Conformed-AMDT004_W912PM22B0033-MOTSU-Berms-Tech-Summary-Changes-25OCT22.pdf
PDF 8 MB Posted
- Attached to
- MOTSU Berm Repair Construction Phase 1 Federal contract opportunity
- Solicitation number
- W912PM22B0033
About this file
This document provides details for a federal contract opportunity to perform site preparation work at the Military Ocean Terminal at Sunny Point (MOTSU) in North Carolina. The project includes heavy tree clearing, sediment and erosion control, potential wetland mitigation primarily in the North Rail Holding Yard, and significant earthwork to improve deficient earthen berms between ammunition and explosive storage areas. The North American Industry Classification System code is 237990 for other heavy and civil engineering construction. The contract value is estimated between $10,000,000 to $25,000,000. This will be a 100% competitive small business set-aside awarded as a single firm fixed price contract by the U.S. Army Corps of Engineers, Wilmington District. Offerors must register in the System for Award Management to be eligible for award. The solicitation number is W912PM22B0033 and the opportunity was posted on the SAM website.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B1 Abstract W912PM22B0033.pdf | ||
| Bid Opening Sign-in Sheet.pdf | ||
| W912PM22B0033-0004(1).pdf | ||
| South_Rail_Holding_Yard.pdf | ||
| Conformed-AMDT003_W912PM22B0033-MOTSU-Berms-Tech-Summary-Changes.pdf | ||
| W912PM22B0033-0003 SF30(1).pdf | ||
| W912PM22B0033-0002 (Conformed Copy).pdf | ||
| W912PM22B0033-0002.pdf | ||
| Conformed-AMDT0002_W912PM22B0033_MOTSU-BermImp_Tech_Summary_Changes.pdf | ||
| W912PM22B0033-0001.pdf | ||
| W912PM22B0033-0001 (Conformed Copy).pdf | ||
| SAW_MO-20-03 MOTSU BLAST BERM DESIGN - PHASE 1 - RTA - CDs (Locked).pdf | ||
| MOTSU-Berms-Phase1-Specs-RTA.pdf | ||
| W912PM22B0033.pdf | ||
| NCIC CONSENT FORM.pdf | ||
| SAW_MO-20-03 MOTSU BLAST BERM DESIGN - PHASE 1 - RTA - CDs (UnLocked).pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation # W912PM22B0033 Project Title – MOTSU Berm Repair Construction Phase 1 Amendment No. 004 Date: 25-OCTOBER-2022
TECHNICAL SUMMARY OF CHANGES
1. CHANGES TO SPECIFICATIONS. Attached hereto are the revised specifications. Additions to the specifications are shown in green text and deletions are shown with red strikethrough text.
A. REVISED SECTIONS. A summary of the sections that were revised is shown below.
1. 01 50 00 TEMPORARYCONSTRUCTION FACILITIES AND CONTROLS
o Subpart 3.7: GOVERNMENT FIELD OFFICE – This subpart has been deleted.
3.7.1: Resident Engineer’s Office 3.7.2: Trailer Type Mobile Office
Subparts have been deleted.
2. 31 00 00 EARTHWORK
o Subpart 3.7: GROUND SURFACE PREPARATION -Subpart deleted.
3.7.1: General Requirements
This subpart has been deleted.
o Subpart 3.15.2: In-Place Densities b: This subpart has been revised.
o Subpart 3.15.3: Moisture Contents
This subpart has been deleted.
o Subpart 3.15.3: Optimum Moisture and Laboratory Maximum Density
Reinstated; redlines from Amendment 003 removed.
2. CHANGES TO DRAWINGS. Attached hereto are revised drawing sheets.
A. REVISED DRAWINGS (ISSUED). The following revised drawings replace like numbered drawings and are issued herewith:
CE-502 – EROSION AND SEDIMENT CONTROL DETAILS
o The notes associated with details G1 and G10 have been revised.
…end of summary…
MO-20-03, MOTSU Blast Berm Design Contract #W912PM-19-D-0002 Amendment 004
SECTION 01 50 00
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
11/ 20, CHG 1: 08/ 21
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)
MUTCD (2009; Rev 2012) Manual on Uniform Traffic Control Devices
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Construction Site Plan ; G
Traffic Control Plan ; G
Haul Road Plan ; G
Contractor Computer Cybersecurity Compliance Statements ; G
Contractor Temporary Network Cybersecurity Compliance Statements ; G
SD-03 Product Data
Backflow Preventers ; G
SD-06 Test Reports
Backflow Preventer Tests ; G
SD-07 Certificates
Backflow Tester Certification
Backflow Preventers Certificate of Full Approval; G
SECTION 01 50 00 Page 1
1.3 CONSTRUCTION SITE PLAN
Prior to the start of work, submit for Government approval a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.
1.4 BACKFLOW PREVENTERS CERTIFICATE
1.4.1 Backflow Tester Certificate
Prior to testing, submit to the Contracting Officer certification issued by the State or local regulatory agency attesting that the backflow tester has successfully completed a certification course sponsored by the regulatory agency. Tester must not be affiliated with a company participating in other phases of this Contract.
1.4.2 Backflow Prevention Training Certificate
Submit a certificate recognized by the State or local authority that states the Contractor has completed at least 10 hours of training in backflow preventer installations. The certificate must be current.
1.5 DOD CONDITION OF READINESS (COR)
DOD will set the Condition of Readiness (COR) based on the weather forecast for sustained winds 50 knots ( 58 mph ) or greater. Contact the Contracting Officer for the current COR setting.
Monitor weather conditions a minimum of twice a day and take appropriate actions according to the approved Emergency Plan in the accepted Accident Prevention Plan, EM 385-1-1 Section 01 Emergency Planning and the instructions below.
Unless otherwise directed by the Contracting Officer, comply with:
a. Condition FOUR (Sustained winds of 58 mph or greater expected within 72 hours): Normal daily jobsite cleanup and good housekeeping practices. Collect and store in piles or containers scrap lumber, waste material, and rubbish for removal and disposal at the close of each work day. Maintain the construction site including storage areas, free of accumulation of debris. Stack form lumber in neat piles less than 3.3 feet high. Remove all debris, trash, or objects that could become missile hazards. Review requirements pertaining to "Condition THREE" and continue action as necessary to attain "Condition FOUR" readiness. Contact Contracting Officer for weather and COR updates and completion of required actions.
b. Condition THREE (Sustained winds of 58 mph or greater expected within 48 hours): Maintain "Condition FOUR" requirements and commence securing operations necessary for "Condition ONE" which cannot be completed within 18 hours. Cease all routine activities which might interfere with securing operations. Commence securing and stow all
SECTION 01 50 00 Page 2 gear and portable equipment. Make preparations for securing buildings. Reinforce or remove formwork and scaffolding. Secure machinery, tools, equipment, materials, or remove from the jobsite.
Expend every effort to clear all missile hazards and loose equipment from general base areas. Contact Contracting Officer for weather and COR updates and completion of required actions. Review requirements pertaining to "Condition TWO" and continue action as necessary to attain "Condition THREE" readiness.
c. Condition TWO (Sustained winds of 58 mph or greater expected within 24 hours): Secure the jobsite, and leave Government premises.
d. Condition ONE. (Sustained winds of 58 mph or greater expected within 12 hours): Contractor access to the jobsite and Government premises is prohibited.
1.6 CYBERSECURITY DURING CONSTRUCTION
{For Reference Only: This subpart (and its subparts) relates to AC-18, SA-3, CCI-00258.} Meet the following requirements throughout the construction process.
1.6.1 Contractor Computer Equipment
Contractor owned computers may be used for construction. When used, contractor computers must meet the following requirements:
1.6.1.1 Operating System
The operating system must be an operating system currently supported by the manufacturer of the operating system. The operating system must be current on security patches and operating system manufacturer required updates.
1.6.1.2 Anti-Malware Software
The computer must run anti-malware software from a reputable software manufacturer. Anti-malware software must be a version currently supported by the software manufacturer, must be current on all patches and updates, and must use the latest definitions file. All computers used on this project must be scanned using the installed software at least once per day.
1.6.1.3 Passwords and Passphrases
The passwords and passphrases for all computers must be changed from their default values. Passwords must be a minimum of eight characters with a minimum of one uppercase letter, one lowercase letter, one number and one special character.
1.6.1.4 Contractor Computer Cybersecurity Compliance Statements
Provide a single submittal containing completed Contractor Computer Cybersecurity Compliance Statements for each company using contractor owned computers. Contractor Computer Cybersecurity Compliance Statements must use the template published at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/forms-graphics-tables . Each Statement must be signed by a cybersecurity representative for the relevant company.
SECTION 01 50 00 Page 3
1.6.2 Temporary IP Networks
Temporary contractor-installed IP networks may be used during construction. When used, temporary contractor-installed IP networks must meet the following requirements:
1.6.2.1 Network Boundaries and Connections
The network must not extend outside the project site and must not connect to any IP network other than IP networks provided under this project or Government furnished IP networks provided for this purpose. Any and all network access from outside the project site is prohibited.
1.6.3 Government Access to Network
Government personnel must be allowed to have complete and immediate access to the network at any time in order to verify compliance with this specification.
1.6.4 Temporary Wireless IP Networks
In addition to the other requirements on temporary IP networks, temporary wireless IP (WiFi) networks must not interfere with existing wireless network and must use WPA2 security. Network names (SSID) for wireless networks must be changed from their default values.
1.6.5 Passwords and Passphrases
The passwords and passphrases for all network devices and network access must be changed from their default values. Passwords must be a minimum 8 characters with a minimum of one uppercase letter, one lowercase letter, one number and one special character.
1.6.6 Contractor Temporary Network Cybersecurity Compliance Statements
Provide a single submittal containing completed Contractor Temporary Network Cybersecurity Compliance Statements for each company implementing a temporary IP network. Contractor Temporary Network Cybersecurity Compliance Statements must use the template published at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/ forms-graphics-tables . Each Statement must be signed by a cybersecurity representative for the relevant company. If no temporary IP networks will be used, provide a single copy of the Statement indicating this.
PART 2 PRODUCTS
2.1 TEMPORARY SIGNAGE
2.1.1 Bulletin Board
Prior to the commencement of work activities, provide a clear weatherproof covered bulletin board not less than 36 by 48 inches in size for displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the Contract, Wage Rate Information poster, Safety and Health Information as required by EM 385-1-1 Section 01 and other information approved by the Contracting Officer. Coordinate requirements herein with 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS. Locate the bulletin board at the project site in a conspicuous place easily
SECTION 01 50 00 Page 4 accessible to all employees, and in location as approved by the Contracting Officer.
2.1.2 Project Identification Signs
The requirements for the signs, their content, and location are as specified in Section 01 58 00 PROJECT IDENTIFICATION. Erect signs within 15 days after receipt of the notice to proceed. Correct the data required by the safety sign daily, with light colored metallic or non-metallic numerals.
2.1.3 Warning Signs
Post temporary signs, tags, and labels to give workers and the public adequate warning and caution of construction hazards according to the EM 385-1-1 Section 04. Attach signs to the perimeter fencing every 150 feet warning the public of the presence of construction hazards. Signs must require unauthorized persons to keep out of the construction site.
Correct the data required by safety signs daily. Post signs at all points of entry designating the construction site as a hard hat area.
2.2 TEMPORARY TRAFFIC CONTROL
2.2.1 Haul Roads
Prescribed haul routes are shown on the drawings. Construct access necessary for proper prosecution of the work under this Contract in accordance with EM 385-1-1 Section 04. Construct with suitable grades and widths; avoid sharp curves, blind corners, and dangerous cross traffic.
Submit haul road plan for approval. Provide necessary signs, barricades, and distinctive markings for the safe movement of traffic. The method of dust control, although optional, must be adequate to ensure safe operation at all times. Location, width, and alignment of construction and haul roads are subject to approval by the Contracting Officer.
2.2.2 Barricades
Erect and maintain temporary barricades to limit public access to hazardous areas. Barricades are required whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic. Securely place barricades clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.
2.3 FENCING
Provide fencing along the construction site and at all open excavations and tunnels to control access by unauthorized personnel. Safety fencing must be highly visible to be seen by pedestrians and vehicular traffic.
All fencing must meet the requirements of EM 385-1-1 . Remove the fence upon completion and acceptance of the work.
2.3.1 Polyethylene Mesh Safety Fencing
Temporary safety fencing must be a high visibility orange colored, high density polyethylene grid, a minimum of 48 inches high and maximum mesh size of 2 inches . Fencing must extend from the grade to a minimum of 48 inches above the grade and be tightly secured to T-posts spaced as
SECTION 01 50 00 Page 5 necessary to maintain a rigid and taut fence. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.
2.3.2 Post-Driven Chain Link Fencing
Temporary post-driven fencing must be galvanized chain link fencing 6 feet high supported by an tightly secured to galvanized steel posts driven below grade. Fence posts must be located on minimum 10 foot centers.
Posts may be set in various surfaces such as sand, soil, asphalt or concrete as necessary. Chain link fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection. Completely remove fencing and posts at the completion of construction and restore surfaces disturbed or damaged to its original condition. Locate and identify underground utilities prior to setting fence posts. Equip fence with a lockable gate. Gate must remain locked when construction personnel are not present.
2.4 TEMPORARY WIRING
Temporary wiring shall be in accordance with Appendix A, MOTSU Electrical Standard and Utility Standard.
2.5 BACKFLOW PREVENTERS
Backflow Preventers shall be in accordance with Appendix A, MOTSU Utility Standard.
PART 3 EXECUTION
3.1 EMPLOYEE PARKING
Construction Contract employees must park privately owned vehicles in an area designated by the Contracting Officer. Employee parking must not interfere with existing and established parking requirements of the Government installation.
3.2 AVAILABILITY AND USE OF UTILITY SERVICES
3.2.1 Temporary Utilities
Provide temporary utilities required for construction. Materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.
3.2.2 Payment for Utility Services
a. Payment for temporary electrical power shall be in accordance with Appendix A, MOTSU Utility Standard. Potable water will be made available to the contractor at no charge. Contractor shall connect to fire hydrants adjacent to identified staging areas shown on the drawings. A map of the installation's fire hydrants is included as an attachment to this section. Carefully conserve utilities furnished without charge.
b. The point at which the Government will deliver such utilities or services and the quantity available must be coordinated with the Contracting Officer. Pay all costs incurred in connecting, converting, and transferring the utilities to the work. Make
SECTION 01 50 00 Page 6 connections, including providing backflow-preventing devices on connections to domestic water lines; and providing transformers; and make disconnections. Taps to base fire hydrants are allowed for obtaining domestic water.
3.2.3 Temporary Connections
Provide and maintain necessary temporary connections and distribution lines.
3.2.4 Sanitation
Provide and maintain within the construction area minimum field-type sanitary facilities in accordance with EM 385-1-1 Section 02. Locate the facilities behind the construction fence or out of the public view. Clean units and empty wastes at least once a week or more frequently into a municipal, district, or station sanitary sewage system, or remove waste to a commercial facility. Obtain approval from the system owner prior to discharge into a municipal, district, or commercial sanitary sewer system. Penalties or fines associated with improper discharge will be the responsibility of the Contractor. Coordinate with the Contracting Officer and follow station regulations and procedures when discharging into the station sanitary sewer system. Maintain these conveniences at all times.
Include provisions for pest control and elimination of odors. Government toilet facilities will not be available to Contractor's personnel.
3.2.5 Telephone
Make arrangements and pay all costs for telephone facilities desired.
3.2.6 Fire Protection
Provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials daily to minimize potential hazards.
3.3 STATION OPERATION AFFECT ON CONTRACTOR OPERATIONS
The MOTSU installation provides mission critical services on a 24/7, 365 day calendar. Under no circumstances shall the Contractor prevent the installation from performing the mission critical operations or cause any delays due to the Contractor's activities.
3.3.1 Restricted Access Areas
The Government will monitor work in all areas of construction. Notify Contracting Officer at least 14 calendar days prior to starting work and when mobilizing from one construction site to another.
3.4 TRAFFIC PROVISIONS
3.4.1 Maintenance of Traffic
a. Conduct operations in a manner that will not close a thoroughfare or interfere with traffic on railways or highways except with written permission of the Contracting Officer at least 15 calendar days prior to the proposed modification date, and provide a Traffic Control Plan for Government approval detailing the proposed controls to traffic
SECTION 01 50 00 Page 7 movement for approval. The plan must be in accordance with State and local regulations and the MUTCD, Part VI. Contractor may move oversized and slow-moving vehicles to the worksite provided requirements of the highway authority have been met.
b. Conduct work so as to minimize obstruction of traffic, and maintain traffic on at least half of the roadway width at all times. Obtain approval from the Contracting Officer prior to starting any activity that will obstruct traffic. Access and haul traffic patterns in the North Railroad Holding Yard and in the South Railroad Holding Yard shall be in a designated clockwise one-way direction.
c. Provide, erect, and maintain, at Contractor's expense, lights, barriers, signals, passageways, detours, and other items, that may be required by the Life Safety Signage, overhead protection authority having jurisdiction.
d. Provide cones, signs, barricades, lights, or other traffic control devices and personnel required to control traffic. Do not use foil-backed material for temporary pavement marking because of its potential to conduct electricity during accidents involving downed power lines.
3.4.2 Protection of Traffic
Maintain and protect traffic on all affected roads and railroads during the construction period except as otherwise specifically directed by the Contracting Officer. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment the work, and the erection and maintenance of adequate warning, danger, and direction signs, will be as required by the State and local authorities having jurisdiction. Provide self-illuminated (lighted) barricades during hours of darkness. Brightly-colored (orange) vests are required for all personnel working in roadways. Protect the traveling public from damage to person and property. Minimize the interference with public traffic on roads selected for hauling material to and from the site. Investigate the adequacy of existing roads and their allowable load limit. Contractor is responsible for the temporary repair of damage to roads caused by construction operations.
3.4.3 Travel Restrictions
Do not interfere or impede MOTSU operational rail, container transport and transfer vehicles without notification to and approval by the Contracting Officer.
3.4.4 Dust Control
Dust control methods and procedures must be approved by the Contracting Officer. Coordinate dust control methods with 01 57 19 TEMPORARY
ENVIRONMENTAL CONTROLS.
3.5 REDUCED PRESSURE BACKFLOW PREVENTERS
Provide an approved reduced pressure backflow prevention assembly at each location where the Contractor taps into the Government potable water supply.
SECTION 01 50 00 Page 8
Perform backflow preventer tests in accordance with Appendix A, MOTSU Utility Standard.
3.6 CONTRACTOR'S TEMPORARY FACILITIES
Contractor is responsible for security of their property. Provide adequate outside security lighting at the temporary facilities. Trailers must be anchored to resist high winds and meet applicable state or local standards for anchoring mobile trailers. Coordinate anchoring with EM 385-1-1 Section 04. The Contract Clause entitled "FAR 52.236-10, Operations and Storage Areas" and the following apply:
3.6.1 Administrative Field Offices
Provide and maintain administrative field office facilities as shown on the drawings as "Contractor Construction Office". Government office and warehouse facilities will not be available to the Contractor's personnel.
Equip the building with approved electrical wiring, at least one double convenience outlet and the required switches and fuses to provide 110-120 volt power. Provide a work table with stool, desk with chair, two additional chairs, and one legal size file cabinet that can be locked.
The building must be waterproof, supplied with a heater, have a minimum of two doors, electric lights, a telephone, a battery-operated smoke detector alarm, a sufficient number of adjustable windows for adequate light and ventilation, and a supply of approved drinking water. Provide approved sanitary facilities. Screen the windows and doors and provide the doors with deadbolt type locking devices or a padlock and heavy-duty hasp bolted to the door. Door hinge pins must be non-removable. Arrange the windows to open and to be securely fastened from the inside. Protect glass panels in windows by bars or heavy mesh screens to prevent easy access. In warm weather, provide air conditioning capable of maintaining the office at 50 percent relative humidity and a room temperature 20 degrees F below the outside temperature when the outside temperature is 95 degrees F . Unless otherwise directed by the Contracting Officer, remove the building from the site upon completion and acceptance of the work.
3.6.2 Quality Control Manager Records and Field Office
Provide on the jobsite an office with approximately 100 square feet of useful floor area for the exclusive use of the QC Manager. Provide a weathertight structure with adequate heating and cooling, toilet facilities, lighting, ventilation, a 4 by 8 foot plan table, a standard size office desk and chair, computer station, and working communications facilities. Provide either a 1,500 watt radiant heater and a window-mounted air conditioner rated at 9,000 Btus minimum or a window-mounted heat pump of the same minimum heating and cooling ratings.
Provide a door with a cylinder lock and windows with locking hardware.
Make utility connections. Locate as directed. File quality control records in the office and make available at all times to the Government.
After completion of the work, remove the entire structure from the site.
3.6.3 Storage Area
Construct a temporary 6 foot high chain link fence around trailers and materials. Fence posts may be driven, in lieu of concrete bases, where soil conditions permit. Do not place or store trailers, materials, or equipment outside the fenced area unless such trailers, materials, or
SECTION 01 50 00 Page 9 equipment are assigned a separate and distinct storage area by the Contracting Officer away from the vicinity of the construction site but within the installation boundaries. Trailers, equipment, or materials must not be open to public view with the exception of those items which are in support of ongoing work on the current day. Do not stockpile materials outside the fence in preparation for the next day's work.
Construction equipment such as wheeled and tracked earth moving equipment, trucks and like equipment may remain at the construction site overnight provided conformance to MOSTU Environmental Supplemental Specifications.
Designated "Area A" as shown on the drawings shall serve as storage for bulk fuel and water, vehicle parking for bulk fuel, bulk water, POL maintenance vehicles, and vehicle washing station.
Keep fencing in a state of good repair and proper alignment. Grassed or unpaved areas, which are not established roadways, and will be traversed with construction equipment or other vehicles, must be covered with a layer of gravel or mulch as necessary to prevent rutting and the tracking of mud onto paved or established roadways, should the Contractor elect to traverse them with construction equipment or other vehicles. Mow and maintain grass located within the boundaries of the construction site for the duration of the project. Grass and vegetation along fences, buildings, under trailers, and in areas not accessible to mowers must be edged or trimmed neatly. Contractor shall install and maintain specified erosion and sediment control measures throughout the use of Staging and Storage Areas.
3.6.4 Supplemental Storage Area
As shown on the drawings, three staging areas are available to the Contractor. This area may not be in close proximity of the construction site but will be within the installation boundaries. Maintain the area in a clean and orderly fashion and secured if needed to protect supplies and equipment. Utilities will not be provided to this area by the Government.
3.6.5 Appearance of Trailers
a. Trailers must be roadworthy and comply with all appropriate state and local vehicle requirements. Trailers which are rusted, have peeling paint or are otherwise in need of repair will not be allowed on Installation property. Trailers must present a clean and neat exterior appearance and be in a state of good repair.
b. Maintain the temporary facilities. Failure to do so will be sufficient reason to require their removal at the Contractor's expense.
3.6.6 Trailers or Storage Buildings
a. Trailers or storage buildings will be permitted, where space is available, subject to the approval of the Contracting Officer.
3.6.7 Safety Systems
Protect the integrity of all installed safety systems or personnel safety devices. Obtain prior approval from the Contracting Officer if entrance into systems serving safety devices is required. If it is temporarily necessary to remove or disable personnel safety devices in order to accomplish Contract requirements, provide alternative means of protection prior to removing or disabling any permanently installed safety devices or equipment and obtain approval from the Contracting Officer.
SECTION 01 50 00 Page 10
3.6.8 Weather Protection of Temporary Facilities and Stored Materials
Take necessary precautions to ensure that roof openings and other critical openings in the building are monitored carefully. Take immediate actions required to seal off such openings when rain or other detrimental weather is imminent, and at the end of each workday. Ensure that the openings are completely sealed off to protect materials and equipment in the building from damage.
3.6.8.1 Building and Site Storm Protection
When a warning of gale force winds is issued, take precautions to minimize danger to persons, and protect the work and nearby Government property.
Precautions must include, but are not limited to, closing openings;
removing loose materials, tools and equipment from exposed locations; and removing or securing scaffolding and other temporary work. Close openings in the work when storms of lesser intensity pose a threat to the work or any nearby Government property.
3.7 GOVERNMENT FIELD OFFICE
3.7.1 Resident Engineer's Office
Provide the Government Engineer with an office, approximately 200 square feet in floor area, located where directed and providing space heat, air conditioning unit, electric light and power, and toilet facilities consisting of one lavatory and one water closet complete with connections to water and sewer mains. Provide a mail slot in the door or a lockable mail box mounted on the surface of the door. Include a 4 by 8 foot plan table, computer work space a standard size office desk and chair, and telephone. At completion of the project, the office will remain the property of the Contractor and be removed from the site. Utilities must be connected and disconnected in accordance with local codes and to the satisfaction of the Contracting Officer. Compliance with safety and appearance requirements for temporary facilities stated in previous paragraphs is required.
3.7.2 Trailer-Type Mobile Office
The option is available to, furnish and maintain a trailer-type mobile office acceptable to the Contracting Officer to meet the requirements of the minimum facilities specified above. Securely anchor the trailer to the ground at all four corners to guard against movement during high winds. Coordinate requirements for proper anchoring with EM 385-1-1 Section 04.
3.7 TEMPORARY PROJECT SAFETY FENCING
As soon as practicable, but not later than 15 days after the date established for commencement of work, furnish and erect temporary project safety fencing at the work site. Maintain the safety fencing during the life of the Contract and, upon completion and acceptance of the work, remove from the work site.
3.8 DUMPSTERS
Equip dumpsters with a secure cover and paint the standard installation color. Keep dumpster closed, except when being loaded with trash and
SECTION 01 50 00 Page 11 debris. Empty site dumpsters at least once a week, or as needed to keep the site free of debris and trash. If necessary, provide 55 gallon trash containers painted the darker installation color to collect debris in the construction site area. For large demolitions, large dumpsters without lids are acceptable, but must not have debris higher than the sides before emptying.
3.9 CLEANUP
Remove construction debris, waste materials, packaging material and the like from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways must be cleaned away.
3.10 RESTORATION OF STORAGE AREA
Upon completion of the project remove the bulletin board, signs, barricades, haul roads, and all other temporary products from the site.
After removal of trailers, materials, and equipment from within the fenced area, remove the fence. Restore areas used during the performance of the Contract to the original or better condition. Remove gravel used to traverse grassed areas and restore the area to its original condition, including top soil and seeding as necessary.
-- End of Section --
SECTION 01 50 00 Page 12
SECTION 31 00 00
EARTHWORK
08/ 08, CHG 2: 02/ 21
PART 1 GENERAL
1.1 CRITERIA FOR BIDDING
Base bids on the following criteria:
a. Surface elevations are as indicated.
b. Pipes or other artificial obstructions, except those indicated, will not be encountered.
c. Ground water elevations indicated by the boring log were those existing at the time subsurface investigations were made and do not necessarily represent ground water elevation at the time of construction.
d. Material character is indicated by the boring logs should not be misconstrued to represent all existing berm material.
e. Hard materials and rock will not be encountered in 100 percent of the excavations at 4 feet below existing surface elevations.
f. Undercut rutting or pumping of material as directed by the Contracting Officer replace with fill and backfill material. Prepare bids based on replacing approximately 0.5 acres, with an average depth of 12 inch at various locations. For bidding purposes, this volume shall be evenly divided by the total number of berms included in this Phase.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C600 (2017) Installation of Ductile-Iron Mains and Their Appurtenances
ASTM INTERNATIONAL (ASTM)
ASTM C136/C136M (2019) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates
ASTM D698 (2012; E 2014; E 2015) Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft-lbf/cu. ft.
(600 kN-m/cu. m.))
ASTM D1140 (2017) Standard Test Methods for Determining the Amount of Material Finer than 75-µm (No. 200) Sieve in Soils by
SECTION 31 00 00 Page 1
Washing
ASTM D1556/D1556M (2015; E 2016) Standard Test Method for Density and Unit Weight of Soil in Place by Sand-Cone Method
ASTM D2487 (2017; E 2020) Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)
ASTM D4318 (2017; E 2018) Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils
ASTM D6938 (2017a) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA 600/4-79/020 (1983) Methods for Chemical Analysis of Water and Wastes
EPA SW-846.3-3 (1999, Third Edition, Update III-A) Test Methods for Evaluating Solid Waste:
Physical/Chemical Methods
1.3 DEFINITIONS
1.3.1 Satisfactory Materials
Satisfactory materials comprise any materials classified by ASTM D2487 as SM, SC, SC-SM CL, ML, and CL-ML,. Satisfactory materials for grading and fill material comprise of stones less than 3 inches in any dimension.
1.3.2 Unsatisfactory Materials
Materials which do not comply with the requirements for satisfactory materials are unsatisfactory. Unsatisfactory materials also include man-made fills; trash; refuse; any soil material which contains more than 5% by weight organic matter, has an unstable bearing capacity, contains deleterious debris (wood, plastic, coal, etc.), or soils with a Liquid Limit (LL) greater than 40 percent and a Plasticity Index (PI) greater than 12 percent. These soils are generally classified as CLAY (CH and OH), SILT (MH and OH) and PEAT (PT). Notify the Contracting Officer when encountering any contaminated materials.
1.3.3 Cohesionless and Cohesive Materials
Cohesionless materials include materials classified in ASTM D2487 as GW, GP, SW, and SP. Cohesive materials include materials classified as GC, SC, ML, CL, MH, and CH. Materials classified as GM and SM will be
SECTION 31 00 00 Page 2 identified as cohesionless only when the fines are nonplastic. Perform testing, required for classifying materials, in accordance with ASTM D4318, ASTM C136/C136M and ASTM D1140.
1.3.4 Degree of Compaction
Degree of compaction required is expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D698 abbreviated as a percent of laboratory maximum density.
1.3.5 Topsoil
Material suitable for topsoils obtained from offsite areas and excavations is defined as: Natural, friable soil representative of productive, well-drained soils in the area, free of subsoil, stumps, rocks larger than one inch diameter, brush, weeds, toxic substances, and other material detrimental to plant growth. Amend topsoil pH range to obtain a pH of 5.5 to 7.
1.3.6 Hard/Unyielding Materials
Hard/Unyielding materials comprise dense consolidated deposits or conglomerate materials which are not included in the definition of "rock" with stones greater than 3 inch in any dimension or as defined by the pipe manufacturer, whichever is smaller. These materials usually require the use of heavy excavation equipment, ripper teeth, or jack hammers for removal.
1.3.7 Rock
Solid homogeneous interlocking crystalline material with firmly cemented, laminated, or foliated masses or conglomerate deposits, neither of which can be removed without systematic drilling and blasting, drilling and the use of expansion jacks or feather wedges, or the use of backhoe-mounted pneumatic hole punchers or rock breakers; also large boulders, buried masonry, or concrete other than pavement exceeding 1/2 cubic yard in volume. Removal of hard material will not be considered rock excavation because of intermittent drilling and blasting that is performed merely to increase production.
1.3.8 Unstable Material
Unstable materials are too wet to properly support construction traffic, the utility pipe, conduit, or appurtenant structure.
1.3.9 Select Granular Material
1.3.9.1 General Requirements
Select granular material consist of materials classified as GW, GP, SW, or SP by ASTM D2487 where indicated. The liquid limit of such material must not exceed 35 percent when tested in accordance with ASTM D4318. The plasticity index must not be greater than 12 percent when tested in accordance with ASTM D4318, and not more than 35 percent by weight may be finer than No. 200 sieve when tested in accordance with ASTM D1140.
1.3.10 Initial Backfill Material
Initial backfill consists of select granular material or satisfactory
SECTION 31 00 00 Page 3 materials free from rocks 3 inches or larger in any dimension or free from rocks of such size as recommended by the pipe manufacturer, whichever is smaller.
1.3.11 Expansive Soils
Expansive soils are defined as soils that have a plasticity index equal to or greater than 35 percent when tested in accordance with ASTM D4318.
1.4 SYSTEM DESCRIPTION
Subsurface soil boring logs are appended to this specifications. These data represent the best subsurface information available; however, variations may exist in the subsurface between boring locations.
1.4.1 Classification of Excavation
No consideration will be given to the nature of the materials, and all excavation will be designated as unclassified excavation.
1.4.2 Blasting
Blasting will not be permitted.
1.4.3 Dewatering Work Plan
Submit procedures for accomplishing dewatering work.
1.5 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Dewatering Work Plan ; G
Borrow Plan ; G
SD-03 Product Data
Utilization of Excavated Materials ; G
Opening of any Excavation or Borrow Pit
SD-06 Test Reports
Testing
Borrow Site Testing
Within 24 hours of conclusion of physical tests, submit 5 copies of test results, including calibration curves and results of calibration tests.
SECTION 31 00 00 Page 4
SD-07 Certificates
Testing
PART 2 PRODUCTS
2.1 BORROW PLAN
Prepare Borrow Plan for materials proposed for earthwork use. Borrow Plan shall include borrow source, applicable borrow site permits, Borrow Site Testing Report and applicable Lab Testing submittals.
2.2 REQUIREMENTS FOR OFFSITE SOILS
Test offsite soils brought in for use as backfill for Total Petroleum Hydrocarbons (TPH), Benzene, Toluene, Ethyl Benzene, and Xylene (BTEX) and full Toxicity Characteristic Leaching Procedure (TCLP) including ignitability, corrosivity and reactivity. Backfill shall contain a maximum of 100 parts per million (ppm) of total petroleum hydrocarbons (TPH) and a maximum of 10 ppm of the sum of Benzene, Toluene, Ethyl Benzene, and Xylene (BTEX) and shall pass the TCPL test. Determine TPH concentrations by using EPA 600/4-79/020 Method 418.1. Determine BTEX concentrations by using EPA SW-846.3-3 Method 5030/8020. Perform TCLP in accordance with EPA SW-846.3-3 Method 1311. Provide Borrow Site Testing for TPH, BTEX and TCLP from a composite sample of material from the borrow site, with at least one test from each borrow site. Do not bring material onsite until tests have been approved by the Contracting Officer.
2.3 BURIED WARNING AND IDENTIFICATION TAPE
Provide polyethylene plastic and metallic core or metallic-faced, acid-and alkali-resistant, polyethylene plastic warning tape manufactured specifically for warning and identification of buried utility lines.
Provide tape on rolls, 3 inches minimum width, color coded as specified below for the intended utility with warning and identification imprinted in bold black letters continuously over the entire tape length. Warning and identification to read, "CAUTION, BURIED (intended service) LINE BELOW" or similar wording. Provide permanent color and printing, unaffected by moisture or soil.
Warning Tape Color Codes
Red Electric
Orange Telephone and Other Communications
Blue Water Systems
2.3.1 Warning Tape for Metallic Piping
Provide acid and alkali-resistant polyethylene plastic tape conforming to the width, color, and printing requirements specified above, with a minimum thickness of 0.003 inch and a minimum strength of 1500 psi lengthwise, and 1250 psi crosswise, with a maximum 350 percent elongation.
SECTION 31 00 00 Page 5
2.3.2 Detectable Warning Tape for Non-Metallic Piping
Provide polyethylene plastic tape conforming to the width, color, and printing requirements specified above, with a minimum thickness of 0.004 inch , and a minimum strength of 1500 psi lengthwise and 1250 psi crosswise. Manufacture tape with integral wires, foil backing, or other means of enabling detection by a metal detector when tape is buried up to 3 feet deep. Encase metallic element of the tape in a protective jacket or provide with other means of corrosion protection.
2.4 DETECTION WIRE FOR NON-METALLIC PIPING
Insulate a single strand, solid copper detection wire with a minimum of 12
AWG.
2.5 MATERIAL FOR RIP-RAP
Provide Bedding material or Filter fabric and rock conforming to NC Erosion and Sediment Control Planning and Design Manual, Standard 6.31 for construction indicated.
2.5.1 Bedding Material
Provide bedding material consisting of sand, gravel, or crushed rock, well graded, or poorly graded with a maximum particle size of 2 inches .
Compose material of tough, durable particles. Allow fines passing the No.
200 standard sieve with a plasticity index less than six.
2.5.2 Rock
Provide rock fragments sufficiently durable to ensure permanence in the structure and the environment in which it is to be used. Use rock fragments free from cracks, seams, and other defects that would increase the risk of deterioration from natural causes. Provide fragments sized as indicated in the drawings.
PART 3 EXECUTION
3.1 STRIPPING OF TOPSOIL
Strip topsoil to the full depth of the strata prior reconstructing and improving blast berms. Spread topsoil on areas already graded and prepared for topsoil, or transported and deposited in stockpiles convenient to areas that are to receive application of the topsoil later, or at locations indicated or specified. Keep topsoil separate from other excavated materials, brush, litter, objectionable weeds, roots, stones larger than 2 inches in diameter, and other materials that would interfere with planting and maintenance operations. Stockpile in locations indicated.
3.2 GENERAL EXCAVATION
Perform excavation of every type of material encountered within the limits of the project to the lines, grades, and elevations indicated and as specified. Perform the grading in accordance with the typical sections shown and the tolerances specified in paragraph FINISHING. Transport satisfactory excavated materials and place in fill or embankment within the limits of the work. Excavate unsatisfactory materials encountered within the limits of the work below grade and replace with satisfactory
SECTION 31 00 00 Page 6 materials as directed. Include such excavated material and the satisfactory material ordered as replacement in excavation. Dispose surplus satisfactory excavated material not required for fill and unsatisfactory excavated material as specified in paragraph DISPOSITION OF SURPLUS MATERIAL. During construction, perform excavation and fill in a manner and sequence that will provide proper drainage at all times.
Excavate material required for fill or embankment in excess of that produced by excavation within the grading limits from other approved areas selected by the Contractor as specified.
3.2.1 Ditches, Gutters, and Channel Changes
Finish excavation of ditches, gutters, and channel changes by cutting accurately to the cross sections, grades, and elevations shown on the Drawing. Do not excavate ditches and gutters below grades shown.
Backfill the excessive open ditch or gutter excavation with satisfactory, thoroughly compacted, material or with suitable stone or cobble to grades shown. Dispose excavated material as shown or as directed, except in no case allow material be deposited a maximum 4 feet from edge of a ditch.
Maintain excavations free from detrimental quantities of leaves, brush, sticks, trash, and other debris until final acceptance of the work.
3.2.2 Drainage
Provide for the collection and disposal of surface and subsurface water encountered during construction. Completely drain construction site during periods of construction to keep soil materials sufficiently dry.
Throughout construction grade the construction area to provide positive surface water runoff away from the construction activity and provide temporary ditches, swales, and other drainage features and equipment as required to maintain dry soils. When unsuitable working platforms for equipment operation and unsuitable soil support for subsequent construction features develop, remove unsuitable material and provide new soil material as specified herein. It is the responsibility of the Contractor to assess the soil and ground water conditions presented by the plans and specifications and to employ necessary measures to permit construction to proceed.
3.2.3 Dewatering
Control groundwater flowing toward or into excavations to prevent sloughing of excavation slopes and walls, boils, uplift and heave in the excavation and to eliminate interference with orderly progress of construction. Do not permit French drains, sumps, ditches or trenches within 3 feet of the foundation of any structure, except with specific written approval, and after specific contractual provisions for restoration of the foundation area have been made. Take control measures by the time the excavation reaches the water level in order to maintain the integrity of the in situ material. While the excavation is open, maintain the water level continuously, at least 2 feet below the working level. Operate dewatering system continuously until construction work below existing water levels is complete. Submit performance records weekly. Measure and record performance of dewatering system at same time each day by use of observation wells or piezometers installed in conjunction with the dewatering system. Relieve hydrostatic head in previous zones below subgrade elevation in layered soils to prevent uplift.
SECTION 31 00 00 Page 7
3.2.4 Trench Excavation Requirements
Excavate the trench as recommended by the manufacturer of the pipe to be installed. Slope trench walls below the top of the pipe, or make vertical, and of such width as recommended in the manufacturer's printed installation manual. Provide vertical trench walls where no manufacturer's printed installation manual is available. Shore trench walls, cut back to a stable slope, or provide with equivalent means of protection for employees who may be exposed to moving ground or cave in, as determined by the Contractor’s Safety Engineer or other competent person; refer to USACE publication EM 385-1-1 . Excavate trench walls which are cut back to at least the angle of repose of the soil. Give special attention to slopes which may be adversely affected by weather or moisture content. Do not exceed the trench width below the pipe top of 24 inches plus pipe outside diameter (O.D.) for pipes of less than 24 inches inside diameter, and do not exceed 36 inches plus pipe outside diameter for sizes larger than 24 inches inside diameter. Where recommended trench widths are exceeded, provide redesign, stronger pipe, or special installation procedures by the Contractor. The Contractor is responsible for the cost of redesign, stronger pipe, or special installation procedures without any additional cost to the Government.
3.2.4.1 Bottom Preparation
Grade the bottoms of trenches accurately to provide uniform bearing and support for the bottom quadrant of each section of the pipe. Excavate bell holes to the necessary size at each joint or coupling to eliminate point bearing. Remove stones of 3 inch or greater in any dimension, or as recommended by the pipe manufacturer, whichever is smaller, to avoid point bearing.
3.2.4.2 Removal of Unyielding Material
Where overdepth is not indicated and unyielding material is encountered in the bottom of the trench, remove such material 12 inch below the required grade and replaced with suitable materials as provided in paragraph
BACKFILLING AND COMPACTION.
3.2.4.3 Removal of Unstable Material
Where unstable material is encountered in the bottom of the trench, remove such material to the depth directed and replace it to the proper grade with select granular material as provided in paragraph BACKFILLING AND…