W912PM-16-B-0008 _Amd_0002_(SF30).pdf
PDF 26 KB Posted
- Attached to
- Wilmington Harbor Mid-River & Military Ocean Terminal at Sunny Point Dredging Maintenance
- Solicitation number
- W912PM-16-B-0008
About this file
Amendment 0002
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of the amendment is to update the period of performance.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 30-Jun-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PM-16-B-0008
X 9B. DATED (SEE ITEM 11)
17-Jun-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
30-Jun-2016
CODE
U S ARMY CORPS OF ENGINEERS
CONTRACTING - WILMINGTON DISTRICT
69 DARLINGTON AVENUE
WILMINGTON NC 28403
W912PM 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912PM-16-B-0008
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
The contractor period of performance end date has increased by 180 days from 120 days to 300 days.
The following have been modified:
BID SCHEDULE
FY 16-17 Maintenance Dredging Wilmington Harbor Mid-River/MOTSU
Bidding Schedule (Amend 0001)
TOTAL FOR ITEMS 0001 - 0009 $__________________________
OPTIONAL BID ITEMS
TOTAL FOR OPTIONAL BID ITEM #1 $___________________
Lower Big Island Channel
TOTAL FOR OPTIONAL BID ITEM #2 $___________________
Keg Island Channel
TOTAL FOR OPTIONAL BID ITEM #3 $___________________
Upper Midnight Channel
TOTAL FOR OPTIONAL BID ITEM #4 $___________________
Approach Channel Center to North Wharf & North Wharf Turning Basin
TOTAL FOR OPTIONAL BID ITEM #5 $___________________
Security Boat Basin
OVERALL TOTAL FOR ALL $__________________________
OPTIONAL BID ITEMS
OVERALL TOTAL FOR ALL $__________________________
CLIN ITEMS & OPTIONAL BID ITEMS
NOTICE TO BIDDERS
THE GOVERNMENT RESERVES THE RIGHT TO EXERCISE ANY OR ALL OF
THE OPTIONAL BID ITEMS WITHIN 90 CALENDAR DAYS AFTER DATE OF
AWARD.
(AMENDMENT 0002 CHANGE------------------------------------------
THE COMPLETION OF ALL WORK TO INCLUDE ALL OPTIONAL BID
ITEMS, IF EXERCISED, SHALL BE NOT LATER THAN THREE HUNDRED
(300) CALENDAR DAYS AFTER ISSUANCE OF NOTICE TO PROCEED.
PERFORMANCE OF ALL WORK UNDER THIS CONTRACT, INCLUDING
OPTIONAL BID ITEMS, IF AWARDED, SHALL BE COMPLETED IN
ACCORDANCE WITH THE FOLLOWING ENVIRONMENTAL WINDOWS
ACCORDING TO THE LOCATION AND DREDGE USED:
1. FOR SECURITY BOAT BASIN: 1 October – 31 March
2. FOR HOPPER DREDGES:
- Horseshoe Shoal Channel, 1 December – 31 March
- Upstream of Horseshoe Shoal Channel to Upper Lilliput Channel, 1 December – 31 January
- From Upper Lilliput Channel to Wilmington, 1 August to 31 January
3. FOR HYDRAULIC CUTTER SUCTION DREDGES:
- Horseshoe Shoal Channel, NO environmental window
- Upstream of Horseshoe Shoal Channel, 1 August – 31 January
4. FOR MECHANICAL DREDGES (clamshell, dragline or dipper):
NO environmental windows
PRE-AWARD INFORMATION
A contract shall be awarded to a responsible prospective contractor.
Before award, to be determined responsible, a prospective contractor must submit the following information with the bid:
THE FOLLOWING INFORMATION MUST BE SUBMITTED WITH BID
a. Current Financial Statement
b. Furnish a completed Small Business Subcontracting Plan (LARGE BUSINESS ONLY)
SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the
Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than three hundred (300) days after issuance of notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
(End of Summary of Changes)