This document provides details for a federal contract opportunity to rehabilitate the outlet works at Coolidge Dam on the San Carlos Indian Reservation in Arizona. The Bureau of Indian Affairs is seeking proposals to selectively rehabilitate and modify the existing outlet towers and low level conduits, add new isolation valves, upgrade existing regulating and guard gates operating equipment and control systems, and complete other miscellaneous improvements. Work will include both above water and underwater activities. The contract type will be firm-fixed-price. The projected value of construction is between $10-25 million. Proposals are due by June 5, 2020 after plans are issued on May 1, 2020. Offerors must register in the System for Award Management to receive an award. The document instructs offerors to check for amendments daily online and register with beta.sam to access technical data. It notes that project details may change and is subject to funding availability.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
W912PP20R0004
AMENDMENT No. 0004
2. SPECIFICATIONS: Delete the following listed pages and substitute the pages attached hereto. On the revised pages, for convenience, changes are emphasized by STRIKETHROUGH for deletions and UNDERLINE for additions from the previous issue. All portions of the revised (or new) pages shall apply whether or not changes have been indicated.
Delete Page Insert Page
VOLUME I VOLUME I
TABLE OF CONTENTS, page 4 TABLE OF CONTENTS, page 4 (New Page added in Amendment 0003 of VOL I Sol. and Specs.)
00 50 00 CONTRACTING FORMS AND 00 50 00 CONTRACTING FORMS AND
SUPPLEMENTS, Entire Section SUPPLEMENTS, Entire Section (Pages 76-94 of VOL I Sol. and Specs.)
00 70 00 CONDITIONS OF THE 00 70 00 CONDITIONS OF THE
CONTRACT, pages 108-109 CONTRACT, pages 108-109 (Pages 123-124 of VOL I Sol. and Specs.)
VOLUME II VOLUME II
TABLE OF CONTENTS, page 4 TABLE OF CONTENTS, page 4 (New Page added in Amendment 0003 of VOL II Sol. and Specs.)
N/A REFERENCE K- Environmental Assessment and Finding of No Significant Impact (158 pages, New) Insert after
REFERENCE J
3. DRAWING CHANGES: The following drawings have been revised and the sequence number changed to indicate such revision:
G-001 G-001
////////LAST ITEM////////
Coolidge Dam Outlet Works Rehab San Carlos Indian Reservation, AZ
TOC -4
W912PP20R0004
RTA
END OF CONTENTS
Reference J Boat Ramp Survey
RReeffeerreennccee DDrraawwiinnggss ((11))
REFERENCES (Continued)
Reference K Environmental Assessment and Finding of No Significant Impact
Amendment 0004
Section 00 50 00 - Contracting Forms and Supplements
General Decision Number: AZ20200007 06/05/2020
Superseded General Decision Number: AZ20190007
State: Arizona
Construction Type: Heavy Dams
Counties: Apache, Cochise, Coconino, Gila, Graham, Greenlee, La Paz, Navajo, Santa Cruz and Yavapai Counties in Arizona.
DAM CONSTRUCTION PROJECTS
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2020 1 01/10/2020 2 01/24/2020 3 01/31/2020 4 05/15/2020 5 06/05/2020
BOIL0627-003 10/01/2017
Rates Fringes
BOILERMAKER......................$ 35.30 28.41
BRAZ0003-005 07/01/2019
Rates Fringes
BRICKLAYER.......................$ 25.31 8.13
ZONE PAY:
(Radius miles from the intersection of Central Ave. and Washington St., Phoenix, AZ)
Zone A: 0-60 miles- Base Rate Zone B: 61-75 miles- Base Rate plus $2.00 per hour Zone C: 75-100 miles- Base Rate plus $3.00 per hour Zone D: 101-200 miles- Base Rate plus $3.50 per hour Zone E: Over 200 miles- Base Rate plus $6.50 per hour
BRAZ0003-013 07/01/2019
COCHISE and SANTA CRUZ COUNTIES; and the area of GRAHAM and GREENLEE COUNTIES located East and South of the San Francisco River to the Gila River
Rates Fringes
BRICKLAYER.......................$ 25.31 8.13
ZONE PAY:
(Radius miles from the intersection of Central Ave. and Washington St., Phoenix, AZ)
Zone A: 0-60 miles- Base Rate Zone B: 61-75 miles- Base Rate plus $2.00 per hour Zone C: 75-100 miles- Base Rate plus $3.00 per hour Zone D: 101-200 miles- Base Rate plus $3.50 per hour Zone E: Over 200 miles- Base Rate plus $6.50 per hour
CARP0408-004 07/01/2019
Rates Fringes
CARPENTER (Including Form Work)............................$ 28.08 12.74
PILEDRIVERMAN....................$ 27.38 12.44
CARP1914-001 09/01/2019
Rates Fringes
MILLWRIGHT.......................$ 40.61 17.53
ZONE DEFINITIONS FOR MILLWRIGHTS: Mileage shall be calculated from the construction site to the City Hall in Phoenix or Tucson, or to the workmen's residence, whichever is less:
Zone 1: 0-30 miles Zone 2: 31-49 miles Zone 3: 50 miles and over
CARP1914-002 09/01/2003
Rates Fringes
DIVER (Standby) Zone 1......................$ 22.98 8.93 Zone 2......................$ 25.37 8.93 Zone 3......................$ 28.49 8.93
DIVER (Wet) Zone 1......................$ 43.79 8.93 Zone 2......................$ 45.17 8.93 Zone 3......................$ 48.29 8.93
ZONE DEFINITIONS:
Mileage shall be calculated from the construction site to the City Hall in Phoenix or Tucson, or to the workmen's residence, whichever is less:
Zone 1: 0-30 miles Zone 2: 31-49 miles Zone 3: 50 miles and over
ELEC0518-001 08/01/2018
APACHE COUNTY [South of Highway 66]; All of GILA COUNTY; NAVAJO COUNTY [South and East of boundary beginning at a point where Clear Creek crosses the Coconino-Navajo County line, extending Northeasterly along Clear Creek and Northeasterly to Cottonwood Wash, along Cottonwood Wash North easterly to where it intersects the Navajo Indian Reservation, then East along the Navajo Indian Reservation Boundary line to a point where it intersects the Navajo-Apache County Line]; and PINAL COUNTY [North of the line, ""First Standard Parallel South"" and East of the line, ""Second Guide Meridian East""]
Rates Fringes
ELECTRICIAN......................$ 28.60 11.36
ELEC0570-004 12/01/2019
COCHISE, GRAHAM, LA PAZ, AND SANTA CRUZ COUNTIES
Rates Fringes
ELECTRICIAN......................$ 27.78 18% + 5.60
ZONE DEFINITIONS-
Zone A: the area within a twenty-nine (29) mile radius from a basing point at the Tucson Town Hall.
Zone B: 29 to 46 mile radius from the town hall in Tucson- an additional $ 1.25 per hour
Zone C: 47 mile radius from the town hall in Tucson to the outer limits of the geographic jurisdiction- an additional $ 3.75 per hour
ELEC0611-005 01/01/2020
APACHE COUNTY [Area North of Highway 66]
Rates Fringes
Electrician/Wireman Zone 1......................$ 32.70 11.67
ZONE 1: 0 to 10 miles from Gallup, NM ZONE 2: 10 to 30 miles from Gallup - Add 9% ZONE 3: 30 to 40 miles from Gallup - Add 15% ZONE 4: Over 40 miles from Gallup - Add 26%
ELEC0640-003 01/01/2020
COCONINO and YAVAPAI COUNTIES; and the following portions of Counties: NAVAJO COUNTY (North and West of a boundary beginning at a point where Clear Creek crosses the Coconino-Navajo County line, Northeasterly along Clear Creek and Northeasterly to Cottonwood Wash, along Cottonwood Wash Northeasterly to where it intersects the Navajo Indian Reservation then Easterly along the Navajo Indian Reservation Boundary line to a point where it intersects the Navajo-Apache County line); PINAL COUNTY (area lying North and West of the boundary line beginning at a point where Papago Indian Reservation Road No. 15 crosses the Pima-Pinal County line, then extending in a Northeasterly direction on Papago Indian Reservation Road No.15 to the intersection with Highway FAS-267, extending North on Highway FAS-267 to the intersection with the Florence Canal, North and East on the Florence Canal to the intersection of the line ""Second Guide Meridian East"" then North to the Pinal-Maricopa County lines)
Rates Fringes
ELECTRICIAN......................$ 30.00 11.05
* ENGI0428-002 06/01/2020
Rates Fringes
POWER EQUIPMENT OPERATOR
Group 1.....................$ 27.04 11.72 Group 2.....................$ 30.31 11.72 Group 3.....................$ 31.39 11.72 Group 4.....................$ 32.42 11.72
POWER EQUIPMENT OPERATORS CLASSIFICATIONS:
GROUP 1: A-frame boom truck, winch truck, air compressor, Beltcrete, boring bridge and texture, concrete mixer (skip type), conductor, brakeman, handler, conveyor, cross timing and pipe float, curing machine, dinky (under 20 tons), elevator hoist (Husky and similar), firemen (all), forklift and Ross carrier, generator (all), highline cableway signalman, hydrographic mulcher, hydrographic seeder, joint inserter, jumbo finishing machine, Kolman belt loader, machine conveyor, multiple power concrete saw, oiler, pavement breaker, power grizzly, power sweeper, pressure grout machine, pump, roller (except as otherwise classified), self-propelled chip spreading machine, skiploader (3 cu. yd. and less), slurry seal machine (Moto paver driver), small self-propelled compactor (with blade)-backfill, ditch operation, straw blower, tractor (D-5 and under), tripper, tugger, welding machine, wheel-type tractor (Ford, Ferguson type with attachments, Bee Gee etc.)
GROUP 2: Aggregate plant (including crushing, screening and sand plants, etc.), asphalt plant mixer, asphalt laydown machine, backhoe (rubber tired or track, less than 1 cu.
yd. MRC), Bee Gee operator boring machine, concrete batch plant (all types and sizes), concrete mechanical tamping, spreading or finishing machine (including Clary, Johnson or similar types), concrete mixer (paving type and mobile mixers), concrete pump, crane (crawler and pneumatic less than 15 ton capacity MRC), drilling machine (including water wells), elevating grader (all types and sizes except as otherwise classified), field equipment serviceman, paver and similar type equipment, motor grader (any type power blade-rough), oiler driver, operating engineer rigger, pneumatic tired scraper (all sizes and types), power jumbo form setter, road oil mixing machine, roller (on all types asphalt pavement), screed, self-propelled compactor (with blade, 815, 825 or equivalent-grade operation), skip loader (all types with a rated capacity over 3 but less than 6 cu.
yd.), slip form (power driven lifting device for concrete forms), soil cement road mixingmachine (single pass type), heater and planer, tractor (dozer, pusher-all), traveling pipe-wrapping machine, trenching machine, tugger (two or more)
GROUP 3: Asphalt or concrete planing, rotomill and milling machine, auto grade machine (CMI and similar equipment), boring machine (including mole, badger and similar type), concrete pump (truck mounted with boom), crane (crawler and pneumatic over 15 tons but less than 100 tons capacity MRC), crawler type tractor with boom attachment and slope bar, derrick, Gradall, heavy duty mechanic/welder, helicopter hoist operator or pilot, highline cableway, mass excavator (150 Bucyrus, Erie and similar type), mechanical hoist (two or more drums), motor grader (any type power blade-finish), mucking machine, overhead crane, Grade Checker, piledriver engineer (portable, stationary or skid rig), power driven ditch lining or ditch trimming machine, remote control earth moving machine, skip loader (all types with rated capacity 6 cu. yd. but less than 10 cu. yd.), slip form paving machine (including Gunnert, Zimmerman and similar types), tower crane or similar type, universal equipment operator (backhoe, clamshell, dragline, shovel etc., up to 10 cu. yd.); Operating Engineers Electrician including Tower Erector, Lineman & Cable Splicer (load side of main disconnect).
GROUP 4: Crane operator (pneumatic or crawler-100 tons hoisting capacity and over, MRC rating), skip loader (all types with rated capacity of 10 cu. yd. or more), universal equipment operator (backhoe, clamshell, dragline, shovel, etc., 10 cu. yd. and over)
Multiple-Unit Earth Equipment (Holland Loader etc.), Tractor operator, Pneumatic-Tired or Track type, Two Units-$0.50 per hour over base rate; and $1.00 per hour for each additional unit
All Operators, Oilers, and Motor Crane Drivers on equipment with Booms, except concrete pumping truck booms, including Jibs, shall receive $0.01 per hour per foot over 80 ft in addition to regular rate of pay
Premium pay for performing hazardous waste removal $0.50 per hour over base rate.
IRON0075-001 08/01/2019
Rates Fringes
IRONWORKER.......................$ 27.80 19.05
Zone 1: 0 to 50 miles from City Hall in Phoenix or Tucson Zone 2: 050 to 100 miles - Add $4.00 Zone 3: 100 to 150 miles - Add $5.00 Zone 4: 150 miles & over - Add $6.50
PAIN0086-004 04/01/2014
Rates Fringes
PAINTER..........................$ 22.42 4.85
PLAS0394-005 07/01/2019
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 25.08 8.57
PLUM0469-006 07/01/2019
Rates Fringes
PLUMBER/PIPEFITTER
Apache, Coconino,Gila, Greenlee, La Paz, Navajo, and Yavapai.................$ 44.00 17.15
Cochise and Santa Cruz......$ 38.65 17.15
TEAM0104-002 09/01/2019
Rates Fringes
TRUCK DRIVER
Group 2.....................$ 18.57 1.50+a Group 3.....................$ 19.03 1.50+a Group 4.....................$ 20.28 1.50+a Group 5.....................$ 19.40 1.50+a Group 6.....................$ 21.07 1.50+a
A. Health & Welfare $1,053.46 per month.
FOOTNOTE:
a. Health & Welfare $984.26 per month.
TRUCK DRIVER CLASSIFICATIONS:
GROUP 2: 2 or 3 axle Dump , Water Truck under 2500 gal.
GROUP 3: 4 axle Dump, Water Truck Drive- (2500 gal but less than 4000 gal)
GROUP 4: 5 axle Dump, Water Truck 4000 gal and over GROUP 5: 6-axle Dump GROUP 6: 7-axle Dump, 8-axle Dump
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
General Decision Number: AZ20200006 06/05/2020
Superseded General Decision Number: AZ20190006
State: Arizona
Construction Type: Heavy Dams
Counties: Maricopa, Mohave, Pima, Pinal and Yuma Counties in Arizona.
DAM CONSTRUCTION PROJECTS
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2020 1 05/15/2020 2 06/05/2020
BOIL0627-003 10/01/2017
Rates Fringes
BOILERMAKER......................$ 35.30 28.41
BRAZ0003-006 07/01/2019
MARICOPA, MOHAVE, PINAL, AND YUMA COUNTIES
Rates Fringes
BRICKLAYER.......................$ 25.31 8.13
ZONE PAY:
(Radius miles from the intersection of Central Ave. and Washington St., Phoenix, AZ)
Zone A: 0-60 miles- Base Rate Zone B: 61-75 miles- Base Rate plus $2.00 per hour Zone C: 75-100 miles- Base Rate plus $3.00 per hour Zone D: 101-200 miles- Base Rate plus $3.50 per hour Zone E: Over 200 miles- Base Rate plus $6.50 per hour
BRAZ0003-012 07/01/2019
PIMA COUNTY
Rates Fringes
BRICKLAYER.......................$ 25.31 8.13
ZONE PAY:
(Radius miles from the intersection of Central Ave. and Washington St., Phoenix, AZ)
Zone A: 0-60 miles- Base Rate Zone B: 61-75 miles- Base Rate plus $2.00 per hour Zone C: 75-100 miles- Base Rate plus $3.00 per hour Zone D: 101-200 miles- Base Rate plus $3.50 per hour Zone E: Over 200 miles- Base Rate plus $6.50 per hour
CARP0408-004 07/01/2019
Rates Fringes
CARPENTER (Including Form Work)............................$ 28.08 12.74
PILEDRIVERMAN....................$ 27.38 12.44
CARP1914-001 09/01/2019
Rates Fringes
MILLWRIGHT.......................$ 40.61 17.53
ZONE DEFINITIONS FOR MILLWRIGHTS: Mileage shall be calculated from the construction site to the City Hall in Phoenix or Tucson, or to the workmen's residence, whichever is less:
Zone 1: 0-30 miles Zone 2: 31-49 miles Zone 3: 50 miles and over
CARP1914-002 09/01/2003
Rates Fringes
DIVER (Standby) Zone 1......................$ 22.98 8.93 Zone 2......................$ 25.37 8.93 Zone 3......................$ 28.49 8.93
DIVER (Wet) Zone 1......................$ 43.79 8.93 Zone 2......................$ 45.17 8.93 Zone 3......................$ 48.29 8.93
ZONE DEFINITIONS:
Mileage shall be calculated from the construction site to the City Hall in Phoenix or Tucson, or to the workmen's residence, whichever is less:
Zone 1: 0-30 miles Zone 2: 31-49 miles Zone 3: 50 miles and over
* ENGI0428-002 06/01/2020
Rates Fringes
POWER EQUIPMENT OPERATOR
Group 1.....................$ 27.04 11.72 Group 2.....................$ 30.31 11.72 Group 3.....................$ 31.39 11.72 Group 4.....................$ 32.42 11.72
POWER EQUIPMENT OPERATORS CLASSIFICATIONS:
GROUP 1: A-frame boom truck, winch truck, air compressor, Beltcrete, boring bridge and texture, concrete mixer (skip type), conductor, brakeman, handler, conveyor, cross timing and pipe float, curing machine, dinky (under 20 tons), elevator hoist (Husky and similar), firemen (all), forklift and Ross carrier, generator (all), highline cableway signalman, hydrographic mulcher, hydrographic seeder, joint inserter, jumbo finishing machine, Kolman belt loader, machine conveyor, multiple power concrete saw, oiler, pavement breaker, power grizzly, power sweeper, pressure grout machine, pump, roller (except as otherwise classified), self-propelled chip spreading machine, skiploader (3 cu. yd. and less), slurry seal machine (Moto paver driver), small self-propelled compactor (with blade)-backfill, ditch operation, straw blower, tractor (D-5 and under), tripper, tugger, welding machine, wheel-type tractor (Ford, Ferguson type with attachments, Bee Gee etc.)
GROUP 2: Aggregate plant (including crushing, screening and sand plants, etc.), asphalt plant mixer, asphalt laydown machine, backhoe (rubber tired or track, less than 1 cu.
yd. MRC), Bee Gee operator boring machine, concrete batch plant (all types and sizes), concrete mechanical tamping, spreading or finishing machine (including Clary, Johnson or similar types), concrete mixer (paving type and mobile mixers), concrete pump, crane (crawler and pneumatic less than 15 ton capacity MRC), drilling machine (including water wells), elevating grader (all types and sizes except as otherwise classified), field equipment serviceman, paver and similar type equipment, motor grader (any type power blade-rough), oiler driver, operating engineer rigger, pneumatic tired scraper (all sizes and types), power jumbo form setter, road oil mixing machine, roller (on all types asphalt pavement), screed, self-propelled compactor (with blade, 815, 825 or equivalent-grade operation), skip loader (all types with a rated capacity over 3 but less than 6 cu.
yd.), slip form (power driven lifting device for concrete forms), soil cement road mixingmachine (single pass type), heater and planer, tractor (dozer, pusher-all), traveling pipe-wrapping machine, trenching machine, tugger (two or more)
GROUP 3: Asphalt or concrete planing, rotomill and milling machine, auto grade machine (CMI and similar equipment), boring machine (including mole, badger and similar type), concrete pump (truck mounted with boom), crane (crawler and pneumatic over 15 tons but less than 100 tons capacity MRC), crawler type tractor with boom attachment and slope bar, derrick, Gradall, heavy duty mechanic/welder, helicopter hoist operator or pilot, highline cableway, mass excavator (150 Bucyrus, Erie and similar type), mechanical hoist (two or more drums), motor grader (any type power blade-finish), mucking machine, overhead crane, Grade Checker, piledriver engineer (portable, stationary or skid rig), power driven ditch lining or ditch trimming machine, remote control earth moving machine, skip loader (all types with rated capacity 6 cu. yd. but less than 10 cu. yd.), slip form paving machine (including Gunnert, Zimmerman and similar types), tower crane or similar type, universal equipment operator (backhoe, clamshell, dragline, shovel etc., up to 10 cu. yd.); Operating Engineers Electrician including Tower Erector, Lineman & Cable Splicer (load side of main disconnect).
GROUP 4: Crane operator (pneumatic or crawler-100 tons hoisting capacity and over, MRC rating), skip loader (all types with rated capacity of 10 cu. yd. or more), universal equipment operator (backhoe, clamshell, dragline, shovel, etc., 10 cu. yd. and over)
Multiple-Unit Earth Equipment (Holland Loader etc.), Tractor operator, Pneumatic-Tired or Track type, Two Units-$0.50 per hour over base rate; and $1.00 per hour for each additional unit
All Operators, Oilers, and Motor Crane Drivers on equipment with Booms, except concrete pumping truck booms, including Jibs, shall receive $0.01 per hour per foot over 80 ft in addition to regular rate of pay
Premium pay for performing hazardous waste removal $0.50 per hour over base rate.
IRON0075-001 08/01/2019
Rates Fringes
IRONWORKER.......................$ 27.80 19.05
Zone 1: 0 to 50 miles from City Hall in Phoenix or Tucson Zone 2: 050 to 100 miles - Add $4.00 Zone 3: 100 to 150 miles - Add $5.00 Zone 4: 150 miles & over - Add $6.50
* LABO1184-006 06/01/2020
Rates Fringes
Laborers:
Group 1.....................$ 20.93 6.06 Group 2.....................$ 20.93 6.06 Group 3.....................$ 21.63 6.06 Group 4.....................$ 22.57 6.06 Group 5.....................$ 23.43 6.06
LABORERS CLASSIFICATIONS:
GROUP 1: Laborer, general or construction; tool dispatcher or checker; manually controlled signal operator; fence builder, guard rail builder-highway; chat box man; dumpman and/or spotter; rip rap stone man; rock slinger; form stripper; packing rod steel and pans; cesspool diggers and installers; astro turf layer; clean up-bull gang trackman, railroad; chipper (clearing and grubbing);
kettleman-tarman; spikers, wrenchers-creosote tieman; floor sanders-concrete; sandblaster (pot tender); powderman tender; fine grader; all tenders not herein separately classified; window cleaner; flagger
GROUP 2: Concrete laborer (belt, pipe and/or hoseman);
cement mason tender; cutting torch operator; power type concrete buggy; bander; guinea chaser
GROUP 3: Operator and tender of pneumatic and electric tools; concrete vibrating machines, chain saw (on clearing and grubbing); hydraulic jacks and similar mechanical tools not separately herein classified; pipe caulker and/or backup man-pipeline; riggers and signal man-pipeline; pipe wrapper; cribber & shorer (except tunnel); pneumatic gopher; pre-cast manhole erector
GROUP 4: Asphalt raker and ironer; air and water washout nozzleman (low and high pressure); scaler (using bos'n's chair or safety belt); tamper (mechanical-all types);
sandblaster (nozzleman); concrete saw (hand-guided);
concrete cutting torch; gunite (gunman, mixerman, rodman);
bio-filer, pressman, installer, operator; hand-guided trencher and similarly operated equipment; driller (jackhammer and/or pavement breaker); grade setter (pipeline); pipe layer including but not limited to non-metallic transite and plastic pipe, water pipe, sewer pipe, drain pipe, and underground tile pipe and conduit);
chuck tender (except tunnel)
GROUP 5: Drill doctor and/or air tool repairman; scaler (driller); form setter and/or builder; welder and/or pipelayer installing process piping; driller-core, diamond, wagon, air track, Joy, Mustang, PR-143, 220 Gardner-Denver, Hydrasonic, powderman; water blaster operator
NOTE: $0.50 per hour premium for performing hazardous waste removal
PAIN0086-004 04/01/2014
Rates Fringes
PAINTER..........................$ 22.42 4.85
PLAS0394-004 07/01/2019
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 25.08 8.57
PLUM0469-005 07/01/2019
Rates Fringes
PLUMBER/PIPEFITTER
Maricopa, Mohave, Pinal, and Yuma....................$ 44.00 17.15
Pima........................$ 38.65 17.15
TEAM0104-002 09/01/2019
Rates Fringes
TRUCK DRIVER
Group 2.....................$ 18.57 1.50+a Group 3.....................$ 19.03 1.50+a Group 4.....................$ 20.28 1.50+a Group 5.....................$ 19.40 1.50+a Group 6.....................$ 21.07 1.50+a
A. Health & Welfare $1,053.46 per month.
FOOTNOTE:
a. Health & Welfare $984.26 per month.
TRUCK DRIVER CLASSIFICATIONS:
GROUP 2: 2 or 3 axle Dump , Water Truck under 2500 gal.
GROUP 3: 4 axle Dump, Water Truck Drive- (2500 gal but less than 4000 gal)
GROUP 4: 5 axle Dump, Water Truck 4000 gal and over GROUP 5: 6-axle Dump GROUP 6: 7-axle Dump, 8-axle Dump
SUAZ1994-012 02/01/1994
Rates Fringes
ELECTRICIAN......................$ 16.00 2.84
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
By: ___
(End of clause)
52.230-3 DISCLOSURE AND CONSISTENCY OF COST ACCOUNTING PRACTICES (DEVIATION 2018-
O0015) (MAY 2018)
(1) Comply with the requirements of 48 CFR 9904.401, Consistency in Estimating, Accumulating, and Reporting Costs; 48 CFR 9904.402, Consistency in Allocating Costs Incurred for the Same Purpose; 48 CFR 9904.405, effect on the date of award of this contract as indicated in 48 CFR Part 9904.
(2) (CAS-covered Contracts Only) If it is a business unit of a company required to submit a Disclosure Statement, disclose in writing its cost accounting practices as required by 48 CFR 9903.202-1 through 9903.202-5. If the Contractor has notified the Contracting Officer that the Disclosure Statement contains trade secrets and commercial or financial information which is privileged and confidential, the Disclosure Statement shall be protected and shall not be released outside of the Government.
however, by either the Government or the Contractor, and the Contractor agrees to negotiate with the Contracting Officer the terms and conditions under which a change may be made. After the terms and conditions under which the change is to be made have been agreed to, the change must be applied prospectively to this contract, and the Disclosure Statement, if affected, must be amended accordingly.
(ii) The Contractor shall, when the parties agree to a change to a cost accounting practice and the Contracting Officer has made the finding required in 48 CFR 9903.201-6(c), that the change is desirable and not detrimental to the interests of the Government, negotiate an equitable adjustment as provided in the Changes clause of this contract. In the absence of the required finding, no agreement may be made under this contract clause that will increase costs paid by the United States.
(4) Agree to an adjustment of the contract price or cost allowance, as appropriate, if the Contractor or a subcontractor fails to comply with the applicable CAS or to follow any cost accounting practice, and such failure results in any increased costs paid by the United States. Such adjustment shall provide for recovery of the increased costs to the United States together with interest thereon computed at the annual rate established under section 6621(a)(2) of the Internal Revenue Code of 1986 (26 U.S.C. 6621(a)(2)), from the time the payment by the United States was made to the time the adjustment is effected.
(b) If the parties fail to agree whether the Contractor has complied with an applicable CAS, rule, or regulation as specified in 48 CFR 9903 and 9904 and as to any cost adjustment demanded by the United States, such failure to agree will constitute a dispute under 41 U.S.C. chapter 71, Contract Disputes.
(c) The Contractor shall permit any authorized representatives of the Government to examine and make copies of any documents, papers, and records relating to compliance with the requirements of this clause.
(d) The Contractor shall include in all negotiated subcontracts, which the Contractor enters into, the substance of
(1) If the subcontract is awarded to a business unit which pursuant to 48 CFR 9903.201-2 is subject to other types of CAS coverage, the substance of the applicable clause set forth in subsection 30.201-4 of the Federal Acquisition Regulation shall be inserted.
(2) This requirement shall apply only to negotiated subcontracts in excess of $2 million.
(3) The requirement shall not apply to negotiated subcontracts otherwise exempt from the requirement to include a CAS clause as specified in 48 CFR 9903.201-1.
(End of clause)
52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)
(a) Except as stated in paragraph (b) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:
(1) Any such clause is unenforceable against the Government.
(2) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an ``I agree'' click box or other comparable mechanism (e.g., ``click-wrap'' or ``browse-wrap'' agreements), execution does not bind the Government or any Government authorized end user to such clause.
(3) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.
(b) Paragraph (a) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
(End of clause)
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS
SUBCONTRACTORS (DEC 2013)
(a) Upon receipt of accelerated payments from the Government, the Contractor shall make accelerated payments to its small business subcontractors under this contract, to the maximum extent practicable and prior to when such payment is otherwise required under the applicable contract or subcontract, after receipt of a proper invoice and all other required documentation from the small business subcontractor.
(b) The acceleration of payments under this clause does not provide any new rights under the Prompt Payment Act.
(c) Include the substance of this clause, including this paragraph (c), in all subcontracts with small business concerns, including subcontracts with small business concerns for the acquisition of commercial items.
(End of clause)
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)
Coolidge Dam Outlet Works Rehab San Carlos Indian Reservation, AZ
TOC -4
W912PP20R0004
RTA
END OF CONTENTS
Reference J Boat Ramp Survey
RReeffeerreennccee DDrraawwiinnggss ((11))
REFERENCES (Continued)
Reference K Environmental Assessment and Finding of No Significant Impact
COOLIDGE DAM OUTLET
WORKS REHABILITATION
K ENVIRONMENTAL ASSESSMENT AND
FINDING OF NO SIGNIFICANT IMPACT
IN R EPLY REFER To·
Division of Natural Resources
Memorandum
United States Department of the Interior
BUREAU OF INDIAN AFFAIRS
WESTERN REGIONAL OFFICE
2600 North Central Avenue Phoenix, Arizona 85004
FEB 2 7 2018
To: Interested Parties (see attached distribution list)
From: ACT1NC3Regional Director ~ ~
TAKE PRIDE
INAMERICA
Subject: Notice of Availability - Coolidge Dam Cylinder Gate Replacement Project
Attached please find the Final Environmental Assessment and Finding of No Significant Impact and Decision Statement for the Coolidge Dam Cylinder Gate Replacement Project. The documents are provided on the attached compact disk.
If you have any questions, please contact Ms. Catherine Wilson, Supervisory Water Rights
Specialist, at (602) 379-6789.
Attachments: Distribution List Compact Disk cc: Entities on Distribution List Project Manager, San Carlos Irrigation Project Superintendent, San Carlos Agency Division of Water and Power, Branch of Irrigation and Power
Coolidge Dam Cylinder Gate Replacement Project Distribution List
Affiliation M First Last Title Agency A1 City ST ZIP Tribe Mr. Terry Rambler Chairman San Carlos Apache Tribe P.O. Box 0 San Carlos AZ 85550 Tribe Mr. Tim Stevens Director San Carlos Apache Tribe Recreation and Wildlife Department P.O. Box 97 San Carlos AZ 85550 GRIC Mr. Stephen Roe Lewis Governor Gila River Indian Community P.O. Box 97 Sacaton AZ 85147 GRIIDD Mr. Ron Allison Director Gila River Indian Irrigation and Drainage District 192 S. A St., P.O. Box 2202 Sacaton AZ 85147 SCIDD Mr. Michael Urton General Manager San Carlos Irrigation and Drainage District 120 S. 3rd St. Coolidge AZ 85128 USGS Mr. Christopher Smith U.S. Geological Survey 520 N. Park Ave. Tucson AZ 85719 USGS Mr. Kenneth Fossum U.S. Geological Survey 1769 W. University Drive Tempe AZ 85281 BLM Mr. Scott Feldhausen District Manager Gila District Office, Bureau of Land Management 3201 E. Universal Way Tucson AZ 85756-5021 BLM Mr. Scott Cooke Field Manager Safford Field Office, Bureau of Land Management 711 14th Ave. Safford AZ 85546-3321 BLM Ms. Roxie Trost Deputy State Director Resources and Planning, Bureau of Land Management, Arizona State Office 1 N. Central Ave. Phoenix AZ 85004 Hayden Mr. Bobby Smith Mayor Town of Hayden P.O. Box B Hayden AZ 85135 Winkelman Mr. Louis Bracamonte Mayor Town of Winkelman P.O Box 386 Winkelman AZ 85192 Kearney Ms. Debra Sommers Mayor Town of Kearney P.O Box 639 Kearney AZ 85137 Asarco Mr. Jack Garrity Asarco Hayden Complex 100 Hayden Ave. Hayden AZ 85137 Water Ms. Patricia A. Doyle Gila Water Commissioner 512 S. 2nd Ave. Safford AZ 85546 DPS Capt.