Questions and Answers 31 March 2023 W912QG23B0001.pdf
PDF 594 KB Posted
- Attached to
- PSTE162011 Repair & Widen Taxiways
- Solicitation number
- W912QG-23-B-0001
About this file
This document contains questions and answers related to a solicitation for repair and widening of taxiways at McEntire Joint National Guard Base in South Carolina. The solicitation seeks a firm fixed price contract to replace existing taxiway surfaces and widen them to standards, with new concrete pavements. Key details include a 365 day period of performance, a pre-bid conference on March 17, 2023, proposals due by the amended date, a magnitude between $10-25 million, NAICS code 237310 with 100% set-aside for small business, and work located at McEntire JNGB.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. On plan sheet GC150 under “Construction Phasing/Scheduling”, it states that construction will be performed in two stages; first stage being an approximate 6-month administrative period and then 150 day construction period, totaling 330 days. On block 13 of the SF1442, it is stated that the entire project must be completed with 365 days. Will the Contractor be required to complete the project in 330 days, as stated in the contract drawings? Or will the Contractor be required to complete the project in 365 days, as stated in the SF1442?
Answer: 365 days.
2. On plan sheet GC150, "Construction Phasing / Scheduling" notes state, "This project is estimated to begin in the spring of 2023, with Taxiway closure starting in the summer of 2023 and completion at the time stated.". Please confirm a better estimate for Stage 2 (Taxiway closure / construction) would be a notice to proceed being issues around January of 2024.
Answer: We anticipate the Notice to Proceed for the 365 days for both phases to be issued in August 2023.
3. If Stage 1 (Preconstruction Phase - 180 Calendar Days) is completed earlier will bidding contractors be allowed to use the extra time saved in Stage 1 to complete the work in Stage 2?
Answer: Yes, 365 days is for both phases; and if phase 1 is completed earlier than projected that would allow more time for phase 2. Anticipate Notice to Proceed occurring in August 2023.
4. Specification 31 00 00 section 3.13.1 Proof Rolling states, "Perform proof rolling in the presence of the Contracting Officer. Undercut rutting or pumping of material to a sufficient depth inch and replace with select material.". Please provide rutting and pumping limits that will require removal and replacement (ie. Ruts greater than 1 inch of deformation will require removal and replacement.).
Answer: See Paragraph 3.13.2 “Construction” for 1/2” requirement.
5. If deformation is observed after subgrade proof rolling that constitutes a Contracting Officer’s determination of removal and replacement, will bidding contractors be required to remedy the situation at their own cost if they have met all the subgrade compaction requirements?
Answer: Per Paragraph 3.2.3 Construction, it is the responsibility of the contractor to have a well-draining site to keep soil materials sufficiently dry. Subgrade failures due to saturated soils because of the contractor’s operations are the responsibility of the contractor to correct.
It depends on the situation and if the reason for the undercut is a result of the Contractor’s operations or not.
Contractors shall account for the removal of 1,500 CY of unsatisfactory subgrade material (undercut) and 1,500 CY of satisfactory fill material to replace the unsatisfactory subgrade material is included in the Bid.
6. Specification 31 00 00 section 3.13.1 Proof Rolling states, "Perform proof rolling in the presence of the Contracting Officer. Undercut rutting or pumping of material to a sufficient depth inch and replace with select material.". Please confirm if required compaction is achieved prior to proof rolling, any rutting and pumping requiring removal and replacement will constitute a differing site condition.
Answer: See answer to 5. Also see Paragraph 3.13.2 Construction.
7. Specification 31 00 00 section 1.4.1 Classification of Excavation states, "No consideration will be given to the nature of the materials, and all excavation will be designated as unclassified excavation.". Currently subsurface soil boring logs are shown on the drawings but do not provide the full soil boring log data (ie. N-Values). FAR 52.236-3 Site Investigations and Conditions Affecting the Work (Ref. Solicitation 31 of 79) states, "The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonable ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract."
Please provide the full geotechnical soil boring log reports for bidding contractors to complete their due diligence in complying with FAR 52.236-3.
Answer: The soil boring logs will be provided for the soil borings located within the project foot print.
8. If all excavation is designated as unclassified excavation (specification 31 00 00, section 1.4.1 Classification of Excavation) and deformation occurs during subgrade proof rolling that constitutes a Contracting Officer’s determination of removal and replacement, will bidding contractors be required to remedy the situation at their own cost?
Answer: See answer to #5.
9. There is no way for bidding contractors to quantify how much undercutting of the subgrade will be required. Expecting the contractor to accept the risk of the subgrade without providing the geotechnical report used for the design of this project will drive the cost of this project up. Will the government entertain accepting the risk for the subgrade and provide a separate CLIN for Subgrade Unclassified Excavation?
Answer: Yes. See answer to #5.
10. Will the government consider a separate CLIN for an undercut unit price with an estimated about of undercut?
Answer: Yes. See answer to #5.
11. Will the government consider soil cement application in replace of compacting existing clay subgrade?
Answer: The existing subgrade shall be compacted in place per 31 00 00 para. 3.13. The Contractor can propose to cement treat subgrade once they are awarded the project, but at no additional cost to the government. A specification will be provided by the Engineer if that decision is made.
12. On page 5 of 78 of the solicitation/ITB, it states "(a) Offer, Standard Form (SF) 1442 front and back signed." Please confirm there is, in fact, only one space provided for execution, Box 20B., located on the back of this form. Therefore, only one side of the SF 1442 is to be executed at the time of proposal submission.
Answer: Block 20B is the only place the contractor is required to sign on the SF 1442.
13. On page 8 of 78 of the solicitation/ITB, it states that there is a repository provided for hand carried bids and that bids must be deposited there. Please consider offering an electronic upload delivery method, as well as providing a link for viewing the bid opening virtually.
Answer: Yes, electronic bids will be accepted. See Amendment 0002 to the Solicitation. Added language to allow bids to be electronically submitted via DoD Safe, mailed in, or hand delivered. Mail address is 9 National Guard Road, as compared to bid opening/hand delivered repository which is 1 National Guard Road (See Section 00100, paragraph 5). Contractors can submit a bid electronically only by emailing the request to submit the bid electronically to kevin.j.esber.mil@army.mil and badri.francis.1@us.af.mil on or before 2:00 P.M. Eastern Standard Time on 10 April 2023. A link to drop off the bid electronically will be sent via DoD SAFE https://safe.apps.mil/.
The Government will also broadcast the bid opening live via Teams, anyone interested in attending the bid opening virtually shall email kevin.j.esber.mil@army.mil and badri.francis.1@us.af.mil on or before 2:00 P.M. Eastern Standard Time on 10 April 2023 requesting the link be sent to a specified email(s).
14. On page 5 of 78 of the solicitation/ITB, it states "(b) Section 00010 Line Items - all items must be priced." This consists of one (1) page (Page 3 of 78). We also discovered Section 00 41 00 - Bidding Schedule in the specification documents (Section 00 41 00 Page 1 - Page 5). Please confirm if this Bidding Schedule is to be included in the proposal in addition to Section 00010 from the solicitation/ITB.
Answer: The revised specifications included in Amendment 1 of the Solicitation removed 00 41 00 from the specifications. Only refer to the revised specifications and drawings. The original specifications and drawing will be removed from the Solicitation to avoid any additional confusion.
15. On page 5 of 78 of the solicitation/ITB, it states "(d) Section 00600, Representations and Certifications, completed and return only additional certifications found in this section." Please clarify "return only additional certifications found in this section." Typically, the entire Representations and Certifications section is included with the proposal (Pages 15 of 78 - 27 of 78).
Answer: All Representations and Certifications are required. However, if there are Representations and Certifications contained in Section 00600 that are not already answered or are not current/correct in a Contractor’s Online Representations and Certifications at WWW.SAM.GOV then it would be an additional certification required to be submitted. For example, FAR 52.204-7 is included in the Solicitation and FAR 52.204-8(b)(1) states: If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies…
(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https://www.sam.gov. After reviewing the SAM information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [ offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
FAR Clause Title Date Change Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.
16. Will Runway 14-32 be closed to flight operations for work within 200’ of the runway, such as TW H and fillet work at TW G, or will a displaced threshold be put in place?
Answer: Taxiway G fillet has been completed as well as first row of concrete slabs on Taxiway H. We will coordinate with Airfield Management to maximize productive work adjacent to the runway. We cannot predict the operational requirements and do not intend to physically displace the threshold. We may be able to operate with an operationally displaced threshold.
There will be some 2-4 day periods when flying will not be scheduled and those would be times when work closest to the runway will be most efficient.
17. Will a free zone be established where contractor forces can move about the construction site without escort?
Answer: The General Contractor shall have responsibility for its work force at all times.
Contractor shall daily check out a radio from Airfield Management, be briefed on the day’s flight operations, maintain control of its personnel on the work site, and be in continuous contact with Base Operations and Air Traffic Control. In general, the Government will have inspections during construction but not be escorting each crew.
18. Will the contractor be required to provide escort of construction vehicles and equipment from the airfield access point to the work area?
Answer: See Question 17. Contractor will have control of its employees, subcontractors, suppliers, delivery drivers, etc. That can be a combination of escorts, training, delegation, etc.
19. Will the contractor be required to provide security at the airfield access point?
Answer: No. See Question 17.
20. Is a temporary fence required around the Phase 1 stockpile area? If so, is it to be removed at the completion of Phase 1 activities?
Answer: Temporary security fence will be at the contractor’s discretion. Silt fence and proper stormwater management is required. Previous contractor did not install security fence at batch plant site.
21. Is a silt fence required around the Phase 1 stockpile area? If so, is it to be removed at the completion of Phase 1 activities and stabilization of the stockpile?
Answer: Yes and yes. Silt fence is required and is required to be removed at completion.
22. Is the stockpile required to be grassed?
Answer: Proper sediment and erosion control is required through grassing, grading, drainage control, etc. Temporary topsoil stockpile need not be grassed if control is maintained otherwise.
23. Is the existing PCC pavement indicated for removal on Drawing CD104 assumed to be 4” thick?
Answer: Assume that the pavement is six inches thick.
24. Reference Drawing CM531: Is a black background required for the ILS Hold marking? If so, what are the dimensions?
Answer: Yes. A black background shall extend 6” beyond the ILS marking.
25. Please address a discrepancy in the RFP documents concerning grassing. Specification 32 92 23-
3.1.1 states all areas disturbed by the contractor are to be sodded, and Specification 32 92 19-
3.1.1 states all areas disturbed by the contractor are to be seeded. RFP grading and drainage drawings (CG111) notes disturbed areas are to be seeded. Please clarify.
Answer: Project should be predominantly seeded. Erosion Control General Notes #5 on CE501 states when SOD shall be used.
26. Please confirm existing runway/taxiway lights scheduled for removal are to be reused in new light cans.
Answer: That is correct.
27. Are taxiway lights located in the asphalt shoulder to be flush type?
Answer: Taxiway edge lights and end lights are generally elevated.
28. Will the Government confirm the runway/taxiway lights scheduled for removal & reuse currently meet photometric requirements. Specification Section 26 56 20-3.9 requires photometric testing of all newly installed lights.
Answer: Existing lights meet photometric requirements.
29. Amendment 01 appears to have removed a specific requirement to have an on-site lab during PCC pavement production. Please confirm an on-site testing lab is not required.
Answer: For Contractor Quality Control: All sampling and testing is required to be performed by an approved, on-site, independent, commercial laboratory, or for cementitious materials and admixtures, the manufacturers’ laboratory.
30. Specification Section 01 45 00.00 10-3.4.3 states specialized QC personnel must be an employee of the contractor. Can an exception be made for the geotechnical material technician, as a materials lab will already be performing materials testing for the project.
Answer: Section 3.4.3 states that CQC personnel shall be contracted with the Prime Contractor not a subcontractor or supplier.
31. Is existing electrical conduit concrete encased?
Answer: Yes
32. Are any of the existing joints at Taxiways F & G scheduled for resealing to be of the preformed type. If so, what is the estimated quantity?
Answer: No. Resealing of Twy F and G should be the silicone type. See Detail 10 on CP501.
33. Will the Government consider proposal submittal via email or courier (Fed-Ex, UPS)?
Answer: Yes, see answer to #13.
34. RFP specifications include Section 32 01 29.61 Partial Depth Patching of Rigid Paving. Part 1 states this specification is applicable to indicated repairs on Runway 14-32. We see no mention of repairs on the runway. Please confirm.
Answer: No repairs on Runway.
35. Would Owner please consider Electronic Bid Submission of the Solicitation in lieu of hand delivering to 9 National Guard Rd? If electronic bid submission is not allowed, please indicate and provide an address (if different from current solicitation) as to where an overnight express delivery can be delivered and accepted for bid submission. Also, please confirm the correct address for bid submission. Solicitation box 7 states 9 National Guard Rd. and Pre-Bid Power Point page 10 states 1 National Guard Rd.?
36. Is there existing underdrains and cleanouts to be removed under the existing Taxiway being removed? Current plans do not show any existing underdrains.
Answer: No existing underdrains.
37. 01 14 00 Work restrictions 1.3.1 Activity regulations states “To minimize traffic congestion, delivery of materials must be outside of peak traffic hours (6:30 to 8:00 am and 3:30 to 5:00 pm) unless otherwise approved by the contracting officer.
Answer: Delivery will be allowed during normal gate hours. Contractor should account for delays at busy times and coordinate deliveries needing special assistance. Delivery vehicles will be inspected and all vehicles are subject to random inspections.
38. Please confirm that material deliveries will be permitted during all approved work hours, especially cement and aggregates to the concrete batch plant site.
Answer: See Question 37.
39. 32 11 23.23 Base course drainage layer section 2.4 cementitious materials. Please confirm that a type IL or other cement products noted in 32-13-14.13 will be permitted for use for 32-11- 23.23.
Answer: Type IL will be permitted.
40. Sheet CD104 depicts an area of existing concrete pavement to be removed. Please provide a concrete pavement thickness for this section to be removed. Current bid documents do not provide this information.
Answer: Assume concrete is six inches thick.
41. Sheet CD103 shows asphalt removal at the intersection of Taxiway H and Runway 14-32. Please review and confirm that this area is in fact asphalt pavement. If it is asphalt please provide asphalt pavement composition and thickness for this portion of removal. Current plans do not provide the information.
Answer: This temporary asphalt section was placed during recent construction and is four inches of hot mix asphalt over variable crushed aggregate base course (19-38 inches).
42. Pages CS113, CG133, CP404 show a proposed road/drive towards the basin area. CP404 notes “proposed road HMA section”. Please provide typical section for this proposed road with pavement, aggregate base composition section thickness.
Answer: This is a pickup truck parking spot. Pave with the same section as the taxiway shoulders.
43. Section 01 50 00 3.5.4 storage area states to construct a 6 FT high chain link fence around trailers and materials. Plans do not depict any temporary fence in the laydown or plant site area. Please review and confirm that a temporary fence is not required.
Answer: Temporary security fence is at the contractor’s discretion. See Question 20.
44. Geotextile section 31 05 19 - 3.3.2 sewn seams states that seams are the be field sewn, however plan details on sheet CU521 depict an 18” minimum overlap with pins. Please review and confirm that all seams can be overlapped and pinned as shown on the plans, and not sewn.
Answer: Overlap and pin method is acceptable.
45. General. Will a displaced threshold be required to complete the Phase 1A work? If not, how will the work within the RSA be completed?
Answer: See Question 16.
46. General. Will the government consider electronic bid submission?
47. CU162. Is Class III, IV or V RCP required?
Answer: Per Note 4 on CU161, circular RCP to be class III.
48. CU162. Please provide details for the Manhole (375) and Endwall (376).
Answer: See Detail 7 on CU522 for manhole detail. The endwall is your standard precast concrete endwall.
49. GC150. Is the contractor-supplied gate guard required to armed and/or bonded?
Answer: Guard not required.
50. General. Can the contractor escort delivery drivers, mechanics, etc.? If so, can more than one vehicle be escorted?
Answer: Yes and yes.
51. General. How much time does it take for driver training for the base?
Answer: Airfield Driver Training takes approximately thirty minutes.
52. Will an option for electronic bid submission be allowed?
53. Paragraph 3.6.1 of specification section 01 50 00 requires that the contractor provide the Government Resident Engineer with an office. Please confirm that this office will be required.
Answer: Office will be required for inspector.
54. Paragraph 3.5.4 of specification section 01 50 00 requires a temporary 6' high chain link fence with green strip inserts around trailers and material storage areas. Per our observations during the site visit it appeared that this fencing is not required. Is the 6' chain link fence with green strip inserts required on this project?
Answer: No. See Question 20.
55. Paragraph 3.10 of specification section 01 50 00 requires the storage/laydown area to be returned to its current condition. Based on our observations during the site visit, the entire storage/laydown area was covered in stone from a recent project. Please confirm if the condition of the storage/laydown area as observed during the site visit should be assumed as the condition at the start of construction for this project and if it should be left in the same condition upon completion of this project.
Answer: The batch plant site will remain approximately as observed during the site visit. This includes gravel surface, silt fence, electrical power, etc. Contractor will be responsible for preserving integrity of erosion control measures and other development. At completion of this project, contractor may leave the gravel surfacing, power, etc and appropriate erosion control in place.
56. Drawing CD104 of the contract drawings shows a section of concrete pavement that is to be removed and replaced with enough soil/topsoil to create positive drainage. No thickness of the existing concrete pavement to be removed is provided. How thick is the existing concrete pavement that is shown to be removed?
Answer: Six inches. See Question 23.
57. Note 2 on Drawing CD101 of the contract drawings states "Refer to sheets BB101 and BB102 for soil borings and existing pavement thicknesses." Existing typical pavement sections are shown on Drawing CP301. The pavement thicknesses shown in the borings on Drawings BB101 and BB102 are not the same as the pavement thicknesses shown in the typical sections shown on Drawing CP301. What thicknesses should be used for bidding purposes, those shown in the borings or those shown in the typical sections?
Answer: The typical sections are a range taken from various resources (reports, soil borings, as-builts). Use the typical sections when quantifying the removals. On Typical Section C-C, replace “12” concrete pavement (to be removed)” with “10-13” (+/-) concrete pavement (to be removed).”
58. In the contract specifications paragraph 3.4.3 of Section 01 45 00 requires an Electrical Quality Control Specialist. This paragraph further requires that this Electrical QC Specialist be directly employed by the prime contractor and not by a supplier or subcontractor, be responsible to the CQC System Manager and be physically present at the construction site during work on the specialized personnel's area of responsibility. The Electrical QC Specialist must be a graduate electrical engineer with 3 years related experience or a person with 5 years of experience supervising electrical features of work in the field with a construction company. Please confirm that the CQC System Manger cannot fill this role even if he or she meets the qualification requirements for the Electric QC Specialist and that the Electrical QC Specialist has to be a separate individual from the CQC System Manager.
Answer: Yes the CQC System Manager can not fill the specialist roles.
59. In the contract specifications paragraph 3.4.3 of Section 01 45 00 requires a Civil Quality Control
Specialist. This paragraph further requires that this Civil QC Specialist be directly employed by the prime contractor and not by a supplier or subcontractor, be responsible to the CQC System Manager and be physically present at the construction site at all times during which work within his or her area of responsibility is taking place. The Civil QC Specialist must be a graduate civil engineer or construction manager with 10 years of experience in the type of work being performed on this project or a technician with 10 years related experience. Please confirm that the CQC System Manger cannot fill this role even if he or she meets the qualification requirements for the Civil QC Specialist and that the Civil QC Specialist has to be a separate individual from the CQC System Manager.
60. In the contract specifications paragraph 3.4.3 of Section 01 45 00 requires an Environmental Quality Control Specialist. This paragraph further requires that this Environmental QC Specialist be directly employed by the prime contractor and not by a supplier or subcontractor, be responsible to the CQC System Manager and be physically present at the construction site at all times during which work within his or her area of responsibility is taking place.. The Environmental QC Specialist must be a graduate environmental engineer with 3 years of experience. Please confirm that the CQC System Manger cannot fill this role even if he or she meets the qualification requirements for the Environmental QC Specialist and that the Environmental QC Specialist has to be a separate individual from the CQC System Manager.
61. In the contract specifications paragraph 1.6.2 of section 01 30 00 requires a superintendent with 10 years experience in construction and at least 5 years experience as a superintendent on projects similar in size and complexity. Paragraph 1.6.1 of section 01 35 26 requires a Site Safety and Health Officer (SSHO) that has the training, experience, and qualifications in accordance with EM 385-1-1 Section 01.A.17 and all associated subparagraphs. The SSHO must be onsite at all times when work is in progress. Per paragraph 1.6.1.1.1 the SSHO May not serve as the Quality Control Manager or as the superintendent. Paragraph 3.4.2 of section 01 45 00.00 states that a CQC System Manager must be provided for this project and this person can have no other duties. The CQC System Manger is required to be a graduate engineer or a graduate of construction management with a minimum of 10 years construction experience on airfield construction similar to this Contract. Please confirm that all 3 of the positions above are separate full time individuals and are all required to be present on site when work is in progress.
Answer: Yes all 3 position a separate full time individuals and are required to be present when work is in progress.
62. In the contract specifications paragraph 3.4.3 of Section 01 45 00 requires a Concrete/Pavements and Soils Quality Control Specialist. This paragraph further requires that this Concrete/Pavements and Soil QC Specialist be directly employed by the prime contractor and not by a supplier or subcontractor, be responsible to the CQC System Manager and be physically present at the construction site at all times during which work within his or her area of responsibility is taking place. The Concrete/Pavements and Soils QC Specialist must be a materials technician with 5 years of experience in the area of specialty. Please confirm that the CQC System Manger cannot fill this role even if he or she meets the qualification requirements for the Concrete/Pavements and Soils QC Specialist and that the Concrete/Pavements and Soils QC Specialist has to be a separate individual from the CQC System Manager.
63. In the contract specifications paragraphs 1.5.1.a and 1.5.1.b of Section 32 13 14.13 require a Concrete Paving CQC Manager. These paragraphs require that the Concrete Paving CQC Manager is a separate person and is in addition to the CQC System Manager. The Concrete Paving CQC Manger must have a minimum of 10 years airfield concrete paving experience similar to work required under this contract with a minimum of 4 years in a concrete paving CQC role and be an ACI Concrete Transportation Inspector. Please confirm that the Concrete Paving CQC Manager can be the same person as the Concrete/Pavement and Soils QC Specialist required in paragraph 3.4.3 of section 01 45 00.
Answer: Yes if work load allows it. If paving and soil work is ongoing at the same time, one person can likely not be filled by the same individual.
64. In specification section 32 12 15.13 paragraph 1.5.a requires an Airfield Asphalt Pavement QC Manager, paragraph 1.5.b requires an Airfield Asphalt Pavement Inspector and paragraph 1.5.c requires an Airfield Asphalt Pavement Laboratory Technician. Can these three positions be filled by one individual provided he or she has all the required certifications?
Answer: No.
65. In specification section 32 12 15.13 paragraph 1.5.a requires an Airfield Asphalt Pavement QC Manager, paragraph 1.5.b requires an Airfield Asphalt Pavement Inspector and paragraph 1.5.c requires an Airfield Asphalt Pavement Laboratory Technician. Please confirm that these three positions can be the same person as the Concrete/Pavement and Soils QC Specialist required by paragraph 3.4.3 of section 01 45 00.
Answer: No. Airfield Asphalt Pavement QC manager, Airfield Asphalt Pavement Inspector, and Airfield Asphalt Pavement Laboratory Technician should be individuals. Those roles can serve as specialist roles if time allows. Shall asphalt paving, concrete paving, and soils work are all ongoing at one time, one individual can not serve as the CQC specialist for all three items.
66. Please clarify the max calendar day duration for stage 2 if there is one.
Answer: 365 days for both phases.
67. 2. If we complete stage 1 in less than 6 months, can stage 2 begin early?
68. 3. Can stage 2 begin early and exceed 150 / 180 CD if the whole project finishes within 365 days?
69. When do you expect to grant NTP?
Answer: August 2023
70. Our understanding is that the project is going to be bid as one lump sum; will an SOV for incidental items be provided similar to section 00 41 00 in the plan set?
Answer: No.
71. 6. Is 3-phase power available at the batch plant site?
72. Are there any equipment height restrictions on site?
Answer: Yes. The Batch Plant hight is limited to 98’ AGL and other equipment shall not exceed 20’ AGL As the work area gets closer to the runway the height becomes more restrictive.
73. Please provide specification sections 34 73 13 and 34 73 16.
Answer: These specification sections are not included in the project.
74. Will the bid form be re-issued, due to removal of CLIN0002?
Answer: Solicitation has been amended in Amendment 0001 Conformed Copy.
75. How will quantity discrepancies be handled, from what was provided in the original bid form?
For example, converting volume of asphalt to tons of asphalt, earthwork, etc.
Answer: The contractor is to bid the project to complete the work as a whole. The previously included quantities weren’t a complete list of items and/or quantities for the project and is no longer applicable.
76. Will Type IL cement be permitted to be used in the mix design for the drainage layer?
77. Are 5 signs to be removed and reinstalled? Specific reference to EA-1 and EX2 given note 7 detail 3/EA504 vs the removal and layout plans.
Answer: Signs will be removed, protected, and reinstalled.
78. The possible jumper location for the T/W circuit is shown on EA101. Will the sign circuit require a jumper to keep the circuit operational possibly across T/W G? Please provide circuit routing information on the existing sign circuit.
Answer: TBD
79. How should the counterpoise be installed in the area of the two raceways on the south side of T/W A between Station 80+00 and 88+60? How many counterpoise runs will be needed and where will they be located given the details on EA/503 do not show a scenario with multiple parallel raceways?
80. Do the lights in turf on T/W F and T/W G get drains connecting to the underdrain given that CU141 and CU142 do not show underdrains in these areas.
81. The light base installation details show 2” PVC drain pipe to “under drain”. Given detail 2/CU521, is the intent to terminate the 2” pipe through the filter fabric into the filter material keeping positive drainage or is the intent to connect the 2” PVC to the 6” underdrain pipe?
82. What is the meaning of the dark key notes and cross section in the shaded area near the runway on EA123?
83. Reference notes on EA122 at the new duct bank location, where will the following cables be routed and spliced point to point: 4-#6, 8-#8, 1-12/C #12, 2-#4? Will any of these cable routes require equipment grounds per note 1 detail 4/EA501. If yes, are the equipment grounds included in the listed cables?
84. What are the new duct cross sections for the short runs between the new and existing electrical hand holes on each side of T/W G on EA122?
85. Reference 26 08 00 3.1.a, what electrical testing is required to be tested by a third party?
Specifically, spec 26 56 20 outlines testing for the airport lighting circuits vs 33 71 02 (requiring the third party) for underground electrical distribution.
86. Should the detail reference in note 5/EA123 be detail 3 vs detail 5/EA501?
87. Should the inset lights be installed with L-868B bases w/ flange rings or L-868C bases w/ snow plow rings? There is a conflict between detail 2 and 3/EA501. If snow plow rings are required for the L-852T inset omni directional fixtures please explain spec 26 56 20 requiring bidirectional snow plow rings.
88. Are two-piece L-868 base cans acceptable for two inset MITLs similar to detail 1/EA501?
89. Is note 1/EA122 applicable to anything on this plan page?
90. Per note 1 detail 1/EA501, are the existing fixtures 14”?
91. There are 5 more elevated MITLs being reinstalled than being removed. Will the additional lights be provided by the owner or will the contractor need to provide them?
92. If new MIRLs lights are to be provided please confirm the light specifications 26 56 20 2.3.1. 45w
LED?
93. Reference detail 1/EA501, is the 1” crown shown in the asphalt required? We are not sure how this could be executed with any level of quality control. If the crown is required, a possible solution could be to install a 24” diameter section of concrete to grade vs the flexible pavement shown.
94. Reference detail 3/EA504, please confirm the number of modules and legend for AS-10.
95. Are the existing T/W and runway circuits 6.6amp?
Answer: Yes. Taxiway lighting circuit is 6.6 amps.
96. Please provide more detail on the requirements for photometric testing found in spec 26 56 20
3.9.3. The specification seems more applicable to bidirectional runway lights vs omnidirectional taxiway lights.
97. Are fluoropolymer bolts only required for the two L-852T inset light installations vs the elevated lights calling for stainless steel in spec 26 56 20 3.1.3? Clarify the term inset (flush mount) vs in-pavement which could refer to both flush and elevated lights.
98. Reference spec 26 56 20 3.1.3, are two piece washers required for both inset and elevated lights?
99. What spare parts quantity and type are required per spec 26 56 20 2.9.8?
100. Are the external base cans grounds to be #6 per the plans or #4 per spec 26 56 20 3.7.1.b?
101. Offeror requests that the contract be awarded as a Firm Fixed Price with Economic Price Adjustment clause.?
Answer: There will not be an Economic Price Adjustment clause.
102. Bid Inquiry #2: To accurately price and ensure compliance with the following regulations included in the contract, offerors must have clarity from the Contracting Officer on whether performance of this contract will involve the handling of CUI. Please confirm whether offerors will handle CUI in the performance of this contract, identify what documents are considered CUI, and specify what marking will be placed on the CUI. DFARS 252.204-7019 Notice of NIST SP 800-171 DOD Assessment Requirements; DFAR 252.204-7020 NIST SP 800-171 DoD Assessment Requirements; DFAR 252.207-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting.
Answer: Plans and specifications are not CUI.
103. Bid Inquiry #3: To accurately price and ensure compliance with the following regulations included in the contract, offerors must have clarity form the Contracting Officer on whether a “basic”, “medium” or “high” assessment is required. Please clarify. DFARS 252.204-7019 Notice of NIST SP 800-171 DOD Assessment Requirements; DFAR 252.204-7020 NIST SP 800-171 DoD Assessment Requirements.
Answer: Plans and specifications are not CUI.
104. Bid Inquiry #4: Offeror requests that this task order be given the highest priority rating appropriate under the Defense Production Act in order to mitigate the effects of supply chain risk and ensure timely delivery of construction materials.
Answer: This requirement is not rated.