W912QR20R0005Specs_Vol2-0000.pdf
PDF 10 MB Posted
- Attached to
- Scott Air Force Base Bldg. 1575 Add/Alt
- Solicitation number
- W912QR20R0005
About this file
This Request for Proposal solicits construction services for the addition and renovation of a computer data center facility at Scott Air Force Base, Illinois. The scope of work includes renovating an existing 50,965 square foot facility into dedicated data center space through seismic retrofit of the building and raised floor system, replacing air handling units and undertaking electrical and chilled water upgrades. An additional 23,702 square foot secure administrative addition will be constructed along with new furniture installation. Proposals are due by the date listed on www.FBO.gov, with award anticipated on the subsequent date also listed. The selected contractor will provide all labor, materials and equipment required to complete the project in accordance with the specifications.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For Add/Alter Consolidated Communications Facility B1575 Scott Air Force Base, IL
P2: 456269
Design Bid Build
Specifications Certified Final Submittal Vol. 2 of 3 (Divisions 02 - 13)
ARIMS: 200A
Disposition: Maintain for 15yrs after construction
27 February 2020
W912QR20R0005
W912QR20R0005-0000
Woolpert 343 Fountains Parkway, Suite 100
Fairview Heights, Illinois 62208
Certified Final Design Specifications
Volume 2: Divisions 02 - 13
Consolidated Communications Facility Scott Air Force Base, IL
FY17
October 2019
VDYD 10-1053, OPPT. 100429
P2#: 45629
ADD/ALTER CONSOLIDATED COMMUNICATIONS FACILITY 1575 W912QR-20-R-0005
SCOTT AFB, IL
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 10 00 PRICE BREAKOUT SCHEDULE
00 80 00.00 06 SPECIAL PROVISIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 10 SUMMARY OF WORK
01 32 01.00 06 PROJECT SCHEDULE
01 33 00.00 06 SUBMITTAL PROCEDURES
01 33 29.00 06 SUSTAINABILITY REPORTING
01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.10 06 CONTRACTOR QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 46 00.00 06 TOTAL BUILDING COMMISSIONING (CONTRACTOR CxA)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19.00 06 TEMPORARY ENVIRONMENTAL CONTROLS AND PERMITS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION AND DECONSTRUCTION
02 82 13.00 10 ASBESTOS ABATEMENT
02 83 13.00 20 LEAD IN CONSTRUCTION
02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs
AND MERCURY
DIVISION 03 - CONCRETE
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 20 00.00 10 CONCRETE REINFORCING
03 30 00 CAST-IN-PLACE CONCRETE
03 35 00.00 10 CONCRETE FINISHING
03 39 00.00 10 CONCRETE CURING
DIVISION 04 - MASONRY
04 01 20.70 UNIT MASONRY CLEANING AND RESTORATION
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 12 10 STRUCTURAL CAST STEEL COMPONENTS
05 21 00 STEEL JOIST FRAMING
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 50 14 STRUCTURAL METAL FABRICATIONS
05 51 00 METAL STAIRS
05 51 33 METAL LADDERS
05 52 00 METAL RAILINGS
PROJECT TABLE OF CONTENTS Page 1
CERTIFIED FINAL DESIGN
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
BUILDING ADDITION ONLY
07 13 53 ELASTOMERIC SHEET WATERPROOFING
07 21 13 BOARD AND BLOCK INSULATION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 22 00 ROOF AND DECK INSULATION
07 27 10.00 10 BUILDING AIR BARRIER SYSTEM
07 27 36 SPRAY FOAM AIR BARRIERS
07 52 00 MODIFIED BITUMINOUS MEMBRANE ROOFING
07 60 00 FLASHING AND SHEET METAL
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 14 00 WOOD DOORS
08 31 00 ACCESS DOORS AND PANELS
08 33 23 OVERHEAD COILING DOORS
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL AND DOOR LOUVERS
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 68 00 CARPETING
09 69 13 RIGID GRID ACCESS FLOORING
09 84 20 ACOUSTICAL WALL PANELS
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 11 00 VISUAL DISPLAY UNITS
10 14 00.20 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 21 23.13 CUBICLE CURTAINS
10 21 23.16 CUBICLE TRACK AND HARDWARE
10 22 13 WIRE MESH PARTITIONS
10 26 00 WALL AND DOOR PROTECTION
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
DIVISION 11 - EQUIPMENT
PROJECT TABLE OF CONTENTS Page 2
11 13 19.13 LOADING DOCK LEVELERS (STATIONARY LOADING DOCK EQUIPMENT)
DIVISION 12 - FURNISHINGS
12 24 13 ROLLER WINDOW SHADES
12 59 00 SYSTEMS FURNITURE
DIVISION 13 - SPECIAL CONSTRUCTION
13 48 00 SEISMIC BRACING FOR MISCELLANEOUS EQUIPMENT
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48.19 SEISMIC BRACING FOR HVAC
23 05 93.00 06 TESTING, ADJUSTING, AND BALANCING (TAB) OF HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 11 25 FACILITY GAS PIPING
23 21 13.00 20 LOW TEMPERATURE WATER (LTW) HEATING SYSTEM
23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS
23 52 00 HEATING BOILERS
23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS
23 65 00 COOLING TOWERS AND REMOTE EVAPORATIVELY-COOLED CONDENSERS
23 82 00.00 20 TERMINAL HEATING UNITS
DIVISION 25 - INTEGRATED AUTOMATION
25 50 00.00 20 CYBERSECURITY OF FACILITY-RELATED CONTROL SYSTEMS
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 13 SWITCHBOARDS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 36 00.00 10 AUTOMATIC TRANSFER SWITCH AND BY-PASS/ISOLATION SWITCH
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
PROJECT TABLE OF CONTENTS Page 3
27 11 16 COMMUNICATIONS RACKS, FRAMES, ENCLOSURES, AND
CONTAINMENT SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 08 10 ELECTRONIC SECURITY SYSTEM ACCEPTANCE TESTING
28 10 05 ELECTRONIC SECURITY SYSTEMS (ESS)
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 05 19 GEOTEXTILE
31 11 00 CLEARING AND GRUBBING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 23 AGGREGATE BASE COURSES
32 12 17 HOT MIX BITUMINOUS PAVEMENT
32 12 36.13 ASPHALTIC SEAL AND FOG COATS
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS
32 16 15 CONCRETE BLOCK PAVEMENTS
32 17 23 PAVEMENT MARKINGS
32 92 19 SEEDING
32 93 00 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERS
33 40 00 STORM DRAINAGE UTILITIES
33 46 16 SUBDRAINAGE PIPING
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
DIVISION 34 - TRANSPORTATION
34 71 13.19 ACTIVE VEHICLE BARRIERS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
SECTION 02 41 00
DEMOLITION AND DECONSTRUCTION
05/10
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO M 145 (1991; R 2012) Standard Specification for Classification of Soils and Soil-Aggregate Mixtures for Highway Construction Purposes
AASHTO T 180 (2017) Standard Method of Test for Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop
AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)
ASSE/SAFE A10.6 (2006) Safety Requirements for Demolition Operations
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 61 National Emission Standards for Hazardous Air Pollutants
1.2 PROJECT DESCRIPTION
1.2.1 Demolition/Deconstruction Plan
Prepare a Demolition Plan Deconstruction Plan and submit proposed salvage, demolition, deconstruction, and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress, a disconnection schedule of utility services a detailed description of methods and equipment to be used for each operation and of the sequence of operations. Identify components and materials to be salvaged for reuse or recycling with reference to paragraph Existing Facilities to be Removed. Append tracking forms for all removed materials indicating type, quantities, condition, destination, and end use.
Coordinate with Waste Management Plan. Provide procedures for safe conduct of the work in accordance with EM 385-1-1 . Plan shall be approved by Contracting Officer prior to work beginning.
SECTION 02 41 00 Page 1
1.2.2 General Requirements
Do not begin demolition or deconstruction until authorization is received from the Contracting Officer. The work of this section is to be performed in a manner that maximizes the value derived from the salvage and recycling of materials. Remove rubbish and debris from the project site;
do not allow accumulations inside or outside the buildings. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1 , Section 23, Demolition, and other applicable Sections.
1.3 ITEMS TO REMAIN IN PLACE
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer.
Coordinate the work of this section with all other work indicated.
Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract. Do not overload structural elements pavements to remain.
Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.
1.3.1 Existing Construction Limits and Protection
Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide temporary shoring and bracing for support of building components to prevent settlement or other movement. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove snow, dust, dirt, and debris from work areas daily.
1.3.2 Weather Protection
For portions of the building to remain, protect building interior and materials and equipment from the weather at all times. Where removal of existing roofing is necessary to accomplish work, have materials and workmen ready to provide adequate and temporary covering of exposed areas.
1.3.3 Trees
Protect trees within the project site which might be damaged during demolition or deconstruction, and which are indicated to be left in place, by a 6 foot high fence. Erect and secure fence a minimum of 5 feet from the trunk of individual trees or follow the outer perimeter of branches or clumps of trees. Replace any tree designated to remain that is damaged during the work under this contract with like-kind or as approved by the Contracting Officer.
1.3.4 Utility Service
Maintain existing utilities indicated to stay in service and protect against damage during demolition and deconstruction operations. Prior to start of work, utilities serving each area of alteration or removal will be shut off by the Government and disconnected and sealed by the Contractor
SECTION 02 41 00 Page 2
1.3.5 Facilities
Protect electrical and mechanical services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities. Floors, roofs, walls, columns, pilasters, and other structural components that are designed and constructed to stand without lateral support or shoring, and are determined to be in stable condition, must remain standing without additional bracing, shoring, or lateral support until demolished or deconstructed, unless directed otherwise by the Contracting Officer.
Ensure that no elements determined to be unstable are left unsupported and place and secure bracing, shoring, or lateral supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract.
1.4 BURNING
The use of burning at the project site for the disposal of refuse and debris will not be permitted . Where burning is permitted, adhere to federal, state, and local regulations.
1.5 AVAILABILITY OF WORK AREAS
Areas in which the work is to be accomplished will be available in accordance with the following schedule:
Schedule
Area Date
1.6 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29.00 06 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00.00 06 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Demolition Plan; G Deconstruction Plan; G Existing Conditions
SD-07 Certificates
Notification; G
1.7 QUALITY ASSURANCE
Submit timely notification of demolition deconstruction and renovation projects to Federal, State, regional, and local authorities in accordance
SECTION 02 41 00 Page 3 with 40 CFR 61 , Subpart M. Notify the local air pollution control district/agency and the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61 , Subpart M. Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSE/SAFE A10.6 . Comply with the Environmental Protection Agency requirements specified. Use of explosives will not be permitted.
1.7.1 Dust and Debris Control
Prevent the spread of dust and debris to occupied portions of the building and avoid the creation of a nuisance or hazard in the surrounding area.
Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution.
1.8 PROTECTION
1.8.1 Traffic Control Signs
a. Where pedestrian and driver safety is endangered in the area of removal work, use traffic barricades with flashing lights. Anchor barricades in a manner to prevent displacement by wind, jet or prop blast. Notify the Contracting Officer prior to beginning such work.
1.8.2 Protection of Personnel
Before, during and after the demolition and deconstruction work continuously evaluate the condition of the structure being demolished and deconstructed and take immediate action to protect all personnel working in and around the project site. No area, section, or component of floors, roofs, walls, columns, pilasters, or other structural element will be allowed to be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or failure while workmen remove debris or perform other work in the immediate area.
1.9 FOREIGN OBJECT DAMAGE (FOD)
Aircraft and aircraft engines are subject to FOD from debris and waste material lying on airfield pavements. Remove all such materials that may appear on operational aircraft pavements due to the Contractor's operations. If necessary, the Contracting Officer may require the Contractor to install a temporary barricade at the Contractor's expense to control the spread of FOD potential debris. The barricade shall include a fence covered with a fabric designed to stop the spread of debris. Anchor the fence and fabric to prevent displacement by winds or jet/prop blasts.
Remove barricade when no longer required.
1.10 RELOCATIONS
Perform the removal and reinstallation of relocated items as indicated with workmen skilled in the trades involved. Repair or replace items to be relocated which are damaged by the Contractor with new undamaged items as approved by the Contracting Officer.
1.11 EXISTING CONDITIONS
Before beginning any demolition or deconstruction work, survey the site and examine the drawings and specifications to determine the extent of the
SECTION 02 41 00 Page 4 work. Record existing conditions in the presence of the Contracting Officer showing the condition of structures and other facilities adjacent to areas of alteration or removal. Photographs sized 4 inch will be acceptable as a record of existing conditions. Include in the record the elevation of the top of foundation walls, finish floor elevations, possible conflicting electrical conduits, plumbing lines, alarms systems, the location and extent of existing cracks and other damage and description of surface conditions that exist prior to before starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. Submit survey results.
PART 2 PRODUCTS
2.1 FILL MATERIAL
a. Comply with excavating, backfilling, and compacting procedures for soils used as backfill material to fill basements, voids, depressions or excavations resulting from demolition or deconstruction of structures. Fill material shall be waste products from demolition or deconstruction until all waste appropriate for this purpose is consumed.
b. Fill material shall conform to the definition of satisfactory soil material as defined in AASHTO M 145, Soil Classification Groups A-1, A-2-4, A-2-5 and A-3. In addition, fill material shall be free from roots and other organic matter, trash, debris, frozen materials, and stones larger than 2 inches in any dimension.
c. Proposed fill material must be sampled and tested by an approved soil testing laboratory, as follows:
Soil classification AASHTO M 145
Moisture-density relations AASHTO T 180, Method B or D
PART 3 EXECUTION
3.1 DISPOSITION OF MATERIAL
3.1.1 Title to Materials
Except for salvaged items specified in related Sections, and for materials or equipment scheduled for salvage, all materials and equipment removed and not reused or salvaged, shall become the property of the Contractor and shall be removed from Government property. Title to materials resulting from demolition and deconstruction, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer of the Contractor's demolition, deconstruction, and removal procedures, and authorization by the Contracting Officer to begin demolition and deconstruction. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.
SECTION 02 41 00 Page 5
3.1.2 Salvaged Materials and Equipment
Remove materials and equipment that are indicated to be removed by the Contractor and that are to remain the property of the Government, and deliver to a storage site , as directed within 3 miles of the work site.
a. Salvage items and material to the maximum extent possible.
b. Store all materials salvaged for the Contractor as approved by the Contracting Officer and remove from Government property before completion of the contract. On site sales of salvaged material is prohibited.
c. Remove salvaged items to remain the property of the Government in a manner to prevent damage, and packed or crated to protect the items from damage while in storage or during shipment. Items damaged during removal or storage must be repaired or replaced to match existing items. Properly identify the contents of containers. Deliver the following items reserved as property of the Government to the areas designated on base by the Contracting Officer..
d. Remove the following items reserved as property of the using service prior to commencement of work under this contract: Northeast unit for chilled water.
3.2 CLEANUP
Remove debris and rubbish from basement and similar excavations. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.
3.3 DISPOSAL OF REMOVED MATERIALS
3.3.1 Regulation of Removed Materials
Dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations as contractually specified in the Waste Management Plan .
Storage of removed materials on the project site is prohibited.
3.3.2 Burning on Government Property
Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property .
3.3.3 Removal to Spoil Areas on Government Property
Transport noncombustible materials removed from demolition and deconstruction structures to designated spoil areas on Government property.
3.3.4 Removal from Government Property
Transport waste materials removed from demolished and deconstructed structures, except waste soil, from Government property for legal disposal. Dispose of waste soil as directed.
3.4 REUSE OF SALVAGED ITEMS
Recondition salvaged materials and equipment designated for reuse before
SECTION 02 41 00 Page 6 installation. Replace items damaged during removal and salvage operations or restore them as necessary to usable condition.
-- End of Section --
SECTION 02 41 00 Page 7
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 02 41 00 Page 8
SECTION 02 82 13.00 10
ASBESTOS ABATEMENT
02/10
PART 1 GENERAL
1.1 PAYMENT PROCEDURES
Submit copies of weight bills and delivery tickets for payment to the Contracting Officer during the progress of the work. Furnish scale tickets for each load of ACM weighed and certified. These tickets must include tare weight; identification mark for each vehicle weighed; and date, time and location of loading and unloading. Tickets must be furnished at the point and time individual trucks arrive at the worksite.
A master log of all vehicle loading must be furnished for each day of loading operations. Before the final statement is allowed, file with the Contracting Officer certified weigh bills and/or certified tickets and manifests of all ACM actually disposed by the Contractor for this contract.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)
ASSE/SAFE Z9.2 (2012) Fundamentals Governing the Design and Operation of Local Exhaust Ventilation Systems
ASTM INTERNATIONAL (ASTM)
ASTM D4397 (2016) Standard Specification for Polyethylene Sheeting for Construction, Industrial, and Agricultural Applications
ASTM E1368 (2014) Visual Inspection of Asbestos Abatement Projects
COMPRESSED GAS ASSOCIATION (CGA)
CGA G-7 (2014) Compressed Air for Human Respiration; 6th Edition
INTERNATIONAL SAFETY EQUIPMENT ASSOCIATION (ISEA)
ANSI/ISEA Z87.1 (2015) Occupational and Educational Personal Eye and Face Protection Devices
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 701 (2019) Standard Methods of Fire Tests for Flame Propagation of Textiles and Films
SECTION 02 82 13.00 10 Page 1
NATIONAL INSTITUTE FOR OCCUPATIONAL SAFETY AND HEALTH (NIOSH)
NIOSH NMAM (2016; 5th Ed) NIOSH Manual of Analytical Methods
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
EP 1110-1-11 (1992; Change 1 1997) Engineering and Design -- Asbestos Abatement Guideline Detail Sheets
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA 340/1-90/018 (1990) Asbestos/NESHAP Regulated Asbestos Containing Materials Guidance
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910.134 Respiratory Protection
29 CFR 1910.141 Sanitation
29 CFR 1910.147 Control of Hazardous Energy (Lock Out/Tag Out)
29 CFR 1926.1101 Asbestos
29 CFR 1926.32 Safety and Health Regulations for Construction - Definition
40 CFR 61 National Emission Standards for Hazardous Air Pollutants
40 CFR 763 Asbestos
42 CFR 84 Approval of Respiratory Protective Devices
49 CFR 107 Hazardous Materials Program Procedures
49 CFR 171 General Information, Regulations, and Definitions
49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communications, Emergency Response Information, and Training Requirements
49 CFR 173 Shippers - General Requirements for Shipments and Packagings
UNDERWRITERS LABORATORIES (UL)
UL 586 (2009; Reprint Dec 2017) Standard for High-Efficiency Particulate, Air Filter Units
SECTION 02 82 13.00 10 Page 2
1.3 DEFINITIONS
1.3.1 Amended Water
Water containing a wetting agent or surfactant with a surface tension of at least 29 dynes per square centimeter.
1.3.2 Asbestos-Containing Material (ACM)
Any materials containing more than one percent asbestos.
1.3.3 Authorized Person
Any person authorized by the Contractor and required by work duties to be present in the regulated areas.
1.3.4 Building Inspector
Individual who inspects buildings for asbestos and has EPA Model Accreditation Plan (MAP) "Building Inspector" training; accreditation required by 40 CFR 763 , Subpart E, Appendix C, has EPA/State certification/license as a "Building Inspector".
1.3.5 Class I Asbestos Work
Activities defined by OSHA involving the removal of thermal system insulation (TSI) and surfacing ACM.
1.3.6 Class II Asbestos Work
Activities defined by OSHA involving the removal of ACM which is not thermal system insulation or surfacing material. This includes, but is not limited to, the removal of asbestos - containing wallboard, floor tile and sheeting, roofing and siding shingles, and construction mastic.
Certain "incidental" roofing materials such as mastic, flashing and cements when they are still intact are excluded from Class II asbestos work. Removal of small amounts of these materials which would fit into a glovebag may be classified as a Class III job.
1.3.7 Class III Asbestos Work
Activities defined by OSHA that involve repair and maintenance operations, where ACM, including TSI and surfacing ACM, is likely to be disturbed.
Operations may include drilling, abrading, cutting a hole, cable pulling, crawling through tunnels or attics and spaces above the ceiling, where asbestos is actively disturbed or asbestos-containing debris is actively disturbed.
1.3.8 Class IV Asbestos Work
Maintenance and custodial construction activities during which employees contact but do not disturb ACM and activities to clean-up dust, waste and debris resulting from Class I, II, and III activities. This may include dusting surfaces where ACM waste and debris and accompanying dust exists and cleaning up loose ACM debris from TSI or surfacing ACM following construction
SECTION 02 82 13.00 10 Page 3
1.3.9 Clean Room
An uncontaminated room having facilities for the storage of employees' street clothing and uncontaminated materials and equipment.
1.3.10 Competent Person
In addition to the definition in 29 CFR 1926.32 (f), a person who is capable of identifying existing asbestos hazards as defined in 29 CFR 1926.1101 , selecting the appropriate control strategy, has the authority to take prompt corrective measures to eliminate them and has EPA Model Accreditation Plan (MAP) "Contractor/Supervisor" training; has EPA/State certification/license as a "Contractor/Supervisor".
1.3.11 Contractor/Supervisor
Individual who supervises asbestos abatement work and has EPA Model Accreditation Plan "Contractor/Supervisor" training; has EPA/State certification as a "Contractor/Supervisor".
1.3.12 Critical Barrier
One or more layers of plastic sealed over all openings into a regulated area or any other similarly placed physical barrier sufficient to prevent airborne asbestos in a regulated area from migrating to an adjacent area.
1.3.13 Decontamination Area
An enclosed area adjacent and connected to the regulated area and consisting of an equipment room, shower area, and clean room, which is used for the decontamination of workers, materials, and equipment that are contaminated with asbestos.
1.3.14 Demolition
The wrecking or taking out of any load-supporting structural member and any related razing, removing, or stripping of asbestos products.
1.3.15 Disposal Bag
A 6 mil thick, leak-tight plastic bag, pre-labeled in accordance with 29 CFR 1926.1101 , used for transporting asbestos waste from containment to disposal site.
1.3.16 Disturbance
Activities that disrupt the matrix of ACM, crumble or pulverize ACM, or generate visible debris from ACM. Disturbance includes cutting away small amounts of ACM, no greater than the amount which can be contained in 1 standard sized glovebag or waste bag, not larger than 60 inches in length and width in order to access a building component.
1.3.17 Equipment Room or Area
An area adjacent to the regulated area used for the decontamination of employees and their equipment.
SECTION 02 82 13.00 10 Page 4
1.3.18 Fiber
A fibrous particulate, 5 micrometers or longer, with a length to width ratio of at least 3 to 1.
1.3.19 Friable ACM
A term defined in 40 CFR 61 , Subpart M and EPA 340/1-90/018 meaning any material which contains more than 1 percent asbestos, as determined using the method specified in 40 CFR 763 , Polarized Light Microscopy (PLM), that when dry, can be crumbled, pulverized, or reduced to powder by hand pressure.
1.3.20 Glovebag
Not more than a 60 by 60 inch impervious plastic bag-like enclosure affixed around an asbestos-containing material, with glove-like appendages through which material and tools may be handled.
1.3.21 High-Efficiency Particulate Air (HEPA) Filter
A filter capable of trapping and retaining at least 99.97 percent of all mono-dispersed particles of 0.3 micrometers in diameter.
1.3.22 Intact
ACM which has not crumbled, been pulverized, or otherwise deteriorated so that the asbestos is no longer likely to be bound with its matrix.
Removal of "intact" asphaltic, resinous, cementitious products does not render the ACM non-intact simply by being separated into smaller pieces.
1.3.23 Model Accreditation Plan (MAP)
USEPA training accreditation requirements for persons who work with asbestos as specified in 40 CFR 763 .
1.3.24 Negative Initial Exposure Assessment
A demonstration by the Contractor to show that employee exposure during an operation is expected to be consistently below the OSHA Permissible Exposure Limits (PELs).
1.3.25 NESHAP
National Emission Standards for Hazardous Air Pollutants. The USEPA NESHAP regulation for asbestos is at 40 CFR 61 , Subpart M.
1.3.26 Nonfriable ACM
A NESHAP term defined in 40 CFR 61 , Subpart M and EPA 340/1-90/018 meaning any material containing more than 1 percent asbestos that, when dry, cannot be crumbled, pulverized or reduced to powder by hand pressure.
1.3.27 Nonfriable ACM (Category I)
A NESHAP term defined in 40 CFR 61 , Subpart E and EPA 340/1-90/018 meaning asbestos-containing packings, gaskets, resilient floor covering, and asphalt roofing products containing more than 1 percent asbestos.
SECTION 02 82 13.00 10 Page 5
1.3.28 Nonfriable ACM (Category II)
A NESHAP term defined in 40 CFR 61 , Subpart E and EPA 340/1-90/018 meaning any material, excluding Category I nonfriable ACM, containing more than 1 percent asbestos.
1.3.29 Permissible Exposure Limits (PELs)
1.3.29.1 PEL-Time Weighted Average(TWA)
Concentration of asbestos not in excess of 0.1 fibers per cubic centimeter of air (f/cc) as an 8 hour time weighted average (TWA).
1.3.29.2 PEL-Excursion Limit
An airborne concentration of asbestos not in excess of 1.0 f/cc of air as averaged over a sampling period of 30 minutes.
1.3.30 Regulated Area
An OSHA term defined in 29 CFR 1926.1101 meaning an area established by the Contractor to demarcate areas where Class I, II, and III asbestos work is conducted; also any adjoining area where debris and waste from such asbestos work accumulate; and an area within which airborne concentrations of asbestos exceed, or there is a reasonable possibility they may exceed, the permissible exposure limit.
1.3.31 Removal
All operations where ACM is taken out or stripped from structures or substrates, and includes demolition operations.
1.3.32 Repair
Overhauling, rebuilding, reconstructing, or reconditioning of structures or substrates, including encapsulation or other repair of ACM attached to structures or substrates.
1.3.33 Surfacing ACM
Asbestos-containing material which contains more than 1 percent asbestos and is sprayed-on, troweled-on, or otherwise applied to surfaces, such as acoustical plaster on ceilings and fireproofing materials on structural members, or other materials on surfaces for acoustical, fireproofing, or other purposes.
1.3.34 Thermal System Insulation (TSI) ACM
ACM which contains more than 1 percent asbestos and is applied to pipes, fittings, boilers, breeching, tanks, ducts, or other interior structural components to prevent heat loss or gain or water condensation.
1.3.35 Transite
A generic name for asbestos cement wallboard and pipe.
1.3.36 Worker
Individual (not designated as the Competent Person or a supervisor) who
SECTION 02 82 13.00 10 Page 6 performs asbestos work and has completed asbestos worker training required by 29 CFR 1926.1101 , to include EPA Model Accreditation Plan (MAP) "Worker" training; accreditation if required by the OSHA Class of work to be performed or by the state where the work is to be performed.
1.4 SYSTEM DESCRIPTION
This section covers all operations in which asbestos-containing materials (ACM) are encountered. These procedures and equipment are required to protect workers and building occupants from airborne asbestos fibers and ACM dust and debris. Activities include OSHA Class II and Class IV work operations. This section also includes containment, storage, transportation and disposal of the generated ACM wastes. Submit Detailed Drawings in accordance with EP 1110-1-11 and containing descriptions, and site layout to include worksite containment area(s), local exhaust systems locations, decontamination units and load-out units, other temporary waste storage facility, access tunnels, location of temporary utilities (electrical, water, sewer) and boundaries of each regulated area. When the detail sheets are not attached to this specification, the Contractor can get them from the web at:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerPamphlets/EP_1110-1-11.pdf
1.4.1 Abatement Work Tasks
The specific ACM to be abated is identified on the detailed plans and project drawings . A summary for each work task including the appropriate RESPONSE ACTION DETAIL SHEET (item to be abated and methods to be used) and SET-UP DETAIL SHEETS (containment techniques to include safety precautions and methods) is included in Table 1, "Individual Work Task Data Elements" at the end of this section.
1.4.2 Unexpected Discovery of Asbestos
For any previously untested building components suspected to contain asbestos and located in areas impacted by the work, notify the Contracting Officer (CO) who will have the option of ordering up to 15 bulk samples to be obtained at the Contractor's expense and delivered to a laboratory accredited under the National Institute of Standards and Technology (NIST) "National Voluntary Laboratory Accreditation Program (NVLAP)" and analyzed by PLM. If the asbestos content is less than 10 percent, as determined by a method other than point counting, the asbestos content must be verified by point counting. Any additional components identified as ACM that have been approved by the CO for removal must be removed and will be paid for by an equitable adjustment to the contract price under the CONTRACT CLAUSE titled "changes". Sampling must be conducted by personnel who have successfully completed the EPA Model Accreditation Plan (MAP) "Building Inspector" training course and is EPA/State certified/licensed as a "Building Inspector".
1.4.3 Wallboard/Joint Compound
Samples of the wallboard systems (wallboard and joint compound) have been tested. Samples of the wallboard system were tested and found to contain no detectable level of asbestos.
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control
SECTION 02 82 13.00 10 Page 7 approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29.00 06 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00.00 06 SUBMITTAL
PROCEDURES:
SD-02 Shop Drawings
Detailed Drawings; G
SD-03 Product Data
Asbestos Waste Shipment Records; G Weight Bills and Delivery Tickets Encapsulants; G Respiratory Protection Program; G Cleanup and Disposal; G Qualifications; G Training Program Licenses, Permits and Notifications Asbestos Management Plan; G
SD-06 Test Reports
Exposure Assessment and Air Monitoring Local Exhaust System
SD-07 Certificates
Local Exhaust System Encapsulants; G Medical Surveillance Requirements
1.6 QUALITY ASSURANCE
In addition to detailed requirements of this specification, work performed under this contract must comply with EM 385-1-1 , applicable federal, state, and local laws, ordinances, criteria, rules and regulations regarding handling, storing, transporting, and disposing of asbestos waste materials. Matters of interpretation of standards must be submitted to the appropriate administrative agency for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements must apply. The following state and local laws, rules and regulations regarding demolition, removal, encapsulation, construction alteration, repair, maintenance, renovation, spill/emergency cleanup, housekeeping, handling, storing, transporting and disposing of asbestos material apply.
1.6.1 Written Qualifications and Organization Report
Submit a written qualifications and organization report providing evidence of qualifications of the Contractor, Contractor's Project Supervisor, Designated Competent Person, supervisors and workers; Designated IH;
independent testing laboratory; all subcontractors to be used including disposal transportation and disposal facility firms, subcontractor supervisors, subcontractor workers ; and any others assigned to perform asbestos abatement and support activities. Include in the report an
SECTION 02 82 13.00 10 Page 8 organization chart showing the Contractor's staff organization chain of command and reporting relationship with all subcontractors. The report must be signed by the Contractor, the Contractor's onsite project manager, Designated Competent Person, Designated IH, designated testing laboratory and the principals of all subcontractors to be used. Include the following statement in the report: "By signing this report I certify that the personnel I am responsible for during the course of this project fully understand the contents of 29 CFR 1926.1101 , 40 CFR 61 , Subpart M, and the federal, state and local requirements for those asbestos abatement activities that they will be involved in."
1.6.2 Specific Requirements
Designate in writing, personnel meeting the following qualifications:
a. Asbestos Abatement Contractor: Certified/licensed Illinois Department of Public Health (IDHP) to perform asbestos-related activities.
b. Designated Competent Person: Qualified in accordance with 29 CFR 1926.32 and 29 CFR 1926.1101 , has EPA MAP "Contractor/Supervisor" training accreditation, has EPA/State certification/license as a "Contractor/Supervisor" and is experienced in the administration and supervision of asbestos abatement projects , including exposure assessment and monitoring, work practices, abatement methods, protective measures for personnel, setting up and inspecting asbestos abatement work areas, evaluating the integrity of containment barriers, placement and operation of local exhaust systems, ACM generated waste containment and disposal procedures, decontamination units installation and maintenance requirements, site safety and health requirements, notification of other employees onsite, etc. The Designated Competent Person must be responsible for compliance with applicable federal, state and local requirements, the Contractor's Accident Prevention Plan (APP) and Asbestos Hazard Abatement Plan (AHAP). Submit the "Contractor/Supervisor" course completion certificate and the most recent certificate for required refresher training, IDHP certification/license with the employee "Certificate of Worker Acknowledgment". Submit evidence that this person has a minimum of 2 years of on-the-job asbestos abatement experience relevant to OSHA competent person requirements. The Designated Competent Person must be onsite at all times during the conduct of this project.
c. Project and Other Supervisors: Have EPA MAP "Contractor/Supervisor" training accreditation. Submit the "Contractor/Supervisor" course completion certificate and the most recent certificate for required refresher training, IDHP State certification/license with the employee "Certificate of Worker Acknowledgment". Also submit evidence that the Project Supervisor has a minimum of 2 years of on-the-job asbestos abatement experience relevant to project supervisor responsibilities and the other supervisors have a minimum of 1 year on-the-job asbestos abatement experience commensurate with the responsibilities they will have on this project.
d. Designated Industrial Hygienist: Resume for the Industrial Hygienist (IH) selected to prepare the Contractor's AHAP, prepare and perform training, direct air monitoring and assist the Contractor's Competent Person in implementing and ensuring that safety and health requirements are complied with during the performance of all required work. The Designated IH must be a person who is board certified in
SECTION 02 82 13.00 10 Page 9 the practice of industrial hygiene or board eligible (meets all education and experience requirements) as determined and documented by the American Board of Industrial Hygiene (ABIH), has EPA MAP "Contractor/Supervisor" training accreditation, IDHP certification/license, and has a minimum of 2 years of comprehensive experience in planning and overseeing asbestos abatement activities.
Submit the "Contractor/Supervisor" course completion certificate and the most recent certificate for required refresher training and EPA/State certification/license with the employee "Certificate of Worker Acknowledgment". The Designated IH must be completely independent from the Contractor according to federal, state, or local regulations; that is, must not be a Contractor's employee or be an employee or principal of a firm in a business relationship with the Contractor negating such independent status. A copy of the Designated IH's current valid ABIH certification or confirmation of eligibility in writing from the ABIH must be included. The Designated IH must visit the site at least 1 time per week for the duration of asbestos activities and must be available for emergencies. In addition, submit resumes of additional IH's and industrial hygiene technicians (IHT) who will be assisting the Designated IH in performing onsite tasks.
IHs and IHTs supporting the Designated IH must have a minimum of 1 year of practical onsite asbestos abatement experience. Indicate the formal reporting relationship between the Designated IH and the support IHs and IHTs, the Designated Competent Person, and the Contractor.
e. Asbestos Abatement Workers: Meet the requirements contained in 29 CFR 1926.1101 , 40 CFR 61 , Subpart M, and other applicable federal, state and local requirements. Worker training documentation must be provided as required on the "Certificate of Workers Acknowledgment".
Training documentation is required for each employee who will perform OSHA Class I, Class II, Class III, or Class IV asbestos abatement operations. Such documentation must be submitted on a Contractor generated form titled "Certificate of Workers Acknowledgment", to be completed for each employee in the same format and containing the same information as the example certificate at the end of this section.
Training course completion certificates (initial and most recent update refresher) required by the information checked on the form must be attached.
f. Physician: Resume of the physician who will or has performed the medical examinations and evaluations of the persons who will conduct the asbestos abatement work tasks. The physician must be currently licensed by the state where the workers will be or have been examined, have expertise in pneumoconiosis and must be responsible for the determination of medical surveillance protocols and for review of examination/test results performed in compliance with 29 CFR 1926.1101 .
The physician must be familiar with the site's hazards and the scope of this project.
g. Independent Testing Laboratory: identify the independent testing laboratory selected to perform the sample analyses and report the results. The testing laboratory must be completely independent from the Contractor as recognized by federal, state or local regulations.
Written verification of the following criteria, signed by the testing laboratory principal and the Contractor, must be submitted:
(1) Phase contrast microscopy (PCM): The laboratory is fully equipped and proficient in conducting PCM of airborne samples
SECTION 02 82 13.00 10 Page 10 using the methods specified by 29 CFR 1926.1101 , OSHA method ID-160, the most current version of NIOSH NMAM Method 7400 as shown in Table 3 at the end of this Section. The laboratory must be currently judged proficient (classified as acceptable) in counting airborne asbestos samples by PCM by successful participation in each of the last 4 rounds in the American Industrial Hygiene Association (AIHA) Proficiency Analytical Testing (PAT) Program or by participating in the AIHA PAT Program, and being judged proficient in counting samples.
(2) Polarized light microscopy (PLM): The laboratory is fully equipped and proficient in conducting PLM analyses of suspect ACM bulk samples in accordance with 40 CFR 763 , Subpart E, Appendix E;
the laboratory is currently accredited by NIST under the NVLAP for bulk asbestos analysis and will use analysts with demonstrated proficiency to conduct PLM analyses.
(3) Transmission electron microscopy (TEM): The laboratory is fully equipped and proficient in conducting TEM analysis of airborne samples using the mandatory method specified by 40 CFR 763 , Subpart E, Appendix E; the laboratory is currently accredited by NIST under the NVLAP for airborne sample analysis of asbestos by TEM; the laboratory will use analysts with demonstrated proficiency under NVLAP.
(4) PCM/TEM: The laboratory is fully equipped and each analyst is proficient in conducting PCM and TEM analysis of airborne samples using NIOSH NMAM Method 7400 PCM and NIOSH NMAM Method 7402 (TEM confirmation of asbestos content of PCM results) from the same filter.
h. Disposal Facility, Transporter: Written evidence that the landfill to be used is approved for asbestos disposal by the applicable regulatory agencies. Copies of signed agreements between the Contractor (including subcontractors and transporters) and the asbestos waste disposal facility to accept and dispose of all asbestos containing waste must be provided. The Contractor and transporters must meet the DOT requirements of 49 CFR 171 , 49 CFR 172 , and 49 CFR 173 as well as registration requirements of 49 CFR 107 and other applicable state or local requirements. The disposal facility must meet the requirements of 40 CFR 61 , Sections .154 or .155, as required in 40 CFR 61 150(b), and other applicable state or local requirements.
1.6.3 Federal, State or Local Citations on Previous Projects
The Contractor and all subcontractors must submit a statement, signed by an officer of the company, containing a record of any citations issued by Federal, State or local regulatory agencies relating to asbestos activities (including projects, dates, and resolutions); a list of penalties incurred through non-compliance with asbestos project specifications, including liquidated damages, overruns in scheduled time limitations and resolutions; and situations in which an asbestos-related contract has been terminated (including projects, dates, and reasons for terminations). If there are none, a negative declaration signed by an officer of the company must be provided.
1.6.4 Preconstruction Conference
The Contractor and the Contractor's Designated Competent Person, Project
SECTION 02 82 13.00 10 Page 11
Supervisor, and Designated IH must meet with the Contracting Officer (CO) prior to beginning work at a safety preconstruction conference to discuss the details of the Contractor's submitted APP to include the AHAP and AHAs appendices. Deficiencies in the APP will be discussed. Onsite work must not begin until the APP has been accepted.
1.7 SAFETY
Prepare a written comprehensive site-specific Accident Prevention Plan (APP) at least 10 days prior to the preconstruction conference. The APP must be in accordance with the format and requirements in Appendix A of EM 385-1-1 . The APP must incorporate an Asbestos Hazard Abatement Plan (AHAP), and Activity Hazard Analyses (AHAs) as separate appendices into one site-specific document. The APP must take into consideration all the individual asbestos abatement work tasks identified in Table 1.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .