This solicitation is for the design and construction of a storage and shipping facility at Holloman Air Force Base in New Mexico. The project involves constructing a 69,945 square foot facility for storage and shipping of warehouse reserve materials. The facility will include a reinforced concrete foundation, masonry walls, prefabricated insulated metal construction, standing seam metal roof, utilities, HVAC, fire protection and detection systems, ventilation and exhaust, large rollup doors, office space, restrooms and shower facilities, kitchen area, site improvements, landscaping, and all necessary supporting infrastructure. The project also includes demolishing six existing structures totaling approximately 20,000 square feet and proper disposal of resulting materials. The solicitation type is a lowest price technically acceptable request for proposal with unrestricted eligibility. The estimated value is between $10-25 million and bonding is required. The response due date is March 9, 2021 and the solicitation will be issued and amended solely via the internet.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION NO. W912PP21R0002

DATE: FEBRUARY 2021

U.S. ARMY CORPS OF ENGINEERS

ALBUQUERQUE DISTRICT

NC3 Weapons Reserve Material Facility (WRM)

Holloman Air Force Base Otero County, New Mexico

RTA Submittal

THIS PAGE INTENTIONALLY LEFT BLANK

NC3 Support WRM Storage/Shipping Facility W912PP21R0002 Holloman AFB, NM RTA

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 10 00

00 50 00 00 70 00

DIVISION 01 - GENERAL REQUIREMENTS

01 01 01 SPECIAL CONTRACT REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 20 00 INTERFACE WITH OTHER WORK

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 54 00 SECURITY

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 62 35 RECYCLED / RECOVERED MATERIALS

01 72 80 TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTY

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 24.00 10 FACILITY DATA REQUIREMENTS

01 91 00.15 TOTAL BUILDING COMMISSIONING

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

DIVISION 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

04 20 00 UNIT MASONRY

DIVISION 05 - METALS

05 12 00 STRUCTURAL STEEL

05 21 00 STEEL JOIST FRAMING

05 30 00 STEEL DECKS

05 50 13 MISCELLANEOUS METAL FABRICATIONS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

PROJECT TABLE OF CONTENTS Page 1

00 2 1 00 00 22 16 00 45 00

SOLICITATION, OFFER, AND AWARD, SF 1442; PROPOSAL

SCHEDULE, PARTNERSHIP, JOINT VENTURE CERTIFICATES

INSTRUCTIONS FOR PROCUREMENT

INSTRUCTIONS

SUPPLEMENTARY INSTRUCTIONS TO PROPOSERS

REPRESENTATIONS AND CERTIFICATIONS

CONTRACTING FORMS AND SUPPLEMENTS - Wage Determination

CONDITIONS OF THE CONTRACT

00 20 00

06 10 00 ROUGH CARPENTRY

06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

06 61 16 SOLID SURFACING FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

07 21 13 BOARD AND BLOCK INSULATION

07 21 16 MINERAL FIBER BLANKET INSULATION

07 22 00 ROOF AND DECK INSULATION

07 27 10.00 10 BUILDING AIR BARRIER SYSTEM

07 27 19.01 SELF-ADHERING AIR BARRIERS

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 27 36 SPRAY FOAM AIR BARRIERS

07 42 13 METAL SOFFIT PANELS

07 42 63 FABRICATED WALL PANEL ASSEMBLIES

07 54 23 THERMOPLASTIC POLYOLEFIN (TPO) ROOFING

07 60 00 FLASHING AND SHEET METAL

07 61 14.00 20 STEEL STANDING SEAM ROOFING

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 14 00 WOOD DOORS

08 31 00 ACCESS DOORS AND PANELS

08 34 19.10 20 ROLLING SERVICE DOORS

08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

08 51 13 ALUMINUM WINDOWS

08 60 45 TRANSLUCENT PANELS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 06 00 SCHEDULES FOR FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 68 00 CARPETING

09 90 00 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 14 00.10 EXTERIOR SIGNAGE

10 14 00.20 INTERIOR SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 26 00 WALL AND DOOR PROTECTION

10 28 13 TOILET ACCESSORIES

DIVISION 12 - FURNISHINGS

12 21 00 WINDOW BLINDS

PROJECT TABLE OF CONTENTS Page 2

DIVISION 13 - SPECIAL CONSTRUCTION

13 34 19 METAL BUILDING SYSTEMS

13 48 00 BRACING FOR MISCELLANEOUS EQUIPMENT

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

21 30 00 FIRE PUMPS

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS

23 05 48.19 BRACING FOR HVAC

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.01 LONWORKS DIRECT DIGITAL CONTROL FOR HVAC AND OTHER

BUILDING CONTROL SYSTEMS

23 11 25 FACILITY GAS PIPING

23 54 16.00 10 HEATING SYSTEM; GAS-FIRED HEATERS

23 81 00.00 20 UNITARY AIR CONDITIONING EQUIPMENT

23 82 00.00 20 TERMINAL HEATING UNITS

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11.01 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS HVAC

DIRECT DIGITAL CONTROLLER (DDC) ENERGY MANAGEMENT CONTROL

SYSTEM (EMCS) BUILDING LEVEL ONLY

25 05 11.02 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS FIRE

ALARM REPORTING SYSTEM/MASS NOTIFICATION SYSTEM BUILDING

LEVEL ONLY

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 48.00 10 BRACING FOR ELECTRICAL EQUIPMENT

26 08 00 APPARATUS INSPECTION AND TESTING

26 12 19.10 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED TRANSFORMERS

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 27 13.10 30 ELECTRIC METERS

26 29 23 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS UNDER 600 VOLTS

26 41 00 LIGHTNING PROTECTION SYSTEM

26 42 14.00 10 CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

PROJECT TABLE OF CONTENTS Page 3

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 31 16.13 CHEMICAL TERMITE CONTROL

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID

PAVEMENTS

32 11 23 AGGREGATE BASE COURSES

32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE

FACILITIES

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 PAVEMENT MARKINGS

DIVISION 33 - UTILITIES

33 11 00 WATER UTILITY DISTRIBUTION PIPING

33 30 00 SANITARY SEWERAGE

33 51 15 NATURAL-GAS / LIQUID PETROLEUM GAS DISTRIBUTION

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 4

ROBERT J MCPHERREN

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

01-Mar-2021

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________600 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________00 70 00

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

US ARMY ENGINEER DISTRICT, ALBUQUERQUE

4101 JEFFERSON PLAZA NE

ALBUQUERQUE NM 87109-3435

W912PP

PAGE OF PAGES

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

(hour) Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

505-342-3496FAX:TEL: TEL: FAX:

W912PP21R0002 1 OF 100

02:00 PM

16-APR-2021

Design Bid Build NC3 Support WRM Storage/Shipping Facility at Holloman Air Force Base, New Mexico

This is a Full and Open Low est Price Technically Acceptable (LPTA) Procurement, and therefore open to all businesses under NAICS 236220.

Magnitude of construction is betw een $10,000,000.00 and $25,000,000.

Proposals must be submitted in accordance w ith the requirements in Section 00 22 16. Proposals are due at the time specif ied in Block 13. See Section 00 21 00 for information pertaining to the Pre-Proposal Conference and Site Visit. For technical questions, see the Instructions to Offerors (Section 00 20 00) pertaining to ProjNet. As this is not a sealed bid, offers w ill not be opened publicly. Offerors are advised that this requirement may be delayed, cancelled, or revised at any time and is subject to the availability of funds. Funds are not presently available for this acquisition. No contract aw ard w ill be made until appropriated funds are made available.

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Solicitation No. W912PP21R0002

PROPOSAL SCHEDULE

(To be attached to SF 1442)

Item Unit No. Description Quantity Unit Price Amount

BASE BID

0001 Total cost of Construction within 5’ footprint, Complete

1 JOB *** $

0002 Total cost of Site Work outside 5’ footprint, Complete

1 JOB *** $

0003 Total Cost of Demolition – B920,B921,B922,B923 B924,B930

1 JOB *** $

0004 Bond Premium (Base Bid) 1 JOB *** $

TOTAL AMOUNT BASE BID $

BID OPTIONS

0005 Option 1 – Add One Bay 1 JOB *** $

0006 Bond Premium (Option 1) 1 JOB *** $

TOTAL AMOUNT BID OPTION 1 $

0007 Option 2 – Add One Bay (must be awarded with Option 1)

1 JOB *** $

0008 Bond Premium (Option 2) 1 JOB *** $

TOTAL AMOUNT BID OPTION 2 $

0009 Option 3 – Add Battery Room

1 JOB *** $

0010 Bond Premium (Option 3) 1 JOB *** $

TOTAL AMOUNT BID OPTION 3 $

TOTAL AMOUNT – ALL OPTIONS $

Page 3a of 100

PROPOSAL SCHEDULE

RECAPITULATION

1. TOTAL AMOUNT - BASE BID $

2. TOTAL AMOUNT - BID OPTIONS $

3. TOTAL AMOUNT - BASE BID AND BID OPTIONS $

NOTES:

1. Award of all proposal items will be made to one bidder. Award of Base Bid and Bid Options (if awarded) will be made to one bidder. Bidders must bid on all items.

2. EXERCISE OF OPTIONS. The Government reserves the right to exercise the option(s) by written notice to the Contractor either singularly or in any combination for up to 90 calendar days after award of the Base Bid without an increase in the Offeror's bid price. Completion of added options shall continue at the same schedule as the Base Bid unless otherwise noted in Section 00 70

00, CONDITIONS OF THE CONTRACT.

3. ARITHMETIC DISCREPANCIES:

(a) For the purpose of initial evaluation of bids, the following will be utilized in the resolving arithmetic discrepancies found on the face of bidding schedule as submitted by the bidder:

(1) Obviously misplaced decimal points will be corrected;

(2) Discrepancy between unit price and extended price, the unit price will govern;

(3) Apparent errors in extension of unit prices will be corrected;

(4) Apparent errors in addition of lump-sum and extended prices will be corrected.

(b) For the purposes of bid evaluation, the government will proceed on the assumption that the bidder intends the bid to be evaluated on basis of the unit prices, the totals arrived at by resolution of arithmetic discrepancies as provided above and the bid will be so reflected on the abstract of bids.

(c) These correction procedures shall not be used to resolve any ambiguity concerning which bid is low.

Page 3b of 100

PROPOSAL SCHEDULE

NOTES: (Cont’d)

4. If a modification to a bid based on unit prices is submitted, which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price in the bid schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the bid schedule.

5. PROGRESS PAYMENT REQUESTS made by the Contractor pursuant to the provisions of Contract Clause, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, shall be submitted on ENG FORM 93 to the administration office as designated in Block 26, Standard Form 1442 Back, Solicitation, Offer and Award. ENG FORM 93 shall be submitted to that office on the 1st of each month in appropriate form and certified. Photocopies of the form shall be furnished on that same date to the Corps of Engineers offices designated at the Pre-Construction Conference.

6. ACCRUALS. In accordance with USACE Engineer Financial Regulation (ER) 37- 1-30, and other applicable Federal and DOD financial accounting standards, the Contractor must assist government personnel with providing reasonably accurate estimates of the value of goods and/or services rendered to the Government pursuant to this contract for each calendar month during which goods and services are delivered. Standard forms and instructions will be provided by the Government to assist with meeting this requirement. These monthly estimates, which facilitate timely entry of accruals, must be received by the Government on or before four (4) business days prior to each calendar month-end.

7. ALL OTHER WORK NOT SEPARATELY LISTED shall not include Mobilization, Demobilization and Distributed Cost (for example Insurance, Quality Control, and/or Home Office Overhead, Field Overhead) related to other Bid Items.

8. UNIT ABBREVIATIONS

EA. = EACH M. = METER

L.S. = LUMP SUM S.M. = SQUARE METER

L.F. = LINEAR FEET C.M. = CUBIC METER

S.F. = SQUARE FEET S.Y. = SQUARE YARD

C.F. = CUBIC FEET C.Y. = CUBIC YARD

- END OF PROPOSAL SCHEDULE -

W912PP21R0002

Section 00 10 00 - Solicitation

JV/CORP

CORPORATE, PARTNERSHIP, JOINT VENTURE CERTIFICATES

If the offer is submitted by a corporation, partnership or a Joint Venture, the applicable form listed below must be completed and submitted with the Standard Form 1442. In the alternative, other evidence must be submitted to substantiate the authority of the person signing the offer. If a corporation, the same officer shall not execute both the offer and the certificate.

CORPORATE CERTIFICATE

I, _______________________________________________, certify that I am the Secretary of the corporation named as Offeror/Contractor herein; that __________________________________________________ who signed this offer/contract on behalf of the Offeror/Contractor was then __________________________ of said corporation; that said offer/contract was duly signed for and on behalf of said corporation by authority of its governing body, and is within the scope of its corporate powers.

______________________________ (CORPORATE SEAL)

(Secretary)

AUTHORITY TO BIND PARTNERSHIP

This is to certify that the names and signatures of all partners are listed below and that the person signing the offer had authority to actually bind the partnership pursuant to its partnership agreement. Each of the partners individually has full authority to enter into and execute contractual instruments, on behalf of said partnership, with the United States of America, except as follows: (State “none” or describe limitations, if any.)

This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to, and acknowledged by, the Contracting Officer.

(Type or Print Name) (Signature)

JOINT VENTURE

Provide a copy of the Joint-Venture (JV) agreement. The SF 1442, Solicitation, Offer and Award form must be signed by the party with the authority to bind the JV as indicated in the agreement. Each party to the JV agreement shall complete one of the following entries:

I, _______________________________________________, certify that I am the Secretary of the Corporation named as Offeror/Contractor herein, that __________________________________________________ who signed this offer/contract on behalf of the Offeror/Contractor was then _________________________ of said corporation by authority of its governing body and is within the scope of its corporate powers.

IN WITNESS WHEROF, I have hereunto affixed my hand and the seal of said corporation this ______________________ day of _____________________.

AFFIX CORPORATE SEAL ___________________________

(Secretary)

(Corporation A)

I, _______________________________________________, certify that I am the Secretary of the Corporation named as Offeror/Contractor herein, that __________________________________________________ who signed this offer/contract on behalf of the Offeror/Contractor was then _________________________ of said corporation by authority of its governing body and is within the scope of its corporate powers.

IN WITNESS WHEROF, I have hereunto affixed my hand and the seal of said corporation this ______________________ day of _____________________.

AFFIX CORPORATE SEAL ___________________________

(Secretary)

(Corporation B)

Section 00 20 00 - Instructions for Procurement

INSTRUCTION TO OFFERORS

THE FOLLOWING ARE INSTRUCTIONS TO OFFERORS:

USE OF THE WORDS “PROPOSER” AND “OFFEROR”

Whenever the word “Proposer” appears in the RFP it shall be construed to have the same meaning as the word “Offeror.”

AVAILABILITY OF PLANS AND SPECIFICATIONS

This solicitation will be issued via Internet only. Notification of amendments shall be made via Internet only, as well.

It is therefore the contractor’s responsibility to check the following address daily for any posted changes to this solicitation. For security reasons, all technical and engineering data related to this solicitation will be distributed using beta.SAM.gov, formerly Federal Business Opportunties (fbo.gov). Beta.SAM.gov is a consolidation of ten legacy sites into a single database. In order to save searches, follow contract opportunities, request secure documents or sign up for an Interested Vendor List, you will need a login.gov account in beta.SAM.gov. To create a login.gov account or link an existing login.gov account with beta.SAM.gov follow the instructions on the beta.SAM.gov website.

Contractors registered with beta.SAM.gov may view and/or download this solicitation and all amendments from the Internet after solicitation issuance at this site.

IMPLEMENTATION OF OPORD 2013-74: INTEGRATING ANTITERRORISM AND OPERATIONS

SECURITY (OPSEC) INTO THE USACE ACQUISITION PROCESS

The successful Offeror will be required to conduct a background check on all on-site personnel. The results of the background check shall be made available to the COR upon request.

BIDDER INQUIRY AND PROPOSAL INFORMATION

A. Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at www.projnet.org.

1. To submit and review bid inquiry items, bidders will need to be a current registered user or self register into the system. To self-register, go to the aforementioned web page and click on the BID tab. Select Bidder Inquiry, select agency USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your email address, and then click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.

2. From this page, you may view all bidder inquiries or add inquiry.

3. Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

4. The Solicitation Number is:

The Bidder Inquiry Key is:

W912PP21R0002

DUVK3J-W756BX

B. The Bidder Inquiry System will close Friday, April 9, 2021 at 2:00 PM MDT, in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation if necessary.

C. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

D. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

E. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

http://www.projnet.org/

CONTRACTING OFFICER AUTHORITY

The Contracting Officer who signs this contract will be the primary Contracting Officer for this contract. However, any Contracting Officer assigned to the Albuquerque District, contracting within his or her authority, may take formal action on this contract when a contract action needs to be taken and the primary Contracting Officer is unavailable.

NAICS CODE AND SMALL BUSINESS SIZE STANDARD

The North American Industry Classification System (NAICS) code for this acquisition is 236220. The small business size standard is: the average annual receipts of the concern and its affiliates for the preceding three fiscal years must not exceed $39.5 million.

The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

ESTIMATED MAGNITUDE OF CONSTRUCTION (FAR 36.204)

The estimated magnitude of construction for this project is between $10,000,000 and $25,000,000.

SYSTEM FOR AWARD MANAGEMENT (SAM)

Offerors must ensure that your company’s data at the System for Award Management (SAM) website, https://www.sam.gov/portal/public/SAM/, is current per System for Award Management Maintenance. (Oct 2018).

(This clause is in Section 007200 of the IDIQ MATOC.)

WHO WILL EVALUATE THE PROPOSALS

The Evaluation Committee will be composed of Corps of Engineers and Customs and Border Protection personnel.

A list of the members of the committee will not be released and contact with members of the committee is prohibited. Efforts to solicit support from the committee will be considered grounds for disqualification of an Offeror’s proposal.

BONDS (FAR 28.102-2)

a. Bid Bond. Each Offeror shall submit with his offer a Bid Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in FAR 52.228-1.

When the penal sum is expressed as a percentage, a maximum dollar limitation may be stated. The bid bond shall remain in effect until Performance and Payment Bonds are provided and accepted.

b. Performance and Payment Bonds. Within ten (10) calendar days after contract award, and prior to contract performance, the Contractor shall furnish two bonds, a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25-A), each with good and sufficient surety or sureties acceptable to the Government. The penal sum of such bonds will be as indicated in FAR 52.228-15.

NEW MEXICO GROSS RECEIPTS TAX (NMGR)

The Offeror should be aware that NMGR tax is applicable to this contract and the rate may vary for each county and city. The Gross Receipts Tax Rate is available from the New Mexico Taxation and Revenue Department, (505) 841-6200. The Gross Receipts Tax Rate is available at http://www.tax.newmexico.gov.

FEDERAL, STATE AND LOCAL TAXES

The Offeror shall include all applicable federal, state and local taxes in the contract price. See FAR 52.229-3, Federal, State, and Local Taxes in the MATOC award for additional information.

UTILIZATION OF INDIAN ORGANIZATIONS, INDIAN-OWNED ECONOMIC ENTERPRISES, AND

NATIVE HAWAIIAN SMALL BUSINESS CONCERNS

DFARS 252.226-7001 is applicable to this contract. It should be read in its entirety for more specific guidance, in particular regarding subcontracts for commercial items. This clause requires the Contractor to use its best efforts to give Indian Organizations, Indian-owned economic enterprises, and Native Hawaiian small business concerns the https://www.sam.gov/portal/public/SAM/ maximum practical opportunity to participate in the subcontracts it awards to the fullest extent consistent with efficient performance of its contract. In return, an incentive payment is available of 5 percent of the amount subcontracted to an Indian organization or Indian-owned economic enterprise at any sub-tier. The successful Offeror for this contract should ensure that the DFARS Clause 252.226-7001 is inserted into contracts of sub-tier contractors.

PERFORMANCE OF WORK BY CONTRACTOR (FAR 36.501)

Unless such description has been submitted with the offer, the successful Offeror must furnish the Contracting Officer within 20 days after award, a description of the work that he intends to perform with his own organization (e.g., earthwork, paving, brickwork, or roofing), the percentage of the total work this represents, and the estimated cost thereof.

U.S. ARMY CORPS OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS MANUAL, EM 385-1-1

AND OSHA REQUIREMENTS

The successful contractor to this Request for Proposals will be required to comply with all pertinent provisions of the latest version of the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation. EM 385-1-1 and its changes are available at http://www.publications.usace.army.mil. by selecting “Safety and Occupational Health” followed by “EM 385-1- 1”. The Contractor must also comply with Occupational Safety and Health Act (OSHA) standards. OSHA standards are subject to change. It is the Contractor's responsibility to maintain familiarity with current OSHA standards.

AMENDMENTS TO REQUEST FOR PROPOSALS

The right is reserved, as the interest of the Government may require, to revise the specifications and drawings both before and after the date set for receipt of offers. Such revisions, if any, will be announced by amendment(s) to the Request for Proposal. If the revisions and amendments are of a nature which require material changes in quantities, or prices offered, or both, the date set for receipt of offers may be postponed by such number of days as in the opinion of the Contracting Officer will enable the Offeror to revise the offer. In such cases, the amendment will include an announcement of the new date for receipt of offer.

COSTS RELATED TO PROPOSAL PREPARATION

All costs related to proposal preparation, including travel, will be borne solely by the Offeror. The Government is not liable for any costs incurred by the Offeror submitting an offer in response to this solicitation.

RETENTION

The Government will retain all original proposals submitted in response to this Request for Proposals and will retain the extra copies of the successful technical proposal; the copies of the unsuccessful technical proposals will be destroyed.

CONTRACTOR PERFORMANCE EVALUATIONS

In accordance with the provisions of Subpart 36.201(Evaluation of Contractor Performance) of the Federal Acquisition Regulation (FAR), construction contractor’s performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering Regulation 415-1-17 to fulfill this FAR requirement. For construction contracts awarded at or above $700,000.00, the USACE will evaluate contractor’s performance and prepare a performance report using the Construction Contractor Appraisal Support System (CCASS), which is a web-based system. After an evaluation (interim or final) is written up by the USACE, the contractor will have the ability to access, review and comment on the evaluation for a period of 30 days. Accessing and using CCASS requires specific software, called PKI certification, which is installed on the user’s computer. The certification is a Department of Defense requirement http://www.publications.usace.army.mil/ and was implemented to provide security in electronic transactions. The certification software could cost approximately $110 - $125 per certificate per year and is purchased from an External Certificate Authorities (ECA) vendor. Current information about the PKI certification process and for contacting vendors can be found on the web site: http://www.cpars.gov/. If the Contractor wishes to participate in the performance evaluation process, access to PPIRS and PKI certification is the sole responsibility of the Contractor.

http://www.cpars.gov/

OFFEROR’S CHECKLIST

OFFEROR’S CHECKLIST

Administrative Notice to Offerors. Before signing and submitting this proposal, please take note of the following administrative details, as failure to properly perform any one of these actions may cause your proposal to be rejected:

[ ] Have you acknowledged receipt of ALL solicitation amendments? If in doubt as to the number of amendments issued, please contact Robert McPherren, Contract Specialist, at (505) 342-3455.

[ ] Have you completed Section 00 45 00, Representations and Certifications?

[ ] Is your offer, price and technical, marked to show the Offeror’s name and address, the solicitation number, and the date and time offers are due?

[ ] If any of the solicitation amendments involved changes to the proposal schedule, did you use the amended schedule for submitting your proposal?

[ ] Is your proposal guarantee in the proper form and amount?

[ ] Will your proposal arrive on time? In order for a late proposal to be considered, it must have been dispatched in accordance with the provisions of FAR 52.215-1, “Instructions to Offerors— Competitive Acquisition.” Facsimile proposals will not be accepted.

[ ] Have you reviewed your proposal for possible errors in calculations or work left out?

Section 00 21 00 - Instructions

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.217-5 Evaluation Of Options JUL 1990 52.222-5 Construction Wage Rate Requirements--Secondary Site of the

Work

MAY 2014

52.225-12 Notice of Buy American Requirement - Construction Materials Under Trade Agreements

MAY 2014

252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements NOV 2020 252.215-7010 Requirements for Certified Cost or Pricing Data and Data

Other Than Certified Cost or Pricing Data

JUL 2019

252.215-7013 Supplies and Services Provided by Nontraditional Defense Contractors.

JAN 2018

CLAUSES INCORPORATED BY FULL TEXT

52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)

Any contract awarded as a result of this solicitation will be DX rated order; X DO rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation. [Contracting Officer check appropriate box.]

(End of provision)

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed Price contract resulting from this solicitation.

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

38.3% 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

Holloman Air Force Base, Otero County, New Mexico

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be twenty (20) percent of the bid price or $3,000,000, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

U.S. ARMY CORPS OF ENGINEERS

ATTN: CONTRACTING DIVISION (CONTRACTING OFFICER)

4101 JEFFERSON PLAZA NE

ALBUQUERQUE, NM 87109-3435

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for-- Tuesday, March 17, 2021 at 1:00 PM MDT

(c) Participants will meet at the Contractor’s (West) Gate to obtain their base pass then proceed to the jobsite.

Participants from outside the State of New Mexico must provide their travel itinerary for getting to Holloman AFB.

Itineraries must be submitted to Blaine Kemsley, Project Manager at Blaine.R.Kemsley@usace.army.mil NLT Tuesday, March 9, 2021 to ensure access to the site visit. The following information must be provided:

1. Departure City, State and County

2. Rest/Layover/Transportation Changes

3. Projected Travel Dates

Masks will be required and participants will be required to practice social distancing by staying 6 feet apart at all times.

(d) Offerors are cautioned that nothing said or done at the pre-proposal conference or site visit will qualify or modify the terms of the solicitation document. The only instrument that shall qualify or modify the solicitation document is a formal amendment, in writing, per FAR 15.206. NO QUESTIONS WILL BE ANSWERED AT THE SITE VISIT. ALL QUESTIONS MUST BE SUBMITTED VIA PROJNET IN ACCORDANCE WITH THE RFP.

Anyone who plans on attending the site visit should not attend if they are feeling ill or have any symptoms of COVID. Additionally, anyone who has been in contact with anyone who has tested positive for COVID or is awaiting the outcome of a COVID test in the past 14 days should not attend the site visit. CDC recommendations will be followed during the site visit and Kirtland Air Force Base may make a decision to not allow entry to certain individuals based on the aforementioned.

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any DFARS (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

Section 00 22 16 - Supplementary Instructions to Proposers

SECTION 00 22 16

PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA, AND BASIS

FOR AWARD FOR DESIGN BID BUILD FY20 NC3 SUPPORT WAR RESERVE

MATERIAL (WRM) STORAGE/SHIPPING FACILITY, HOLLOMAN AIR FORCE

BASE, OTERO COUNTY, NEW MEXICO

A. PROPOSAL SUBMISSION

1. GENERAL REQUIREMENTS

1.1 The intent of this Request for Proposal (RFP) is to solicit proposals for the NC3 Support War Reserve Materiel (WRM) Storage/Shipping Facility, Holloman AFB, New Mexico. The Government reserves the right to award a contract without discussions in accordance with (IAW) FAR 52.215-1, therefore, the offeror’s initial proposal should contain the offeror’s best terms from a technical and cost/price standpoint. Offerors shall organize their proposals as described herein. Proposals may be determined non-responsive for failure to follow this format.

1.2 The proposal shall describe the capability of the Offeror to perform the requirements of the solicitation. The proposal should be specific and complete in every detail, and should be prepared simply and economically, providing a straightforward and concise description of capabilities to satisfactorily perform the requirements. The proposal should be practical, legible, clear, and coherent.

1.3 In order to effectively and equitably evaluate all proposals, the Contracting Officer must receive information containing sufficient detail to allow review and evaluation by the Government. Proposal clarity, organization, and cross-referencing are mandatory.

Failure to submit and organize proposals as requested may adversely affect an offeror’s evaluation.

2. PROPOSAL SUBMISSION REQUIREMENTS

2.1 Each volume shall be submitted electronically. There are two electronic options: via email or using the DoD SAFE (formerly AMRDEC SAFE) if proposals are too large to send via email. When using SAFE, Offerors are required to request a drop off code from the contract specialist Robert McPherren, robert.j.mcpherren@usace.army.mil prior to the proposal due date and time. Bonds may be submitted electronically with the proposal, however, a hard copy of the bonds must be submitted to attn: Robert McPherren at 4101 Jefferson Plaza NE, Albuquerque, NM 87109.

2.2 Each paragraph shall be single spaced and be separated by at least one blank line.

A standard, 12-point minimum font size applies. Arial or New Times Roman fonts are required. Tables and illustrations may use a reduced font size no less than 10-point and may be produced in landscape mode. Sheet size shall be 8.5 x 11 inches, however if mailto:robert.j.mcpherren@usace.army.mil drawings, charts, or other graphics are submitted, sheets no larger than 11 x 17 inches shall be used. Each 11 x 17 page shall count as one (1) single page toward the page count.

2.3 The following volumes of material shall be submitted:

Volume/Title Electronic Copies Page limit

Volume 1: Technical Proposal One (1) 30*

Volume 2: Price Proposal One (1) N/A

Volume Tab Title Digital

Copies Hard Copy

Maximum Pages

Rating

I A Factor 1: Relevant Contractor Experience

1 0 20 Acceptable/Unacceptable

I B Factor 2: Management Approach

1 0 10 Acceptable/Unacceptable

I C Factor 3: Past Performance

1 0 N/A Acceptable/Unacceptable

2 Factor 4: Cost/Price 1 0 N/A Not Rated

2 A Solicitation, Offer and Award Documents, and Certifications / Representations

1 0 N/A Not Rated

2 B Proposal Schedule 1 0 N/A Not Rated

2 C Bid Guarantee (Bid Bond)

1 1 N/A Not Rated

2 D Financials and Financial Standing Questionnaire

1 0 N/A Not Rated

2 E Small Business Subcontracting Plan

1 0 N/A Acceptable/Unacceptable

2 F JV Agreement or Teaming Agreement (if applicable) and/or Corporate, Partnership, Joint Venture Certificate

1 0 N/A Not Rated

* Past Performance Questionnaires, Representations and Certifications, performance recognition documents, Small Business Participation Past Performance, and Small Business Participation Commitment Document are excluded from the page count. Title sheets, indices, a detailed work schedule, and tables of contents are EXCLUDED from the page limitation.

NOTE 1: Pages that exceed the required page limitations will not be evaluated.

Additional pages over the maximum allowed will be removed or not read and will not be evaluated by the Government.

NOTE 2: A RATING OF UNACCEPTABLE ON ANY FACTOR WILL RESULT IN AN

OVERALL RATING OF UNACCEPTABLE.

3. PROPOSAL FILES

3.1 Format. The submission shall be clearly indexed and logically assembled. Each volume shall be clearly identified and shall begin at the top of a page. All pages of each volume shall be appropriately numbered and identified by the complete company name, date and Request for Proposal (RFP) number in the header and/or footer. A Table of Contents should be created using the Table of Content feature in MS Word. MS Word (doc) files shall use the following page setup parameters:

Margins – Top, Bottom, Left, Right – 1” Gutter – 0” From Edge – Header, Footer 0.5” Page Size, Width – 8.5” Page Size, Height – 11”

3.2 The following additional restrictions apply:

3.2.1 File Packaging. Files shall be in read-only, searchable format, using PDF files.

All price breakdown information to aide in the cost/price evaluation shall be submitted in Microsoft Office Excel.

3.2.2 Content Requirement. All information shall be confined to the appropriate file.

The offeror shall confine submissions to essential matters sufficient to define the proposal in a concise manner to permit a complete and accurate evaluation of each proposal. Proprietary information shall be clearly marked.

3.2.3 Where the word “project” appears, it is understood to mean a project(s), contract(s), task order(s), or any other contract document provided for in the Federal Acquisition Regulation (FAR 2.101). Examples of projects submitted by the Prime Contractor may be projects performed for a State or Federal Government Agency, or for a commercial or private sector customer.

B. FACTORS AND EVALUATION APPROACH

VOLUME I, Tabs A-C – Technical. The volume shall be organized in accordance with the 2. PROPOSAL SUBMISSION REQUIREMENTS and include the following:

1. Factor 1: Relevant Contractor Experience

1.1 The offeror shall submit examples of recent construction projects which best illustrate the experience of the construction contractor on relevant projects of similar scope, type, complexity, and magnitude as defined below. A minimum of three (3) projects but not more than five (5) are to be submitted for the Prime Contractor.

Limit the information to Factor 1 to twenty (20) pages or less.

1.2 Where the word “recent” appears it is understood to mean construction type project for which construction is at least 70% complete (measured by performance period days) as of the RFP closing date, or a construction type project that has been completed within 7 years of the RFP closing date. Projects completed more than 7 years before the RFP closing date will not be considered for evaluation purposes.

1.3 Where the word “relevant” appears, it is understood to mean that project experience submitted is similar to the context of the solicitation in terms of scope, type, magnitude of effort and complexity as described and required in this RFP. For this RFP, “relevant” projects are defined as projects that are similar in terms of:

• Scope: Project includes: reinforced concrete foundation, masonry walls, metal prefabricated insulated construction, standing seam metal roof, utilities, HVAC, fire detection/protection, pavements, access road, office space, site improvements, and all supporting work for a complete useable facility. The project also involves demolition of six existing structures with appropriate disposal of resulting materials.

• Type: Construction of large warehouse facility and associated features.

• Complexity: Working on military installation with the security requirements imposed on a…

This is the start of the file's text. The full file is on GovTribe.