This solicitation is for the new construction of a two-story, 22,564 square foot facility to house squadron operations for the Department of the Army Corps of Engineers in Minneapolis, Minnesota. Functional requirements for the facility include administrative office space, honor guard equipment storage, conference rooms for training and bid openings, and operational functions such as break and kitchen areas. The project must comply with antiterrorism and force protection requirements. Offerors should also note that the facility is intended to house functions including an emergency operations center, military personnel section, ID processing, testing section, sustainment section, and mission planning.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912QR21R0068-0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMDT 0003 SUMMARY OF CHANGES

Amendment Number: 0003 Project Title: Mission Support Group Facility Project Location: Minneapolis-St. Paul ARS, MN Date of Amendment: October 21, 2021

The purpose of Amendment 0003 to the design documents for the new construction of the Mission Support Group Facility is to revise the Ready To Advertise documents. Changes are outlined below.

a. The following SPECIFICATIONS have been REPLACED in their entirety:

1) 03 30 00 CAST‐IN‐PLACE CONCRETE

2) 10 53 00 MANUFACTURED CANOPY

b. The following DOCUMENTS have been REPLACED in their entirety:

1) PRICE BREAKOUT SCHEDULE

SECTION 00 10 00 - SOLICITATION

The following have been modified:

PRICE BREAKOUT SCHEDULE

PRICE BREAKOUT SCHEDULE

PROJECT: Mission Support Group Facility, DBB LOCATION: Minneapolis-Saint Paul Air Reserve Station, MN

PROPOSER’S NAME:

BASE PROPOSAL

Item No.

Description

New Construction, Mission Support Group

Unit

JOB

Amount __

0002 Site Work JOB $ __________

Subtotal

OPTION ITEMS

0003 Option‐1 – Parking Lot at B852 JOB $ _____________

0004 Option‐2 – Modular Brick Veneer – Exterior Finish

JOB $ _ ________

0005 Option‐3 – Primary System Loop Feed JOB $ ____________

0006 Option‐4 – Telecom Hardware & Active Electronics

JOB $ ___________

0007 Option‐5 – Furniture, Fixtures, and Equipment

(FFE)

JOB $ ____________

TOTAL OPTIONS $ _____________

TOTAL BASE PROPOSAL + OPTION ITEMS $

W912QR21R0068

Description of Base Proposal Items

(a) Item No. 0001 "New Construction Mission Support Group" shall constitute full compensation for furnishing all materials, tools, labor costs, and other associated incidentals necessary to complete the design requirements of the MISSION SUPPORT GROUP FACILITY as required by the contract document drawings and specifications, except that work covered by Items No. 0002, 0003, 0004, 0005, and 0006.

(b) Item No. 0002 "Site work" shall constitute full compensation for furnishing all materials, tools, labor costs, and other associated incidentals necessary to complete the design requirements of the MISSION SUPPORT GROUP FACILITY as required by the contract document drawings and specifications., except that work covered by Items No. 0001, 0003, 0004, 0005, and 0006.

Description of Option Items

(c) Option‐1, Item No. 0003 "Parking Lot at B852" shall constitute full compensation for furnishing all materials, tools, labor costs, and other associated incidentals necessary to complete the full construction of the parking lot at the demolished Building 852 site as indicated on Sheet C‐111. Option includes all asphalt paving, curb and gutter, islands, sidewalks and striping indicated.

This option may be exercised within 60 calendar days from Notice To Proceed.

(d) Option‐2, Item No. 0004 "Modular Brick Veneer – Exterior Finish" shall constitute full compensation for furnishing all materials, tools, labor costs, and other associated incidentals necessary to replace 3” Exterior Insulation and Finish System (EIFS) with brick veneer on the north, south, east, and west facades above the cast stone sill course as indicated on drawing sheets AE203 and AE204. Option includes cavity wall insulation, brick ties and cast stone headers and sills at windows.

This option may be exercised within 120 calendar days from Notice To Proceed.

(e) Option‐3, Item No. 0005 "Primary System Loop Feed" shall constitute full compensation for furnishing all materials, tools, labor costs, and other associated incidentals necessary to complete the installation of the primary system loop feed for the project.

This option may be exercised within 180 calendar days from Notice To Proceed.

(f) Option‐4, Item No. 0006 "Telecom Hardware & Active Electronics" shall constitute full compensation for furnishing all materials, tools, labor costs, and other associated incidentals necessary to complete the installation of telecommunications hardware and active electronic devices as scheduled on Sheet ET601.

This option may be exercised within 180 calendar days from Notice To Proceed.

(g) Option‐5, Item No. 0007 “Furniture, Fixtures, and Equipment (FFE)” shall constitute full compensation for furnishing all materials, tools, labor costs, and other associated incidentals necessary to complete the purchase and installation of all FFE items. Contractor shall purchase furniture including checking accuracy of all acknowledgements and schedules from manufacturers and making necessary corrections to ensure that the manufacturer has a correct understanding of the order and requirement. Contractor shall purchase furniture from the open market. If necessary, to meet project timeline requirements, furniture may be purchased using manufacturer’s quick‐ship programs or by coordinating factory times.

This option may be exercised within 300 days from Notice To Proceed.

(End of Summary of Changes)

Minneapolis-St. Paul ARS, MN (P2: 480584) CERTIFIED FINAL SUBMITTAL Mission Support Group Facility 01 JULY 2021

SECTION 03 30 00

CAST-IN-PLACE CONCRETE

05/14

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)

ACI 117 (2010; Errata 2011) Specifications for Tolerances for Concrete Construction and Materials and Commentary

ACI 121R (2008) Guide for Concrete Construction Quality Systems in Conformance with ISO

ACI 211.1 (1991; R 2009) Standard Practice for Selecting Proportions for Normal, Heavyweight and Mass Concrete

ACI 301 (2016) Specifications for Structural Concrete

ACI 302.1R (2015) Guide for Concrete Floor and Slab Construction

ACI 304.2R (1996; R 2008) Placing Concrete by Pumping Methods

ACI 304R (2000; R 2009) Guide for Measuring, Mixing, Transporting, and Placing Concrete

ACI 305R (2010) Guide to Hot Weather Concreting

ACI 306.1 (1990; R 2002) Standard Specification for Cold Weather Concreting

ACI 306R (2016) Guide to Cold Weather Concreting

ACI 308.1 (2011) Specification for Curing Concrete

ACI 318 (2014; Errata 1-2 2014; Errata 3-5 2015;

Errata 6 2016) Building Code Requirements for Structural Concrete and Commentary

ACI 347 (2004; Errata 2008; Errata 2012) Guide to Formwork for Concrete

ACI SP-15 (2011) Field Reference Manual: Standard Specifications for Structural Concrete ACI 301-05 with Selected ACI References

SECTION 03 30 00 Page 1

AMENDMENT 003

Amendment 0003

ACI SP-2 (2007; Abstract: 10th Edition) ACI Manual of Concrete Inspection

ACI SP-66 (2004) ACI Detailing Manual

AMERICAN HARDBOARD ASSOCIATION (AHA)

AHA A135.4 (1995; R 2004) Basic Hardboard

AMERICAN WELDING SOCIETY (AWS)

AWS D1.4/D1.4M (2011) Structural Welding Code - Reinforcing Steel

ASTM INTERNATIONAL (ASTM)

ASTM A1064/A1064M (2016b) Standard Specification for Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete

ASTM A53/A53M (2012) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless

ASTM A615/A615M (2016) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement

ASTM A706/A706M (2016) Standard Specification for Low-Alloy Steel Deformed and Plain Bars for Concrete Reinforcement

ASTM A934/A934M (2016) Standard Specification for Epoxy-Coated Prefabricated Steel Reinforcing Bars

ASTM A996/A996M (2016) Standard Specification for Rail-Steel and Axle-Steel Deformed Bars for Concrete Reinforcement

ASTM C1017/C1017M (2013; E 2015) Standard Specification for Chemical Admixtures for Use in Producing Flowing Concrete

ASTM C1077 (2016) Standard Practice for Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Laboratory Evaluation

ASTM C1107/C1107M (2014a) Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)

ASTM C1157/C1157M (2011) Standard Specification for Hydraulic Cement

ASTM C1218/C1218M (1999; R 2008) Standard Specification for

SECTION 03 30 00 Page 2

AMENDMENT 003

Water-Soluble Chloride in Mortar and Concrete

ASTM C1260 (2014) Standard Test Method for Potential Alkali Reactivity of Aggregates (Mortar-Bar Method)

ASTM C138/C138M (2016a) Standard Test Method for Density (Unit Weight), Yield, and Air Content (Gravimetric) of Concrete

ASTM C143/C143M (2015a) Standard Test Method for Slump of Hydraulic-Cement Concrete

ASTM C150/C150M (2016; E 2016) Standard Specification for Portland Cement

ASTM C1567 (2013) Standard Test Method for Potential Alkali-Silica Reactivity of Combinations of Cementitious Materials and Aggregate (Accelerated Mortar-Bar Method)

ASTM C1602/C1602M (2012) Standard Specification for Mixing Water Used in Production of Hydraulic Cement Concrete

ASTM C172/C172M (2014a) Standard Practice for Sampling Freshly Mixed Concrete

ASTM C173/C173M (2016) Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method

ASTM C192/C192M (2016a) Standard Practice for Making and Curing Concrete Test Specimens in the Laboratory

ASTM C231/C231M (2014) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method

ASTM C260/C260M (2010a; R 2016) Standard Specification for Air-Entraining Admixtures for Concrete

ASTM C295/C295M (2012) Petrographic Examination of Aggregates for Concrete

ASTM C31/C31M (2015a; E 2016) Standard Practice for Making and Curing Concrete Test Specimens in the Field

ASTM C311/C311M (2013) Sampling and Testing Fly Ash or Natural Pozzolans for Use as a Mineral Admixture in Portland-Cement Concrete

ASTM C33/C33M (2016) Standard Specification for Concrete Aggregates

ASTM C39/C39M (2016b) Standard Test Method for

SECTION 03 30 00 Page 3

Compressive Strength of Cylindrical Concrete Specimens

ASTM C42/C42M (2013) Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of Concrete

ASTM C494/C494M (2016) Standard Specification for Chemical Admixtures for Concrete

ASTM C552 (2016a) Standard Specification for Cellular Glass Thermal Insulation

ASTM C567/C567M (2014) Determining Density of Structural Lightweight Concrete

ASTM C578 (2016) Standard Specification for Rigid, Cellular Polystyrene Thermal Insulation

ASTM C591 (2016) Standard Specification for Unfaced Preformed Rigid Cellular Polyisocyanurate Thermal Insulation

ASTM C595/C595M (2016) Standard Specification for Blended Hydraulic Cements

ASTM C618 (2012a) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete

ASTM C78/C78M (2016) Standard Test Method for Flexural Strength of Concrete (Using Simple Beam with Third-Point Loading)

ASTM C920 (2014a) Standard Specification for Elastomeric Joint Sealants

ASTM C94/C94M (2016a) Standard Specification for Ready-Mixed Concrete

ASTM C989/C989M (2014) Standard Specification for Slag Cement for Use in Concrete and Mortars

ASTM D1751 (2004; E 2013; R 2013) Standard Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types)

ASTM D1752 (2004a; R 2013) Standard Specification for Preformed Sponge Rubber Cork and Recycled PVC Expansion

ASTM D2628 (1991; R 2011) Standard Specification for Preformed Polychloroprene Elastomeric Joint Seals for Concrete Pavements

ASTM D2835 (1989; R 2012) Lubricant for Installation of Preformed Compression Seals in Concrete

SECTION 03 30 00 Page 4

Pavements

ASTM D5759 (2012) Characterization of Coal Fly Ash and Clean Coal Combustion Fly Ash for Potential Uses

ASTM D6690 (2015) Standard Specification for Joint and Crack Sealants, Hot Applied, for Concrete and Asphalt Pavements

ASTM E1155 (2014) Standard Test Method for Determining Floor Flatness and Floor Levelness Numbers

ASTM E1643 (2011) Standard Practice for Selection, Design, Installation, and Inspection of Water Vapor Retarders Used in Contact with Earth or Granular Fill Under Concrete Slabs

ASTM E1745 (2011) Standard Specification for Water Vapor Retarders Used in Contact with Soil or Granular Fill under Concrete Slabs

ASTM E1993/E1993M (1998; R 2013; E 2013) Standard Specification for Bituminous Water Vapor Retarders Used in Contact with Soil or Granular Fill Under Concrete Slabs

ASTM E329 (2014a) Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction

ASTM E96/E96M (2016) Standard Test Methods for Water Vapor Transmission of Materials

CONCRETE REINFORCING STEEL INSTITUTE (CRSI)

CRSI 10MSP (2009; 28th Ed) Manual of Standard Practice

NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY (NIST)

NIST PS 1 (2009) DOC Voluntary Product Standard PS 1-07, Structural Plywood

1.2 DEFINITIONS

a. "Cementitious material" as used herein must include all portland cement, pozzolan, fly ash,and ground granulated blast-furnace slag.

b. "Exposed to public view" means situated so that it can be seen from eye level from a public location after completion of the building. A public location is accessible to persons not responsible for operation or maintenance of the building.

c. "Chemical admixtures" are materials in the form of powder or fluids that are added to the concrete to give it certain characteristics not obtainable with plain concrete mixes.

SECTION 03 30 00 Page 5

d. "Supplementary cementing materials" (SCM) include coal fly ash, granulated blast-furnace slag, natural or calcined pozzolans, and ultra-fine coal ash when used in such proportions to replace the portland cement that result in improvement to sustainability and durability and reduced cost.

e. "Design strength" (f'c) is the specified compressive strength of concrete at time(s) specified in this section to meet structural design criteria.

f. "Mass Concrete" is any concrete system that approaches a maximum temperature of 158 degrees F within the first 72 hours of placement.

In addition, it includes all concrete elements with a section thickness of 3 feet or more regardless of temperature.

g. "Mixture proportioning" is the process of designing concrete mixture proportions to enable it to meet the strength, service life and constructability requirements of the project while minimizing the initial and life-cycle cost.

h. "Mixture proportions" are the masses or volumes of individual ingredients used to make a unit measure (cubic meter or cubic yard) of concrete.

i. "Pozzolan" is a siliceous or siliceous and aluminous material, which in itself possesses little or no cementitious value but will, in finely divided form and in the presence of moisture, chemically react with calcium hydroxide at ordinary temperatures to form compounds possessing cementitious properties.

j. "Workability (or consistence)" is the ability of a fresh (plastic) concrete mix to fill the form/mould properly with the desired work (vibration) and without reducing the concrete's quality. Workability depends on water content, chemical admixtures, aggregate (shape and size distribution), cementitious content and age (level of hydration).

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29.00 06 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00.00 06

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Concrete Curing Plan

Quality Control Plan ; G

Quality Control Personnel Certifications ; G

Quality Control Organizational Chart

Laboratory Accreditation ; G

Form Removal Schedule ; G

SECTION 03 30 00 Page 6

SD-02 Shop Drawings

Formwork

Reinforcing Steel ; G

Construction Joint Plan and Details; G

SD-03 Product Data

Joint Sealants ; S

Joint Filler ; S

Materials for Forms

Cementitious Materials ; S

Vapor Retarder

Concrete Curing Materials

Reinforcement ; S

Liquid Chemical Floor Hardener

Penetrating Water Repellent

Admixtures

Biodegradable Form Release Agent Pumping Concrete

Biobased Materials

SD-04 Samples

Slab Finish Sample

SD-05 Design Data

Concrete Mix Design ; G

Formwork Calculations

SD-06 Test Reports

Concrete Mix Design ; G

Fly Ash

Pozzolan

Ground Granulated Blast-Furnace Slag

Aggregates

Tolerance Report

SECTION 03 30 00 Page 7

Compressive Strength Tests ; G

Unit Weight of Structural Concrete

Ion Concentration

Air Content

Slump Tests

Water

SD-07 Certificates

Reinforcing Bars

Welder Qualifications

Concrete Polisher Qualifications

VOC Content for Form Release Agents, Curing Compounds, and Concrete Penetrating Sealers

Material Safety Data Sheets Field Testing Technician and Testing Agency

SD-08 Manufacturer's Instructions

Liquid Chemical Floor Hardener

Penetrating Water Repellent

Curing Compound

1.4 MODIFICATION OF REFERENCES

Accomplish work in accordance with ACI publications except as modified herein. Consider the advisory or recommended provisions to be mandatory.

Interpret reference to the "Building Official," the "Structural Engineer," and the "Architect/Engineer" to mean the Contracting Officer.

1.5 PRE-INSTALLATION MEETING

a. At least 30 days prior to the start of the concrete slab construction, conduct a meeting at the project site to review the proposed concrete mix designs and to discuss the required methods and procedures to achieve the requirements of this specification. Send a pre-concrete meeting agenda to all attendees 10 days prior to the scheduled date of the conference. Require the following to be in attendance:

1. Contractor's superintendent.

2. Independent testing agency responsible for concrete design mixtures.

3. Ready-mix concrete supplier.

4. Cast-in-place architectural concrete supplier.

5. Polished concrete supplier.

b. Review concrete finishes and finishing, cold- and hot-weather

SECTION 03 30 00 Page 8 concreting procedures, curing procedures, construction joints, forms and form-removal limitations, reinforcement accessory installation, concrete repair procedures, and polished concrete procedures.

c. Before submitting design mixtures, review concrete design mixture and examine procedures for ensuring quality of concrete materials.

1.6 DELIVERY, STORAGE, AND HANDLING

Follow ACI 301 , ACI 304R and ASTM A934/A934M requirements and recommendations. Do not deliver concrete until vapor retarder, forms, reinforcement, embedded items, and chamfer strips are in place and ready for concrete placement. Do not store concrete curing compounds or sealers with materials that have a high capacity to adsorb volatile organic compound (VOC) emissions, including acoustical ceilings, carpet, textiles, and unprimed gypsum wall board. Do not store concrete curing compounds or sealers in occupied spaces.

1.6.1 Reinforcement

Store reinforcement of different sizes and shapes in separate piles or racks raised above the ground to avoid excessive rusting. Protect from contaminants such as grease, oil, and dirt. Ensure bar sizes can be accurately identified after bundles are broken and tags removed.

1.7 QUALITY ASSURANCE

1.7.1 Design Data

1.7.1.1 Formwork Calculations

ACI 347 . Include design calculations indicating arrangement of forms, sizes and grades of supports (lumber), panels, and related components.

Furnish drawings and calculations of shoring and re-shoring methods proposed for floor and roof slabs, spandrel beams, and other horizontal concrete members. Calculations must indicate concrete pressure with both live and dead loads, along with material types.

1.7.1.2 Concrete Mix Design

Sixty days minimum prior to concrete placement, submit a mix design for each strength and type of concrete. Submit a complete list of materials including type; brand; source and amount of cement, complementary cementitious materials, and admixtures; and applicable reference specifications. Submit mill test and all other test for cement, complementary cementitious materials, aggregates, and admixtures.

Provide documentation of maximum nominal aggregate size, gradation analysis, percentage retained and passing sieve, and a graph of percentage retained verses sieve size. Provide mix proportion data using at least three different water-cementitious material ratios for each type of mixture, which produce a range of strength encompassing those required for each type of concrete required. If source material changes, resubmit mix proportion data using revised source material. Provide only materials that have been proven by trial mix studies to meet the requirements of this specification, unless otherwise approved in writing by the Contracting Officer. Indicate clearly in the submittal where each mix design is used when more than one mix design is submitted. Resubmit data on concrete components if the qualities or source of components changes.

For previously approved concrete mix designs used within the past twelve

SECTION 03 30 00 Page 9 months, the previous mix design may be re-submitted without further trial batch testing if accompanied by material test data conducted within the last six months. Obtain mix design approval from the contracting officer prior to concrete placement.

1.7.2 Shop Drawings

1.7.2.1 Formwork

Drawings showing details of formwork including, but not limited to;

joints, supports, studding and shoring, and sequence of form and shoring removal. Indicate placement schedule, construction, location and method of forming control joints. Include locations of inserts, conduit, sleeves and other embedded items. Reproductions of contract drawings are unacceptable. Submit form removal schedule indicating element and minimum length of time for form removal.

Design, fabricate, erect, support, brace, and maintain formwork so that it is capable of supporting without failure all vertical and lateral loads that may reasonably be anticipated to be applied to the formwork.

1.7.2.2 Reinforcing Steel

ACI SP-66 . Indicate bending diagrams, assembly diagrams, splicing and laps of bars, shapes, dimensions, and details of bar reinforcing, accessories, and concrete cover. Do not scale dimensions from structural drawings to determine lengths of reinforcing bars. Reproductions of contract drawings are unacceptable.

1.7.3 Control Submittals

1.7.3.1 Concrete Curing Plan

Submit proposed materials, methods and duration for curing concrete elements in accordance with ACI 308.1 .

1.7.3.2 Pumping Concrete

Submit proposed materials and methods for pumping concrete. Submittal must include mix designs, pumping equipment including type of pump and size and material for pipe, and maximum length and height concrete is to be pumped.

1.7.3.3 VOC Content for form release agents, curing compounds, and concrete penetrating sealers

Submit certification for the form release agent, curing compounds, and concrete penetrating sealers that indicate the VOC content of each product.

1.7.3.4 Material Safety Data Sheets

Submit Material Safety Data Sheets (MSDS) for all materials that are regulated for hazardous health effects. MSDS must be readily accessible during each work shift to employees when they are at the construction site.

SECTION 03 30 00 Page 10

1.7.4 Test Reports

1.7.4.1 Fly Ash and Pozzolan

Submit test results in accordance with ASTM C618 for fly ash and pozzolan. Submit test results performed within 6 months of submittal date.

1.7.4.2 Ground Granulated Blast-Furnace Slag

Submit test results in accordance with ASTM C989/C989M for ground granulated blast-furnace slag. Submit test results performed within 6 months of submittal date.

1.7.4.3 Aggregates

ASTM C1260 for potential alkali-silica reactions, ASTM C295/C295M for petrographic analysis.

1.7.5 Field Samples

1.7.5.1 Slab Finish Sample

Install minimum of 10 foot by 10 foot slab. Slab finish samples must not be part of the final project. Finish as required by specification.

1.7.5.1.1 Polished Finish Sample

Apply polished finish as specified herein to one 10 foot by 10 foot slab. To determine the actual level of finish required, apply the polish process, including application of liquid chemical floor hardener, using the same equipment, tools and methods as will be used to polish the interior floor slab, on one half of the slab to a level of of 800 grit and on the other half of the slab to a level of 1500 grit. The Contracting Officer will then select the actual level of polish required for the project.

1.7.5.1.2 Light Broom Finish Sample

Apply a two different levels of light broom finish to each half of one 10 foot by 10 foot slab. Make one a little heaver than the other and include the water repellent application. The Contracting Officer will then select the actual level of broom finish required for the project.

1.7.6 Quality Control Plan

Develop and submit for approval a concrete quality control program in accordance with the guidelines of ACI 121R and as specified herein. The plan must include approved laboratories. Provide direct oversight for the concrete qualification program inclusive of associated sampling and testing. All quality control reports must be provided to the Contracting Officer, Quality Manager and Concrete Supplier. Maintain a copy of ACI SP-15 and CRSI 10MSP at project site.

1.7.7 Quality Control Personnel Certifications

The Contractor must submit for approval the responsibilities of the various quality control personnel, including the names and qualifications of the individuals in those positions and a quality control organizational chart defining the quality control hierarchy and the responsibility of the

SECTION 03 30 00 Page 11 various positions. Quality control personnel must be employed by the Contractor.

Submit American Concrete Institute certification for the following:

a. CQC personnel responsible for inspection of concrete operations.

b. Lead Foreman or Journeyman of the Concrete Placing, Finishing, and Curing Crews.

c. Field Testing Technicians: ACI Concrete Field Testing Technician, Grade I.

1.7.7.1 Quality Manager Qualifications

The quality manager must hold a current license as a professional engineer in a U.S. state or territory with experience on at least five (5) similar projects. Evidence of extraordinary proven experience may be considered by the Contracting Officer as sufficient to act as the Quality Manager.

1.7.7.2 Field Testing Technician and Testing Agency

Submit data on qualifications of proposed testing agency and technicians for approval by the Contracting Officer prior to performing testing on concrete.

a. Work on concrete under this contract must be performed by an ACI Concrete Field Testing Technician Grade 1 qualified in accordance with ACI SP-2 or equivalent. Equivalent certification programs must include requirements for written and performance examinations as stipulated in

ACI SP-2 .

b. Testing agencies that perform testing services on reinforcing steel must meet the requirements of ASTM E329.

c. Testing agencies that perform testing services on concrete materials must meet the requirements of ASTM C1077.

1.7.8 Laboratory Qualifications for Concrete Qualification Testing

The concrete testing laboratory must have the necessary equipment and experience to accomplish required testing. The laboratory must meet the requirements of ASTM C1077 and be Cement and Concrete Reference Laboratory (CCRL) inspected.

1.7.9 Laboratory Accreditation

Laboratory and testing facilities must be provided by and at the expense of the Contractor. The laboratories performing the tests must be accredited in accordance with ASTM C1077, including ASTM C78/C78M and ASTM C1260. The accreditation must be current and must include the required test methods, as specified. Furthermore, the testing must comply with the following requirements:

a. Aggregate Testing and Mix Proportioning: Aggregate testing and mixture proportioning studies must be performed by an accredited laboratory and under the direction of a registered professional engineer in a U.S. state or territory who is competent in concrete materials and must sign all reports and designs.

SECTION 03 30 00 Page 12

b. Acceptance Testing: Furnish all materials, labor, and facilities required for molding, curing, testing, and protecting test specimens at the site and in the laboratory. Furnish and maintain boxes or other facilities suitable for storing and curing the specimens at the site while in the mold within the temperature range stipulated by

ASTM C31/C31M.

c. Contractor Quality Control: All sampling and testing must be performed by an approved, onsite, independent, accredited laboratory.

1.7.10 Concrete Polisher Qualifications

Concrete polisher shall have completed a minimum of three similar and successful projects that clearly indicates the concrete polisher's ability to successfully perform the work required in this specification. The concrete supplier's team shall have participated in the majority of these projects, and that team shall remain the same through the duration of this project.

1.8 ENVIRONMENTAL REQUIREMENTS

Provide space ventilation according to manufacturer recommendations, at a minimum, during and following installation of concrete curing compound and sealer. Maintain one of the following ventilation conditions during the curing period or for 72 hours after installation:

a. Supply 100 percent outside air 24 hours a day.

b. Supply airflow at a rate of 6 air changes per hour, when outside temperatures are between 55 degrees F and 84 degrees F and humidity is between 30 percent and 60 percent.

c. Supply airflow at a rate of 1.5 air changes per hour, when outside air conditions are not within the range stipulated above.

1.8.1 Submittals for Environmental Performance

a. Provide data indication the percentage of post-industrial pozzolan (fly ash, blast furnace slag) cement substitution as a percentage of the full product composite by weight.

b. Provide data indicating the percentage of post-industrial and post-consumer recycled content aggregate.

c. Provide product data indicating the percentage of post-consumer recycled steel content in each type of steel reinforcement as a percentage of the full product composite by weight.

d. Provide product data stating the location where all products were manufactured

e. For projects using reusable formwork, provide data showing how formwork is reused.

f. Provide MSDS product information data showing that form release agents meet any environmental performance goals such as using vegetable and soy based products.

SECTION 03 30 00 Page 13

g. Provide MSDS product information data showing that concrete adhesives meet any environmental performance goals including low emitting, low volatile organic compound products.

1.9 SUSTAINABLE DESIGN REQUIREMENTS

1.9.1 Voc Content For Form Release Agents, Curing Compounds, And Concrete Penetrating Sealers

Submit certification for the form release agent, curing compounds, and concrete penetrating sealers that indicate the VOC content of each product in accordance with Section 01 33 29.00 06 SUSTAINABILITY REPORTING.

1.9.2 Biobased Materials for Formwork, Form Release Agents, Curing Compounds, And Concrete Penetrating Sealers

Use bio-based materials where specified. Provide Biopreferred label with bio-based content for each product in accordance with Section

01 33 29.00 06 SUSTAINABILITY REPORTING.

1.10 QUALIFICATIONS FOR WELDING WORK

Welding procedures must be in accordance with AWS D1.4/D1.4M .

Verify that Welder qualifications are in accordance with AWS D1.4/D1.4M or under an equivalent qualification test approved in advance. Welders are permitted to do only the type of welding for which each is specifically qualified.

PART 2 PRODUCTS

2.1 MATERIALS FOR FORMS

Provide wood, plywood, or steel. Use plywood or steel forms where a smooth form finish is required.

2.1.1 Wood Forms

Use lumber as specified in Section 06 10 00 ROUGH CARPENTRY and as follows. Provide lumber that is square edged or tongue-and-groove boards, free of raised grain, knotholes, or other surface defects. Provide plywood that complies with NIST PS 1 , B-B concrete form panels or better or AHA A135.4 , hardboard for smooth form lining. Submit data verifying that composite wood products contain no urea formaldehyde resins.

2.1.1.1 Concrete Form Plywood (Standard Rough)

Provide plywood that conforms to NIST PS 1 , B-B, concrete form, not less than 5/8-inch thick.

2.1.1.2 Overlaid Concrete Form Plywood (Standard Smooth)

Provide plywood that conforms to NIST PS 1 , B-B, high density form overlay, not less than 5/8-inch thick.

2.1.2 Steel Forms

Provide steel form surfaces that do not contain irregularities, dents, or sags.

SECTION 03 30 00 Page 14

2.2 FORM TIES AND ACCESSORIES

Provide a form tie system that does not leave mild steel after break-off or removal any closer than 2 inches from the exposed surface. Do not use wire alone. Form ties and accessories must not reduce the effective cover of the reinforcement.

2.2.1 WATERSTOPS

2.2.1.1 Hydrophilic Waterstop

Waterstop shall be furnished and installed by waterproofing installer as indicated in Section 07 13 53 ELASTOMERIC SHEET WATERPROOFING

2.2.2 Perimeter Insulation

Perimeter insulation must be polystyrene conforming to ASTM C578, Type II;

polyurethane conforming to ASTM C591, Type II; or cellular glass conforming to ASTM C552, Type I or IV. Comply with EPA requirements in accordance with Section 01 33 29.00 06 SUSTAINABILITY REPORTING.

2.3 CONCRETE MIX DESIGN

2.3.1 Contractor-Furnished Mix Design

ACI 211.1 , ACI 301 , ACI 318 and ACI 304.2R except as otherwise specified.

Indicate the compressive strength (f'c) of the concrete for each portion of the structure(s) as specified below. Where faster set time is required, use Type III cement .

2.3.1.1 Footings

Proportion normal-weight concrete mixture as follows:

a. Minimum Compressive Strength: 4000 psi at 28 days.

b. Maximum Water-Cementitious Materials Ratio: 0.45 .

c. Slump Limit: 4 inches , plus or minus 1 inch .

d. Air Content: 5.5 percent, plus or minus 1.5 percent at point of delivery for 1-1/2 inch nominal maximum aggregate size.

2.3.1.2 Foundation Walls

Proportion normal-weight concrete mixture as follows:

a. Minimum Compressive Strength: 4000 psi at 28 days.

b. Maximum Water-Cementitious Materials Ratio: 0.45 .

c. Slump Limit: 4 inches , plus or minus 1 inch .

d. Air Content: 5.5 percent, plus or minus 1.5 percent at point of delivery for 1-1/2 inch nominal maximum aggregate size.

SECTION 03 30 00 Page 15

2.3.1.3 Slab-on-Grade

Proportion normal-weight concrete mixture as follows:

a. Minimum Compressive Strength: 4000 psi at 28 days.

b. Maximum Water-Cementitious Materials Ratio: 0.45 .

c. Slump Limit: 8 inches for concrete with verified slump of 2 to 4 inches before adding high-range water-reducing admixture or plasticizing admixture , plus or minus 1 inch .

f. Air Content: Do not allow air content of trowel-finished floors to exceed 3 percent.

2.3.1.4 Suspended Slabs

Proportion normal-weight concrete mixture as follows:

a. Minimum Compressive Strength: 4000 psi at 28 days.

b. Maximum Water-Cementitious Materials Ratio: 0.45 .

c. Slump Limit: 8 inches for concrete with verified slump of 2 to 4 inches before adding high-range water-reducing admixture or plasticizing admixture, plus or minus 1 inch .

f. Air Content: Do not allow air content of trowel-finished floors to exceed 3 percent.

2.3.1.5 Concrete Curbs, Gutters and Sidewalks

Proportion normal-weight concrete mixture as follows:

a. Minimum Compressive Strength: 4000 psi at 28 days.

b. Maximum Water-Cementitious Materials Ratio: 0.45.

c. Slump Limit: 3 inches plus or minus 1 inch for hand placed concrete or 1 inch plus or minus 1/2 inch for slipformed concrete as determined in accordance with ASTM C143/C143M .

d. Air Content: 5 to 7 percent at point of delivery.

e. Monofilament polypropylene Fiber Reinforcement: 1.5 lbs/cubic yard., complying with ASTM C1116/C1116M, Type III.

2.3.1.6 Mix Proportions for Normal Weight Concrete

Trial design batches, mixture proportioning studies, and testing requirements for various classes and types of concrete specified are the responsibility of the Contractor. Base mixture proportions on compressive strength as determined by test specimens fabricated in accordance with ASTM C192/C192M and tested in accordance with ASTM C39/C39M. Samples of all materials used in mixture proportioning studies must be representative of those proposed for use in the project and must be accompanied by the manufacturer's or producer's test report indicating compliance with these specifications. Base trial mixtures having proportions, consistencies, and air content suitable for the work on methodology described in ACI 211.1 .

SECTION 03 30 00 Page 16

In the trial mixture, use at least three different water-cementitious material ratios for each type of mixture, which must produce a range of strength encompassing those required for each class and type of concrete required on the project. The maximum water-cementitious material ratio allowed must be based on equivalent water-cementitious material ratio calculations as determined by the conversion from the weight ratio of water to cement plus pozzolan by weight equivalency method. Design laboratory trial mixture for maximum permitted slump and air content.

Each combination of material proposed for use must have separate trial mixture, except for accelerator or retarder use can be provided without separate trial mixture. Report the temperature of concrete in each trial batch. For each water-cementitious material ratio, at least three test cylinders for each test age must be made and cured in accordance with ASTM C192/C192M and tested in accordance with ASTM C39/C39M for 7, 28, and 90 days. From these results, plot a curve showing the relationship between water-cementitious material ratio and strength for each set of trial mix studies. In addition, plot a curve showing the relationship between 7, 28 and 90 day strengths.

2.3.1.7 Required Average Strength of Mix Design

The selected mixture must produce an average compressive strength exceeding the specified strength by the amount indicated in ACI 301 , but may not exceed the specified strength at the same age by more than 20 percent. When a concrete production facility has a record of at least 15 consecutive tests, the standard deviation must be calculated and the required average compressive strength must be determined in accordance with ACI 301 .

2.3.2 Ready-Mix Concrete

Provide concrete that meets the requirements of ASTM C94/C94M.

Ready-mixed concrete manufacturer must provide duplicate delivery tickets with each load of concrete delivered. Provide delivery tickets with the following information in addition to that required by ASTM C94/C94M:

Type and brand cement

Cement and complementary cementitious materials content in 94-pound bags per cubic yard of concrete

Maximum size of aggregate

Amount and brand name of admixtures

Total water content expressed by water cementitious material ratio

2.3.3 Concrete Curing Materials

Provide moist curing only for concrete in the entire Facility. Provide moist curing only for finished flatwork slabs. At other locations, provide concrete curing material in accordance with ACI 301 Section 5 and ACI 308.1 Section 2. Submit product data for concrete curing compound s.

Submit manufactures instructions for placement of curing compound.

SECTION 03 30 00 Page 17

2.4 MATERIALS

2.4.1 Cementitious Materials

For exposed concrete, use one manufacturer and one source for each type of cement, ground slag, fly ash, and pozzolan.

2.4.1.1 Fly Ash

ASTM C618, Class F, except that the maximum allowable loss on ignition must not exceed 3 percent. Class F fly ash for use in mitigating Alkali-Silica Reactivity must have a Calcium Oxide (CaO) content of less than 8 percent and a total equivalent alkali content less than 1.5 percent.

Add with cement. Fly ash content must be a minimum of 15 percent by weight of cementitious material, provided the fly ash does not reduce the amount of cement in the concrete mix below the minimum requirements of local building codes. Where the use of fly ash cannot meet the minimum level, provide the maximum amount of fly ash permittable that meets the code requirements for cement content. Report the chemical analysis of the fly ash in accordance with ASTM C311/C311M. Evaluate and classify fly ash in accordance with ASTM D5759.

2.4.1.2 Raw or Calcined Natural Pozzolan

Natural pozzolan must be raw or calcined and conform to ASTM C618, Class N, including the optional requirements for uniformity and effectiveness in controlling Alkali-Silica reaction and must have an ignition loss not exceeding 3 percent. Class N pozzolan for use in mitigating Alkali-Silica Reactivity must have a Calcium Oxide (CaO) content of less than 13 percent and total equivalent alkali content less than 3 percent.

2.4.1.3 Ultra Fine Fly Ash and Ultra Fine Pozzolan

Ultra Fine Fly Ash (UFFA) and Ultra Fine Pozzolan (UFP) must conform to ASTM C618, Class F or N, and the following additional requirements:

a. The strength activity index at 28 days of age must be at least 95 percent of the control specimens.

b. The average particle size must not exceed 6 microns.

c. The sum of SiO2 + Al2O3 + Fe2O3 must be greater than 77 percent.

2.4.1.4 Ground Granulated Blast-Furnace Slag

ASTM C989/C989M, Grade 100. Slag content must be a minimum of 25 percent by weight of cementitious material.

2.4.1.5 Portland Cement

Provide cement that conforms to ASTM C150/C150M, Type II, low alkali with tri-calcium aluminates (C3A) content less than 10 percent and a maximum cement-alkali content of 0.80 percent Na2Oe (sodium oxide) equivalent..

Use one brand and type of cement for formed concrete having exposed-to-view finished surfaces.

For portland cement manufactured in a kiln fueled by hazardous waste, SECTION 03 30 00 Page 18 maintain a record of source for each batch. Supplier must certify that no hazardous waste is used in the fuel mix or raw materials.

2.4.1.6 Blended Cements

Blended cement must conform to ASTM C595/C595M and ASTM C1157/C1157M , Type IP or IS, including the optional requirement for mortar expansion and sulfate soundness and consist of a mixture of ASTM C150/C150M Type I, or Type II cement and a complementary cementing material. The slag added to the Type IS blend must be ASTM C989/C989M ground granulated blast-furnace slag. The pozzolan added to the Type IP blend must be ASTM C618 Class F and must be interground with the cement clinker. The manufacturer must state in writing that the amount of pozzolan in the finished cement will not vary more than plus or minus 5 mass percent of the finished cement from lot-to-lot or within a lot. The percentage and type of mineral admixture used in the blend must not change from that submitted for the aggregate evaluation and mixture proportioning.

2.4.2 Water

Water must comply with the requirements of ASTM C1602/C1602M . Minimize the amount of water in the mix. Improve workability by adjusting the grading rather than by adding water. Water must be potable; free from injurious amounts of oils, acids, alkalis, salts, organic materials, or other substances deleterious to concrete. Submit test report showing water complies with ASTM C1602/C1602M .

2.4.3 Aggregates

ASTM C33/C33M, except as modified herein. Furnish aggregates for exposed concrete surfaces from one source. Provide aggregates that do not contain any substance which may be deleteriously reactive with the alkalies in the cement. Submit test report showing compliance with ASTM C33/C33M.

Fine and coarse aggregates must show expansions less than 0.08 percent at 28 days after casting when testing in accordance with ASTM C1260. Should the test data indicate an expansion of 0.08 percent or greater, reject the aggregate(s) or perform additional testing using ASTM C1567 using the Contractor's proposed mix design. In this case, include the mix design low alkali portland cement and one of the following supplementary cementitious materials:

1. GGBF slag at a minimum of 40 percent of total cementitious

2. Fly ash or natural pozzolan at a minimum of total cementitious of

a. 30 percent if (SiO2 plus Al2O3 plus Fe2O3) is 65 percent or more,

b. 25 percent if (SiO2 plus Al2O3 plus Fe2O3) is 70 percent or more,

c. 20 percent if (SiO2 plus Al2O3 plus Fe2O3) is 80 percent or more,

d. 15 percent if (SiO2 plus Al2O3 plus Fe2O3) is 90 percent or more.

If a combination of these materials is chosen, the minimum amount must be a linear combination of the minimum amounts above. Include these materials in sufficient proportion to show less than 0.08 percent expansion at 28 days after casting when tested in accordance with

ASTM C1567.

Aggregates must not possess properties or constituents that are known to have specific unfavorable effects in concrete when tested in accordance with ASTM C295/C295M.

SECTION 03 30 00 Page 19

2.4.3.1 Aggregates/Combined Aggregate Gradation (Floor Slabs Only)

ASTM C33/C33M, uniformly graded and as follows: Nominal maximum aggregate size of 1 inch . A combined sieve analysis must indicate a well graded aggregate from coarsest to finest with not more than 18 percent and not less than 8 percent retained on an individual sieve, except that less than 8 percent may be retained on coarsest sieve and on No. 50 (0.3mm) sieve, and less than 8 percent may be retained on sieves finer than No. 50 (0.3mm). Provide sand that is at least 50 percent natural sand.

2.4.4 Nonshrink Grout

ASTM C1107/C1107M .

2.4.5 Admixtures

ASTM C494/C494M: Type A, water reducing; Type B, retarding; Type C, accelerating; Type D, water-reducing and retarding; and Type E, water-reducing and accelerating admixture. Do not use calcium chloride admixtures. Submit product data for admixtures used in concrete.

2.4.5.1 Air-Entraining

ASTM C260/C260M.

2.4.5.2 High Range Water Reducer (HRWR) (Superplasticizers)

ASTM C494/C494M, Type F and ASTM C1017/C1017M .

2.4.6 Vapor Retarder

ASTM E1745 Class A polyethylene sheeting, minimum 15 mil thickness or ASTM E1993/E1993M bituminous membrane or other equivalent material with a maximum permeance rating of 0.01 perms per ASTM E96/E96M.

Consider plastic vapor retarders and adhesives with a high recycled content, low toxicity low VOC (Volatile Organic Compounds) levels.

2.4.7 Expansion/Contraction Joint Filler

ASTM D1751 or ASTM D1752 Type I or II. Material must be 1/2 inch thick, unless otherwise indicated.

2.4.8 Joint Sealants

Submit manufacturer's product data, indicating VOC content.

2.4.8.1 Horizontal Surfaces, 3 Percent Slope, Maximum

ASTM D6690 or ASTM C920, Type M, Class 25, Use T.

2.4.8.2 Vertical Surfaces Greater Than 3 Percent Slope

ASTM C920, Type M, Grade NS, Class 25, Use T

2.4.8.3 Preformed Polychloroprene Elastomeric Type

ASTM D2628.

SECTION 03 30 00 Page 20

2.4.8.4 Lubricant for Preformed Compression Seals

ASTM D2835.

2.4.9 Biodegradable Form Release Agent

Provide form release agent that is colorless, biodegradable, and water-based, with a zero VOC content. Provide product that does not bond with, stain, or adversely affect concrete surfaces and does not impair subsequent treatments of concrete surfaces. Provide form release agent that does not contain diesel fuel, petroleum-based lubricating oils, waxes, or kerosene. Submit documentation indicating type of biobased material in product and biobased content. Indicate relative dollar value of biobased content products to total dollar value of products included in project.

2.5 REINFORCEMENT

2.5.1 Reinforcing Bars

ACI 301 unless otherwise specified. Use deformed steel. ASTM A615/A615M with the bars marked A, Grade 60 ; or ASTM A996/A996M with the bars marked R, Grade 60 , or marked A, Grade 60. Cold drawn wire used for spiral reinforcement must conform to ASTM A1064/A1064M . See Section 01 33 29.00 06 SUSTAINABILITY REPORTING for recycled content requirements. Submit mill certificates for reinforcing bars.

2.5.1.1 Weldable Reinforcing Bars

Provide weldable reinforcing bars that conform to ASTM A706/A706M and ASTM A615/A615M and Supplement S1, Grade 60, except that the maximum carbon content must be 0.55 percent.

2.5.2 Wire

2.5.2.1 Welded Wire Reinforcement

ASTM A1064/A1064M .See Section 01 33 29.00 06 SUSTAINABILITY REPORTING for recycled content requirements. Provide flat sheets of welded wire reinforcement for elevated slabs and toppings.

2.5.2.2 Steel Wire

Wire must conform to ASTM A1064/A1064M .

2.5.3 Reinforcing Bar Supports

Supports include bolsters, chairs, spacers, and other devices necessary for proper spacing, supporting, and fastening reinforcing bars and welded wire reinforcement in place.

Provide wire bar type supports of coated or non-corrodible material conforming to ACI SP-66 and CRSI 10MSP.

Legs of supports in contact with formwork must be hot-dip galvanized, or plastic coated after fabrication, or stainless-steel bar supports.

SECTION 03 30 00 Page 21

2.5.4 Dowels for Load Transfer in Floors

Provide greased dowels for load transfer in floors of the type, design, weight, and dimensions indicated. Provide dowel bars that are plain-billet steel conforming to ASTM A615/A615M , Grade 40. Provide dowel pipe that is steel conforming to ASTM A53/A53M.

2.6 FLOOR FINISH MATERIALS

2.6.1 Liquid Chemical Floor Hardener

Hardener must be a colorless aqueous solution containing a blend of inorganic silicate or siliconate material and proprietary components combined with a wetting agent; that penetrates, hardens, and densifies concrete surfaces. Submit manufactures instructions for placement of liquid chemical floor hardener.

Use concrete penetrating sealers with a low (maximum 100 grams/liter, less water and less exempt compounds) VOC content.

2.6.2 Penetrating Water Repellent

Repellent must be a water-based siloxane/silane penetrating water repellent sealer. Repellent must soak into the substrate and form a water and chloride barrier that protects concrete from the damaging effects of water and salts. Repellent must be a breathable sealer that does not alter the appearance or texture of the substrate. Repellent must be non film-forming and leave no gloss or shine.

Use concrete water repellents with a low (maximum 100 grams/liter, less water and less exempt compounds) VOC content.

PART 3 EXECUTION

3.1 EXAMINATION

Do not begin installation until substrates have been properly constructed;

verify that substrates are level.

If substrate preparation is the responsibility of another installer, notify Contracting Officer of unsatisfactory preparation before…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .