W912QR20B0008-0001.pdf
PDF 868 KB Posted
- Attached to
- Regional Hydraulic Dredging Federal contract opportunity
- Solicitation number
- W912QR20B0008
About this file
This is a solicitation for regional hydraulic dredging services. The U.S. Army Corps of Engineers Louisville District intends to issue an Invitation for Bid for a dredge and attendant plant to perform channel maintenance dredging on the Ohio River from River Mile 150.0 to 981.0 and tributaries, the Cumberland River from River Mile 0.0 to 105.0, and the Upper Mississippi River from River Mile 0.0 to 185.0. The dredge will be required to move an estimated 97,200,000 cubic feet of material during the one-year base contract period and four one-year option periods. Interested parties should monitor the System for Award Management Contract Opportunities website for release of the solicitation anticipated on or around February 13, 2020, as no paper copies will be issued. Responses to this synopsis are not required.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Opening Results.pdf | ||
| W912QR20B0008-0003.pdf | ||
| W912QR20B0008-0002.pdf | ||
| W912QR20B0008-Final.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W22W9K93099388
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Lease of Dredge Attendant Plant and On-Shore Disposal of Equipment for Channel Maintenance, Ohio River (RM 150-981) and Ohio River Pool Areas of Tributaries, Cumberland River (RM 0.0-105), and Upper Mississippi River (RM 0.0-185.0) is hereby modif ied as follow s:
SEE SUMMARY OF CHANGES
1. CONTRACT ID CODE PAGE OF PAGES
J 1 15
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912QR20B0008
X 9B. DATED (SEE ITEM 11)
28-Feb-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
U0001
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE
DATE
11-Mar-2020
CODE 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912QR20B0008
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0001
SUMMARY OF CHANGES
1. The following shall be submitted with the offeror’s bid: signed SF1442 to include acknowledgement of all amendments, Reps and Certs, Bid Schedules for Base and All Option Years, Bid Schedule for Sample Task Order, Calcuation Sheets for Effective Rate and Distance to Home Port, Bid Bonds, and Appendix C. The Subcontracting Plan may be submitted after the apparent low bidder is determined.
2. Clause 52.216-1 has been revised.
3. Clause 52.236-1 has been added.
4. The sample task order scope of work is hereby replaced in its entirety. Language has been revised to state the following, “Notice to Proceed as listed in Solicitation allows 15 calendar days to report to dredge site.”
5. The “Effective Rate Calculation Required to Complete Bid Schedule” and “Distance to Home Port
Calculation Required to Complete Bid Schedule” is hereby replaced in its entirety. Descrtiption and applicable CLINS were revised.
6. The bid schedule for the Sample Task Order is hereby replaced in its entirety.
7. The bid schedule for the base and four option years is hereby replaced in its entirety.
8. The Definitive Responsibility Criteria for Dredge and Plant Equipment is hereby replaced in its entirety.
Item #4 has been revised.
9. The bid schedule notes have been replaced in its entirety.
10. The spec section is hereby replaced in its entirety.
a. Section 00120 Bid Evaluation Factors (3)(a)(b) “The Cost of Mileage for Mobilization and Demobilization of dredge and attendant plant” section has been revised.
b. Section 00120 Bid Evaluation Factors (5) ”The Cost of Operating Additional Floating Pontoon Pipeline will be computed by add the products of:” has been deleted.
c. Section 00120 Bid Evaluation Factors (6) “Short term dredge events outside the normal dredge season bid items. A short term event narmally does not exceed 10 calendar days at one site” language has been deleted.
d. Spec Section 7.2.3 Additional Equipment Demobilization has been revised.
SECTION 00 01 10 - TABLE OF CONTENTS
The following have been modified:
00 10 00 BID SCHEDULE/INSTRUCTIONS TO OFFERORS
Price Evaluation Scheme:
The anticipated activities will be estimated for the life of the contract to arrive at a Total Estimated Contract Price to the Government for the entire contract, which will be added to the price of the SAMPLE task order to arrive at the Grand Total evaluated price, which will be used in order to determine the low bidder.
Effective Rate Calculation Required to Complete Bid Schedule:
Cubic Yards per Hour Effective Time Rate Based on Bid Schedule Note 10 (below), Specifications Appendix B Evaluation of the Dredge Pump, and Specifications Appendix C Equipment Schedule:
NOTE: See Section 00120 Evaluation Factors cubic yards/hour used to calculate estimated Effective Time Hours below
1,200,000 cubic yards of estimated quantity of dredge material each year of the contract (Base Year through Option Year 4), divided by Effective Time Rate (cubic yards/hour):
estimated hours for CLINs 0002, 0010, 0018, 0026, 0034
Distance to Home Port Calculation Required to Complete Bid Schedule:
Home Port Location River Name: used to complete Distance from Home Port below River Mile:
(A)Distance from Home Port Location to River Mile 975 of Ohio River in River Miles:
(B)Distance from Ohio River Mile 532 of Ohio River to Home Port Location in River Miles
TOTAL SUM of A plus B mileage for CLINs 0004, 0012, 0020, 0028, 0036, 0044
BID SCHEDULE – BASE YEAR
Contract Line Item
(CLIN)
Description Estimated Quantity Unit
Unit Price (Identical to Base Year Unit Prices
Above)
Price for
Estimated Quantity
Dredge and Floating Plant Mobilization and Demobilization from Home Port9
1 Job x $ = $
Dredge and Floating Plant Effective Time Operation10* from above
Hours x $ = $
Dredge and Floating Plant Non-Effective Time Operation11
30% of Est.
Effective Time Hours from CLIN
Hours x
70% of Effective Time Operation Unit
Price
Dredge and Floating Plant Mileage for Mobilization and Demobilization12* above
Miles x $ = $
0005 Transit Mileage13 800 Miles x $ = $
Onshore Disposal Equipment Mobilization and Demobilization14
1 Job x $ = $
Onshore Disposal Equipment Effective Time Operation15
150 Hours x $ = $
Onshore Disposal Equipment Non- Effective Time Operation16
50 Hours x
70% of Onshore Disposal Equipment Effective Time Unit
BASE YEAR TOTAL: $
*See above bid schedule worksheets for instructions on calculating Estimated Quantities for Effective Time Operation and Mileage for Mobilization and Demobilization.
#See Bid Schedule Note that corresponds with superscripted number.
BID SCHEDULE – OPTION YEAR 1
Line Item
(CLIN)
Description Estimate d Quantity
Unit
Unit Price (Identical to Base
Quantity
Dredge and Floating Plant Mobilization and Demobilization from Home Port9
1 Job x $ = $
Dredge and Floating Plant above
Hours x $ = $
Dredge and Floating Plant Non-Effective Time Operation11
30% of Est.
Effective Time Hours from
CLIN
Dredge and Floating Plant Mileage for above
Miles x $ = $
0013 Transit Mileage13 800 Miles x $ = $
Onshore Disposal Equipment Mobilization and Demobilization14
1 Job x $ = $
Onshore Disposal Equipment Effective Time Operation15
150 Hours x $ = $
Onshore Disposal Equipment Non- Effective Time Operation16
50 Hours x
70% of Onshore Disposal Equipment
OPTION YEAR 1 TOTAL: $
*See above bid schedule worksheets for instructions on calculating Estimated Quantities for Effective Time
BID SCHEDULE – OPTION YEAR 2
Line Item
(CLIN)
Description Estimated
Quantity Unit
Unit Price (Identical to Base
Quantity
Dredge and Floating Plant Mobilization and Demobilization from Home Port9
1 Job x $ = $
Dredge and Floating Plant from above Hours x $ = $
Dredge and Floating Plant Non-Effective Time Operation11
30% of Est.
Effective Time Hours from CLIN
Dredge and Floating Plant Mileage for
Miles x $ = $
0021 Transit Mileage13 800 Miles x $ = $
Onshore Disposal Equipment Mobilization and Demobilization14
1 Job x $ = $
Onshore Disposal Equipment Effective Time Operation15
150 Hours x $ = $
Onshore Disposal Equipment Non- Effective Time Operation16
50 Hours x
70% of Onshore Disposal Equipment
OPTION YEAR 2 TOTAL: $
*See above bid schedule worksheets for instructions on calculating Estimated Quantities for Effective Time
BID SCHEDULE – OPTION YEAR 3
Line Item
(CLIN)
Description Estimated Quantity Unit
Unit Price (Identical to Base
Quantity
Dredge and Floating Plant Mobilization and Demobilization from Home Port9
1 Job x $ = $
Dredge and Floating Plant
Hours x $ = $
Dredge and Floating Plant Non-Effective Time Operation11
30% of Est.
Effective
Time Hours from CLIN
Dredge and Floating Plant Mileage for
_____ from above Miles x $ = $
0029 Transit Mileage13 800 Miles x $ = $
Onshore Disposal Equipment Mobilization and Demobilization14
1 Job x $ = $
Onshore Disposal Equipment Effective Time Operation15
150 Hours x $ = $
Onshore Disposal Equipment Non- Effective Time Operation16
50 Hours x
70% of Onshore Disposal Equipment Effective Time Unit
OPTION YEAR 3 TOTAL: $
*See above bid schedule worksheets for instructions on calculating Estimated Quantities for Effective Time
BID SCHEDULE – OPTION YEAR 4
(CLIN)
Description
Estimate d
Quantity Unit
Unit Price (Identical to Base
Quantity
Dredge and Floating Plant Mobilization and Demobilization from Home Port9
1 Job x $ = $
Dredge and Floating Plant above
Hours x $ = $
Dredge and Floating Plant Non-Effective Time Operation11
30% of Est.
Effective Time Hours from
CLIN
Dredge and Floating Plant Mileage for above
Miles x $ = $
0037 Transit Mileage13 800 Miles x $ = $
Onshore Disposal Equipment Mobilization and Demobilization14
1 Job x $ = $
Onshore Disposal Equipment Effective Time Operation15
150 Hours x $ = $
Onshore Disposal Equipment Non- Effective Time Operation16
50 Hours x
70% of Onshore Disposal Equipment
OPTION YEAR 4 TOTAL: $
*See above bid schedule worksheets for instructions on calculating Estimated Quantities for Effective Time
Sample Task Order
Dredging Ohio River Miles 531 – 981, Upper Mississippi Miles 0 - 50
(CLIN)
Description Estimated
Quantity Unit
Unit Price (Identical to Base
Quantity
Dredge and Floating Plant Mobilization and Demobilization from Home Port9
1 Job x $ = $
Dredge and Floating Plant Effective Time Operation10*
1050 Hours x $ = $
Dredge and Floating Plant Non-Effective Time Operation11
315 Hours x
70% of Effective
Dredge and Floating Plant Mileage for above
Miles x $ = $
0045 Transit Mileage13 800 Miles x $ = $
Onshore Disposal Equipment Mobilization and Demobilization14
1 Job x $ = $
Onshore Disposal Equipment Effective Time Operation15
63 Hours x $ = $
Onshore Disposal Equipment Non- Effective Time Operation16
19 Hours x
70% of Onshore Disposal Equipment
SAMPLE TASK ORDER TOTAL: $
*See above bid schedule worksheets for instructions on calculating Estimated Quantity for Dredge and Floating Plant Mileage for Mobilization and Demobilization.
BID SCHEDULE TOTALS
A Base Year Total: $
B Option Year 1 Total: $
C Option Year 2 Total: $
D Option Year 3 Total: $
E Option Year 4 Total: $
F Sample Task Order Total: $
GRAND TOTAL (SUM of Rows A thru F): $
BID SCHEDULE NOTES
1) Bidders are required to bid on all items listed on the BID SCHEDULE in addition to inserting a total quoted bid in the appropriate space provided. Failure to do so will be considered good cause to disqualify the bid.
2) All quantities shown on the BID SCHEDULE are estimated quantities. Prefilled and bidder-filled estimated quantities are used for bidding purposes only. Task orders will be issued on an as needed basis which will use the unit prices provided on the bid schedule as binding rates. Quantities for task orders will be estimated and subject to a Not-to-Exceed price. Task orders may be modified as necessary to increase or decrease the quantities required under the task order, subject to availability of funds.
3) Bids are being solicited on a unit price basis. However, bidders shall insert in the spaces provided in the
SCHEDULE both the "unit price" and the "estimated amount" resulting from applying the said unit price to the estimated quantity shown.
4) All unit prices shown will be subject to verification by the Government. All bids will be reviewed for mistakes, and if unit prices and estimated amounts do not agree, the unit prices will control. Bid modifications, if any, should take this into account.
5) Unit prices provided in the Bid Schedule will become binding upon award for the life of the contract and must be used on each subsequent task order. Adherence to these rates will be reviewed through submittal of supporting documentation with each task order proposal, including the sample task order.
6) The wage determinations issued in the solicitation are provided in order to assist in calculating unit prices.
Binding wage determinations will be issued on a task order basis. The successful bidder may request an equitable adjustment on the basis of increased wage rates after award of each new task order.
7) The sample task order is for bidding purposes only. Bidders shall use unit prices from the Base Year in order to complete the sample task order. No task order will be awarded from the sample task order;
however, the Sample Task Order Total will be added to the Base Year through Option Year 4 Totals for a Grand Total. The Grand Total will be used in order to determine the lowest evaluated price and apparent low bidder. Refer to the Bid Schedule Notes indicated in the Descriptions above for more information regarding each line item.
8) The dredge and attendant plant used to complete the bid schedule shall be listed on the Equipment Schedule
(see Specifications, Appendix C), and shall be complete with full operating personnel and operating status for the contract period or any extension thereof. Refer to Definitive Responsibility Criteria below. No award will be made to an offeror that does not meet all of the required criteria.
9) CLINs 0001, 0009, 0017, 0025, 0033, 0041: Mobilization and Demobilization from Home Port - Price includes all work and equipment on a per-job basis required to get the dredge and attendant plant (Section 35-20-23 Part 3) ready to leave home port and also the price associated with demobilizing the attendant plant and dredge when it returns to home port after last dredge site. For progress payment purposes, these line items will be split 60% for mobilization and 40% for demobilization.
10) CLINs 0002, 0010, 0018, 0026, 0034, 0042: Dredge and Floating Plant Effective Time Operation -
Estimated quantity of hours to dredge 1,200,000 of material is based on the effective time rate of cubic yards per hour of the proposed dredge and attendant plant, as described on the first page of the bid schedule. Effective time is defined in Specification 35 20 23 Dredging at Paragraph 7.1.2. These CLINs include all work and equipment required to operate the dredge and attendant plant during effective time on a per-hour basis. They do not include effective time for operating the onshore disposal equipment. In order to calculate the production rate, refer to Specifications Appendices B and C, based on an estimated 1,200,000 cubic yards of dredge material to be moved.
11) CLINs 0003, 0011, 0019, 0027, 0035, 0043: Dredge and Floating Plant Non-Effective Time Operation - Non-effective estimated quantities of hours are is assumed for bidding purposes to be 30% of the Effective Time estimated hours. The unit price for non-effective time shall be 70% of the unit price for effective time (to the nearest cent), which is binding on the bidder. For a definition of Non-Effective Time, see Specification 35 20 23 Dredging at Paragraph 7.1.3. These CLINs include all work and equipment required to operate the dredge and attendant plant during non-effective time on a per-hour basis. They do not include non-effective time for operating the onshore disposal equipment.
12) CLINs 0004, 0012, 0020, 0028, 0036, 0044: Dredge and Floating Plant Mileage for Mobilization and
Demobilization - Home port site location will need to be established to determine the mileage from home port to first dredge site and last dredge site back to home port. A chart is provided for calculating this mileage on the first page of the bid schedule. The price per mile includes all labor, fuel, etc. for mobilizing and demobilizing and attendant plant (Section 35-20-23 Part 3) at the beginning and end of each task order under this contract, on a per-river mile basis. It should not include the labor for an entire dredge crew. For bidding purposes, the first dredge site location will be Ohio River Mile 975 and the last dredge site will be Ohio River Mile 532,
13) CLINs 0005, 0013, 0021, 0029, 0037, 0045: Transit Mileage - These CLINs assume 800 miles of transit during the sample task order and during each year of performance. These CLINs include all fuel, and labor, to transit the dredge, floating plant, 3200’floating pontoon pipeline, and all other required equipment, labor and materials on a per-river mile basis.
14) CLINs 0006, 0014, 0022, 0030, 0038, 0046: Onshore Disposal Equipment Mobilization and Demobilization - Price includes all work and equipment a per-job basis required to get the onshore disposal equipment ready to use, or to break it down and stow it as part of the floating plant, at a particular disposal site (See Section 35 20 23 Part 4). For progress payment purposes, these line items will be split 60% for mobilization and 40% for demobilization.
15) CLINs 0007, 0015, 0023, 0031, 0039, 0047: Onshore Disposal Equipment Effective Time Operation - Estimated quantity of hours for anticipated Effective Time Operation of Onshore Disposal Equipment has been pre-filled by the Government for these CLINs. Effective time is defined in Specification 35 20 23 Dredging at Paragraph 7.1.2. These CLINs include all work and equipment required to operate the onshore disposal equipment during effective time on a per-hour basis.
16) CLINs 0008, 0016, 0024, 0032, 0040, 0048: Onshore Disposal Equipment Non-Effective Time Operation - Estimated quantity of hours for anticipated Non-Effective Time Operation of Onshore Disposal Equipment has been pre-filled by the Government for these CLINs. Non-effective time is defined in Specification 35 20 23 Dredging at Paragraph 7.1.3. These CLINs include all work and equipment required to operate the onshore disposal equipment during non-effective time on a per-hour basis.
Definitive Responsibility Criteria for Dredge and Plant Equipment
NOTE: Any bid not meeting the Definitive Responsibility Criteria will be considered non-responsive.
1. Dredges smaller than 20 inches or larger than 24 inches in discharge diameter will not be considered under this Solicitation. Cutterhead Ladder, Hull, and Spuds: These items shall be of sufficient length and construction to perform dredging in depths up to 33 feet below the water surface and in currents up to 5 knots.
2. While making a 300-foot wide cut, the dredge shall be capable of swinging 150 feet from the centerline of the cut without exceeding a 55 degree angle with the head at a depth of 33 feet below the water surface.
3. The hauling engine shall be able to swing the dredge at a minimum speed of 70 feet per minute.
4. The apparent low bidder shall furnish a manufacturer's production curve for the pump prior to award of contract. This curve will be used to verify that the dredge is capable of maintaining the production rate used for bid purposes.
5. Each bidder shall furnish a statement of at least two channel maintenance dredging contracts the bidder has successfully completed in the last 10 years, to include the name of the dredging contract name, point of contact, and the year completed. Bidders who do not demonstrate this experience will not be considered for award.
6. The Government reserves the right to perform a pre-award dredge and attendant plant inspection to verify compliance with the specifications.
CONTRACTING REQUIREMENTS
Section 00 00 00 - Procurement and Contracting Requirements
AWARDING TASK ORDERS
This is an Indefinite Delivery, Indefinite Quantity type Contract (IDIQ) Single Award Task Order Contract (SATOC) for Channel Maintenance Dredging for Ohio River (RM 150-981) & Ohio River Pool Areas of Tributaries, Cumberland River (RM 0.0 – 105), & Upper Mississippi River (RM 0.0-185.0). The contract will result in Firm-Fixed-Price task orders in accordance with FAR Subpart 16.5 to support the civil works and navigational mission for the U.S. Army Corps of Engineers. This contract is a full and open procurement. The total combined contract capacity under the umbrella contract is valued at $45 Million over a one-year base period from the date of award. This SATOC will also include four one-year options, which will not increase the total capacity of the SATOC. Awards will be made as Firm-Fixed-Price Task Orders during the period of performance.
For the base period only, the Government hereby obligates itself to obtain not less than Ten Thousand and No/100 Dollars ($10,000.00) in services. The minimum guarantee will be obligated through the issuance of a Task Order and will de-obligated once the minimum guarantee has been met. There is no guaranteed minimum for the option periods, if exercised.
PERFORMANCE AND PAYMENT BONDS ARE ONLY APPLICABLE TO THE EXTENT INDICATED ON
INDIVIDUAL TASK ORDERS.
SCOPE
This work consists of dredging for channel maintenance, including the use of attendant plant, floating pontoon pipeline, and onshore disposal of dredged materials, along the Ohio River (RM 150-981) & associated Ohio River Pool Areas of Tributaries, Cumberland River (RM 0.0 – 105), & Upper Mississippi River (RM 0.0-185.0), as well as items incidental to the dredging of these sites.
Sample Task Order Scope of Work Channel Maintenance Dredging between Cairo, IL and Racine Lock and Dam along the navigation channel
Ohio River miles 981-150, UMR Miles 0 – 50)
1. General:
a. The contractor shall furnish the equipment, materials, manpower required, and perform the work in accordance with the terms of the contract. The work to be performed under this task order shall include mobilization of the dredge and attendant plant; the dredging of shoals found between Cairo, IL and Racine Lock and Dam along the navigation channel Ohio River miles 981-150, Upper Mississippi River (UMR) Miles 0 – 50. Dredging of the navigation channel and approach areas of Locks and Dams requiring the proper placement of dredged materials in designated disposal locations supplied by the Corps; travel between dredge sites; and demobilization.
b. Both digital and paper maps marking dredge cuts and disposal areas will be provided by the Corps of
Engineers in advance.
2. Bid Schedule Item List:
The contractor's rates used on the attached Bid Schedule Item list shall match those rates on the contract bid schedule.
3. Schedule:
The work of this task order shall commence upon issuance of Notice to Proceed and the proper execution of Performance and Payment Bonds. Notice to Proceed as listed in Solicitation allows 15 calendar days to report to dredge site. All dredging work under this task order shall be initiated and completed by 15 Nov 2020.
4. Security AT/OPSEC
a. The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.
b. The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS
The following have been modified:
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Indefinite Delivery Indefinite Quantity Contract for Firm Fixed Priced Task Orders resulting from this solicitation.
(End of provision)
SECTION 00 70 00 - CONDITIONS OF THE CONTRACT
The following have been added by reference:
52.236-1
(End of Summary of Changes)
Solicitation for Invitation for Bid
(IFB)
Lease of Dredge, Attendant Plant, and On-Shore Disposal Equipment for Channel Maintenance Dredging Ohio River (RM 150.0 – 981.0) and Ohio River Pool Areas of Tributaries, Cumberland River (RM 0.0 – 105.0), and Upper Mississippi River (RM 0.0 – 185.0)
PROJECT TABLE OF
CONTENTS DIVISION 00 - PROCUREMENT AND
CONTRACTING REQUIREMENTS
00 80 00.00 06 SPECIAL CLAUSES
DIVISION 01 - GENERAL REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 57 20.00 10 ENVIRONMENTAL PROTECTION
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 23 DREDGING
35 20 23.33 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM
PIPELINE HYDRAULIC DREDGE SPECIFICATION
-- End of Project Table of Contents --
Section 00120 - Solicitation Contract Form
EVALUATION FACTORS
BID EVALUATION FACTORS.
The following criteria are for bidding purposes:
a. The dredge will remove an estimated 1,200,000 cubic yards (917,500 cubic meters) of sediments from the Ohio River channel and associated tributaries. The sediments consist of primarily medium to coarse-grained sands with a d50 of 0.03 inch (0.8 mm).
Laboratory analysis of the sediment samples taken from the project area indicate an average sediment dry unit weight of 126 lb/ft3 (2.019 g/cc). This measurement indicates 34.50 percent voids, based on the assumption of a 165 lb/ft3 (2.65 g/cc) particle density for sand. In the saturated state, such as sediments on the bottom of the project area, the void space is filled with fresh water, resulting in a saturated sediment density of approximately 141 lb/ft3 (2.257 g/cc).
The dredge efficiencies for this project are given in Table I and depend on the dredge configuration.
TABLE I – DREDGE EFFICIENCIES
Dredge with walking spud De = 0.50 Dredge with spud carriage De = 0.75
Bank height efficiencies are listed in Table II for various dredge sizes.
TABLE II-BANK HEIGHT EFFICIENCIES
20-inch (508-millimeter) Dredge Be = 0.80 22-inch (559-millimeter) Dredge Be = 0.75 24-inch (610-millimeter) Dredge Be = 0.71
The production calculation is to be based on the capability of the dredge plant to pump a 78 lb/ft3 (1.25 g/cc) slurry at the point in the dredging cycle in which the cutterhead is engaging sufficient bank height for loading the pipeline with slurry. The dredge production will be calculated in volumetric production (cubic yards), with the calculations based on the saturated sediment density. The carrier water has an assumed water density of 62.4 lb/ft3 (1.0g/cc). The pump head reduction coefficient (K) is assumed to be 0.24. The dredge production is calculated by the following equation:
PRODUCTION (CUBIC YARD/HR) = C * Q * 133.33 * De * Be with C, or [CUBIC METER/HR = C * Q * 3600 *De * Be] the percent by volume of in situ material in the flow, defined by the following equation:
with, pm - pw C = ------pI – pw pm = The specified slurry density of 78 lb/ft3 (1.25 g/cc) pw = The specified carrier water density of 62.4 lb/ft3 (1.0 g/cc) pI = The specified saturated sediment density of 141 lb/ft3 (2.257 g/cc) and, Q = The discharge flowrate ft3/s, (m3/s) See Appendix B for procedure to determine Q
133.33 = A conversion factor from ft3/s to yd3/hr 3600 = A conversion factor from second to hour De = The stated dredge efficiency of the dredge plant Be = The stated bank height efficiency for the dredge size
The dredge must be capable of picking up and transporting the sediment to disposal within the limitations imposed by conditions of pump cavitation and available horsepower. Calculations used to support the bid production shall be in accordance with this section and Appendix B, EVALUATION OF THE DREDGE PUMP at the end of Section 35 20 23 DREDGING.
b. The dredge will operate an equivalent of 18 hours each calendar day at the effective bid price.
c. The dredge will dredge to a depth of 33 feet (10.0 meters) below the water surface with a terminal elevation of 10 feet (3 meters) above the shore or water surface. Total pipeline length shall include the discharge line on the dredge, plus 2400 feet (731.5 meters) of pontoon discharge line, two (2) swivel elbows and all other associated connection fittings.
d. The information obtained from equipment schedule, production calculations, and pump and system curves for the dredge and plant.
The comparative total cost of each bid received will be computed by adding the following cost elements:
(1) The lump sum cost of mobilization and demobilization of the dredge and attendant plant.
(2) The cost of operating the dredge and attendant plant.
a. Estimating effective pay time, to the nearest hour, will be determined by dividing 1,200,000 cubic yards (917,500 cubic meters) of sediment dredge production for conditions stated above and the Contractor’s corresponding guaranteed production rate.
b. Estimated non-effective pay time will be assumed to be 0.3 times (a) above.
c. The cost of operating the dredge and attendant plant will be computed by adding the products of:
1. Estimated effective pay time multiplied by the appropriate bid price per hour.
2. Estimated non-effective pay time multiplied by the appropriate bid price per hour.
(3) The cost of Mileage for Mobilization and Demobilization of dredge and attendant plant
a. The cost for travel by the dredge, from home port to first dredge site and from last dredge site to home port will be computed by multiplying mileage from home port to ORM 975 by appropriate bid price per mile and mileage from ORM 532 to home port by appropriate bid price.(A chart is provided for calculating this mileage on the first page of the bid schedule).
b. The cost of travel for the dredge while on Transit mileage between dredge sites, will be computed by multiplying an assumed total distance of 800 mile by the appropriate bid price per mile.
(4) The cost of operating On-Shore Disposal Equipment will be computed by adding the products of:
a. The lump sum cost of mobilization and demobilization of the On-Shore Disposal Equipment.
b. The estimated effective pay time multiplied by the appropriate bid price per hour.
c. Estimated non-effective pay time multiplied by the appropriated bid price per hour.
Defined in Section 00 80 00.00 06 PAYMENT FOR MOBILIZATION AND
DEMOBILIZATION, 1.23.
********** AMENDMENT 0001 *********
NOTE: Sample task order is a representation of what a typical dredge season totals would be.
Award will be made to the lowest bidder based on the total dollar amount of sample task order.
********** AMENDMENT 0001 *********
APPENDIX
A
I. Data Format:
Sensor Data Data Character Character Position
Parameter Units Format Length
Row 1:
Date MO-DY-YR ASCII 8 1
Other Header Information Text ASCII 120 10
Row 2..n: where n = number of entries for the 24-hour period
Hour Hr Floating Point 2 1
Minute Min Floating Point 2 4
Second Sec Floating Point 2 7
Velocity Ft/Sec Floating Point 5 13
Slurry Specific Gravity None Floating Point 4 22
Vacuum Psi Floating Point 5 29
Discharge Pres. Psi Floating Point 6 36
Ladder Depth Ft Floating Point 6 44
RPM Cycles/Min Floating Point 6 52
Suction Pipe Length Ft Floating Point 6 60
Discharge Pipe Length Ft Floating Point 7 67
Instantaneous Production Cy/Hr Floating Point 7 75
Cumulative Production Cy/Hr Floating Point 8 82
Offset Ft Floating Point 7 93
Downline Distance Ft Floating Point 8 104
Northing Coordinate Ft Floating Point 10 113
Easting Coordinate Ft Floating Point 10 124
Azimuth Grid North Floating Point 5 135
Swing Cable Pressure:
Port Psi Floating Point 8 141
Starboard Psi Floating Point 8 150
Cutterhead Pressure Psi Floating Point 8 159
Tide Correction Ft Floating Point 6 168
APPENDIX A - 1
Appendix B - i
SAFETY PAYS
APPENDIX B
EVALUATION OF THE DREDGE PUMP
I. The evaluation of a dredge pump's ability to perform under a given set of conditions will be as follows:
GIVEN: d50 - Median particle diameter millimeters ρs - Particle density in lb/ft3, (g/cm3) ρi - Saturated density in lb/ft3, (g/cm3) ρm - Slurry density in lb/ft3, (g/cm3) ρw - Carrier water density in lb/ft3, (g/cm3)
DREDGE PUMP CHARACTERISTICS (Contractor Defined):
dd - Diameter of discharge pipes ft, (m) ds - Diameter of suction pipe ft, (m) ls - Length of suction pipe ft, (m) ld - Length of discharge pipe ft, (m) SPd - Maximum power rating of drive in HP, (J/s, W) RPMp - Maximum RPM of pump at SPd deye - Diameter of pump impeller eye ft, (m) dimp - Diameter of pump impeller ft, (m)
II. Procedure
a. Determine critical suction velocity (Vscrit) as indicated below ft/s or (m/s):
Vscrit = FL × (2 × g × ds × (SGs - SGw))½ where
0.125
-6.9×d50
FL = (1.3 × Cvd ) × (1 - e ) g = Gravitational constant (32.2 ft/s2), or (9.81 m/s2)
SGm - SGw
Cvd = ------------------- Assume Cvd = Cvi
SGs - SGw
SGs = Particle specific gravity (lb/ft3 or g/cm3) SGm = Slurry specific gravity (lb/ft3 or g/cm3) SGw = Carrier water specific gravity (lb/ft3 or g/cm3)
Appendix B - ii
b. Determine equivalent pipe length due to a fitting or bend using loss coefficients and the formula as indicated below:
D × k Le = -------------
4 × C
Le = Equivalent pipe length of a fitting or bend ft, (m) D = Diameter of the pipe ft, (m) k = Loss coefficient (See Table 6.12, Ref. 5) C = 0.004 for pipe dia. > 20 in (50.8 cm)
The total equivalent pipe length for the suction and discharge fittings or bends are given below:
n
Lse = Σ Lsen
I=1 n
Lde = Σ Lden
I=1
Lse = Total equivalent pipe length for suction bends, entrance, or fittings ft, (m) Lde = Total equivalent pipe length for discharge bends, exit, or fittings ft, (m)
The total equivalent pipe length for the system is given as:
Ls = Lse + ls and Ld = Lde + ld where Ls = Total equivalent pipe for the suction side of the pump ft, (m) Ld = Total equivalent pipe for the discharge side of the pump ft, (m)
c. Determine cavitation limits of the pump:
In the absence of Net Positive Suction Head (NPSH) data for the pump, the cavitation limit will be expressed as a function of the impeller eye speed and diameter. The impeller eye speed should be between 40 and 44 feet/second, (12.192 and 13.411 m/s). The cavitation speed (RPMmax) of the pump is calculated as follows:
Veye × 60
RPMmax = -----------deye × π
Veye = Impeller eye speed in ft/s, (m/s) π = PI 60 = Conversion from seconds to minutes
Appendix B - iii
d. The diesel driven engine is essentially a constant torque machine which results in the power output being directly proportional to engine speed. As a result, the maximum diesel driven power available in order to avoid cavitation (SPmaxavail) is calculated according to the following in horsepower:
RPMmax
SPmaxavail = ------------- × SPd
RPMp
e. The Total Dynamic Head (HTDH) requirements for the system will be determined as indicated in the following equations ft, (m) of slurry:
HTDH(units of slurry) = Hs(units of slurry) + Hd(units of slurry)
Hs(units of slurry) =Head requirements on suction side of pump Hd(units of slurry) =Head requirements on discharge side of pump and f×Ls×Vs
1.75 Vs
2 Dd×(SGm-SGw)
Hs(units of slurry) = ------------------- + --------- + -------------------ds×2×g 2×g SGm
Vd
2-Vs 2 f×Ld×Vd
1.75
Hd = ------ + Z + ----------------- 2×g dd×2×g ds
Vd = -----× Vs dd g = Gravitational constant 32.2 ft/s2, (9.81 m/s2) f = 0.028 friction factor for dredge slurries Vs = Suction velocity in ft/s, (m/s) (Vs > Vscrit) Dd = Dredging depth 33 ft, (10.058 m) Vd = Discharge velocity in ft/s, (m/s) Z = Terminal discharge elevation above reference datum 10 ft, (3.048m)
Appendix B - iv
f. The flowrate (Q) at V is calculated as follows in ft3/s, (m3/s):
π×ds
Qmin = ----- × Vscrit ds = diameter of suction pipe ft, (m) vscrit = critical suction velocity ft/s, (m/s)
Determine the minimum and incremental values of the flowrate (Q) and HTDH(units of slurry) by starting with the Vs equal to Vscrit and increasing the Vs in increments of hundreths of a ft/s by repeating paragraphs (e) and (f).
g. Determine the pump head reduction factor (RH) due to the solids effect in the pump as
Cvd dimp
RHo = K × -------, RH = RHo × (-------)-0.9
0.20 do
K = Pump head reduction coefficient, 0.24 RHo = Pump reduction factor for reference pump do = 1.15 ft, (0.351 m)
h. Determine the Pump Efficiency reduction factor (Re) due to the solids effect in the pump as
Re = 0.7 * RH
i. Since the pump head reduction factor (RH) is defined as follows:
HTDH(units of slurry)
RH = 1 - ----------------------------
HTDH(units of water)
The following is implied and should be calculated for all values of HTDH(units of slurry) in order to account for solids effect in pump:
HTDH(units of slurry)
HTDH(units of water) = ---------------------
(1 – RH)
j. Create a plot of HTDH(units of water) versus corresponding flowrates overlapping pump
Appendix B - v characteristic curves. This is the system curve. Determine an operating point, HTDH(units of water) , and flowrate (Q), and corresponding pump efficiency (Ep) in decimal format to the nearest thousandth from the system curve .
k. The Brake (Shaft) Power Required (SPreq) at an operating point is calculated as follows in horsepower or watts:
Q×HTDH(units of water) ×SGm Q×HTDH(units of water) ×SGm SPreq hp = ------------------------------- SPreq W = ------------------------------ × g
550 × 3960 ×(Ep - Re) 3960 ×(Ep - Re)
Q = flow rate ft3/s, (m3/s) HTDH= total dynamic head of water ft, (m) SGm = slurry specific gravity lb/ft3, (g/cm3) Ep = pump efficiency Re = pump efficiency reduction factor G = acceleration due to gravity 32.2 ft/s2, (9.81 m/s2)
l. In accordance with the governing affinity laws, the power demand of a centrifugal pump varies as the cube of the RPM. Therefore, the required pump speed (RPMreq) at an operating point for a centrifugal pump can be calculated as follows:
Procedure: Find a reference RPM and P, brake power in horsepower, from pump manufacturer's characteristic curves along a line of constant pump efficiency (Ep). Calculate RPMreq as indicated in the following equation:
SPreq
RPMreq = RPM × (--------- )1/3
P
m. As explained in part II-d, the diesel driven brake (Shaft) power available (SPavail) at RPMreq is calculated as follows in horsepower:
RPMreq
SPavail = ---------- × SPd
RPMp
n. The system operating point will correspond to the maximum flowrate that satisfies the following inequalities:
RPMreq < RPMmax SPreq < SPmaxavail SPreq < SPavail
Appendix B - vi
HTDH(Q) < HTDH(Qmax) HTDH(Q) > HTDH(Qmin)
o. Calculate Production based upon the operating point that satisfies all of the system parameters and utilizes the maximum flowrate.
III. References
1. Stepanoff, A.J., Centrifugal and Axial Flow Pumps, John Wiley & Sons, Inc., 1957.
2. Huston, J., Hydraulic Dredging, Theoretical and Applied, Cornell Maritime Press, 1970.
3. Herbich, J.B., Coastal & Deep Ocean Dredging, Gulf Publishing Company, 1975.
4. Wilson, K.C., Addie, G.R., & Clift, R., Slurry Transport Using Centrifugal Pumps, Elsevier
Applied Science, 1992.
5. Herbich, J.B., Handbook of Dredging Engineering, McGraw-Hill, Inc., 1992, pg. 6.46.
6. Turner, T.M., Fundamentals of Hydraulic Dredging, Cornell Maritime Press, 1984.
Appendix C - i
APPENDIX C
EQUIPMENT SCHEDULE
DREDGE AND ATTENDANT PLANT
I. Dredge
1. Name , Date Built or Rebuilt , Present Location of Dredge .
2. Hull
Gross Weight (ton) , Length (ft) , Beam (ft) , Draft (ft) .
Distance from Aft End of Hull to Ladder Trunnions (ft) .
3. Spuds
Length (ft) , Weight (ton) , Diameter (feet) , Max. Distance Between Centers (ft) , Min. Distance Between Centers (ft) , Min. Distance Between Spud and Ladder Trunnions (ft) ,
4. Ladder Length (ft) , Suction Entrance Area (ft2) , Distance from Ladder Trunnions to Swing Sheaves (ft) , Swing Cables
Reel Engine power (hp) , Cable Speed (ft/min) at rated power , Reel Diameter (ft) .
Cutterhead
Engine Type , Engine power (hp) , Speed RPMmax , Speed RPMmin , Cutter Type , Length (ft) , Diameter (in) .
5. Pump Characteristics Manufacturer , Impeller Diameter (in) , No. of Vanes , Vane Type , Max. RPM , Suction Diameter (in) , Discharge Diameter (in) , Pump Efficiency at Bid Production Rate .
Appendix C - ii
6. Pump Drive
Manufacturer , Type , No. of Engines , Total Rated power (hp) , RPM at rated Power , Gear Reduction Ratio .
7. Auxiliary Power Plant
Manufacturer , Type , Size , K.W. .
8. Booster Pump Characteristics
Manufacturer , Impeller Diameter (in) , No. of Vanes , Vane Type , Max. RPM , Suction Diameter (in) , Discharge Diameter (in) , Pump Efficiency at Bid Production Rate .
Pump Drive
No. of Engines , Total Rated power (hp) , RPM at rated power , Gear Reduction Ratio .
9. Discharge Pipeline
Pontoon Pipeline Manufacturer , No. of Pieces , Length (ft) , Diameter (I.D.) (in) .
Shore Pipeline
Length (ft) , Diameter (I.D.) (in) .
Booster Pipeline
Length (ft) , Diameter (I.D.) (in) , 10.Attendant Vessels
Tender #1 Name , Date Built , Appendix C - iii
Length (ft) , Beam (ft) , Draft (ft) , Total power (hp) , A-Frame and Winch .
Tender #2
Total power (hp) , A-Frame and Winch .
Fuel/Water/Supply Barge
Derrick or A-frame Barge
Derrick or A-Frame
Manufacturer ,Date Built , Capacity (ton) .
Landing Barge
Inspection/Survey Launch
Name , Manufacturer , Date Built , Total power (hp) , Length (ft) , Beam (ft) , Overall Draft (ft) .
Jon Boat
Crew Boat
Appendix C - iv
Additional Attendant Plant Name , Manufacturer , II. Technical Equipment
1. Slurry Density Monitoring and Display Device Manufacturer , Type
2. Slurry Velocity Monitoring and Display Device
3. Suction Inlet Depth Monitoring and Display Device
4. Pump RPM Monitoring and Display Device
5. Suction Pressure Monitoring and Display Device
6. Cutterhead Pressure Monitoring and Display Device
7. Discharge Pressure Monitoring and Display Device
8. Swing cable pressure monitoring and Display Device
9. Booster Pump Monitoring and Display Device
10. Microprocessor Device
11. Data Storage Device
12.System Display Device
13.Differential Global Positioning System
Radio Link
Frequency - , Broadcast Range (miles) .
14. Surveying System
Manufacturer Depth Sounder
This page was intentionally left blank for duplex printing.
DOCUMENT 00 80 00.00 06 Page 7
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 80 00.00 06
SPECIAL CLAUSES
05/08
PART 1 GENERAL
1.1 REFERENCES - NOT USED
1.2 SUBMITTALS
1.3 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
1.4 NOT USED
1.5 NOT USED
1.6 NOT USED
1.7 NOT USED
1.8 CONTRACT DOCUMENTS
1.9 NOT USED
1.10 NOT USED
1.11 NOT USED
1.12 PHYSICAL DATA (APR 1984) FAR 52.236-4
1.13 UTILITIES
1.14 NOT USED
1.15 LAYOUT OF WORK
1.16 NOT USED
1.17 PERFORMANCE OF WORK BY THE CONTRACTOR
1.18 NOT USED
1.19 NOT USED
1.20 NOT USED
1.21 NOT USED
1.22 NOT USED
1.23 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION (DEC 1991) DFARS
252.236-7004
1.24 NOT USED
1.25 NOT USED
1.26 PROJECT SIGN
1.27 NOT USED
1.28 WAGE RATES
1.29 NOT USED
1.30 TEMPORARY PROJECT AND SAFETY SIGNS
1.31 SEQUENCE OF WORK
1.32 GOVERNMENT FIELD OFFICE FACILITIES AND SERVICES
1.33 NOT USED
1.34 NOT USED
1.35 NOT USED
1.36 NOT USED
1.37 NOT USED
1.38 NOT USED
1.39 NOT USED
1.40 NOT USED
1.41 INSURANCE--WORK ON A GOVERNMENT INSTALLATION (SEP 1989) FAR
52.228-5
1.42 NOT USED
1.43 NOT USED
1.44 NOT USED
1.45 AVAILABILITY OF SAFETY AND HEALTH REQUIREMENTS MANUAL (EM 385-1-1)
1.46 NOT USED
DOCUMENT 00 80 00.00 06 Page 8
1.47 NOT USED
1.48 NOT USED
1.49 NOT USED
1.50 CONSTRUCTION HAZARD COMMUNICATION
1.51 NOT USED
1.52 NOT USED
1.53 NOT USED
1.54 NOT USED
1.55 NOT USED
1.56 VARIATIONS IN ESTIMATED QUANTITIES - SUBDIVIDED ITEMS
1.57 NOT USED
1.58 NOT USED
1.59 NOT USED
1.60 SITE SAFETY AND HEALTH OFFICER (SSHO)
1.61 NOT USED
1.62 NOT USED
1.63 OBSTRUCTION OF NAVIGABLE WATERWAYS (DEC 1991) DFARS 252.236-7002
1.64 SIGNAL LIGHTS
1.65 NOT USED
1.66 NOT USED
1.67 NOT USED
1.68 NOT USED
1.69 NOT USED
1.70 NOT USED
1.71 NOT USED
1.72 NOT USED
1.73 NOT USED
1.74 NOT USED
1.75 NOT USED
1.76 NOT USED
1.77 NOT USED
1.78 NOT USED
1.79 NOT USED
1.80 NOT USED
1.81 EMERGENCY SIGNALS
1.82 CONTRACTOR QUALITY CONTROL
PART 2 PRODUCTS NOT USED
PART 3 EXECUTION NOT USED
-- End of Section Table of Contents --
DOCUMENT 00 80 00.00 06 Page 9
SECTION 00 80 00.00 06
SPECIAL CLAUSES
01/17
PART 1 GENERAL
1.1 REFERENCES - NOT USED
1.2 SUBMITTALS
Government approval/acceptance is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Quality Control Plan, G
SD 07 Certificates
Insurance
SF1413 Statement and Acknowledgement
1.3 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
1.3.1 Commencement, Prosecution, and Completion of Work (Apr 1984) FAR 52.211-10
The Contractor shall be required to
a) commence to assigned work site under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, then proceed travel to the first assigned work site,
b) proceed to dredge site indicated in the notice to proceed prosecute the work diligently, and
c) prosecute the work in a manner to complete all dredging operations within the schedule determined by the Contracting Officer. All work shall be completed within the dates of 15 May to 15 November after receiving notice to report. Upon termination or completion of the contract period, the dredge plant will be released to the Contractor.
1.3.2 Delivery, Inspection, Acceptance/Rejection
The Contractor shall deliver the dredge and attendant plant base equipment ready for operation at the work site, as directed by the Contracting Officer or Representative (COR), the work site shall be reached within 15 calendar days after the date of receipt by the Contractor of the Notice to Proceed.
The plant at this time shall not include any additional equipment as specified in Section 35 20 23 DREDGING, Part 4, unless specifically requested in writing by the Contracting Officer. Upon arrival of the dredge plant at the delivery site, the Contracting Officer's authorized
DOCUMENT 00 80 00.00 06 Page 10 representative will inspect the plant. The Contractor will be notified of acceptance or rejection of the plant within twenty-four hours after delivery. If accepted, the dredge will be given an immediate assignment. If the Contracting Officer determines, during the pre-work inspection at the delivery site or at any time thereafter, that the dredge and/or attendant plant fails to meet the contract specifications, the dredge plant may be rejected, and the contract terminated under Contract Clause: Default.
1.3.3 Additional Plant
The additional plant as specified in Section 35 20 23 DREDGING, Part 4, shall be delivered within fourteen calendar days after the receipt of the written notification from the Contracting Officer outlining the required delivery site and type of equipment requested.
1.3.4 Contract Option for Additional Contract Period(s)
The Contacting Officer may exercise the option to extend the contract for the calendar year 2021 thru 2024 dredging seasons. If the Government intends to exercise the options(s), the Contracting Officer will issue a written notice within 30 calendar days prior to completion of the current contract period. If an option is executed, all specifications and contract requirements will remain the same as the original contract period. Payments will be made using the applicable unit prices for the contract period in which the dredging operations are performed. These contract prices are indicated in Section 00010 within the bid schedule.
1.3.5 Suspended Operations
The Contracting Officer reserves the right to suspend operations whenever river or other conditions make dredging operations impractical or uneconomical. If at the convenience of the Contractor the dredge plant is removed from the site where the suspension occurred during the period of suspension, the Contractor will be required to return the dredge plant to operations within five calendar days as specified in Section 35 20 23 DREDGING, Part 7. Such periods of suspension when ordered by the Contracting Officer will not be counted as part of the contract work period.
1.3.6 Termination
The Contracting Officer may terminate the contract in the event of late delivery of the dredge plant or any time after a contract work…