W912QR20B0024_Specs-0002.pdf
PDF 1 MB Posted
- Attached to
- Repair Airfield Lighting at Grissom ARB, IN
- Solicitation number
- W912QR20B0024
About this file
This federal contract opportunity notice seeks proposals for the repair of airfield lighting systems at Grissom Air Reserve Base in Indiana. Key details include:
-
The project scope involves replacing existing taxiway and runway lighting circuits and conduit, replacing windsocks at each end of the runway, and upgrading airfield lighting subsystems including runway edge lights, taxiway edge lights, signs, and approach lighting.
-
The contract duration is estimated at 540 calendar days. A pre-bid site visit will be held with meeting details provided in the solicitation.
-
This will be a firm-fixed-price contract awarded under FAR Part 14 to the lowest priced bid. The North American Industry Classification System code is 238210.
-
The construction magnitude is anticipated to be between $5-10 million. The procurement will be unrestricted and fully open to competition.
-
Proposals are due in response to Solicitation Number W912QR20B0024 issued by the U.S. Army Corps of Engineers Engineering District Louisville.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912QR20B0024 (Abtsract of Bidders).pdf | ||
| W912QR20B0024_Plans-0002.pdf | ||
| W912QR20B0024-0001.pdf | ||
| W912QR20B0024_Plans-0000.pdf | ||
| W912QR20B0024_Specs-0000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY/RESERVE BRANCH
ATTN: KARLA WRIGHT
600 DR M L KING JR PL RM 821
LOUISVILLE KY 40202-2236
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
W912QR20B0024 for Repair/Replace Airfield Lighting System (PHASE A) at Grissom Air Reserve (GARB) Base, Indiana is hereby modified as follow s:
SEE CONTINUATION
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912QR20B0024
X 9B. DATED (SEE ITEM 11)
18-Aug-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
U0002
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Sep-2020
CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
W912QR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE 964859
FACILITY CODECODE
EMAIL:TEL:
W912QR20B0024_Specs-0002
W912QR20B0024
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMDT 0002 SUMMARY OF CHANGES
SUMMARY OF CHANGES
Solcitation W912QR20B0024 for the Repair/Replace Airfield Lighting Syste (PHASE A) at Grissom Air Reserve (GARB) Base, Indiana is hereby modified as follows:
a. SECTION 00 00 00 – SUBMISSION INSTRUCTIONS – The bid opening call will take place at 2:00 PM Eastern Time on 21 September 2020.
b. SECTION 00 10 00 – SOLICITATION – The required response date/time has changed from 18 September 2020 at 1:00 PM Eastern Time to 21 September 2020 at 1:00 PM Eastern Time.
c. The following PLAN SHEETS have been replaced in their entirety:
C-100
d. The following SPECIFICATION SECTIONS have been replaced in their entirety:
01 45 04.10 06 Contractor Quality Control 03 99 00 Elastomeric Concrete 26 56 20.00 10 Airfield Lighting and Visual Navigation Aids 31 23 00.00 20 Excavation Fill 32 12 15.13 Asphalt Paving for Airfields 33 05 23.13 Utility Horizontal Directional Drilling 33 71 02 Underground Electrical Distribution
e. All other terms and conditions remain unchanged.
SECTION 00 00 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
The following have been modified:
SUBMISSION INSTRUCTIONS
Solicitation W912QR20B0024 will have the Bid opening held virtually via teleconference line. Please utilize the call in information below to call in and hear the opening of the bids information. In addition a bidders list will be posted to the beta.SAM.gov website for all offeror's following the virtual bid opening.
Conference Line: 866-434-5269 Access Code: 6311418 Security Code: 1234
The call will take place at 2:00 PM Eastern Time on 21 September 2020.
W912QR20B0024
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 18-Sep-2020 01:00 PM to 21-Sep-2020 01:00 PM.
(End of Summary of Changes)
Airfield Lighting Improvements - Phase A CTGB-15-2012-A Grissom Air Reserve Base, IN
SECTION 01 45 04.10 06
CONTRACTOR QUALITY CONTROL
04/20
Amendment 0002
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D3740 (2019) Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction
ASTM E329 (2018) Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection
1.2 PAYMENT
Separate payment will not be made for providing and maintaining an effective Quality Control program, and all costs associated therewith shall be included in the applicable unit prices or lump-sum prices contained in the Bidding Schedule.
1.3 SUBMITTALS
Government approval/acceptance is required for submittals with a "G" designation; submittals not having a "G" designation are for Contractor Quality Control approval, or for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with LRL Section 01 33 00.00 06 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Construction Quality Control Plan; G, RO
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
The Contractor is responsible for quality control and shall establish and maintain an effective quality control system in compliance with FAR 52.246-12 - Inspection of Construction. The quality control system shall consist of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. The system shall cover all design and construction operations, both onsite and offsite, and
SECTION 01 45 04.10 06 Page 1
AMENDMENT 0002
shall be keyed to the proposed construction sequence. The site project superintendent will be held responsible for the quality of work on the job and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract. The site project superintendent in this context shall be the highest level manager responsible for the overall construction activities at the site, including quality and production. The site project superintendent shall maintain a physical presence at the site at all times, except as otherwise acceptable to the Contracting Officer, and shall be responsible for all construction and construction related activities at the site.
3.2 NOT USED
Amendment 0002***************************************************************
3.3 CONSTRUCTION QUALITY CONTROL PLAN (CQCP)
The Contractor shall furnish for review by the Government, not later than thirty (30) days after receipt of notice to proceed, the Contractor Construction Quality Control (CQC) Plan proposed to implement the requirements of FAR 52.246-12 - Inspection of Construction. The plan shall identify personnel, procedures, control, instructions, tests, records, and forms to be used. The Government will consider an interim plan for the first thirty (30) days of operation. Construction will be permitted to begin only after acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the features of work included in an accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional features of work to be started.
After award of contract, the contractor shall submit resumes and qualifications for the below listed in-house personnel, subcontractors, and outside associates or consultants proposed to work on this project. Only in-house personnel, subcontractors, and outside associates or consultants approved by the Contracting Officer shall be allowed to perform any work.
The roles/positions that shall require resumes and qualifications approved by the Contracting Officer prior to performing work are:
Quality Control Manager Electrical Superintendent (required Master Electrician) NAVAIDS Superintendent
Minimum qualifications to submit include 5 years of experience and 3 past projects of similar scope and complexity, and a Master Electrician certification for the Electrical Superintendent.
The NAVAIDS Superintendent can be the same person as the Electrical Superintendent, as long as the individual being proposed to serve in both roles can demonstrate the necessary experience levels in each of the two roles, separately and independently.
Due to the nature of this project and complexity of the work involved, the qualifications and experience of the above mentioned roles/positions will be under tight scrutiny by the Contracting Officer based on Section 26 56
20.00 10 "Airfield Lighting and Visual Navigation Aids," Part 1.4 "Quality Assurance".
In the case that the Contracting Officer believes that the in-house
SECTION 01 45 04.10 06 Page 2 personnel, subcontractors, or outside associates or consultants are not performing up to the standards outlined in the contracting documents and the information submitted in the approved proposal, the Contracting Officer can require a forced substitution of said personnel. In this case, the Contractor shall submit the same type of information that was submitted in the accepted proposal to the Contracting Officer for evaluation and approval. The level of qualifications and experience submitted in the accepted proposal or that required by the Solicitation, whichever is greater, is the minimum standard for any substitution.
***************************************************************Amendment 0002
3.3.1 Content of the CQC Plan
The CQC Plan shall include, as a minimum, the following to cover all construction operations, both onsite and offsite, including work by subcontractors, fabricators, suppliers, and purchasing agents:
a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff shall implement the three phase control system for all aspects of the work specified. The staff shall include a CQC System Manager who shall report to someone higher in the Contractor's organization than the project superintendent, shall not be the superintendent.
b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC function.
c. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the contract. The CQC System Manager shall issue letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities. Copies of these letters shall also be furnished to the Government.
d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, offsite fabricators, suppliers, and purchasing agents. These procedures shall be in accordance with LRL Section 01 33 00.00 06 SUBMITTAL
PROCEDURES.
e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facilities will be approved by the Contracting Officer.)
f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.
g. Procedures for tracking construction deficiencies from identification through acceptable corrective action. These procedures shall establish verification that identified
SECTION 01 45 04.10 06 Page 3 deficiencies have been corrected.
h. Reporting procedures, including proposed reporting formats.
i. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and may be identified by different trades or disciplines, or it may be work by the same trade in a different environment. Although each section of the specifications may generally be considered as a definable feature of work, there are frequently more than one definable features under a particular section. This list will be agreed upon during the coordination meeting.
3.3.2 Acceptance of Plan
Acceptance of the Contractor's plan is required prior to the start of construction. Acceptance is conditional and will be predicated on satisfactory performance during the construction. The Government reserves the right to require the Contractor to make changes in his CQC Plan and operations including removal of personnel, as necessary, to obtain the quality specified.
3.3.3 Notification of Changes
After acceptance of the CQC Plan, the Contractor shall notify the Contracting Officer in writing of any proposed change. Proposed changes are subject to acceptance by the Contracting Officer.
3.4 COORDINATION MEETING
After the Preconstruction Conference, before start of construction, and prior to acceptance by the Government of the CQC Plan, the Contractor shall meet with the Contracting Officer or Authorized Representative and discuss the Contractor's quality control system. The CQC Plan shall be submitted for review a minimum of thirty (30) calendar days prior to the Coordination Meeting. During the meeting, a mutual understanding of the system details shall be developed, including the forms for recording the CQC operations, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting shall be prepared by the Government and signed by both the Contractor and the Contracting Officer. The minutes shall become a part of the contract file. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the CQC system or procedures which may require corrective action by the Contractor.
3.4.1 Subcontractor CQC Orientation
Before a Subcontractor begins work on the jobsite, the CQC System Manager will train the Subcontractor and answer any questions pertaining to quality control operations. This requirement is waived only if a Subcontractor attended the initial coordination meeting described above. A record of the orientation shall be documented in the QC Report.
SECTION 01 45 04.10 06 Page 4
3.5 CONSTRUCTION QUALITY CONTROL ORGANIZATION
3.5.1 Personnel Requirements
a. The requirements for the CQC organization are a CQC System Manager and sufficient number of additional qualified personnel to ensure safety and contract compliance. A Site Safety Health Officer (SSHO) will be required for this contract. See LRL Section 01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS for the SSHO qualifications and duties.
b. Personnel identified in the technical provisions as requiring specialized skills to assure the required work is being performed properly will also be included as part of the CQC organization. The Contractor's CQC staff shall maintain a presence at the site at all times during progress of the work and have complete authority and responsibility to take any action necessary to ensure contract compliance. The CQC staff shall be subject to acceptance by the Contracting Officer. The Contractor shall provide adequate office space, filing systems and other resources as necessary to maintain an effective and fully functional CQC, and safety/health organization. Complete records of all letters, material submittals, shop drawing submittals, schedules and all other project documentation shall be promptly furnished to the CQC organization by the Contractor. The CQC organization shall be responsible to maintain these documents and records at the site at all times and made available to the SSHO, except as otherwise acceptable to the Contracting Officer.
3.5.2 CQC System Manager Qualifications and Duties
a. The Contractor shall identify as CQC System Manager an individual within the onsite work organization who shall be responsible for overall management of CQC and have the authority to act in all CQC matters for the Contractor. The CQC System Manager shall be either a graduate engineer or graduate architect, with a minimum of 5 years construction experience on construction similar to this contract, or a construction person with a minimum of 10 years in related quality management work.
b. This CQC System Manager shall be employed by the Prime Contractor and be on the site at all times during construction. Alternate(s) for the CQC System Manager shall be identified in the CQC Plan to serve in the event of the CQC System Manager's absence. The requirements for the alternates shall be the same as for the designated CQC System Manager.
c. The CQC System Manager shall be:
assigned no other duties except being the CQC System Manager. Shall not be the SSHO or the superintendent.
3.5.3 CQC Personnel
b. In addition to CQC personnel specified elsewhere in the contract, the Contractor shall provide as part of the CQC organization specialized personnel to assist the CQC System Manager for the following areas identified per Experience Matrix Table. These individuals may be employees of the prime or subcontractor. These individuals identified per the Experience Matrix Table, shall be responsible to the CQC System Manager; be
SECTION 01 45 04.10 06 Page 5 physically present at the construction site during work on their areas of responsibility; have the necessary education and/or experience in accordance with the experience matrix listed herein. These individuals in the Experience Matrix Table may perform other duties but must be allowed sufficient time to perform their assigned quality control duties as described in the Quality Control Plan.
c. The word "graduate" below indicates an individual possessing a four-year college degree accredited in the respective field listed-with experience obtained following graduation in the type of work being performed on the project.
Experience Matrix Table
AREA QUALIFICATIONS
a. Civil Graduate Civil Engineer with 2 years related experience or person with 5 yrs related experience
b. Geotechnical Graduate Geotechnical Engineer or Civil Engineer specializingin Geotechnical Engineering with 3 yrs relevant experience or Engineering Technician, working under the direction of a Licensed Professional Engineer, with 5 yrs relevant experience
c. Electrical Graduate Electrical Engineer with 2 yrs related experience or person with 5 yrs related experience d.. Concrete, Pavements and Soils Civil Engineer identified in item A or B above, and supplemented with the Corps validated QC testing laboratory
3.5.3.1 NOT USED
3.5.3.2 NOT USED
3.5.4 Additional Requirement
In addition to the above experience and/or education requirements the CQC System Manager and Alternate(s) shall have completed and passed the course
SECTION 01 45 04.10 06 Page 6 entitled "Construction Quality Management For Contractors" within the last 5 years. A copy of the certification shall be provided with the CQCP.
This course is periodically offered by the Associated Builders and Constructors, Inc., or Associated General Contractor, Inc., and the U.S.
Army Corps of Engineers.
3.5.5 Organizational Changes
The Contractor shall maintain the CQC staff at full strength at all times.
When it is necessary to make changes to the CQC staff, the Contractor shall revise the CQC Plan to reflect the changes and submit the changes to the Contracting Officer for acceptance.
3.6 SUBMITTALS AND DELIVERABLES
Submittals, if needed, shall be made as specified in LRL Section 01 33 00.00 06 SUBMITTAL PROCEDURES. The CQC organization shall be responsible for certifying that all submittals and deliverables are in compliance with the contract requirements. When LRL Section 01 46 00.00 06 TOTAL BUILDING COMMISSIONING is included in the contract, the submittals required by those sections shall be coordinated with LRL Section 01 33 00.00 06 SUBMITTAL PROCEDURES to ensure adequate time is allowed for each type of submittal required.
3.7 CONTROL
Contractor Quality Control is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. At least three phases of control shall be conducted by the CQC System Manager for each definable feature of work as follows:
3.7.1 Preparatory Phase
This phase shall be performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase shall include:
a. A review of each paragraph of applicable specifications, reference codes, and standards. A copy of those sections of referenced codes and standards applicable to that portion of the work to be accomplished in the field shall be made available by the Contractor at the preparatory inspection. These copies shall be maintained in the field and available for use by Government personnel until final acceptance of the work.
b. A review of the contract drawings.
c. A check to assure that all materials and/or equipment have been tested, submitted, and approved.
d. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the contract.
e. A physical examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawings or submitted data, and are properly stored.
SECTION 01 45 04.10 06 Page 7
f. A review of the appropriate activity hazard analysis to assure safety requirements are met.
g. Discussion of procedures for controlling quality of the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that feature of work.
h. A check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer.
i. Resolve all differences.
j. Discussion of the initial control phase.
k. Review of provisions that have been made to provide required control inspection and testing.
l. Review of the CQC plan, specifically its organization chart and delegation letters. Insure all required members of the CQC organization for this feature of work are qualified, have been appointed, accepted and have requisite authority delegated.
m. The Government shall be notified at least 24 hours in advance of beginning the preparatory control phase. This phase shall include a meeting conducted by the CQC System Manager and attended by the superintendent, other CQC personnel (as applicable), and the foreman responsible for the definable feature. The results of the preparatory phase actions shall be documented by separate minutes prepared by the CQC System Manager and attached to the daily CQC report. The Contractor shall instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.
3.7.2 Initial Phase
This phase shall be accomplished at the beginning of a definable feature of work. The following shall be accomplished:
a. A check of work to ensure that it is in full compliance with contract requirements. Review minutes of the preparatory meeting.
b. Verify adequacy of controls to ensure full contract compliance.
Verify required control inspection and testing.
c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required sample panels as appropriate.
d. Resolve all differences.
e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.
f. The Government shall be notified at least 24 hours in advance of beginning the initial phase. Separate minutes of this phase shall be prepared by the CQC System Manager and attached to the daily CQC report. Exact location of initial phase shall be indicated
SECTION 01 45 04.10 06 Page 8 for future reference and comparison with follow-up phases.
g. The initial phase should be repeated for each new crew to work onsite, or any time acceptable specified quality standards are not being met.
3.7.3 Follow-up Phase
Daily checks shall be performed to assure control activities, including control testing, are providing continued compliance with contract requirements, until completion of the particular feature of work. The checks shall be made a matter of record in the CQC documentation. Final follow-up checks shall be conducted and all deficiencies corrected prior to the start of additional features of work which may be affected by the deficient work. The Contractor shall not build upon nor conceal non-conforming work.
3.7.4 Additional Preparatory and Initial Phases
Additional preparatory and initial phases shall be conducted on the same definable features of work if: the quality of on-going work is unacceptable; if there are changes in the applicable CQC staff, onsite production supervision or work crew; if work on a definable feature is resumed after a substantial period of inactivity; or if other problems develop.
3.8 TESTS
3.8.1 Testing Procedure
The Contractor shall perform specified or required tests to verify that control measures are adequate to provide a product which conforms to contract requirements. Upon request, the Contractor shall furnish to the Government duplicate samples of test specimens for possible testing by the Government. Testing includes operation and/or acceptance tests when specified. For QC testing of construction materials including soil, rock, aggregate, asphalt, concrete, and steel, the Contractor shall procure the services of a Corps of Engineers (COE) validated testing laboratory or establish a COE validated testing laboratory at the project site.
Technical specifications included in the contract that require materials testing by an approved commercial testing laboratory shall be intended to mean by a COE validated laboratory. The Contractor shall perform the following activities and record and provide the following data:
a. Verify that testing procedures comply with contract requirements.
b. Verify that facilities and testing equipment are available and comply with testing standards.
c. Check test instrument calibration data against certified standards.
d. Verify that recording forms and test identification control number system, including all of the test documentation requirements, have been prepared.
e. Results of all tests taken, both passing and failing tests, shall be recorded on the CQC report for the date taken. Specification paragraph reference, location where tests were taken, and the sequential control number identifying the test shall be given. If
SECTION 01 45 04.10 06 Page 9 approved by the Contracting Officer, actual test reports may be submitted later with a reference to the test number and date taken. An information copy of tests performed by an offsite or commercial test facility shall be provided directly to the Contracting Officer. Failure to submit timely test reports as stated may result in nonpayment for related work performed and disapproval of the test facility for this contract.
3.8.2 Testing Laboratories
3.8.2.1 Capability Check
The Government reserves the right to check laboratory equipment in the proposed laboratory for compliance with the standards set forth in the contract specifications and to check the laboratory technician's testing procedures and techniques. Laboratories utilized for testing soils, concrete, asphalt, and steel shall meet criteria detailed in ASTM D3740 and
ASTM E329.
3.8.2.2 Capability Recheck
If the selected laboratory fails the capability check, the Contractor will be assessed a charge of $1,375.00 to reimburse the Government for each succeeding recheck of the laboratory or the checking of a subsequently selected laboratory. Such costs will be deducted from the contract amount due the Contractor.
3.8.3 Onsite Laboratory
The Government reserves the right to utilize the Contractor's control testing laboratory and equipment to make assurance tests, and to check the Contractor's testing procedures, techniques, and test results at no additional cost to the Government.
3.8.4 Furnishing or Transportation of Samples for Testing
Costs incidental to the transportation of samples or materials shall be borne by the Contractor. Samples of materials for test verification and acceptance testing by the Government shall be delivered to the Corps of Engineers Division Laboratory, f.o.b., at the following address:
For delivery by mail:
Geotechnical & Structures Laboratory Material Testing Center (GS-E) U.S. Army Engineer Research and Development Center 3909 Halls Ferry Road Vicksburg, MS 39180-6199
Coordination for each specific test, exact delivery location, and dates will be made through the Area Office.
3.9 COMPLETION INSPECTION
3.9.1 Punch-Out Inspection
Near the end of the work, or any increment of the work established by a time stated in the FAR 52.211-10 - Commencement, Prosecution, and Completion of Work, or by the specifications, the CQC System Manager shall
SECTION 01 45 04.10 06 Page 10 conduct an inspection of the work. A punch list of items which do not conform to the approved drawings and specifications shall be prepared and included in the CQC documentation, as required by paragraph DOCUMENTATION.
The list of deficiencies shall include the estimated date by which the deficiencies will be corrected. The CQC System Manager or staff shall make a second inspection to ascertain that all deficiencies have been corrected. Once this is accomplished, the Contractor shall notify the Government that the facility is ready for the Government Pre-Final inspection.
3.9.2 Pre-Final Inspection
The Government will perform the pre-final inspection to verify that the facility is complete and ready to be occupied. A Government Pre-Final Punch List may be developed as a result of this inspection. The Contractor's CQC System Manager shall ensure that all items on this list have been corrected before notifying the Government, so that a Final inspection with the customer can be scheduled. Any items noted on the Pre-Final inspection shall be corrected in a timely manner. These inspections and any deficiency corrections required by this paragraph shall be accomplished within the time slated for completion of the entire work or any particular increment of the work if the project is divided into increments by separate completion dates.
3.9.3 Final Acceptance Inspection
The Contractor's Quality Control Inspection personnel, plus the superintendent or other primary management person, and the Contracting Officer's Representative shall be in attendance at the final acceptance inspection. Additional Government personnel including, but not limited to, those from Base/Post Civil Facility Engineer user groups, and major commands may also be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the Pre-Final inspection. Notice shall be given to the Contracting Officer at least fourteen (14) days prior to the final acceptance inspection and shall include the Contractor's assurance that all specific items previously identified to the Contractor as being unacceptable, along with all remaining work performed under the contract, will be complete and acceptable by the date scheduled for the final acceptance inspection.
Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with FAR 52.246-12 - Inspection of Construction.
3.10 DOCUMENTATION
The Contractor shall maintain current records providing factual evidence that required quality control activities and/or tests have been performed.
These records shall include the work of subcontractors and suppliers and shall be on an acceptable form that includes, as a minimum, the following information:
a. Contractor/subcontractor and their area of responsibility.
b. Operating plant/equipment with hours worked, idle, or down for repair.
c. Work performed each day, giving location, description, and by whom. When Network Analysis (NAS) is used, identify each phase of
SECTION 01 45 04.10 06 Page 11 work performed each day by NAS activity number.
d. Test and/or control activities performed with results and references to specifications/drawings requirements. The control phase shall be identified (Preparatory, Initial, Follow-up). List of deficiencies noted, along with corrective action.
e. Quantity of materials received at the site with statement as to acceptability, storage, and reference to specifications/drawings requirements.
f. Submittals and deliverables reviewed, with contract reference, by whom, and action taken.
g. Offsite surveillance activities, including actions taken.
h. Job safety evaluations stating what was checked, results, and instructions or corrective actions.
i. Instructions given/received and conflicts in plans and/or specifications.
j. Contractor's verification statement.
k. These records shall indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered. These records shall cover both conforming and deficient features and shall include a statement that equipment and materials incorporated in the work and workmanship comply with the contract. The original and one copy of these records in report form shall be furnished to the Government daily within 24 hours after the date covered by the report. All calendar days shall be accounted for throughout the life of the contract. Reports shall be signed and dated by the CQC System Manager. The report from the CQC System Manager shall include copies of test reports and copies of reports prepared by all subordinate quality control personnel.
l. Deficiency Tracking System. The Contractor shall maintain a cumulative list of deficiencies identified for the duration of the project. Deficiencies to be listed include those failures, Government oral observations and Notifications of Noncompliance.
The list shall be maintained at the project site. Copies of updated listings shall be submitted to the Government at least every thirty (30) days.
3.11 NOTIFICATION OF NONCOMPLIANCE
The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. The Contractor shall take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, shall be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders shall be made the subject of claim for extension of time or for excess costs or damages by the Contractor.
SECTION 01 45 04.10 06 Page 12
-- End of Section --
SECTION 01 45 04.10 06 Page 13
Airfield Lighting Improvements - Phase A CTGB 15-2012-A Grissom Air Reserve Base, IN P2 No. 472105
Section 03 99 00 Page 1
SECTION 03 99 00
ELASTOMERIC CONCRETE
05/18
Amendment 0002
PART 1 GENERAL
1.1 OVERVIEW
This item consists of filling the partial depth trenches through existing Portland cement concrete and asphalt overlay pavement between the light fixtures installed in full strength airfield pavement. This work consists of: saw cutting, chipping, and removing the existing pavement; cleaning and preparing the area for the infill materials. This work also includes placing, vibrating, and finishing the infill material in accordance with this specification and the construction plans.
PART 2 PRODUCTS
Amendment 0002****************************************************************
2.1 PAVEMENT TRENCH BETWEEN LIGHT BASE CANS
Trench infill elastomeric concrete material shall be a flexible concrete repair material with high tensile strength and strong bonding with PVC. Elastomeric concrete material shall remain flexible throughout anticipated temperature extremes to avoid cracking, delaminating and premature material loss due to thermal climatic changes and traffic loadings. Elastomeric concrete material shall be capable of supporting aircraft loads (250 psi tires), within 1 hour of placement. Elastomeric concrete material shall be gray in color and shall not be adversely affected by jet fuel or de-icing fluids. The elastomeric concrete material shall have a documented history of successful performance at an airfield for a minimum of 3 years.
****************************************************************Amendment 0002
PART 3 EXECUTION
3.1 TIME OF APPLICATION
The ambient temperature and concrete surface temperature shall be within the range specified by the manufacturer’s requirements for that product at the time of application or in accordance with these specifications.
3.2 SAW-CUT PAVEMENT
Prior to performing removal of asphalt overlay and Portland cement concrete between new light base cans, the existing pavement shall be cut by a power driven concrete saw along the lines as indicated in the plans or where directed.
The sawing shall be such that any portion of the pavement to remain shall not be damaged. Any portion that is damaged or removed outside of the designated lines shall be replaced at no additional cost to the Owner. Pre-cutting of the
Airfield Lighting Improvements - Phase A CTGB 15-2012-A Grissom Air Reserve Base, IN P2 No. 472105
Section 03 99 00 Page 2 trench between the lights shall not be permitted ahead of the taxiway closures.
Sawing of the existing concrete pavement to be removed will not be paid for directly, but shall be considered incidental to the item to which it applies.
Where encountered, the Contractor shall exercise extreme caution when working around existing airfield lighting equipment. In-pavement lights consist of a 12” nominal diameter steel base can (24” depth) with conduits entering and existing the base can roughly 20” below the surface elevation. To protect the existing fixture and base can, the Contractor shall core over the base using a 20” diameter core bit. The concrete encasement remaining around the light base shall be protected and remain in place.
3.3 PAVEMENT REMOVAL
Use appropriate-sized impact equipment (e.g., jackhammer, hoe ram) to remove material within the limits of the saw-cuts. All pavement between the saw-cut and the existing joint line shall be carefully broken up and removed using hand-held jackhammers, 30 lb. or less, or other approved light-duty equipment which will not cause stress to propagate across the joint saw-cut and cause distress in the pavement which is to remain in place. In no instance shall the use of a guillotine-type breaker be permitted. Remove by hand any loose materials that remain. Damaged in-pavement light bases shall be removed and replaced at no additional cost to the Owner.
3.4 TRENCH FILL MATERIAL IN PAVEMENT
The procedure for trench fill material in pavement is as follows:
A) Make a vertical cut with a concrete saw to the depth indicated in the plans. For in-pavement lights, the saw cuts shall be parallel to each other approximately 4” apart to allow installation of 2” conduit for airfield lighting. 2” conduit shall be weighted down to prevent floating before setting of the infill material
B) Remove all asphalt overlay and Portland cement concrete to the depth indicated in the plans and details. Break out the concrete with air hammers or pneumatic drills and blow out the area with oil-free compressed air.
C) Clean the area to be repaired with high-pressure water. Allow area to dry completely if required by the material specification.
D) Treat the surface with a bond-promoting agent ONLY ON THE PCC SIDES AND BOTTOM in accordance with the manufacturer’s recommendations. Bonding agent shall not be applied to the asphalt surface of the trench walls.
Apply the bond promoting agent immediately before placing the repair mixture and spread with a stiff-bristle broom or brush. The use of liquid bonding agents shall be acceptable if recommended by the manufacturer’s requirements.
E) Finish the trench to a texture matching the adjacent area.
--END OF SECTION--
SECTION 26 56 20
AIRFIELD LIGHTING AND VISUAL NAVIGATION AIDS
02/19
Amendment 0002
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM A123/A123M (2017) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
ASTM A153/A153M (2016) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware
ASTM D1248 (2016) Standard Specification for Polyethylene Plastics Extrusion Materials for Wire and Cable
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National Electrical Safety Code
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA C119.1 (2016) Electric Connectors - Sealed Insulated Underground Connector Systems Rated 600 Volts
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2019; TIA 19-1; TIA 19-2; TIA 19-3; TIA
19-4; ERTA 1 2019) National Electrical Code
NFPA 70B (2019) Recommended Practice for Electrical Equipment Maintenance
U.S. FEDERAL AVIATION ADMINISTRATION (FAA)
FAA AC 150/5345-7 (2013; Rev F) Specification for L-824 Underground Electrical Cable for Airport Lighting Circuits
FAA AC 150/5345-10 (2014; Rev H) Specification for Constant Current Regulators Regulator Monitors
FAA AC 150/5345-26 (2008; Rev D) FAA Specification for L-823
SECTION 26 56 20.00 10 Page 1
Plug and Receptacle, Cable Connectors
FAA AC 150/5345-27 (2013; Rev E) Specification for Wind Cone Assemblies
FAA AC 150/5345-42 (2019; Rev J) Specification for Airport Light Bases, Transformer Housings, Junction Boxes and Accessories
FAA AC 150/5345-46 (2016; Rev E) Specification for Runway and Taxiway Light Fixtures
FAA AC 150/5345-47 (2005; Rev B) Specification for Series to Series Isolation Transformers for Airport Lighting Systems
FAA AC 150/5345-53 (2012; Rev D) Airport Lighting Equipment Certification Program
FAA AC 150/5345-56B (2011; Rev B) Specification for L-890 Airport Lighting Control and Monitoring System (ALCMS)
FAA AC 150/5370-10 (2018; Rev H; Errata 1 2019) Standard Specifications for Construction of Airports
FAA E-2519 (1972; Rev A) Types I and II
FAA FO 6850.19 (1978) Frangible Coupling
UNDERWRITERS LABORATORIES (UL)
UL 6 (2007; Reprint Sep 2019) UL Standard for Safety Electrical Rigid Metal Conduit-Steel
UL 83 (2017) UL Standard for Safety Thermoplastic-Insulated Wires and Cables
UL 360 (2013; Reprint Nov 2018) UL Standard for Safety Liquid-Tight Flexible Metal Conduit
UL 486A-486B (2018) UL Standard for Safety Wire Connectors
UL 797 (2007; Reprint Mar 2017) UL Standard for Safety Electrical Metallic Tubing -- Steel
UL Electrical Construction (2012) Electrical Construction Equipment Directory
1.2 SYSTEM DESCRIPTION
Provide airfield lighting and visual navigation aids as indicated.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SECTION 26 56 20.00 10 Page 2
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Protection plan; G
Training; G
SD-02 Shop Drawings
Lighting and visual navigation aids; G
Composite drawings showing coordination of work of one trade with that of other trades and with structural and architectural elements of the work. Provide sufficient detail to show overall dimensions of related items, clearances, and relative locations of work in allotted spaces. Indicate where conflicts or clearance problems exist between the various trades.
Wind Cone Indicator Assembly Connection; G
Posted instructions; G
SD-03 Product Data
When equipment or materials are specified to conform to the standards or publications and requirements of AASHTO, ANSI, ASTM, AEIC, ETL, IEEE, IES, NEMA, NFPA, or UL, or to an FAA, FS, or MS, include proof that the items furnished under this section conform to the specified requirements. The label or listing in UL Electrical Construction or ETL or the manufacturer's certification or published catalog specification data statement that the items comply with applicable specifications, standards, or publications and with the manufacturer's standards will be acceptable evidence of such compliance. Provide manufacturer prepared certificates when the manufacturer's published data or drawings do not indicate conformance with other requirements of these specifications.
Airfield lighting control and monitoring system components, complete; G
Type L-823 Connectors; G
Light bases, each type; G
Wind direction indicator; G
Isolation transformers; G
Constant current regulators, each size; G
Control cable; G
Frangible couplings; G
Type P-605 Sealant; G
SECTION 26 56 20.00 10 Page 3
Type P-606 Sealant; G
Materials and equipment; G
SD-06 Test Reports
Visual inspection; G
Progress testing for series lighting circuits; G
Electrical acceptance tests; G
Low-voltage continuity tests; G
High-voltage insulation resistance tests; G
Constant current regulators, each size; G
SD-07 Certificates
Qualifications of contractor; G
Certified documentation of qualifications, as specified.
Special tools; G
List of special tools and test equipment required for installation, maintenance and testing of the products supplied by the Contractor. Items to be listed include, but are not limited to, the following:
Crimping tool; G
Cable penciler
List of parts; G
A list of parts and components for the system by manufacturer's name, part number, nomenclature, and stock level required for maintenance and repair necessary to ensure continued operation with minimal delays.
SD-08 Manufacturer's Instructions
Posted instructions; G
Submit proposed disgrams, instructions, and other sheets prior to posting.
SD-10 Operation and Maintenance Data
Constant current regulators, Data Package 5; G
Maintenance and repair instructions; G
Instructions necessary to check out, troubleshoot, repair, and replace components of the systems, as specified.
SECTION 26 56 20.00 10 Page 4
Posted operations and maintenance instructions
Submit in accordance with Section 01 78 23 OPERATION AND
MAINTENANCE DATA.
SD-11 Closeout Submittals
As-built drawings
1.4 QUALITY CONTROL
1.4.1 Regulatory Requirements
In each standard referred to herein, consider the advisory provisions to be mandatory, as though the word "must" has been substituted for "shall" or "should" wherever it appears. Interpret references in these standards to "authority having jurisdiction," or words of similar meaning, to mean Contracting Officer.
1.4.1.1 Code Compliance
Comply with the requirements and recommendations of NFPA 70 and IEEE C2 and local codes where required.
1.4.2 Standard Products
a. Use only approved equipment listed in FAA AC 150/5345-53 with addendum for the date of delivery the exception of Air Force threshold lights and Army heliport fixture colors and intensities. Inspect wire and cable for date of manufacture. Materials must be certified and listed as "Approved Airport Lighting Equipment" downloadable from:
http://www.faa.gov/arp/pdf/534553ad.pdf. Do not use wire and cable manufactured more than one year before delivery to job site.
b. Provide materials and equipment listed by FAA, UL, or ETL, when such equipment is listed or approved. Do not use askarel, tetrachlorethylene and insulating liquids containing polychlorinated biphenyls (PCBs) in equipment.
c. Material and equipment must be a standard product of a manufacturer regularly engaged in the manufacture of the product and essentially duplicate items that have been in satisfactory use for at least 2 years prior to bid opening.
d. Where two or more items of the same class of equipment are required, provide products of a single manufacturer; however, the component parts of the item need not be products of the same manufacturer unless stated in this section.
1.4.3 Qualifications of Contractor
a. Provide documentation that the aviation lighting equipment contractor and installation electricians are experienced in installing, testing…