Remove and replace dented, bent, or kinked members.

Secure bracing wires to ceiling suspension members and to supports acceptable to Architect/Engineer and or inspector. Suspend bracing from building's structural members and/or structural deck, as required for hangers, without attaching to permanent metal forms, steel deck, or steel deck tabs(unless directed otherwise).

Install edge moldings and trim of type indicated at perimeter of acoustical ceiling area and where necessary to conceal edges of acoustical metal pan. Method of edge trim attachment and design of edge trims to be approved by Architect.

a. Screw attach moldings to substrate at intervals not more than 18 inches o.c. and not more than 6 inches from ends, leveling with ceding suspension system to a tolerance of 1/8 inch in 10 feet. Miter corners accurately and connect securely.

b. Do not use exposed fasteners, including pop rivets, on moldings and trim without prior written approval or unless detailed otherwise.

Scribe and cut acoustical metal panel units for accurate fit at penetrations by, other work through ceilings. Stiffen edges of cut units as required to eliminate evidence of buckling or variations in flatness exceeding referenced standards for stretcher-leveled metal sheet.

Install acoustical metal panel units in coordination with suspension system.

a. Align joints in adjacent courses to form uniform, straight joints parallel to room axis in both directions, unless otherwise indicated.

Install directionally patterned or textured panels in directions indicated on approved shop drawings. Panel-joints shall flow smoothly and in a straight line within 1/8 inch in 10 feet. Intersections shall be continuous.

b. Fit adjoining units to form flush, tight joints. Scribe and cut units for accurate fit at borders and around construction penetrating ceiling.

c. Remove protective film from panels only when space is completely clean and free of airborne particles. Use white cotton gloves for final installation of panels into grid system.

3.4 ADJUST AND CLEAN

Adjust components to provide uniform tolerances. Replace all ceiling panels that are scratched, dented or otherwise damaged. Clean exposed surfaces with non-solvent, non-abrasive commercial type cleaner.

-- End of Section -- ***********************************************************Amendment 0001

SECTION 09 54 60 Page 6

SECTION 09 54 60 Page 7

Amendment 0001***********************************************************

SECTION 13 31 34

Amendment 0001

BIRD NETTING

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM A153/A153M (2016a) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Manufacturer's Qualifications; G RO

Installer's Qualifications; G

SD-02 Shop Drawings

Erection Plan; G RO

SD-03 Product Data

Fabric (Membrane); G RO

Accessories; G RO

Product Data; G RO

SD-04 Samples

Fabric (Membrane); G RO

SD-11 Closeout Submittals

Manufacturer's Warranty; G RO

SECTION 13 31 34 Page 1

1.3 DESIGN REQUIREMENTS

The bird netting membrane structure depicted in the Construction Documents is representative of a permanent, custom designed, prefabricated, commercially available system. Design and fabricate the bird netting membrane to fit within the space allocated, including support for accessory items, and in accordance with the criteria specified herein.

1.3.1 Accessory Items

Provide points of attachment to support and brace all accessory items.

Accessory items are indicated in the contract documents.

1.3.2 Fabric Membrane System

Design to form a continuous, uninterrupted cover over the structural framing. Cover the entire hangar structure with the fabric membrane in accordance with the design drawings included with this specification.

1.3.2.1 Bird Netting Membrane Joints and Seams

Provide adjacent cladding sections with a mechanical tensioning system which allows the bird netting membrane to be fully tensioned around the structure. Maintain proper gaps between sections to allow sufficient distance to enable full tensioning of the material resulting in the bird netting membrane secured tightly and neatly over the structural frame with a remaining range of adjustment.

1.4 QUALITY ASSURANCE

1.4.1 Manufacturer's Qualifications

Provide a complete system from a manufacturer who has regularly engaged in the design, fabrication, erection, and service of bird netting membrane of the type and size required for this project. The manufacturer shall have at least 5 years of similar design experience in membrane clad, structures.

Contractor must submit written evidence of each of the above requirements for similar past designs, fabrications and installations and include a list of the names, locations, contact information of owners, installation dates, overall sizes, features, and other relevant information for experience, qualifications and quality evaluation.

1.4.2 Installer's Qualifications

Installation of the bird netting membrane shall be performed in accordance with approved shop drawings and manufacturers written instructions.

Installers shall be skilled and experienced in the erection of similar bird netting membrane clad structures of the type specified herein, including height and clear span.

Installers must submit written evidence of each of the above requirements for similar past designs installations and include a list of the names, locations, contact information of owners, installation dates, overall sizes, features, and other relevant information for experience, qualifications, and quality evaluation.

SECTION 13 31 34 Page 2

1.5 SHIPPING, HANDLING AND STORAGE

Clearly mark all individual parts or bundles and packages of identical parts for identification or otherwise identify by clear installation procedures. Package bolts and fasteners according to type, size, and length. Deliver materials in original rolls, packages, containers, boxes, or crates bearing the manufacturer's name, brand, and project reference numbers.

Handle carefully to prevent damage. At no time shall materials be dropped, thrown, or dragged over the transport equipment or the ground.

Store materials and equipment in dry locations with adequate ventilation, free from dust and water, and to permit access for inspection and handling. Remove damaged items that cannot be restored to like-new condition and provide new items.

1.6 WARRANTY

For the bird netting membrane, provide a warranty for all materials and workmanship for a period of 10 years beginning from the date of final acceptance. Include full repair or replacement coverage, including labor and materials.

PART 2 PRODUCTS

2.1 BIRD NETTING MEMBRANE

Provide new materials without defects and free of repairs. Provide materials of the quality and requirements specified herein.

Submit bird netting membrane drawings showing details of construction and installation. Show size, shapes, and thickness of materials; hardware;

joints; connections; reinforcing; devices; support/bracing for accessory items.

2.1.1 Bird Netting

a. Material: Ultra-violet stabilized polyethylene (HDPE) abrasion, flame, rot, and UV resistant.

b. Construction: 3 by 2 ply. Three groups of two strands are wrapped into a tight, rope-like group of six. Meets ISO 1806 protocol mesh test.

c. Breaking strength: 50 pounds per strand.

d. Size: 3/4 inch knotted seam set knot square mesh.

e. Sizes: 25 feet by 25 feet, 25 feet by 50 feet, 25 feet by 75 feet, 50 Feet by 50 feet, 50 feet by 75 feet, and 50 feet by 100 feet.

Unlimited custom sizes up to 500 feet by 500 feet.

f. Colors: Black.

2.1.2 Hardware

Hot-dip galvanize all hardware in accordance with ASTM A153/A153M .

Hardware components:

SECTION 13 31 34 Page 3

a. Corner bolts: Galvanized steel.

b. Cable: 5/64 inch and 1/16 inch diameter perimeter cable in galvanized steel.

c. Turnbuckles: small, medium and large in galvanized steel.

d. Miscellaneous fasteners, brackets and clips. All additional mounting systems in galvanized steel.

2.2 LIGHTING

Coordinate the frame supported membrane structure with the light fixtures in accordance with Drawings.

2.3 FALL PROTECTION

Coordinate bird netting membrane with the fall protection system in accordance with Drawings and Section 11 01 05 FALL PROTECTION SYSTEMS.

PART 3 EXECUTION

3.1 INSTALLATION

3.1.1 Corner Attachments

Corner attachments are under the most pressure and must be the strongest part of the system otherwise the entire system Will fail. Corner attachments are used where the cables begin/end and where the cable turns corners. If a square building is being netted, corner attachments will be placed in all four corners of the building.

Corner attachments include:

a. Galvanized or stainless screw eyes which are used for wood.

b. Expanding net bolts which are used for steel.

c. Eye bolts and nuts which are used for steel.

3.1.2 Intermediate attachments

Intermediate attachments hold cable to the structure. The purpose of intermediate attachments is to hold the cable tight against the wall preventing it from bowing and not allowing birds room to enter/exit the area of coverage. Installation of Intermediate attachments should be every 2 to 3 feet. For sparrows, swallows and smaller birds, intermediate attachments should be placed no more than 2 feet apart.

Intermediate attachments include:

a. Multipurpose cable brackets which are anchor rivets and split pins.

Use in wood or concrete frames.

b. Hooks which are hammered directly into concrete.

c. Girder clips which are used for steel.

SECTION 13 31 34 Page 4

3.1.3 Straining wire/cable and ferrules

Once the corner and intermediate attachments have been installed, the straining wire must be run. Straining wire, also called cable, is galvanized. Ferrules are used at the first corner attachment and then later at the turnbuckle.

Installation:

a. Two copper ferrules are run through the end of the cable.

b. The cable looped through the first corner attachment and then back through the ferrules.

c. The ferrules are then secured and crimped to lock the cable Into place with a ratchet crimper. This creates a strong loop.

d. The cable is then run through all intermediate attachments and finally through the turnbuckle at the end of the cable run.

e. Looping and crimping cable through the turnbuckle is repeated. See the section below for correct method on installing turnbuckles.

3.1.4 Turnbuckles

Turnbuckles are available in medium or large and galvanized or stainless steel. Turnbuckles must be well anchored since they are exerting a great deal of tension on the cable/straining wire.

a. Medium turnbuckles are designed for cables up to 75 feet.

b. Large turnbuckles are designed for cables 75 feet and above.

c. Installation:

(1) The turnbuckle must be open all the way.

(2) The cable is pulled as tight as possible through the turnbuckle before the loop is finally crimped. As much tension as possible must be taken up before crimping.

(3) The turnbuckle is tightened using a screwdriver.

(4) This must be done carefully as not to pull out the fasteners/eyehooks when tightening the cable via the turnbuckle.

3.1.5 Hog Rings

Netting is attached to the straining wire/cable with hog rings using a hog ring tool.

a. Installation: One hog ring loop per square for 2 inch or 3/4 inch net.

3.1.6 Miscellaneous

This is a general installation overview. More complicated installations may require additional hardware and/or other products.

SECTION 13 31 34 Page 5

3.2 MOUNTING SYSTEMS

Solid steel: For corner attachments use corner bolts with lock nuts or multipurpose fasteners with powder actuated fire-in pins. Use multipurpose fasteners with powder actuated fire-in pins, for Intermediate attachments.

Steel I-beams: For corner attachments use corner bolts with lock nuts and for intermediate attachments, use the appropriate size girder/flange clip.

Sheet metal: Use multipurpose fasteners with self-tapping screws for corner/intermediate attachments.

Upon completion of installing corner bolts and intermediate attachments, using a crimping tool and ferrules attach cable to a corner bolt. Then guide the cable through the intermediate attachments (straight runs of cable are the only acceptable way to install cable).

At the opposite end of the cable run, a turnbuckle will be installed using ferrules and a crimping tool to tension the cable.

3.3 EXAMINATION

Examine installation area. Notify contracting officer of detrimental work conditions. Do not proceed until conditions are corrected.

3.4 ADJUSTING AND CLEANING

Remove debris and waste materials from project site. Inspect finished installation. Make adjustments required per manufacturer's installation guidelines.

3.5 EXTRA MATERIALS

Provide a patch kit with color matched fabric membrane and associated repair materials and tools. Supply approximately 45 square feet of fabric for bird netting membrane structure.

3.6 OPERATION AND MAINTENANCE DATA

Provide routine inspection, maintenance, cleaning and repair instructions for the bird netting membrane structure, including intervals. Include detailed instructions for re-tensioning, if required. Include inspection recommendations for assessing signs of fabric degradation, fabric connection issues, tightness or any additional manufacturer items deemed critical to the performance of the structure.

***********************************************************Amendment 0001

-- End of Section --

SECTION 13 31 34 Page 6

SECTION 23 09 00

INSTRUMENTATION AND CONTROL FOR HVAC

02/19

Amendment 0001

PART 1 GENERAL

1.1 SUMMARY

Provide a complete Direct Digital Control (DDC) system, except for the Front End which is specified in Section 25 10 10 UTILITY MONITORING AND CONTROL (UMCS) FRONT END AND INTEGRATION, suitable for the control of the heating, ventilating and air conditioning (HVAC) and other building-level systems as indicated and shown and in accordance with Section 23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC, Section 23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING CONTROL SYSTEMS for BACnet or Niagara BACnet systems, and other referenced Sections.

Amendment 0001***********************************************************

1.1.1 System Requirements

Provide systems meeting the requirements this Section and other Sections referenced by this Section, and which have the following characteristics:

a. Control System shall be Seimens BACnet and tie into the existing base Seimens Desigo front end system.

b. The system implements the control sequences of operation shown in the Contract Drawings using DDC hardware to control mechanical and electrical equipment.

c. The system meet the requirements of this specification as a stand-alone system and does not require connection to any other system.

d. Control sequences reside in DDC hardware in the building. The building control network is not dependent upon connection to a Utility Monitoring and Control System (UMCS) Front End or to any other system for performance of control sequences. To the greatest extent practical, the hardware performs control sequences without reliance on the building network , unless otherwise pre-approved by the Contracting Officer .

e. The hardware is installed such that individual control equipment can be replaced by similar control equipment from other equipment manufacturers with no loss of system functionality.

f. All necessary documentation, configuration information, programming tools, programs, drivers, and other software are licensed to and otherwise remain with the Government such that the Government or their agents are able to perform repair, replacement, upgrades, and expansions of the system without subsequent or future dependence on the Contractor, Vendor or Manufacturer.

g. Sufficient documentation and data, including rights to documentation and data, are provided such that the Government or their agents can execute work to perform repair, replacement, upgrades, and expansions

SECTION 23 09 00 Page 1 of the system without subsequent or future dependence on the Contractor, Vendor or Manufacturer.

h. Hardware is installed and configured such that the Government or their agents are able to perform repair, replacement, and upgrades of individual hardware without further interaction with the Contractor, Vendor or Manufacturer.

i. All Niagara Framework components have an unrestricted interoperability license with a Niagara Compatibility Statement (NiCS) following the Tridium Open NiCS Specification and have a value of "ALL" for "Station Compatibility In", "Station Compatibility Out", "Tool Compatibility In" and "Tool Compatibility Out". Note that this will result in the following entries in the license file:

accept.station.in="*" accept.station.out="*" accept.wb.in="*" accept.wb.out="*"

***********************************************************Amendment 0001

1.1.2 End to End Accuracy

Select products, install and configure the system such that the maximum error of a measured value as read from the DDC Hardware over the network is less than the maximum allowable error specified for the sensor or instrumentation.

1.1.3 Verification of Dimensions

After becoming familiar with all details of the work, verify all dimensions in the field, and advise the Contracting Officer of any discrepancy before performing any work.

1.1.4 Drawings

The Government will not indicate all offsets, fittings, and accessories that may be required on the drawings. Carefully investigate the mechanical, electrical, and finish conditions that could affect the work to be performed, arrange such work accordingly, and provide all work necessary to meet such conditions.

1.2 RELATED SECTIONS

Related work specified elsewhere:

a. Section 23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING CONTROL SYSTEMS for BACnet systems with or without Niagara Framework .

b. Section 23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC.

c. Section 25 08 10 UTILITY MONITORING AND CONTROL SYSTEMS TESTING .

d. Section 25 10 10 UTILITY MONITORING AND CONTROL SYSTEMS (UMCS) FRONT

END AND INTEGRATION.

e. Section 25 05 11.01 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS

ENERGY MANAGEMENT CONTROL SYSTEM (EMCS) BUILDING LEVEL ONLY.

SECTION 23 09 00 Page 2

f. Section 01 46 00.00 06 TOTAL BUILDING COMMISSIONING.

1.3 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING

ENGINEERS (ASHRAE)

ASHRAE 135 (2016) BACnet—A Data Communication Protocol for Building Automation and Control Networks

ASHRAE FUN IP (2021) Fundamentals Handbook, I-P Edition

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE C62.41 (1991; R 1995) Recommended Practice on Surge Voltages in Low-Voltage AC Power Circuits

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA 250 (2020) Enclosures for Electrical Equipment (1000 Volts Maximum)

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2020; ERTA 20-1 2020; ERTA 20-2 2020;

ERTA 20-3 2020; TIA 20-1; TIA 20-2; TIA

20-3; TIA 20-4; TIA 20-5; TIA 20-6; TIA

20-7; TIA 20-8; TIA 20-9; TIA 20-10; TIA

20-11; TIA 20-12; TIA 20-13; TIA 20-14;

TIA 20-15; TIA 20-16; ERTA 20-4 2022)

National Electrical Code

NFPA 90A (2021) Standard for the Installation of Air Conditioning and Ventilating Systems

TRIDIUM, INC (TRIDIUM)

Niagara Framework (2012) NiagaraAX User's Guide

Tridium Open NiCS (2005) Understanding the NiagaraAX Compatibility Statement (NiCS)

UNDERWRITERS LABORATORIES (UL)

UL 5085-3 (2006; Reprint Jan 2022) Low Voltage Transformers - Part 3: Class 2 and Class 3 Transformers

1.4 DEFINITIONS

The following list of definitions includes terms used in Sections referenced by this Section and are included here for completeness. The

SECTION 23 09 00 Page 3 definitions contained in this Section may disagree with how terms are defined or used in other documents, including documents referenced by this Section. The definitions included here are the authoritative definitions for this Section and all Sections referenced by this Section.

After each term the protocol related to that term is included in parenthesis.

1.4.1 Alarm Generation (All protocols)

Alarm Generation is the monitoring of a value, comparison of the value to alarm conditions and the creation of an alarm when the conditions set for the alarm are met. Note that this does NOT include delivery of the alarm to the final destination (such as a user interface) - see paragraph ALARM ROUTING in Section 25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS)

FRONT END AND INTEGRATION.

1.4.2 Building Automation and Control Network (BACnet) (BACnet)

The term BACnet is used in two ways. First meaning the BACnet Protocol Standard - the communication requirements as defined by ASHRAE 135 including all annexes and addenda. The second to refer to the overall technology related to the ASHRAE 135 protocol.

1.4.3 BACnet Advanced Application Controller (B-AAC) (BACnet)

A hardware device BTL Listed as a B-AAC, which is required to support BACnet Interoperability Building Blocks (BIBBs) for scheduling and alarming, but is not required to support as many BIBBs as a B-BC.

1.4.4 BACnet Application Specific Controller (B-ASC) (BACnet)

A hardware device BTL Listed as a B-ASC, with fewer BIBB requirements than a B-AAC. It is intended for use in a specific application.

1.4.5 BACnet Building Controller (B-BC) (BACnet)

A hardware device BTL Listed as a B-BC. A general-purpose, field-programmable device capable of carrying out a variety of building automation and control tasks including control and monitoring via direct digital control (DDC) of specific systems and data storage for trend information, time schedules, and alarm data. Like the other BTL Listed controller types (B-AAC, B-ASC etc.) a B-BC device is required to support the server ("B") side of the ReadProperty and WriteProperty services, but unlike the other controller types it is also required to support the client ("A") side of these services. Communication between controllers requires that one of them support the client side and the other support the server side, so a B-BC is often used when communication between controllers is needed.

1.4.6 BACnet Broadcast Management Device (BBMD) (BACnet)

A communications device, typically combined with a BACnet router. A BBMD forwards BACnet broadcast messages to BACnet/IP devices and other BBMDs connected to the same BACnet/IP network. Each IP subnet that is part of a BACnet/IP network must have at least one BBMD. Note there are additional restrictions when multiple BBMDs share an IP subnet.

SECTION 23 09 00 Page 4

1.4.7 BACnet/IP (BACnet)

An extension of BACnet, Annex J, defines the use of a reserved UDP socket to transmit BACnet messages over IP networks. A BACnet/IP network is a collection of one or more IP subnets that share the same BACnet network number. See also paragraph BACNET BROADCAST MANAGEMENT DEVICE.

1.4.8 BACnet Internetwork (BACnet)

Two or more BACnet networks, connected with BACnet routers. In a BACnet Internetwork, there exists only one message path between devices.

1.4.9 BACnet Interoperability Building Blocks (BIBBs) (BACnet)

A BIBB is a collection of one or more ASHRAE 135 Services intended to define a higher level of interoperability. BIBBs are combined to build the BACnet functional requirements for a device in a specification. Some BIBBs define additional requirements (beyond requiring support for specific services) in order to achieve a level of interoperability. For example, the BIBB DS-V-A (Data Sharing-View-A), which would typically be used by a front-end, not only requires the client to support the ReadProperty Service, but also provides a list of data types (Object / Properties) which the client must be able to interpret and display for the user.

In the BIBB shorthand notation, -A is the client side and -B is the server side.

The following is a list of some BIBBs used by this or referenced Sections:

DS-COV-A Data Sharing-Change of Value (A side)

DS-COV-B Data Sharing-Change of Value (B side)

NM-RC-B Network Management-Router Configuration (B side)

DS-RP-A Data Sharing-Read Property (A side)

DS-RP-B Data Sharing-Read Property (B side)

DS-RPM-A Data Sharing-Read Property Multiple (A Side)

DS-RPM-B Data Sharing-Read Property Multiple (B Side)

DS-WP-A Data Sharing-Write Property (A Side)

DM-TS-B Device Management-Time Synchronization (B Side)

DM-UTC-B Device Management-UTC Time Synchronization (B Side)

DS-WP-B Data Sharing-Write Property (B side)

SCHED-E-B Scheduling-External (B side)

SECTION 23 09 00 Page 5

The following is a list of some BIBBs used by this or referenced Sections:

DM-OCD-B Device Management-Object Creation and Deletion (B side)

AE-N-I-B Alarm and Event-Notification Internal (B Side)

AE-N-E-B Alarm and Event-Notification External (B Side)

T-VMT-I-B Trending-Viewing and Modifying Trends Internal (B Side)

T-VMT-E-B Trending-Viewing and Modifying Trends External (B Side)

1.4.10 BACnet Network (BACnet)

In BACnet, a portion of the control Internetwork consisting of one or more segments connected by repeaters. Networks are separated by routers.

1.4.11 BACnet Operator Display (B-OD) (BACnet)

A basic operator interface with limited capabilities relative to a B-OWS.

It is not intended to perform direct digital control. A B-OD profile could be used for LCD devices, displays affixed to BACnet devices, handheld terminals or other very simple user interfaces.

1.4.12 BACnet Segment (BACnet)

One or more physical segments interconnected by repeaters ( ASHRAE 135).

1.4.13 BACnet Smart Actuator (B-SA) (BACnet)

A simple actuator device with limited resources intended for specific applications.

1.4.14 BACnet Smart Sensor (B-SS) (BACnet)

A simple sensing device with limited resources.

1.4.15 BACnet Testing Laboratories (BTL) (BACnet)

Established by BACnet International to support compliance testing and interoperability testing activities and consists of BTL Manager and the BTL Working Group (BTL-WG). BTL also publishes Implementation Guidelines.

1.4.16 BACnet Testing Laboratories (BTL) Listed (BACnet)

A device that has been listed by BACnet Testing Laboratory. Devices may be certified to a specific device profile, in which case the listing indicates that the device supports the required capabilities for that profile, or may be listed as "other".

1.4.17 Binary (All protocols)

A two-state system where an "ON" condition is represented by a high signal level and an "OFF" condition is represented by a low signal level.

'Digital' is sometimes used interchangeably with 'binary'.

SECTION 23 09 00 Page 6

1.4.18 Broadcast (BACnet)

Unlike most messages, which are intended for a specific recipient device, a broadcast message is intended for all devices on the network.

1.4.19 Building Control Network (BCN) (All protocols)

The network connecting all DDC Hardware within a building (or specific group of buildings).

1.4.20 Building Point of Connection (BPOC) (All protocols)

A FPOC for a Building Control System. (This term is being phased out of use in preference for FPOC but is still used in some specifications and criteria. When it was used, it typically referred to a piece of control hardware. The current FPOC definition typically refers instead to IT hardware.)

1.4.21 Commandable (All protocols)

See Overridable.

1.4.22 Commandable Objects (BACnet)

Commandable Objects have a Commandable Property, Priority_Array, and Relinquish_Default Property as defined in ASHRAE 135, Clause 19.2, Command Prioritization.

1.4.23 Configurable (All protocols)

A property, setting, or value is configurable if it can be changed via hardware settings on the device, via the use of engineering software or over the control network from the front end, and is retained through (after) loss of power.

In a Niagara Framework BACnet system, a property, setting, or value is configurable if it can be changed via one or more of:

(1) via BACnet services (including proprietary BACnet services)

(2) via hardware settings on the device

(3) via the Niagara Framework

Note this is more stringent than the ASHRAE 135…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .