SPECS_-_PHASE_2_--_MOTSU_POTABLE_WATER2018-Revised14Aug2019.pdf
PDF 7 MB Posted
- Attached to
- MOTSU Potable Water Improvements Federal contract opportunity
- Solicitation number
- W912PM19B0018
About this file
W912PM19B0018 Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912PM19B0018_Amendment_02.pdf | ||
| W912PM19B0018_Amendment_02_CC.pdf | ||
| Technical_Summary_of_ChangesAmdt0002.pdf | ||
| S-II-201_Rev1.pdf | ||
| Addendum_1.pdf | ||
| W912PM19B0018_P00001-_MOTSU_Potable_Water.pdf | ||
| W912PM19B0018_P00001-_MOTSU_Potable_Water_CC.pdf | ||
| MOTSU_WaterImprovPhII_PLANS_Revised14Aug2019.pdf | ||
| W912PM19B0018_MOSTU_Potable_Water_Repair.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Potable Water Improvements, Phase II Military Ocean Terminal Sunny Point (MOTSU)
Brunswick County, North Carolina
This project was designed by the Wilmington District of the U.S. Army Corps of Engineers. The initials or signatures and registration designations of individuals appear on these project documents within the scope of their employment as required by ER 1110-1-8152.
FOUO
Specifications
August 2019
IFB No. W912PM19B0018
Phase - II - GST MOTSU
PROJECT TABLE OF
CONTENTS DIVISION 01 - GENERAL REQUIREMENTS
00 01 15 LIST OF DRAWINGS
01 10 00.10 38 SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS DREDGING /
CONSTRUCTION
01 14 00 WORK RESTRICTIONS
01 32 01.00 37 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29.00 37 SUSTAINABILITY
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.00 37 INDOOR AIR QUALITY (IAQ) MANAGEMENT
01 62 35.37 RECYCLED/RECOVERED/BIOBASED MATERIALS
01 74 19.00 37 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 91 00.00 37 COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION AND DECONSTRUCTION
02 82 10 ASBESTOS CEMENT PIPE REMOVAL AND DISPOSAL
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 05 23 16 STRUCTURAL WELDING
05 12 23 16 STRUCTURAL STEEL
05 50 13 MISCELLANEOUS METAL FABRICATIONS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 33 23 OVERHEAD COILING DOORS
08 71 00 DOOR HARDWARE
DIVISION 09 - FINISHES
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 44 16 FIRE EXTINGUISHERS
DIVISION 13 - SPECIAL CONSTRUCTION
13 34 19 METAL BUILDING SYSTEMS
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 25 - INTEGRATED AUTOMATION
25 08 10 UTILITY MONITORING AND CONTROL SYSTEM TESTING
25 90 00 SCADA SYSTEM
DIVISION 26 - ELECTRICAL
26 05 19.10 10 INSULATED WIRE AND CABLE
26 08 00 APPARATUS INSPECTION AND TESTING
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 13 SWITCHBOARDS
26 28 00.00 10 MOTOR CONTROL CENTERS, SWITCHBOARDS AND PANELBOARDS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 36 00.00 10 AUTOMATIC TRANSFER SWITCH AND BY-PASS/ISOLATION SWITCH
26 41 00 LIGHTNING PROTECTION SYSTEM
26 42 14.00 10 CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 20 SUBBASES FOR FLEXIBLE PAVING
32 11 23 AGGREGATE BASE COURSES
32 11 27 BITUMINOUS-STABILIZED BASE COURSE, SUBBASE, OR SUBGRADE
32 12 13 BITUMINOUS TACK AND PRIME COATS
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 15 00 AGGREGATE SURFACING
32 92 19 SEEDING
DIVISION 33 - UTILITIES
33 05 23.13 UTILITY HORIZONTAL DIRECTIONAL DRILLING
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 16 13.16 WIRE-WOUND CIRCULAR PRESTRESSED-CONCRETE WATER TANK
33 40 00 STORM DRAINAGE UTILITIES
33 61 13.19 VALVES, PIPING, AND EQUIPMENT IN VALVE MANHOLES
33 90 00 PACKAGED WATER PUMPING STATIONS
DIVISION 40 - PROCESS INTERCONNECTIONS
40 05 13 PIPELINES, LIQUID PROCESS PIPING
40 95 00 PROCESS CONTROL
-- End of Project Table of Contents --
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/11
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings and specifications for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
DRAWING LIST-PHASE II
DRAWING TITLE DRAWING NO.
TITLE SHEET G-II-001
GENERAL NOTES G-II-101
LEGEND G-II-102
ABBREVIATIONS G-II-103
BID ITEM KEY PLAN G-II-104
BORING LOCATION PLAN & PROFILES G-II-105
EXISTING CONDITIONS SURVEY V-2
EXISTING CONDITIONS C-II-101
DEMOLITION PLAN C-II-102
DEMOLITION PLAN -ALTERNATE BERM REMOVAL C-II-103
SITE PLAN C-II-104
GRADING PLAN C-II-105
ROADWAY PLAN C-II-106
SEDIMENTATION AND EROSION CONTROL C-II-107
SEDIMENTATION AND EROSION CONTROL - ALTERNATE C-II-107a
STORMWATER MANAGEMENT PLAN C-II-108
UTILITY PLAN - STORMWATER C-II-109
DETAIL - SED. AND EROSION C-II-110
DETAILS - CIVIL 1 C-II-111
DETAILS - CIVIL 2 C-II-112
DETAILS - CIVIL 3 C-II-113
DETAILS - CIVIL 4 C-II-114
DETAILS - CIVIL 5 C-II-115
GENERAL NOTES S-II-001
MAT FOUNDATION PLAN S-II-101
PEMP FOUNDATION PLAN S-II-102
TANK FOUNDATION DETRAILS S-II-201
PEMP DETAILS S-II-202
WATER SYSTEM SCHEMATIC X-II-101
PRE-STRESSED CONCRETE TANK PLAN X-II-102
PUMP HOUSE PLAN X-II-103
PUMP HOUSE TRENCH PLAN X-II-104
HYDROPNEUMATICS TANK PLAN X-II-
105 UTILITY PLAN - WATER X-II-106
DETAILS - WATER 1 X-II-107
DETAILS - WATER 2 X-II-108
ELECTRICAL LEGEND E-II-101
ELECTRICAL PLAN E-II-102 ELECTRICAL
PLAN PUMP HOUSE E-II-103
EXTERIOR LIGHTING PLAN E-II-106
INTERIOR LIGHTING PLAN PUMP HOUSE E-II-107
LIGHTING PROTECTION PLAN E-II-108
DETAILS - ELECTRICAL 1 E-II-109
DETAILS - ELECTRICAL 2 E-II-110
INSTRUMENTATION T-II-101
OVERALL BASE SITE PLAN T-II-102
SCADA PLAN T-II-103
SCADA PLAN T-II-104
SCADA PLAN T-II-105
SCADA PLAN T-II-106
SCADA PLAN T-II-107
SCADA PLAN T-II-108
SCADA PLAN T-II-109
SCADA PLAN T-II-110
SCADA PLAN T-II-111
SCADA PLAN T-II-112
SCADA PLAN T-II-113
SCADA PLAN T-II-114
SCADA PLAN T-II-115
SCADA PLAN T-II-116
SCADA PLAN T-II-117
SCADA PLAN T-II-118
HVAC PLAN M-II-101
1.3 SUPPLEMENTARY DRAWINGS
These supplementary drawings may not be a part of the contract but are included with the drawings for information.
1.3.1 Reference Drawings
The following reference drawings are intended only to show the original construction. Drawings are the property of the Government and shall not be used for any purpose other than that intended by the contract. The drawings are half size.
Full-size drawings are available at the bidder's or Contractor's expense.
Information on procuring these full-size drawings may be obtained from the Contracting Officer. Full size drawings may be inspected during regular working hours at the office of the Contracting Officer.
NAVFAC DWG NO. TITLE
71-08-09
UTILITIES – WATER & SEWER RESERVOIR – 500,000
GALLONS SECTIONS & DETAILS - SHEET 67
SU 106-01-92
WATERLINE EXTENTION
WATER DISTRIBUTION MAP - W-11
SU 106-01-92
WATERLINE EXTENTION
WATER DISTRIBUTION MAP - W-2
SU 106-01-51
DEMOLITION/NEW ELECTRICAL - E-3
RENOVATION - W-23
71-08-09
UTILITIES – WATER & SEWER RESERVOIR – 500,000
GALLONS SECTIONS & DETAILS - SHEET 68
ELECTRICAL PLAN - E-4
DEMOLITION - W-20
FILTER BUILDING AND BACKWASH SETTLING BASIN
SITE PLAN AND DETAILS - W-19
1.3.2 Boring Logs
Boring logs are available in the Geotechnical Investigation Report prepared by A1 Consulting Group, INC dated March 2019. The Government does not guarantee that borings indicate actual conditions, except for the exact locations and the time that they were made. The data are available for examination by prospective bidders in the office of the Contracting Officer.
1.3.3 Subsurface Data
Subsurface data is available in the Geotechnical Investigation Report prepared by A1 Consulting Group, INC dated March 2019. Subsurface data, not specified or indicated, have been obtained by the Government at the station. The data are available for examination by prospective bidders in the office of the Contracting Officer.
-- End of Document --
POTABLE WATER,
Phase 2
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 10 00.10 38
SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS
08/19
PART 1 GENERAL
1.1 REFERENCES
1.2 DEPARTMENT OF ARMY MANDATED SECURITY REQUIREMENTS
1.3 IDENTIFICATION OF EMPLOYEES - MOTSU
1.4 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.5 PERFORMANCE AND PAYMENT BONDS
1.6 WATER CONSERVATION
1.7 BULLETIN BOARD
1.8 WORK PLAN
1.9 PROGRESS SCHEDULE
1.10 SHOP DRAWINGS AND MATERIALS SUBMITTAL
1.11 SAMPLING, CERTIFICATES, AND TESTING
1.12 CERTIFICATES OF COMPLIANCE
1.13 REQUIRED CONSTRUCTION MEETINGS
1.14 "AS-BUILT" RECORD DRAWINGS
1.15 FINISH MATERIAL SUBMITTALS
1.16 ASBESTOS PERMIT AND NOTIFICATION
1.17 WORK IN QUARANTINED AREA
1.18 ACCEPTANCE
1.19 NCDOT SPECIFICATIONS
1.20 DEFINITIONS FOR NCDOT SPECIFICATIONS
1.21 PUBLIC CONVENIENCE AND SAFETY
1.21.1 Roads To Be Closed
1.21.2 Storage of Materials
1.22 PARTNERING
1.23 LOAD RESTRICTIONS
1.24 BARRICADES, DANGER, WARNING, AND DETOUR SIGNS
1.24.1 Removal of Barricades And Warning Signs
1.24.2 Replacement of Signs
1.24.3 Cost of Protective Devices
1.25 HAUL ROADS
1.26 ASBESTOS - (Occupational Health and Environment)
1.27 COORDINATION WITH OTHER CONTRACTORS
1.28 CONTRACT DRAWINGS AND SPECIFICATIONS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 10 00.10 38 Page 1
SECTION 01 10 00.10 38
SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS
08/19
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
NORTH CAROLINA DEPARTMENT OF TRANSPORTATION (NCDOT)
NCDOT Standard Specifications For Roads And Structures
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1110-1-5 Plant Pest Quarantined Area and Foreign Soil Samples
ER 415-1-15 Construction Time Extensions for Weather
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910.134 Respiratory Protection
29 CFR 1910.1001 Asbestos
29 CFR 1926.55 Gases, Vapors, Fumes, Dusts, and Mists
40 CFR 61.40 General Provisions
49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communications, Emergency Response Information, and Training Requirements
1.2 DEPARTMENT OF ARMY MANDATED SECURITY REQUIREMENTS
The Contractor shall be required to comply with the following security requirements mandated by the Department of the Army:
Short-term employees (working on site less than or equal to 6 months): If a criminal history is found, the employee MAY not be allowed to work at the project site at the sole discretion of the Government.
Long-term employees (working on site more than 6 months):
ALL of the following is required WHEN REPORTING FOR WORK -
a) A completed OMB Form No. 3206-0182 (also designated as Optional Form 306).
SECTION 01 10 00.10 38 Page 2
b) A completed OMB Form No. 3206-0191 (also designated as Standard Form 85P).
c) A resume.
The Government will use all provided information to perform a National Agency Check and Inquiries (NACI) check and will pay the required fee.
The Contractor shall be responsible for furnishing to each employee and for requiring each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer or his/her designated representative. All prescribed identification shall immediately be delivered to the Contracting Officer or his/her designated representative for cancellation upon the release of any employee.
(End of Clause)
1.3 IDENTIFICATION OF EMPLOYEES - MOTSU
At least 10 days before mobilizing, the Contractor shall furnish the Contracting Officer or his/her designated representative, names, driver's license, and vehicular tag numbers of each employee that will be working on this project. The Contractor shall require employees to display identification when requested.
If there are any changes in employees who are assigned to the work at any time after the information is submitted and prior to completion of work, the Contractor shall promptly furnish updated information to the Contracting Officer or his/her designated representative.
It will be the responsibility of the Contractor to take those measures which deem necessary to protect plant and personnel prior to beginning work.
The Contracting Officer or his/her designated representative will arrange an initial coordination meeting between the Contractor and MOTSU which will be held before the Contractor begins work. When work begins, the Contractor shall coordinate all activities with the designated MOTSU personnel on a day to day basis.
(End of Clause)
1.4 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
ER 415-1-15 dtd 31 OCT 89
(a) This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled "DEFAULT (FIXED-PRICE CONSTRUCTION)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be found to be satisfied in the sole discretion of the Contracting Officer:
(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and
SECTION 01 10 00.10 38 Page 3 without the fault or negligence of the Contractor.
(b) The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
9 7 7 6 7 7 9 9 7 5 6 8
(c) Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.
(d) The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph (2), above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "DEFAULT (FIXED-PRICE CONSTRUCTION)".
(End of Clause)
1.5 PERFORMANCE AND PAYMENT BONDS
Each bidder shall include his premiums for performance and payment bonds under the appropriate, "Performance and Payment Bonds" contract line item of the Bidding Schedule. Payment to the Contractor therefore, shall not exceed the bid price and shall be made in accordance with the Contract Clause entitled "PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS." Any additional amount bid in excess of the actual bond premium will be included in the final pay estimate for this contract.
(End of Clause)
1.6 WATER CONSERVATION
Water is one of our valuable natural resources. Accordingly, the Contractor shall be judicious in its use in the performance of the work as specified. Water needed for compaction of roadway and/or foundation materials, and dust control shall be obtained from uncontrolled stream flow instead of potable supply sources to the extent available and suitable as determined by the Contracting Officer or his/her designated representative.
(End of Clause)
SECTION 01 10 00.10 38 Page 4
1.7 BULLETIN BOARD
Within one (1) calendar day after commencement of work under this contract, the Contractor shall provide at the job site a weatherproof, glass-covered bulletin board for displaying the Fair Employment poster, wage rates, posters and safety bulletins as noted in Section 01 35 26 , paragraph DISPLAY OF SAFETY INFORMATION. The bulletin board shall be located in a conspicuous place, easily accessible to all employees, and legible copies of the aforementioned data shall be displayed until work under the contract is complete. No direct payment will be made for the bulletin board.
(End of Clause)
1.8 WORK PLAN
The Contractor shall submit a detailed work plan outlining the Contractor's proposed methods for the execution of all work under this contract. The work plan shall include a schedule that indicates the anticipated time frame to accomplish each definable feature of work within the time specified in the contract. The work plan shall provide an overall program for management of this project consisting of the following required plans:
a. The specific resources and equipment proposed for each definable feature of construction/dredging required by the contract. The Contractor shall describe and document all equipment proposed to demonstrate ability to perform the work in accordance with the proposed schedule, and shall include as a minimum the following information:
Dredges :
- Identification of the Dredge
- Total Horsepower and distribution
- Size of Suction and Discharge Lines
- Associated booster/pipeline equipment
- Estimated Pipeline Length(s) and Location(s) of booster pumps for this contract
- Scow Capacity in cubic yards
- Present location and condition
- Dredge Operation Reports for rock under comparable operating conditions. In addition, submit monthly summaries, to include daily rock production rates from these reports in cubic yards per day
- Dredge Operation Reports for non-rock under comparable operating conditions. In addition, submit monthly summaries, to include daily non-rock production rates from these reports in cubic yards per day
- Existing commitments of this equipment to other projects scheduled during the proposed contract duration
Other accompanying vessels and plant:
- Identification of the vessels
SECTION 01 10 00.10 38 Page 5
- HP/ capacity (as appropriate)
- Existing commitments of this equipment to other projects scheduled during the proposed contract duration
b. A communications plan as required in Section 35 20 23 of the specifications.
c. A dredging plan as required in Section 35 20 23 of the specifications.
d. A dredged material disposal plan as required in Section 35 20 23 of the specifications.
e. A traffic control plan as required in Section 35 20 23 of the specifications.
f. An accident prevention plan (APP) as required in Section 01 35 26 of the specifications.
The offered performance schedule will be incorporated into the contract and will become the required performance period for all contract purposes including assessment of liquidated damages.
1.9 PROGRESS SCHEDULE
Pursuant to the Contract Clause FAR 52.236-15, SCHEDULES FOR CONSTRUCTION CONTRACTS, a project schedule as described in this paragraph PROGRESS SCHEDULE shall be prepared and submitted. The Contractor shall provide the project schedule in the Precedence Diagram Method (PDM) using the Standard Data Exchange Format (SDEF). The project schedule shall be used to measure progress of the work, to evaluate potential time extensions and to provide a basis for all progress payments. It shall be in sufficient detail to properly monitor and manage the work and as a minimum shall include the following:
a. the work shall be divided into activities by acceptance section and phase of work (e.g. preconstruction structure and property condition surveys, blasting, dredging)
b. separate activities shall reflect each mobilization and demobilization of each major plant
c. activities shall be identified by associated bid item
d. all required and proposed submissions shall be included in the progress schedule
e. Government and other agency activities that could impact progress shall be shown (e.g. Government surveys, navigation aid relocations, etc.)
The schedule shall extend from NTP to the established contract completion date.
The initial progress schedule shall be included with the solicitation proposal and demonstrate that the proposed plant and resources are capable of performing the work as scheduled. Periodic schedule updates shall be
SECTION 01 10 00.10 38 Page 6 provided monthly with each payment request, and whenever there is a change in logic or time extension. Each submission shall include the data disks containing the project schedule adhering to the SDEF format specified in ER 1-1-11, Appendix A; the earnings report indicating monthly and cumulative earnings; a narrative report with a description of the activities identifying the critical path(s), current or anticipated problems of delays and their impact, and proposed corrective actions; and the schedule reports containing activity number, activity description, original duration, remaining duration, early start date, early finish date, late start date, late finish date and total float. The schedule reports shall be sorted as activity report, logic report listing preceding and succeeding activities for each activity, total float report listed in ascending order by early state date, early state sort and earning report. A network diagram shall be submitted with the initial submission and each update. The network diagram shall depict the order, sequence and interdependence of activities, shall clearly indicate milestone dates and projected early and late earnings.
1.10 SHOP DRAWINGS AND MATERIALS SUBMITTAL
(a) Five (5) days prior to the preconstruction conference (see paragraph REQUIRED CONSTRUCTION MEETINGS), the Contractor shall complete and submit to the Contracting Officer or his/her designated representative, in duplicate, Submittal Register, listing all submittals and dates. In addition to those items listed on the Submittal Register, the Contractor will furnish submittals for any deviation from the plans or specifications. The scheduled need dates must be recorded on the document for each item for control purposes. In preparing the document, adequate time (minimum of l5 days) will be allowed for review and approval and possible resubmittal. Scheduling shall be coordinated with the approved progress schedule. The Contractor's Quality Control System Manager shall review the listing at least every 30 days and take appropriate action to maintain an effective system. Copies of updated or corrected listings shall be submitted to the Contracting Officer or his/her designated representative at least every 60 days in the quantity specified. Payment will not be made for any material or equipment which does not comply with contract requirements.
(b) Contractor submittals required by the Technical Provisions are indicated in those provisions and are listed on the Submittal Register furnished in Section 01 33 00 SUBMITTAL PROCEDURES. The list does not relieve the Contractor from furnishing submittals required elsewhere in the specifications, those inadvertently omitted from the listing; or from furnishing other submittals that the Government may deem necessary as the work progresses.
(c) Normal review levels for required approvals are indicated by letter designations as follows:
Contractor Quality Control System Manager --- (CQC) Area or Resident Engineer ------------------- (R) Engineering Branch -------------------------- (E)
The Government reserves the right to vary the review levels for (R) and (E) to its convenience.
(d) The Contractor shall use ENG Form 4025, furnished in Section 01 33 00 SUBMITTAL PROCEDURES, to transmit Shop Drawings, Equipment Data, Material Samples or Manufacturer's Certificate of Compliance to the Government.
SECTION 01 10 00.10 38 Page 7
(End of Clause)
1.11 SAMPLING, CERTIFICATES, AND TESTING
(a) General. Within 30 days after acknowledgment of Notice to Proceed, the Contractor shall submit to the Contracting Officer or his/her designated representative five (5) copies of a list of the items for which he proposes to furnish manufacturer's certificates and/or samples for inspection and testing. The list shall include, but is not limited to the following information:
(1) Name of item
(2) Specification paragraph covering this item
(3) Date sample will be furnished
(4) Delivery date of product
(5) Items for which a certificate will be furnished
(b) Submittals. Any product or item mentioned in these specifications and required to meet Federal, ASTM, AASHTO, U. S. Army or Navy, AREMA, AWWA, and UL Specifications or Codes, specified herein with certain limiting or qualifying requirements, or any product or item which is required to be similar and equal to a specified product or item may require the submission, before delivery of the product or item to the job site, of one or more of the following:
(1) Certificate by the manufacturer that the item meets the contract requirements.
(2) Samples for inspection, comparison, and testing, including destructive tests.
(c) Sample delivery. Unless otherwise specified or authorized, all samples shall be delivered (without cost to the Government) to:
U.S. Army Engineer District, Wilmington Corps of Engineers ATTENTION: Military Construction Section 69 Darlington Avenue Wilmington, North Carolina 28403
If required by the Contracting Officer or his/her designated representative, duplicate samples shall be shipped to the Wilmington District Office at no expense to the Government.
(d) Testing. All tests required in the Technical Provisions shall be made by and at the expense of the Contractor except those material tests specifically excluded which will be made by and at the expense of the Government. All instruments and personnel required for the required tests shall be furnished by the Contractor. The Government reserves the right to interrupt the work to make tests on all facets of concreting and other operations. These tests will be made as necessary to insure conformance to applicable specifications and drawings and will be made by and at the expense of the Government except Contractor sampling support as required by the Technical Provisions. In those instances where testing is specified to
SECTION 01 10 00.10 38 Page 8 be made at the Government's expense, the cost of the initial testing will be at the Government's expense; however, any retesting due to failure of the materials to meet the requirements in the initial test shall be performed at the Contractor's expense. The retests shall be made at laboratories approved by the Contracting Officer or his/her designated representative. The costs of retests made at Government laboratories will be deducted from the total amount due the Contractor, at actual cost to the Government, unless otherwise specified.
(End of Clause)
1.12 CERTIFICATES OF COMPLIANCE
(l969 MAY OCE)
Any certificates required for demonstrating proof of compliance of materials with specification requirements shall be executed in 3 copies.
Each certificate shall be signed by an official authorized to certify in behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet the specific requirements.
(End of Clause)
1.13 REQUIRED CONSTRUCTION MEETINGS
(a) In addition to meetings required elsewhere in the specifications, the Contractor and any Subcontractors identified by the Contracting Officer's Representative shall be required to attend a preconstruction meeting (after award of the contract but before Commencement of Work) and a post construction meeting (after final acceptance of the work but before final payment is made). The Contractor and identified Subcontractors shall meet with Corps of Engineers personnel at a time and place determined by the Contracting Officer's Representative.
(b) At the preconstruction conference, the Contractor shall be oriented with respect to Government procedures and line of authority in contractual, administrative, and construction matters. Additionally, a schedule of required submittals will be discussed.
(c) Five (5) days prior to the preconstruction conference, the Contractor shall submit the following items:
Certificate of Insurance Quality Control Plan (see Section 01 45 00.00 10
QUALITY CONTROL, for additional information) Certificate of Completion of Corps CQC Course Preliminary Submittal Register (ENG Form 4288 exclusive of
Contractor submittal dates) Letter Appointing Superintendent (see Contract Clause entitled Superintendence by the Contractor, 52.236-6) List of Subcontractors
(d) The letter of record will be written documenting all items discussed at the conference and a copy will be furnished by the Contracting
SECTION 01 10 00.10 38 Page 9
Officer's Representative to all in attendance.
(End of Clause)
1.14 "AS-BUILT" RECORD DRAWINGS
(a) The Contractor shall be responsible for maintaining in good condition one set of full size drawing prints at the job site, on which he shall keep a careful and neat record of all deviations, field changes and modifications from the original contract drawings which are made to each phase of construction as the work progresses. The Contractor is responsible for noting all changes and corrections on these prints promptly as in-place construction activities occur, but in no case less often than on a weekly basis. In addition to the above, the following shall be included:
(1) Actual location of all Contractor installed subsurface utility lines. Type of materials actually installed, major sizes of lines, etc. In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered or obscured, the record drawings shall show, by offset dimensions to two permanently fixed surface features, both ends of each run and each change in direction. Valves, splice boxes and similar appurtenances shall be located by dimensions along the utility run from a reference point. The average depth below the surface of each run shall also be recorded.
(2) Any shop drawings which constitute part of the design shall be included with the record drawings.
(3) The manufacturer and model number of all major items of equipment shall be shown on the record drawings.
(4) Upon completion of all construction, the Contractor will delete by notation all references to features not constructed.
(b) These annotated prints shall be certified as to their correctness by the signature of the Contractor and turned over to the Contracting Officer or his/her designated representative not later than ten
(10) days after final acceptance of the work by the Government. Marked up prints shall be reviewed for approval by the Contracting Officer or his/her designated representative and returned for corrections as necessary.
(End of Clause)
1.15 FINISH MATERIAL SUBMITTALS
All finish items requiring submittal for approval shall be packaged by the Contractor to form one coordinated submittal for interior finishes and one coordinated and separate submittal for exterior finishes. Each submittal shall clearly convey colors, textures and finishes proposed to permit a complete review on how the finishes interact.
(End of Clause)
1.16 ASBESTOS PERMIT AND NOTIFICATION
Prior to beginning any demolition or renovation of existing buildings, the Contractor shall submit notification to the appropriate state agency by completing there "Asbestos Permit Application and Notification for
SECTION 01 10 00.10 38 Page 10
Demolition/Renovation" form. State law requires notification whether or not asbestos is present. A copy of the state response shall be submitted to the Government for information.
The following state agencies require notification:
State of North Carolina Department of Health and Natural Resources Asbestos Hazard Management Branch Post Office box 27687 Raleigh, North Carolina 27611-7687
(919) 773-0820
Commonwealth of Virginia Department of Labor and Industry 205 North 4th Street Post Office Box 12064 Richmond, Virginia 23241
(804) 786-2376
(End of Clause)
1.17 WORK IN QUARANTINED AREA
USACE and the U.S. Department of Agriculture (USDA) have a compliance agreement requiring measures to prevent the spread of certain plant pests that may be present in the soil (USACE ER 1110-1-5 ). Major portions of all southeastern states are in a quarantine area for such pests, including the imported fire ant. In addition, adjacent states to the north have introduced infestations resulting from movement of soil from infested southeastern states. The Contractor shall thoroughly clean all construction equipment and tools at the previous job site in a manner that ensures that these implements are free from residual soil, egg deposits from plant pests, noxious weeds, and plant seeds. Equipment shall be cleaned using water under pressure, and hand tools shall be thoroughly cleaned by brushing or other means to remove all soil. In addition, all construction equipment and hand tools used for this USACE contract shall be thoroughly cleaned by the Contractor before they are removed from this job site. The Contractor shall consult with the USDA jurisdictional office for additional cleaning requirements that may be necessary.
(End of Clause)
1.18 ACCEPTANCE
(a) Partial Acceptance: If at any time during the prosecution of the project the Contractor completes a portion of the project, such as a bench cut, in its entirety, he may ask the Contracting Officer or his/her designated representative to make final inspection of such work. If the Contracting Officer or his/her designated representative finds upon inspection that the work conforms to the requirements of the Contract and that acceptance is in the interest of the Government, he may accept the work as being completed, and the Contractor will be relieved of further responsibility for the work, except as noted in paragraph FINAL AND CONDITIONAL ACCEPTANCE OF SEEDED PLANTING and as specified in paragraph Contractor's Responsibility for Work . Partial acceptance shall in no way void or alter any terms of the Contract.
If any damage attributable to causes beyond the control of the Contractor
SECTION 01 10 00.10 38 Page 11 is sustained by the accepted section or portion of the project, the Contracting Officer or his/her designated representative may authorize the Contractor to make necessary repairs as a change to the contract.
(b) Final Acceptance: Upon receipt of a written notice from the Contractor of presumptive completion of the entire project, the Contracting Officer Representative will make an inspection. If all work specified in the Contract has been completed, the inspection will constitute the final inspection and the Contracting Officer or his/her designated representative will make the final acceptance. The Contractor will be notified of final acceptance in writing within 5 days.
If the inspection discloses that any work, in whole or in part, is incomplete or unacceptable, the Contractor shall immediately correct the deficiency. Upon completion or correction of the work, another inspection will be made that will constitute the final inspection. In such event, the Contracting Officer or his/her designated representative will make the final acceptance and the Contractor will be notified of final acceptance in writing within 5 days. In any event, the Contractor shall maintain the project until final acceptance except under conditions that may be specifically exempted.
(End of Clause)
1.19 NCDOT SPECIFICATIONS
The North Carolina Department of Transportation ( NCDOT) "Standard Specifications for Roads and Structures English," (hereinafter referred to as the Standard Specifications) applies to this work when so referenced.
(End of Clause)
1.20 DEFINITIONS FOR NCDOT SPECIFICATIONS
Wherever in the North Carolina Department of Transportation "Standard Specifications for Roads and Structures" or on the drawings the following terms are used, the intent shall be as indicated below unless otherwise modified within the specifications:
State - - - - - - - - - - - - - - - - - U. S. Government Department or Department of
Transportation - - - - - - - - - - - Corps of Engineers Engineer or Chief Engineer- - - - - - - Contracting Officer, Corps of Engineers Materials and Test Unit - - - - - - - - Corps of Engineers Division of Highways- - - - - - - - - - Corps of Engineers Board or Board of Transportation- - - - Corps of Engineers
Where NCDOT materials and test unit requirements are referenced in these specifications, they shall be taken as such and not Corps of Engineers Standards unless otherwise stated.
(End of Clause)
1.21 PUBLIC CONVENIENCE AND SAFETY
1.21.1 Roads To Be Closed
No road shall be closed to the public by the Contractor until construction
SECTION 01 10 00.10 38 Page 12 of the new facilities infringe upon the public safety or until construction of the new facilities obliterate the existing facilities. The Contractor shall obtain the Contracting Officer's approval before closing any roads.
Barricades, danger, warning and detour signs, as required, shall be erected before closing any roads.
1.21.2 Storage of Materials
Materials and equipment shall not be stored within roadway rights-of-way or in such a manner as to pose possible danger or obstruction to the traveling public.
(End of Clause)
1.22 PARTNERING
In order to most effectively accomplish this contract, the Government proposes to form a cohesive partnership with the Contractor and its subcontractors. This partnership would strive to draw on the strengths of each organization in an effort to achieve a quality project done right the first time, within budget and on schedule. Integral to the partnership would be a joint Contractor/Government effort to settle any disputes that may arise without costly and time consuming litigation. To that end, a non-binding procedure such as the Alternate Dispute Resolution process could be developed and agreed upon by both parties when it is determined to be necessary. This partnership would be bilateral in make-up and participation will be totally voluntary. Any cost associated with developing this partnership will be agreed to by both parties and will be shared equally with no change in contract price.
(End of Clause)
1.23 LOAD RESTRICTIONS
The Contractor shall comply with all legal load restrictions in the hauling of materials on public roads beyond the limits of the project. A special permit will not relieve the Contractor of liability for damage which may result from such hauling. The Contractor shall not operate equipment of such weight or so loaded as to cause damage to drainage structures or the roadway, or to any other type of improvement, either completed or under construction. Hauling of materials over the existing surface shall be limited as directed, and in no case shall legal load limits be exceeded unless permitted in writing. The Contractor shall repair, at his own expense, all damage to the work caused by his equipment.
(End of Clause)
1.24 BARRICADES, DANGER, WARNING, AND DETOUR SIGNS
The Contractor shall provide, erect, and maintain all necessary traffic control devices in substantial conformance to Part VI of the 1988 "Manual on Uniform Traffic Control Devices for Streets and Highways" as published by the U.S. Department of Transportation, Federal Highway Administration, and available from AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO), U. S. DEPARTMENT OF TRANSPORTATION ( DOT). This requirement shall include flagman as shown in the manual when necessary and the use of electric flashers as conditions of construction may require during hours of darkness. The Contractor shall take all necessary precautions for protection of the work and for the safety of the public at
SECTION 01 10 00.10 38 Page 13
POTABLE WATER, W923PM19B0022
or near the site of construction. Signing, barricades, lights, and other devices shall be well maintained and repositioned or removed as the progress of the work requires. No substandard, poorly maintained device will be acceptable. Particular attention shall be given to the following:
1.24.1 Removal of Barricades And Warning Signs
As soon as construction advances to the extent that temporary barricades, and signs such as "Detour", "One Way Traffic," etc. are no longer needed to inform the traveling public, such signs shall be removed promptly.
1.24.2 Replacement of Signs
When new work is necessary during any period of construction or maintenance, necessary signs shall be replaced as are needed to adequately warn and protect the public in accordance with the provisions outlined above. As soon as the project has been accepted for maintenance, all temporary barricades and warning signs shall be removed promptly.
1.24.3 Cost of Protective Devices
Unless otherwise shown in the Bidding Schedule, the cost of furnishing, erecting, maintaining, and removing protective devices will not be paid for as separate bid items. Where the Contractor is required to perform any of these functions, the cost thereof shall be included in the overall bid submitted. Ownership of the temporary warning devices shall remain with the Contractor provided the devices are removed promptly after completion of the work as specified above. If such warning devices are left in place for more than 30 days after the specified time for removal, the Government shall have the right to remove such devices and to claim possession thereof.
(End of Clause)
1.25 HAUL ROADS
(1985 HQ USACE)
Whenever practical, one-way haul roads shall be used on this contract.
Haul roads built and maintained for this work shall comply with the following:
(a) One-way haul roads for off-the road equipment; e.g., belly bumps, scrapers, and off-the-road trucks shall have a minimum usable width of 25 ft. One-way haul roads for over-the-road haulage equipment only (e.g., dump trucks, etc.) may be reduced to a usable width of 15 ft.
When the Contracting Officer or his/her designated representative determines that it is impractical to obtain the required width for one-way haul roads (e.g., a road on top of a levee), a usable width of not less than 10 ft. may be approved by the Contracting Officer or his/her designated representative, provided a positive means of traffic control is implemented. Such positive means shall be signs, signals, and/or signalman and an effective means of speed control.
(b) Two-way haul roads for off-the-road haulage equipment shall have usable width of 60 ft. Two-way haul roads for over-the-road haulage equipment only may be reduced to a usable width of 30 ft.
(c) Haul roads shall be graded and otherwise maintained to keep the
SECTION 01 10 00.10 38 Page 14
POTABLE WATER, W923PM19B0022
surface free from potholes, ruts, and similar conditions that could result in unsafe operation.
(d) Grades and curves shall allow a minimum sight distance of 200
ft. for one-way roads and 300 ft. for two-way roads. Sight distance is defined as the centerline distance an equipment operator (4.5 ft. above the road surface) can see an object 4.5 ft. above the road surface. When conditions make it impractical to obtain the required sight distance (e.g., ramps over levees), a positive means of traffic control shall be implemented.
(e) Dust abatement shall permit observation of objects on the roadway at a minimum distance of 300 ft.
(f) Haul roads shall have the edges of the usable portion marked with posts at intervals of 50 ft. on curves and 200 ft. maximum elsewhere.
Such markers shall extend 6 ft. above the road surface and, for nighttime haulage, be provided with reflectors in both directions.
(End of Clause)
1.26 ASBESTOS - (Occupational Health and Environment)
(a) THE CONTRACTOR IS WARNED THAT EXPOSURE TO AIRBORNE ASBESTOS HAS
BEEN ASSOCIATED WITH FOUR DISEASES: LUNG CANCER, CERTAIN GASTROINTESTINAL
CANCERS, PLURAL OR PERITONEAL MESOTHELIOMA AND ASBESTOS. Studies indicate there are significantly increased health dangers to persons exposed to asbestos who smoke and further, to family members and other persons who become indirectly exposed as a result of the exposed worker bringing asbestos-laden work clothing home to be laundered.
(b) The Contractor is advised that friable and/or nonfriable asbestos containing material has been identified in area(s) where contract work is to be performed. Friable asbestos containing material means any material that contains more than 1 percent asbestos by weight that hand pressure can crumble, pulverize or reduce to powder when dry. Nonfriable asbestos containing materials do not release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition or other similar activities.
(c) Care must be taken to avoid releasing, or causing to be released, asbestos fibers into the atmosphere where they may be inhaled or ingested. The Occupational Safety and Health Administration (OSHA) has set standards at 29 CFR 1910.1001 , for exposure to airborne concentrations of asbestos fibers, methods of compliance, medical surveillance, housekeeping procedures and other measures that must be taken when working with or around asbestos containing materials which release airborne asbestos fibers at concentrations in excess of those established. 29 CFR 1926.58 has been identified as applicable to construction ( 29 CFR 1926.55 gases, vapors, fumes, dusts and mists). The Environmental Protection Agency (EPA) has established standards at 40 CFR 61.40 - 40 CFR61.156 for the control of asbestos emissions to the environment and the handling and disposal of asbestos wastes.
(d) When contract work activities are carried out in locations where the potential exists for exposure to airborne asbestos fibers as described in (b) or where asbestos waste will be generated, the contractor shall assure that all measures necessary to provide effective protection to
SECTION 01 10 00.10 38 Page 15 persons from exposure to asbestos fibers and prevention of contamination to property, materials, supplies, equipment and the internal and external environment are effectively instituted.
(e) As a minimum, the contractor shall comply with the provisions of 29 CFR 1926.58 and 1926.55; 49 CFR 172 .101, 172.200-204 , 172.316 , 173.1090 ;
40 CFR 61.40 - 61.156 ; any state implementing hazardous waste regulation that regulates asbestos as a hazardous waste under the Resources Conservation and Recovery Act (RCRA) requirements and any other applicable federal, state or local requirements.
(f) In addition to the information required in Section 01 35 26 , the Contractors Accident Prevention Plan must also fully address the following topics, and at the Contractor's option may include additional information as applicable.
(1) Medical Surveillance: (29 CFR 1926.58(m)).
(2) Employee training: Prior to beginning work in asbestos containing material area(s) (29 CFR 1926.58 and 29 CFR 1910.134 ).
(3) Respiratory protection: (29 CFR 1926.58(h) and
29 CFR 1910.134 ).
(4) Personal protective clothing and equipment: (29 CFR 1926.58(i)).
The use of compressed air to remove asbestos from workers' clothing is prohibited. The contractor shall specify the type of change room, wash facilities and laundering facilities as applicable.
(5) Airborne asbestos monitoring: (29 CFR 1926.58(f)).
Specify the monitoring and analytical procedures to be used prior to, during, and after completion of contract in areas where asbestos containing materials are located. All asbestos monitoring shall be conducted under the guidance of an industrial hygienist certified by the American board of Industrial Hygiene. Samples shall be analyzed by an American Industrial Hygiene Association (AIHA) accredited laboratory proficient in the analysis of asbestos and asbestos containing materials. Turn around time from end of sampling period to review of results of analyses by Contractor shall be no longer than 72 hours.
(6) Housekeeping: (29 CFR 1926.58(l)). Dry sweeping of contract work areas contaminated with asbestos containing material is prohibited. The Contractor shall specify methods and materials used to package asbestos containing waste and plan to control any accidental airborne release or spill of asbestos containing material.
(7) Methods of Compliance: (29 CFR 1926.58(g)). Contractor shall include procedures relating to engineering controls, local exhaust ventilation, particular tools to be used and work practices (1926.58(g)).
Specify methods, materials and equipment to be used to prevent asbestos contamination to property, materials, supplies, equipment and the internal and external environment during maintenance, renovation or other contract activities. Local exhaust ventilation equipment including power operated tools equipped with local exhaust ventilation shall conform with the Standard Fundamentals Governing the Design and operation of Local Exhaust Systems ANSI Z9.2 latest revised edition. Describe the type of high-efficiency filtered (HEPA) vacuum cleaners that shall be used to
SECTION 01 10 00.10 38 Page 16 vacuum asbestos containing materials. Describe methods and materials to be used to assure all asbestos containing material will be thoroughly wetted by use of a wetting agent and water before removal land that airborne asbestos dust will be kept to a minimum.
(8) Methods and materials to be used to decontaminate any property, materials, supplies, equipment and the environment if asbestos contamination results. (29 CFR 1926.58(g)).
(9) Recordkeeping procedures. (29 CFR 1926.58(n) and 1910.20).
(10) Specific description of type of packaging, marking and shipping conveyances to be used to transport asbestos containing waste from the generation point to a storage or disposal facility in compliance with Department of Transportation requirements. ( 49 CFR 172 .101, 172.200-204 ,
176.316 , 173-1090 ).
(11) Emergency procedures that would be taken if an accident or spill of asbestos containing materials occurs during the transport of asbestos containing waste. ( 40 CFR 61.140 - 61.156 ).
(12) Methods and equipment used to off load and bury asbestos containing waste to control airborne emissions at the burial site. (
40 CFR 61.140 - 61.156 ).
(g) The Contractor shall complete and…