Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of the amendment is to update the period of performance.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 30-Jun-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PM-16-B-0008

X 9B. DATED (SEE ITEM 11)

17-Jun-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

30-Jun-2016

CODE

U S ARMY CORPS OF ENGINEERS

CONTRACTING - WILMINGTON DISTRICT

69 DARLINGTON AVENUE

WILMINGTON NC 28403

W912PM 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912PM-16-B-0008

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE

The contractor period of performance end date has increased by 180 days from 120 days to 300 days.

The following have been modified:

BID SCHEDULE

FY 16-17 Maintenance Dredging Wilmington Harbor Mid-River/MOTSU

Bidding Schedule (Amend 0001)

TOTAL FOR ITEMS 0001 - 0009 $__________________________

OPTIONAL BID ITEMS

TOTAL FOR OPTIONAL BID ITEM #1 $___________________

Lower Big Island Channel

TOTAL FOR OPTIONAL BID ITEM #2 $___________________

Keg Island Channel

TOTAL FOR OPTIONAL BID ITEM #3 $___________________

Upper Midnight Channel

TOTAL FOR OPTIONAL BID ITEM #4 $___________________

Approach Channel Center to North Wharf & North Wharf Turning Basin

TOTAL FOR OPTIONAL BID ITEM #5 $___________________

Security Boat Basin

OVERALL TOTAL FOR ALL $__________________________

OPTIONAL BID ITEMS

OVERALL TOTAL FOR ALL $__________________________

CLIN ITEMS & OPTIONAL BID ITEMS

NOTICE TO BIDDERS

THE GOVERNMENT RESERVES THE RIGHT TO EXERCISE ANY OR ALL OF

THE OPTIONAL BID ITEMS WITHIN 90 CALENDAR DAYS AFTER DATE OF

AWARD.

(AMENDMENT 0002 CHANGE------------------------------------------

THE COMPLETION OF ALL WORK TO INCLUDE ALL OPTIONAL BID

ITEMS, IF EXERCISED, SHALL BE NOT LATER THAN THREE HUNDRED

(300) CALENDAR DAYS AFTER ISSUANCE OF NOTICE TO PROCEED.

PERFORMANCE OF ALL WORK UNDER THIS CONTRACT, INCLUDING

OPTIONAL BID ITEMS, IF AWARDED, SHALL BE COMPLETED IN

ACCORDANCE WITH THE FOLLOWING ENVIRONMENTAL WINDOWS

ACCORDING TO THE LOCATION AND DREDGE USED:

1. FOR SECURITY BOAT BASIN: 1 October – 31 March

2. FOR HOPPER DREDGES:

- Horseshoe Shoal Channel, 1 December – 31 March

- Upstream of Horseshoe Shoal Channel to Upper Lilliput Channel, 1 December – 31 January

- From Upper Lilliput Channel to Wilmington, 1 August to 31 January

3. FOR HYDRAULIC CUTTER SUCTION DREDGES:

- Horseshoe Shoal Channel, NO environmental window

- Upstream of Horseshoe Shoal Channel, 1 August – 31 January

4. FOR MECHANICAL DREDGES (clamshell, dragline or dipper):

NO environmental windows

PRE-AWARD INFORMATION

A contract shall be awarded to a responsible prospective contractor.

Before award, to be determined responsible, a prospective contractor must submit the following information with the bid:

THE FOLLOWING INFORMATION MUST BE SUBMITTED WITH BID

a. Current Financial Statement

b. Furnish a completed Small Business Subcontracting Plan (LARGE BUSINESS ONLY)

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following have been modified:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the

Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than three hundred (300) days after issuance of notice to proceed. The time stated for completion shall include final cleanup of the premises.

(End of clause)

(End of Summary of Changes)