W912QR-50297498_NRP06-0000.pdf
PDF 19 MB Posted
- Solicitation number
- W912QR-50297498
About this file
This is a solicitation for construction services under the Army Reserve National Roofing Program (NRP) FY25 Project 06, covering roof replacement at two locations in South Carolina. The project involves design-build roof replacement services for two sites: SC013 in Columbia (63,330 total square feet across 7 sections) and SC048 in North Charleston (14,925 total square feet across 4 sections). Both locations have existing roofing systems that are approximately 27 years old and in poor condition, requiring comprehensive replacement.
The solicitation is issued under a Multiple Award Task Order Contract (MATOC) with contract numbers W912QR24D0054 through W912QR24D0063. Key requirements include designing and installing new roofing systems with minimum R-30 insulation, replacing metal wall panels, addressing exterior sealants, and meeting specific technical specifications. The new roof systems will vary by location, including PVC and modified bitumen options. The project is for the U.S. Army Corps of Engineers Louisville District, with a design milestone schedule starting from Notice to Proceed and requiring final certified design submission within 160 days. The Designer of Record must be a Registered Roof Consultant (RRC) with at least ten years of experience in roof repairs.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For Army Reserve National Roofing Program FY25 Task Order 06
P2: 565479 Design-Build
Volume A – SC013 - Columbia, SC Volume B – SC048 - North Charleston, SC
Certified Final
07 July 2025
W912QR-50297498
MATOC W912QR24D0054 thru 24D0063 All requirements of the base MATOC Volume 1 of 2 shall apply to this Task Order unless noted otherwise.
ARIMS: 200A
Disposition: Maintain for 15yrs after construction
W912QR-50297498_NRP06-0000
SECTION 00010 - SOLICITATION CONTRACT FORM
SECTION 00010 – PRICE BREAKOUT SCHEDULE
PROJECT: The Scope of Work (SOW) is for the design and construction services required to repair failed or failing roofs in the United States Army Reserve Command (USARC) roofing inventory under the NRP FY25 Project 6
LOCATIONS:
PROPOSER’S NAME:
ITEM
NUMBER Description UNIT AMOUNT
BASE Work For SC013
0001 Construction: All work, materials, and labor JOB $___________ required to replace the roof at SC013 Building USARC
0002 Design: All work and labor required to JOB $___________ design the roof at SC013 Building USARC
0003 Construction: All work, materials, and labor JOB $___________ required to replace the roof at SC013 Building OMS
0004 Design: All work and labor required to design the roof at SC013 Building OMS JOB $___________
Work For SC048
0005 Construction: All work, materials, and labor JOB $___________ required to replace the roof at SC048 Building AMSA
0006 Design: All work and labor required to JOB $___________ design the roof at SC048 Building AMSA
0007 Construction: All work, materials, and labor JOB $___________ required to replace the roof at SC048 Building Storage Building 1
0008 Design: All work and labor required to design the roof at SC048 Building Storage Building 1 JOB $___________
FACILITY LOCATION
SC013 Columbia, SC SC048 North Charleston, SC
0009 Construction: All work, materials, and labor JOB $___________ required to replace the roof at SC048 Building Storage Building 2
0010 Design: All work and labor required to design the roof at SC048 Building Storage Building 2 JOB $___________
TOTAL PROJECT BASE PROPOSAL $
TOTAL ALL OPTIONS PROPOSAL $
TOTAL PROJECT BASE PLUS OPTIONS PROPOSAL $
Provide the binding contract rates and hours included in job prices above for all base and option tasks.
Project Manager _______ hours x _______ = $___________
Superintendent _______ hours x _______ = $___________
CQC Manager _______ hours x _______ = $___________
Site Safety Health Officer _______ hours x _______ = $___________
NOTES FOR CONTRACT LINE ITEM (CLIN) SCHEDULE
NOTE NO. 1. To better facilitate the receipt and proposal process, all modifications to proposals are to be submitted on copies of the latest Contract Line Item (CLIN) schedules as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to line items, all Offerors should state their revised prices for each item.
NOTE NO. 2. Offerors must insert a price on all numbered items of the CLIN Schedule. Failure to do so may result in the offer being unacceptable.
NOTE NO. 3.
The Offeror’s Base Bid will be evaluated for best value to the Government. The basis for award is the trade-off process. In accordance with 52.217-5, the Government will evaluate offers for award purposes by price.
--END OF CLIN SCHEDULE—
file:///lrd.ds.usace.army.mil/...8/Wage%20Rates/SC20250023%20dtd%2003%20JAN%202025%20Charleston%20County,%20SC-BLDG.txt[7/1/2025 10:50:35 AM]
"General Decision Number: SC20250023 01/03/2025
Superseded General Decision Number: SC20240023
State: South Carolina
Construction Type: Building
County: Charleston County in South Carolina.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.75 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2025. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $13.30 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2025. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this file:///lrd.ds.usace.army.mil/...8/Wage%20Rates/SC20250023%20dtd%2003%20JAN%202025%20Charleston%20County,%20SC-BLDG.txt[7/1/2025 10:50:35 AM] wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2025
IRON0848-006 07/01/2024
Rates Fringes
IRONWORKER, STRUCTURAL...........$ 28.75 17.50
PLUM0421-005 07/01/2024
Rates Fringes
PIPEFITTER.......................$ 36.00 14.19
SUSC2011-019 08/31/2011
Rates Fringes
BRICKLAYER.......................$ 18.00 0.00
CARPENTER (Drywall Hanging Only)............................$ 16.32 ** 1.50
CARPENTER (Form Work Only).......$ 14.09 ** 2.22
CARPENTER, Excludes Drywall Hanging, and Form Work...........$ 16.03 ** 1.16
CEMENT MASON/CONCRETE FINISHER...$ 14.77 ** 0.00
ELECTRICIAN......................$ 15.86 ** 0.00
HVAC MECHANIC (HVAC Duct Installation Only)...............$ 19.24 2.69
LABORER: Common or General......$ 11.06 ** 1.72
LABORER: Landscape..............$ 9.45 ** 0.49
LABORER: Mason Tender-Brick/Concrete/Cement/S tone.............................$ 11.00 ** 0.00
LABORER: Pipelayer..............$ 14.69 ** 2.08 file:///lrd.ds.usace.army.mil/...8/Wage%20Rates/SC20250023%20dtd%2003%20JAN%202025%20Charleston%20County,%20SC-BLDG.txt[7/1/2025 10:50:35 AM]
OPERATOR:
Backhoe/Excavator/Trackhoe.......$ 19.62 3.54
OPERATOR: Bulldozer.............$ 17.07 ** 2.65
OPERATOR: Crane.................$ 19.39 2.02
OPERATOR: Grader/Blade..........$ 17.59 ** 1.56
OPERATOR: Loader................$ 14.18 ** 1.99
PAINTER: Brush, Roller and Spray............................$ 12.74 ** 0.00
PLUMBER..........................$ 18.95 5.35
ROOFER...........................$ 11.92 ** 0.00
TRUCK DRIVER.....................$ 14.21 ** 3.24
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($17.75) or 13658 ($13.30). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 are not currently being enforced as to any contract or subcontract to which the states of Texas, Louisiana, or Mississippi, including their agencies, are a party.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
file:///lrd.ds.usace.army.mil/...8/Wage%20Rates/SC20250023%20dtd%2003%20JAN%202025%20Charleston%20County,%20SC-BLDG.txt[7/1/2025 10:50:35 AM]
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers file:///lrd.ds.usace.army.mil/...8/Wage%20Rates/SC20250023%20dtd%2003%20JAN%202025%20Charleston%20County,%20SC-BLDG.txt[7/1/2025 10:50:35 AM]
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
file:///lrd.ds.usace.army.mil/...8/Wage%20Rates/SC20250023%20dtd%2003%20JAN%202025%20Charleston%20County,%20SC-BLDG.txt[7/1/2025 10:50:35 AM]
Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210.
END OF GENERAL DECISION"
file:///lrd.ds.usace.army.mil/...48/Wage%20Rates/SC20250028%20dtd%2003%20JAN%202025%20Richland%20County,%20SC-BLDG.txt[7/1/2025 10:50:09 AM]
"General Decision Number: SC20250028 01/03/2025
Superseded General Decision Number: SC20240028
State: South Carolina
Construction Type: Building
County: Richland County in South Carolina.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.75 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2025. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $13.30 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2025. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this file:///lrd.ds.usace.army.mil/...48/Wage%20Rates/SC20250028%20dtd%2003%20JAN%202025%20Richland%20County,%20SC-BLDG.txt[7/1/2025 10:50:09 AM] wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2025
ELEC0776-002 03/01/2024
Rates Fringes
ELECTRICIAN......................$ 32.80 13.99
Work more than 40 ft. above the ground on or from swinging scaffolds, boson chairs, or raw structural steel: $1.00 per hour additional.
PLUM0421-005 07/01/2024
Rates Fringes
PIPEFITTER.......................$ 36.00 14.19
SUSC2011-024 08/31/2011
Rates Fringes
BRICKLAYER.......................$ 18.00 0.00
CARPENTER (Drywall Hanging Only)............................$ 16.32 ** 1.50
CARPENTER, Excludes Drywall Hanging, and Form Work...........$ 16.32 ** 3.83
CEMENT MASON/CONCRETE FINISHER...$ 15.29 ** 0.00
FORM WORKER......................$ 13.83 ** 4.69
GLAZIER..........................$ 18.74 0.00
HVAC MECHANIC (HVAC Duct Installation Only)...............$ 19.71 1.93
LABORER: Common or General......$ 10.73 ** 0.00
LABORER: Landscape..............$ 9.45 ** 0.49
LABORER: Mason file:///lrd.ds.usace.army.mil/...48/Wage%20Rates/SC20250028%20dtd%2003%20JAN%202025%20Richland%20County,%20SC-BLDG.txt[7/1/2025 10:50:09 AM]
Tender-Brick/Concrete/Cement/S tone.............................$ 11.00 ** 0.00
LABORER: Pipelayer..............$ 14.69 ** 2.08
OPERATOR:
Backhoe/Excavator/Trackhoe.......$ 16.81 ** 2.67
OPERATOR: Bulldozer.............$ 17.07 ** 2.65
OPERATOR: Crane.................$ 19.39 2.02
OPERATOR: Grader/Blade..........$ 17.50 ** 1.78
OPERATOR: Loader................$ 14.18 ** 1.99
PAINTER: Brush, Roller and Spray............................$ 12.24 ** 0.00
PLUMBER..........................$ 16.86 ** 1.02
ROOFER...........................$ 12.21 ** 0.00
TRUCK DRIVER.....................$ 14.05 ** 3.18
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($17.75) or 13658 ($13.30). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 are not currently being enforced as to any contract or subcontract to which the states of Texas, Louisiana, or Mississippi, including their agencies, are a party.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic file:///lrd.ds.usace.army.mil/...48/Wage%20Rates/SC20250028%20dtd%2003%20JAN%202025%20Richland%20County,%20SC-BLDG.txt[7/1/2025 10:50:09 AM] violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
file:///lrd.ds.usace.army.mil/...48/Wage%20Rates/SC20250028%20dtd%2003%20JAN%202025%20Richland%20County,%20SC-BLDG.txt[7/1/2025 10:50:09 AM]
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination file:///lrd.ds.usace.army.mil/...48/Wage%20Rates/SC20250028%20dtd%2003%20JAN%202025%20Richland%20County,%20SC-BLDG.txt[7/1/2025 10:50:09 AM]
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210.
END OF GENERAL DECISION"
National Roofing Program (NRP) FY25 Project 06 SC013 – Columbia, SC & NC048 North Charleston, SC, US
TABLE OF CONTENTS
VOLUME A: SC013 Columbia, SC
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 50.00 06 SPECIAL PROVISIONS FOR TASK ORDERS
00 80 50.00 06 Submittal Register
DIVISION 01 – GENERAL REQUIREMENTS
01 11 50.00 06 Task Order SCOPE OF WORK
ATTACHMENTS
ATTACHMENT A: Site Location
ATTACHMENT B: Building Layout
ATTACHMENT C: Site Inspection Report, 19 November, 2025 (For Information Only)
VOLUME B: SC048 North Charleston, SC
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 50.00 06 SPECIAL PROVISIONS FOR TASK ORDERS
00 80 50.00 06 Submittal Register
DIVISION 01 – GENERAL REQUIREMENTS
01 11 50.00 06 Task Order SCOPE OF WORK
ATTACHMENTS
ATTACHMENT A: Site Location
ATTACHMENT B: Building Layout
ATTACHMENT C: Site Inspection Report, 19 November, 2025 (For Information Only)
--End of Table of Contents--
April 2025 Solicitation
ARIMS: 200A
Disposition: Maintain for 15 yrs after construction
Army Reserve National Roofing Program
FY25 Task Order 06
Volume A
SC013 - Columbia, SC
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 50.00 06 SPECIAL PROVISIONS FOR TASK ORDERS
00 80 50.00 06 Submittal Register
DIVISION 01 – GENERAL REQUIREMENTS
01 11 50.00 06 Task Order SCOPE OF WORK
ATTACHMENTS
ATTACHMENT A:
ATTACHMENT B:
ATTACHMENT C:
Site Location
Building Layout
Site Inspection Report, Dec 19, 2024 (For Information Only)
NRP FY22 Project 06
NC013 Columbia, SC
P2 565479
31-Mar-25
SECTION 00 80 50.00 06
Version CERTIFIED FINAL
SECTION
00 80 50.00 06
SPECIAL PROVISIONS FOR TASK ORDERS
1. PART 1 GENERAL
1.1. SUBMITTALS
Government approval/acceptance is required for submittals with a "GOVT” designation; submittals not having a "GOVT" designation are for information only. When used, a designation following the "GOVT" designation identifies the office that will review the submittal for the
Government. The submittals listed in the Submittal Register at the end of this specification section shall be submitted in accordance with Section
01 33 00.00 06.
SD-01 Preconstruction Submittals
SD-02 Shop Drawings
SD-05 Design Data
SD-07 Certificates
SD-11 Closeout Submittals
1.2. NOT USED
1.3. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK - Paragraph 1.3 of Section 00 80 00.00 06 is replaced with the following:
1.3.1 After approval of the required bonds, the Government will issue an Administrative Notice-to-Proceed (NTP) to allow for preconstruction activities to be initiated in accordance with the contract requirements. The contract period of performance specified in Contract
Clause 52.211-10 will begin upon issuance of Administrative NTP. No onsite demolition or construction work will be permitted during the
Administrative NTP period. All required preconstruction activities and submittals must be submitted and accepted by the Government, where applicable, within the Administrative NTP period. The Government will issue a Construction NTP to allow commencement of all other contract work after the Administrative NTP period, or after the contractor's completion of all work specified in the Administrative NTP. Failure to complete all required preconstruction activities may result in the contract being terminated for default in accordance with Contract
Clause 52.249-10 Default (Fixed-Price Construction).
P2 565479
31-Mar-25
SECTION 00 80 50.00 06
Version CERTIFIED FINAL
1.3.2 Refer to FAR 52.211-12 "LIQUIDATED DAMAGES" in Section 00 70 50 for the amount of Liquidated Damages for the Task order project.
1.3.3 Refer to FAR 52.211-10 "Commencement, Prosecution, and Completion of Work" in Section 00 70 50 for a notification of significant contract dates.
1.3.4 Additional Requirements/Clarifications of Work Included Within the Contract
The time stated in FAR 52.211-10 "Commencement, Prosecution, and
Completion of Work" in Section 00 70 50 for completion shall include as-built drawings, O&M manuals, operational tests/reports/training/instructions, and equipment lists.
1.4. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. ER 415-1-15
This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the "Default
(Fixed-Price Construction)" as discussed in Section 00 70 00 of the base contract and Section 00 70 50 of this task order. In order for the
Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORKDAYS BASED ON (5) DAY WORK
WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
NC013 22 21 21 17 6 6 5 6 3 8 18 20
Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the
Contractor's scheduled workday. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated listed above, the
Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair-weather workdays, and issue a modification in accordance with the "Default (Fixed-Price
Construction)" in section 00 70 00 of the base contract, Volume 1 .
1.5. WAGE RATES
The decision of the Secretary of Labor, covering rates of wages, including fringe benefits to be paid laborers and mechanics performing work under this contract, is attached to this solicitation. The payment for all classes of laborers and mechanics actually employed to perform work under the contract will be specified in the following contract provisions: "Contract Work Hours and Safety Standards --
Overtime Compensation"; "Construction Wage Rate Requirements"; and
"Compliance with Copeland Act Requirements" in Section 00 70 00 of the base contract.
Wage decision included: SC0028 Building
The work to be performed is located in Columbia, SC, Richland County.
1.6. NOT USED
1.7. Antiterrorism (AT) and Operations Security (OPSEC)- Paragraph 1.7 of Section 00 80 00.00 06 is replaced with the following:
1.7.1 AT Level I training. This standard language is for contractor employees with an area of performance within an Army-controlled installation, facility, or area. All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or to the contracting officer, if a COR is not assigned, within 30 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http://jko.jten.mil.
http://jko.jten.mil/
1.7.2 Access and general protection/security policy and procedures.
This standard language is for contractor employees with an area of performance within an Army-controlled installation, facility, or area.
Contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by the installation Provost Marshal
Office, Director of Emergency Services, or Security Office. Contractor workforce must comply with all personal identity verification requirements (CFR clause 52.204-9, Personal Identity Verification of
Contract Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
1.7.3 AT Awareness Training for Contractor Personnel Traveling
Overseas. This standard language requires U.S.-based contractor employees and associated subcontractor employees to make available and to receive Government-provided area of responsibility (AOR)–specific AT awareness training as directed by AR 525-13. Specific AOR training content is directed by the combatant commander, with the unit ATO being the local point of contact.
1.7.4 Army Training Certification Tracking System (ATCTS) registration for contractor employees who require access to Government information systems. All contractor employees with access to a Government info system must be registered in the ATCTS at commencement of services and must successfully complete the DoD Information Assurance Awareness prior to access to the information system and annually thereafter.
1.7.5 For contracts that require a formal OPSEC program. The contractor shall develop an OPSEC Standing Operating Procedure (SOP)/Plan within
90 calendar days of contract award, to be reviewed and approved by the responsible Government OPSEC officer. This plan will include a process to identify critical information, where it is located, who is responsible for it, how to protect it, and why it needs to be protected. The contractor shall implement OPSEC measures as ordered by the commander. In addition, the contractor shall have an identified certified Level II OPSEC coordinator per AR 530-1.
1.7.6 Controlled Unclassified Information (CUI). Include DFARS clause
252.204-7012, which requires the contractor to comply with NIST 800-
171. Also include DFARS provision 252.204-2019 into solicitations.
Acquisition officials should follow procedures outlined in DFARS 204.73 and verify vendors have an adequate NIST SP 800-171 summary assessment score within the Supplier Performance Risk System (within PIEE). If the score doesn’t show a medium- or high-level assessment with a score of
110 or better (as described in the “NIST SP 800-171 DoD Assessment
Methodology”), include clause252.204-7020 and obtain the vendor’s
“system security plan” and “plan of action” for NIST SP 800-171 verification and assurance by Army security officials.
1.8. NOT USED
1.9. NOT USED
1.10. NOT USED
1.11. NOT USED
1.12. NOT USED
1.13. NOT USED
1.14. NOT USED
1.15. NOT USED
1.16. NOT USED
1.17. NOT USED
1.18. NOT USED
1.19. NOT USED
1.20. NOT USED
1.21. NOT USED
1.22. NOT USED
1.23. NOT USED
1.24. NOT USED
1.25. NOT USED
1.26. NOT USED
2. PART 2 PRODUCTS NOT USED
3. PART 3 EXECUTION NOT USED
Line
Act-ivity
Trans-mittal # Specification Section SD # SD Description Item Submitted
Paragraph
Classi-fication:
GA for
GOVT or A/E Revwr Submit
Approval Needed
By
Material Needed
By Action Code
Date Of Action
Date FWD to APPR /
Auth - Date RCD
From
CONTR
Date FWD To
Other Revwr
Date
RCD
From Other Revwr
Action Code
Date Of Action
Mailed To
CONTR/
Date RCD From
APPR
Authority Remarks
01 11 00.00 06 SD-01 Preconstruction Submittal Contractor’s Safety Program 3.7.2 GA
01 11 00.00 06 SD-01 Preconstruction Submittal Demolition Plan 4.2.1 GA
01 32 01.00 06 SD-01 Preconstruction Submittal Project Schedule 3.4 GA
01 35 26.00 06 SD-01 Preconstruction Submittal Scaffolding Erection Plan 3.4 GA
01 35 26.00 06 SD-01 Preconstruction Submittal Accident Prevention Plan (APP) 1.7 GA
01 35 26.00 06 SD-01 Preconstruction Submittal Accident Prevention Plan 1.8 GA
01 35 26.00 06 SD-01 Preconstruction Submittal Activity Hazard Analysis (AHA) 1.8 GA
01 35 26.00 06 SD-01 Preconstruction Submittal Site Safety & Health Officer Qualifications
(SSHO) 1.5.1 GA
01 45 04.10 06 SD-01 Preconstruction Submittal Design Quality Control Plan 3.2 GA
01 45 04.10 06 SD-01 Preconstruction Submittal Construction Quality Control Plan 3.3 GA
01 50 00 SD-01 Preconstruction Submittal Construction Site Plan 1.3 GA
01 57 19.00 06 SD-01 Preconstruction Submittal Environmental Protection Plan 1.7 GA
01 74 19 SD-01 Preconstruction Submittal Construction Waste Management Plan 1.7 GA
00 80 00.00 06 SD-05 Design Data Progress Photographs 1.45 GA
00 80 00.00 06 SD-07 Certificates No Asbestos - Containing Material (ACM) Certification 1.14 GA
00 80 00.00 06 SD-07 Certificates Insurance 1.31 GA
00 80 00.00 06 SD-07 Certificates Warranties 1.15 GA
00 80 00.00 06 SD-08 Certificates Crane Certificate of Compliance 1.12.6 GA
00 80 00.00 06 SD-11 Closeout Submittals Records, Waste Generated/Diverted 1.10 GA
00 80 00.00 06 SD-11 Closeout Submittals Preliminary (Working) As-Built Drawings 3.4 GA
00 80 00.00 06 SD-11 Closeout Submittals Final As-Built Drawings 3.4 GA
TITLE: NRP FY25 Project 06
SUBMITTAL REGISTER
JOB NAME: SC013
LOCATION: Columbia, SC
CONTRACT NO:
CONTRACTOR:
SB MATOC CONTRACTOR SCHEDULE
DATES
CONTRACTOR
ACTION APPROVING AUTHORITY
FY25 NRR Project 06
SC013, Columbia, SC
SECTION 01 11 50.00 06
SECTION
01 11 50.00 06
Task Order SCOPE OF WORK
1. PROJECT INFORMATION
1.1. GENERAL
Design/Build: The Contractor shall provide all labor, equipment, supplies, and consultant services and all site investigations, surveys, analysis, sampling, testing and verification of existing field conditions as required for design and construction of the Roof Replacement Project at
SC013 to result in a complete and useable Facility. Contractor shall provide complete design analysis incorporating all engineering computations, analysis, test, and survey results, building code (including fire protection, life safety, environmental and accessibility) review as it pertains/affects/relates to this project, equipment and material data and documentation of existing conditions.
1.2. SCOPE OF WORK
Unless specifically noted otherwise in this Specification Section or in the base MATOC contract Volume 1 of 2 itself, all requirements of the base
MATOC contract Volume 1 of 2 shall apply to this Task Order. The work includes design and construction to replace the following roof systems located at SC013:
Building Section(s) Existing Roof System
USARC 1-3, 5-7 SSMR
USARC 4 TPO
OMS All SSMR
Design/Build: Design and construction shall comply with the requirements contained in this Task Order Request for Proposal (RFP). The design and technical criteria contained and cited in this RFP and the Unified
Facilities Guide Specifications (UFGS) establish minimum standards for design and construction quality. The Designers of Record shall use the
Unified Facilities Guide Specifications (UFGS) and the requirements contained in this RFP to fully develop the technical specifications and construction drawings. The objective of this solicitation is to obtain an energy efficient, durable, maintainable, and sustainable space.
Design/Build: The illustrations and exhibits included in this RFP illustrate the existing conditions of the project and are provided to define the scope of work and budget. The concepts provided shall be further developed by the Design/Build Contractor to comply with the customer’s functional needs.
All demolition required to construct the project is included as part of the work of this Contract.
1.3. SITE LOCATION
This project is located at 13000 Jackson BLVD Columbia, SC.
1.4. EXISTING SITE UTILITIES
1.4.1. The contractor shall verify the location of all utilities serving the building. Upgrading the existing utilities, (unless noted otherwise) outside the limits of construction, is not a part of this project.
1.5. NOT USED
1.6. NOT USED
1.7. ATTACHMENTS
Design/Build: Information provided in the Attachments is intended to guide the completion of the design by establishing existing conditions, and the desired character, appearance, and function of the new construction. The following Attachments are included and shall be used and strictly adhered-to in completing the design and construction of the project.
a. ATTACHMENT A: Site Location
b. ATTACHMENT B: Building Layout Plans
c. ATTACHMENT C: Site Inspection Report, 19-Dec-24
1.8. NOT USED
1.9. NOT USED
1.10. NOT USED
1.11. NOT USED
1.12. NOT USED
1.13. NOT USED
1.14. PERSONNEL REQUIREMENTS AND QUALIFICATIONS
1.15. The Designer of Record shall be a Registered Roof Consultant
(RRC) and shall be a Registered Architect or Professional Engineer and have at least ten (10) years of experience in roof repairs. The RRC must be currently licensed by the International Institute of Building
Envelope Enclosures (IIBEC).
1.16. NOT USED
1.17. NOT USED
1.18. NOT USED
1.19. NOT USED
2. DESIGN REQUIREMENTS
2.1. GENERAL
The Contractor shall prepare complete construction documents for all work designed as required by the RFP. The construction documents to be prepared shall include, but are not limited to, construction drawings, specifications, submittals, and design analysis as required in Section 01
33 16.00 10 DESIGN DATA (DESIGN AFTER AWARD), Volume 1. Materials and equipment shall be limited to those specified except that where no specific material and equipment is specified or no basis of design is identified, the Contractor shall use materials and equipment accepted within the construction industry and in compliance with Design Criteria.
2.2. DESIGN
2.2.1. The Contractor shall prepare a 100% design for the project in accordance with the RFP using industry standard materials and efficient practices. The design of the materials selected shall be high quality, durable and easily maintained. The Contractor shall be responsible for the professional quality, code compliance, technical accuracy, and coordination of all designs, drawings, specifications, and other documents or publications upon which the design and construction are based. It shall be the responsibility of the Design/
Build Contractor to verify the accuracy of the documents provided.
2.2.2 CAD/BIM Requirement
The contractor will not be required to produce advanced modeling and design drawings and as-built drawings will be limited to CAD files.
2.2.3 Design Submittal Requirement
The contractor will submit a final design, a corrected final design, and a certified final design. The independent Registered Roof Observer
(RRO) identified under Section 01 11 00.00 06 Paragraph 3.3.2.3 shall review the final design as part of the contractor design QC review team. The RRO shall attend the final design plan-in-hand review meeting.
2.1.4 NOT USED
2.2.2. Design Milestone Schedule
Notice to Proceed (NTP) Day 0
Design Quality Control Plan (DQCP) NTP + 14 Days
Design Kick-off (on site) NTP + 40 Days
Charette Report (FIO no review) NTP + 60 Days
Final Submittal NTP + 120 Days
Final Plan in Hand Meeting (on-site) NTP + 138 Days
Corrected Final Submittal NTP + 152 Days
Certified Final Submittal NTP + 160 Days
2.3. REQUEST FOR PROPOSAL (RFP) INTENT
The intent of this RFP section is to describe the requirements for appearance, function, materials, and types of construction in sufficient detail to enable engineering and design to be completed by the Contractor.
2.4. Design Milestone Meetings
2.4.1. Charette / Kickoff Meeting
2.4.1.1. Shall be in person and on-site.
2.4.2. Final Design / Plan-in-hand Review Meeting
2.4.2.1. Shall be in person and on-site.
2.5. NOT USED
2.6. NOT USED
2.7. NOT USED
2.8. NOT USED
2.9. NOT USED
2.10. NOT USED
2.11. NOT USED
2.12. GOVERNMENT FURNISHED MATERIALS
2.12.1. GFM Handover
The GFM has been provided as part of the Solicitation package.
2.12.2. GFM File Formats
GFM are provided only in PDF format.
2.13. (See Paragraph 2.1 Section 01 11 00.00 06 )DESIGN SUBMITTAL
DISTRIBUTION MATRIX
Submittal Reviewers & Mailing Addresses
U.S. Army Corps of Engineers
Timothy M. McClellan, P.E., RRC
Timothy.m.mcclellan@usace.army.mil
LRL-ED-MA Room 414
600 Doctor Martin Luther King Junior Place
Louisville, KY 40202
Michael Brooks
Michael.s.brooks@usace.army.mil
LRL-CDR
Jeffrey E. Bayers, P.E., P.M.P.
Jeffrey.e.bayers@usace.army.mil
LRL-PM-R
Steve Coffey, PE
USARC G 3/5/7 Engineers - Desk 4N-4001-62
4700 Knox Street, Bldg 8-8108
Ft. Bragg, NC 28310
Phone: 910-570-8961
Email: steven.w.coffey3.civ@army.mil
Justin Reeder, PE, RRC, RRO, CDT
USARC-ARIMD Engineering Branch / SAIN Engineering
USAR National Roofing Program REM
Phone: 843.813.2423
Email: justin.reeder@saineng.com
81st RD
William (Bill) Fogarty
81 Wildcat Way
Fort Jackson, SC 29207
Phone: 803-351-0977
Email: William.c.fogarty.civ@army.mil
3. GENERAL CONSTRUCTION REQUIREMENTS
3.1. SUMMARY
3.1.1. The requirements include:
a. Construction considerations and use of the premises.
b. Protection of personnel and Government property.
c. Construction facilities and job site standards.
W912QR-50297498_NRP06-0000
mailto:Timothy.m.mcclellan@usace.army.mil mailto:Michael.s.brooks@usace.army.mil mailto:Jeffrey.e.bayers@usace.army.mil mailto:justin.reeder@saineng.com mailto:William.c.fogarty.civ@army.mil
d. The requirements of this section apply to the entire project including all amendments or modifications that may be issued to modify the contract documents.
3.2. GENERAL INFORMATION
3.2.1. NOT USED
3.2.2. NOT USED
3.2.3. Coordinate all construction activities with:
a. Contracting Officer’s Representative
b. Base Fire Department
c. Base Security/Police
d. Base Civil Engineer
e. Building Occupants
3.2.4. NOT USED
3.2.5. NOT USED
3.2.6. NOT USED
3.2.7. NOT USED
3.2.8. NOT USED
3.2.9. Project and Safety Signs. See 01 50 00, Paragraph 2.1.3.
3.3. DOCUMENTATION
3.3.1. NOT USED
3.3.2. NOT USED
3.4. NOT USED
3.5. Work Schedule under Section 01 11 00.00 06 Paragraph 3.9.1.2 is changed to “Work S WORK SCHEDULE: The Contractor shall schedule the work between the hours of 7:00 a.m. and 4:30 p.m.
This is the start of the file's text. The full file is on GovTribe.