W912PL19B0009_Amendment0002.pdf

PDF 6 MB Posted

Attached to
Analytical Lab AFRL B8523 at Edwards Air Force Base. Federal contract opportunity
Solicitation number
W912PL19B0009
Issued by
Department of the Army Corps of Engineers Engineering District Los Angeles

About this file

Amendment 0002

View the file

Other files for this federal contract opportunity

Other files attached to Analytical Lab AFRL B8523 at Edwards Air Force Base., newest first.
File Type Posted
W912PL19B0009_AbstractofOffers_Construction.pdf PDF
W912PL19B0009_Amendment0003.pdf PDF
W912PL19B0009_Amendment0001.pdf PDF
W912PL19B0009_FIO_SiteVisitSign-InSheet.pdf PDF
100_Percent_643005_Analytics_Lab_AFRL_Edwards_AFB_Combined_Specifications.pdf PDF
100_Percent_643005_Analytics_Lab_AFRL_Edwards_AFB_Combined_Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

0002 Sep 9, 2019

W912PL

USACE-LOS ANGELES DISTRICT

CONTRACTING DIVISION, WEST REGION BRANCH

915 WILSHIRE BLVD, SUITE 930

LOS ANGELES, CA 90017

W912PL19B0009

Jul 30, 2019

REPAIR ANALYTICAL LAB, AFRL, B8523, EDWARDS AIR FORCE BASE, CA

Projnet Bid Inquiry No. 8150493 is revised as follows: Spray fireproofing is required as shown on Drawing. Please see revised Drawing A-210.

List of Revised Specification Sections and Drawings is attached.

Due date for receipt of bids is September 16th, 2019 at 1:00 PM local time.

INSTRUCTIONS

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code) . Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date) .

(1)

(2)

(3)

(4)

(5)

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contacting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(a)

(b)

(c)

(d)

(e)

(f)

Item 6 (Issued By) . Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor) . For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Item 9, (Amendment of Solicitation No. - Dated), and 10, (Modification of Contract/Order No. - Dated ). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

Item 12 (Accounting and Appropriation Data) .

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries.

(2) Accounting classification Net decrease $

Include subject matter or short title of solicitation/contract where feasible.

Item 16B . The contracting officer's signature is not required on solicitation amendments. The contracting offier's signature is normally affixed last on supplemental agreements.

(i)

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13 . Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification) .

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

Total contract price increased by $

Total contract price decreased by $

Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

A reference to the letter determination; and

A statement of the net amount determined to be due in settlement of the contract.

(g)

(h)

(i)

(ii)

(1)

(2)

(3)

(4)

(5)

(6)

(i)

(ii)

(iii)

STANDARD FORM 30 (REV. 10-83) BACK

(1) Accounting classification Net increase $

Repair Analytical Lab, AFRL, Building 8523 W912PL19B0009 Edwards AFB, CA

Amendment 0002

SF‐30 Continuation W912PL19B0009, Amendment No. 2.

Project: Repair Analytical Lab, AFRL, Building 8523, Edwards AFB, CA

SUMMARY OF REVISED SPECIFICATION SECTIONS – September 2019

Section 07 81 00, Spray, Applied Fireproofing

Section 11 53 23.16, Overhead Service Carriers

Section 12 31 00, Manufacture Metal Laboratory Casework

Section 22 00 00, Plumbing, General Purpose

Section 26 29 23, Variable Frequency Drive Systems Under 600 Volts

Section 27 10 10, Building Telecommunications Cabling System

Section 28 31 76, Interior Fire Alarm and Mass Notification System

SUMMARY OF REVISED DRAWINGS – SEPTEMBER 2019

S-101 Foundation Plan

S-501 Sections and Details

S-502 Section and Details.

A-101 First Floor Plan

A-201 Building Elevations

A-210 Interior Elevations and Building Sections

I-001 Finish Schedule, Specifications and Notes

Q-402 Enlarged Laboratory Plans

Q-501 Details

Q-601 Schedules

P-105 First Floor Piping Plan

P-106 First Floor Lab Gas Piping Plan

P-502 Details

P-902 Isometrics

M-102 First Floor HVAC Plan – Area A

M-103 First Floor HVAC Plan – Area B

M-601 Schedules

Repair Analytical Lab, AFRL, Building 8523 W912PL19B0009 Edwards AFB, CA

Amendment 0002

SF-30 Continuation W912PL19B0009, Amendment No. 2.

Project: Repair Analytical Lab, AFRL, Building 8523, Edwards AFB, CA

M-704 Controls

M-705 Controls

M-706 Controls

M-707 Controls

M-708 Controls

M-709 Controls

E-102 Equipment Platform Lighting Plan

E-201 First Floor Power Plans

T-001 General Notes Legend and Abbreviations

T-101 First Floor Telecommunications Plan

SECTION 07 81 00

SPRAY-APPLIED FIREPROOFING

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASSOCIATION OF THE WALL AND CEILING INDUSTRY (AWCI)

AWCI TM 12-A (1997; 3rd Ed) Standard Practice for the Testing and

Inspection of Field Applied Sprayed Fire-Resistive Materials; An Annotated Guide

ASTM INTERNATIONAL (ASTM)

ASTM E1042 (2002; R 2014) Acoustically Absorptive Materials Applied by

Trowel or Spray

ASTM E119 (2018) Standard Test Methods for Fire Tests of Building

Construction and Materials

ASTM E605/E605M (1993; R 2015; E 2015) Standard Test

Methods for Thickness and Density of Sprayed Fire-Resistive Material (SFRM) Applied to Structural Members

ASTM E736 (2000; R 2011) Cohesion/Adhesion of Sprayed Fire-Resistive

Materials Applied to Structural Members

ASTM E759/E759M (1992; R 2015; E 2015) Standard Test

Method for Effect of Deflection on Sprayed Fire-Resistive Material Applied to Structural Members

ASTM E760/E760M (1992; R 2015; E 2015) Standard Test

Method for Effect of Impact on Bonding of Sprayed Fire-Resistive Material Applied to

ASTM E761/E761M (1992; R 2015; E 2015) Standard Test

Method for Compressive Strength of Sprayed Fire-Resistive Material Applied to

ASTM E84 (2018) Standard Test Method for Surface Burning Characteristics of Building Materials

SECTION 07 81 00 Page 1

AFCEC - Edwards AFB - Analytic Lab 643005

ASTM E859/E859M (1993; R 2015; E 2015) Standard Test Method for Air Erosion of Sprayed Fire-Resistive Materials (SFRMs) Applied to Structural Members

ASTM E937/E937M (1993; R 2015; E 2015) Standard Test

Method for Corrosion of Steel by Sprayed Fire-Resistive Material (SFRM) Applied to Structural Members

ASTM G21 (2015) Standard Practice for Determining Resistance of

Synthetic Polymeric Materials to Fungi

ICC EVALUATION SERVICE, INC. (ICC-ES)

ICC-ES AC23 (2012; R 2016) Acceptance Criteria for Sprayed Fire-resistant Materials (SFRMs), Intumescent Fire-resistant Coatings and Mastic Fire-resistant Coatings Used to Protect Structural Steel Members

UNDERWRITERS LABORATORIES (UL)

UL 263 (2011; Reprint Mar 2018) Fire Tests of Building Construction and Materials

UL Fire Resistance (2014) Fire Resistance Directory

1.2 SYSTEM DESCRIPTION

1.2.1 General Requirements

Protect all structural steel, as indicated on drawings with spray-applied fireproofing to a fire resistance hour-rating as indicated below, unless otherwise indicated.

1.2.2 Fire Resistance Rating

Fire resistance ratings shall be in accordance with the fire rated assemblies listed in UL Fire Resistance. Proposed materials not listed in UL Fire Resistance shall have fire resistance ratings at least equal to the UL Fire Resistance ratings as determined by an approved independent testing laboratory, based on tests specified in UL 263 or ASTM E119.

Submit reports and test records, attesting that the fireproofing material conforms to the specified requirements. Each test report shall conform to the report requirements specified by the test method. Apply fireproofing to structural steel members, with the following hourly fire resistance rating and in accordance with the following UL design or approved equivalent. Use unrestrained fire resistance ratings, unless the architect/engineer has specified that the degree of thermal restraint of the construction meets or exceeds the degree of thermal restraint of the tested assembly.

Performance tests shall be in accordance with ASTM E119. Refer also general notes A-101.

SECTION 07 81 00 Page 2

Fire Rating Schedule

Element Hourly Rating UL Design Reference

Beams supporting equipment platform floor slab

1.2.3 Evaluation Reports - ICC-ES Reports

Materials shall be evaluated in accordance with ICC-ES AC23. ICC-ES Reports shall be included as part of the Submittals below. The reports will identify the product as code compliant and having met the physical performance requirements outlined in paragraphs "Dry Density and Cohesion/Adhesion" through "Air Erosion".

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-03 Product Data

Fireproofing Material;

G

SD-04 Samples

Spray-Applied Fireproofing;

G SD-06 Test Reports

Fire Resistance Rating;

G Field Tests; G Evaluation Reports;

G SD-07 Certificates

Installer Qualifications; G Surface Preparation Report;

G Manufacturer's Inspection Report; G

1.5 QUALITY ASSURANCE

1.4.1 Installer Qualifications

Engage an experienced installer that is certified, licensed, or otherwise qualified by the spray-on fireproofing manufacturer as having the necessary experience, staff, and training to install the manufacturer's products in accordance with specified requirements. Submit manufacturer's certification that each listed installer is qualified and trained to install the specified fireproofing. Show evidence that each fireproofing installer has had a minimum of 3 years experience in installing the specified type of fireproofing. Each installer of fireproofing material shall be trained, have a minimum of 3 years experience and a minimum of

SECTION 07 81 00 Page 3 three installations using fireproofing of the type specified. A manufacturer's willingness to sell its products to the Contractor or installer does not infer qualification of the buyer.

1.4.2 Pre-Installation Meeting

Hold a meeting with the installer, field testing agency, the manufacturer, subcontractors (whose employees come into contact with the fireproofing), and the Contracting Officer prior to the installation of any fireproofing material to review the substrates for acceptability, method of application, applied thickness, patching, repair, inspection and testing procedures.

1.4 DELIVERY, STORAGE, AND HANDLING

Deliver packaged material in the original unopened containers, marked to show the brand name, the manufacturer, and the UL markings. Keep fireproofing material dry until ready to be used, and store off the ground, under cover and away from damp surfaces. Damaged or opened containers will be rejected. Apply material with shelf-life prior to expiration of the shelf-life.

1.5 PROJECT/SITE CONDITIONS

1.5.3 Temperature

Maintain substrate and ambient air temperatures above 40 degrees F during application and for 24 hours before and after application.

Maintain relative humidity within the limits recommended by the fireproofing manufacturer.

1.5.4 Ventilation

Provide adequate ventilation to properly dry the fireproofing after application. In enclosed areas, provide a minimum of 4 air exchanges per hour by forced air circulation.

PART 2 PRODUCTS

2.1 SPRAY-APPLIED FIREPROOFING

Provide spray-applied fireproofing material, including sealer, conforming to ASTM E1042, Class (a), Category A, either Type I or Type II, except that the dust removed shall not exceed 0.0025 gram per square foot of fireproofing material applied as specified in the project. Only products that have been evaluated at UL and bear and "investigated for exterior use" approval are allowed in waterfront areas where the fireproofing may be directly exposed to a natural body of water. Material shall be asbestos free, and shall resist fungus for a period of 28 days when tested in accordance with ASTM G21. Material shall have a flame spread of 25 or less and a smoke developed rating of 50 or less when tested in accordance with ASTM E84. Submit one sample panel, 18 inches square, for each specified type of fireproofing. Also, a designated sample area of not less than 100 square feet shall be prepared. Sample area shall be representative of typical installation of fireproofing including beams and attachments.

Equipment, materials and procedures used in the sample area shall be the same as, or representative of, that to be used in the work. The sample area shall be approved prior to proceeding with fireproofing work in any other area. The approved sample area shall be used as a reference standard for applied fireproofing material. Sample area shall remain in place and

SECTION 07 81 00 Page 4 open to observation until all spray-applied fireproofing is completed and accepted, at which time it may become part of the work.

a. Dry Density and Cohesion/Adhesion

Fireproofing shall have a minimum ASTM E605/E605M dry density and ASTM E736 cohesion/adhesion properties as follows:

• Concealed Structural Components

Fireproofing for structural components concealed above the ceiling, or within a wall, chase, or furred space, shall have a average applied dry density of 15 pounds per cubic foot and a cohesion/adhesion strength of 200 psf.

• Exposed Structural Components

Fireproofing for exposed structural components, except where otherwise specified or indicated, shall have a minimum applied dry density of 22 pounds per cubic foot and a cohesion/adhesion strength of 434 psf.

• Deflection

Spray-applied fireproofing shall not crack, spall, or delaminate when backing to which it is applied is subject to downward deflection 1/120 of 10 foot clear span, when tested in accordance with ASTM E759/E759M.

• Bond-Impact

Spray-applied fireproofing material shall not crack, spall or delaminate when tested in accordance with ASTM E760/E760M.

• Compressive Strength

The minimum compressive strength shall be 1000 psf when tested in accordance with ASTM E761/E761M.

• Corrosion

Spray-applied fireproofing material shall not contribute to corrosion of test panels when tested as specified in ASTM E937/E937M.

• Air Erosion

Dust removal shall not exceed 0.025 gram per square foot when tested in accordance with ASTM E859/E859M.

1.7 SEALER

Sealer shall be the type approved by the manufacturer of the fireproofing material, shall be fungus resistant, shall have a flame spread of 25 or less and a smoke developed rating of 50 or less when tested in accordance with ASTM E84, and shall be white color.

1.8 WATER

Water used for material mixing and surface preparation shall be potable.

SECTION 07 81 00 Page 5

1.7 SPRAY-APPLIED INTUMESCENT EPOXY COATING SYSTEM

Provide a two-component epoxy based intumescent fire protective coating that meets the following requirements.

1.7.1 On curing it forms a flexible and tough epoxy barrier which transforms into a ceramic-like, insulating char to provide thermal protection of the substrate in the event of a fire.

1.7.2 The coating system includes the manufacturer's required surface preparation, primer, and fire protective layer, and topcoat.

1.7.3 The coating system protects the substrate from corrosion and retain its fire protection properties under aggressive chemical environments.

1.7.4 Resistant to solvents, acids, alkalis, salts and abrasion while retaining its fire protective properties.

Provide a system that exhibits the following properties:

1.7.1 Percent Solids by Weight

100 percent

1.7.2 In Service Temperature

Restrictions Up to 150 degrees F

1.7.3 Application Method

Air spray or specialized plural component airless equipment approved by the manufacture. Troweling can be used for small areas or touch-up work.

1.7.4 Drying Time

Approximately 24 hours to achieve a Shore D hardness of 25.

1.7.5 Shelf Life

Minimum shelf life under proper storage condition is 1 Year from date of manufacture.

1.7.6 Pot Life

Approximately 40 minutes at 77 degrees F and 50 percent relative humidity. Pot life is not a factor when using specialized plural component airless spray equipment.

1.7.7 Flash Point

Greater than 212 degrees F Pensky-Martens for each component.

PART 3 EXECUTION

3.1 SURFACE PREPARATION

Thoroughly clean surfaces to be fireproofed of dirt, grease, oil, paint, primers, loose rust, rolling lubricant, mill scale or other contaminants that will interfere with the proper bonding of the sprayed fireproofing to

SECTION 07 81 00 Page 6 the substrate. Test painted/primed steel substrates in accordance with ASTM E736, with specified sprayed fireproofing material, to provide the required fire-resistance rating; painted or primed steel surfaces may require a fireproofing bond test to determine if the paint formulation will impair proper adhesion. Certify the acceptability of surfaces to receive sprayed-applied fireproofing by inspection and submit a Surface Preparation Report accordingly. The statement shall list the structural members and the areas that have been inspected and certified. Overhead areas to be fireproofed shall be cleared of all obstructions interfering with the uniform application of the spray-applied fireproofing. Hardware such as support sleeves, inserts, clips, hanger attachment devices and the like shall be installed prior to the application of the fireproofing.

Condition of the surfaces shall be acceptable to the manufacturer prior to application of spray-applied fireproofing. Applications listed for use on primed surfaces shall be in accordance with the manufacturer's recommendations and standards, and detailed in submittal item SD-03 Product Data.

1.7 PROTECTION

Cover surfaces not to receive spray-applied fireproofing to prevent contamination by splatter, rebound and overspray. Cover exterior openings in areas to receive spray-applied fireproofing prior to and during application of fireproofing with tarpaulins or other approved material.

Clean surfaces not to receive fireproofing of fireproofing and sealer.

1.8 FIREPROOFING MATERIAL

Mix fireproofing material in accordance with the manufacturer's recommendations. Submit data identifying performance characteristics of fireproofing material. Data includes recommended application requirements and indicate thickness of fireproofing to be applied to achieve each required fire rating.

1.9 APPLICATION

1.9.2 Sequence

Prior to application of fireproofing the manufacturer shall inspect and approve application equipment, water supply and pressure, and the application procedures. No floor traffic shall be allowed during application. Fireproofing material shall be applied prior to the installation of ductwork, piping and conduits which would interfere with uniform application of the fireproofing.

1.9.3 Application Technique

Maintain water pressure and volume to manufacturer's recommendations throughout the fireproofing application. Apply fireproofing material to the thickness and density established for the specified fire resistance rating, in accordance with the procedure recommended by the manufacturer, and to a uniform density and texture. Do not tamp fireproofing material to achieve the desired density.

1.9.4 Sealer Application

If sealer is required by the product used, apply it after field testing has been conducted and after corrective measures and repairs, if required, have been completed.

SECTION 07 81 00 Page 7

2.1.1 Applied Thickness

The minimum average thickness shall be no less than 0.375 inches.

Thicknesses shall not be less than required to achieve designated fire resistance ratings. If the specified thickness is greater than or equal to 1 inch, any individual measurement shall not be less than the specified thickness minus 0.25 inches. If the specified thickness is less than 1 inch, any individual measurement shall not be less than the specified thickness minus 25 percent.

2.1.2 Application of Spray-Applied Intumescent Epoxy Coating System

Prepare surfaces and apply the spray-applied Intumescent epoxy coating system in accordance with the manufacturer's written recommendations.

2.2 MANUFACTURER'S SERVICES

2.2.1 General

The manufacturer, or its representative, shall be onsite prior to, periodically during, and at completion of the application, to provide the specified inspections and certifications; and to ensure that preparations are adequate and that the material is applied according to manufacturer's recommendations and the contract requirements.

2.2.2 Manufacturer's Inspection

The manufacturer shall inspect the fireproofing work after the work is completed on each floor or area, including testing, repair and clean-up, and shall certify that the work complies with the manufacturer's criteria and recommendations. Before the sprayed material is covered, and after all of the fireproofing work is completed, including repair, testing, and clean-up; and after mechanical, electrical and other work in contact with fireproofing material has been completed, the manufacturer shall re-inspect the work and certify that the entire project complies with the manufacturer's criteria and recommendations. Obtain and submit the Manufacturer's Inspection Report and certifications of approval stating that the spray-applied fireproofing in the entire project complies with the manufacturer's criteria and recommendations.

3.6 FIELD TESTS

The applied fireproofing shall be tested by an approved independent testing laboratory to be selected by the A/E and paid for by the Contractor.

Submit test reports documenting results of tests on the applied material in the project. Report shall include defects identified, repair procedures, and results of the retests when required. Perform the tests in approved locations: for density in accordance with ASTM E736, cohesion/adhesion in accordance with ASTM E736, and for thickness in accordance with ASTM E605/E605M. Determine densities in accordance with ASTM E605/E605M or Appendix A, "Alternate Method for Density Determination" of AWCI TM 12-A.

Take density determinations at the flat portion of deck, beam bottom flange, beam web, column, and an equivalent area from the top of the lower beam flange. Areas showing a density less than specified will be rejected. A test sample shall be located every 10,000 square feet of floor area or two for each floor, whichever produces the greatest number of test areas. Any area showing less than minimum requirements shall be corrected. Proposed corrective measures, in writing, shall be approved

SECTION 07 81 00 Page 8 before starting the corrective action. Corrected work shall be retested.

3.6.1 Structural Components

Test each structural component type. Minimum average thickness shall be as required by UL Fire Resistance. Density and cohesion/adhesion shall be as specified.

3.6.2 Repair

Additional fireproofing material may be added to provide proper thickness. Correct rejected areas of fireproofing to meet specified requirements by adding fireproofing material to provide the proper thickness, or by removing defects and respraying with new fireproofing material. Use same type of fireproofing material for repairs as originally applied or use patching materials recommended by the manufacturer. Retest and reinspect repaired areas. Apply fireproofing material to voids or damaged areas by hand-trowel, or by respraying.

2.3.2 Visual Inspections

Inspections shall be made by the certified independent laboratory prior to closure of concealed areas. These inspections may be phased, but shall not occur less than 5 working days prior to the enclosure of the fireproofing.

Sprayed areas shall receive a final inspection. Fireproofed surfaces shall be inspected after mechanical, electrical, and other work in contact with fireproofing material has been completed and before sprayed material is covered. Any locations missing fireproofing shall be patched in accordance with the manufacturer's requirements.

2.3.3 Patching

Patch and repair damaged fireproofing. The patching material shall be the same as that specified for that area.

3.7 CLEANUP

Thoroughly clean surfaces not indicated to receive fireproofing of sprayed material within a 24 hour period after application.

-- End of Section --

SECTION

SECTION 11 53 23.16

OVERHEAD SERVICE CARRIERS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM A1008/A1008M (2016) Standard Specification for Steel, Sheet, Cold-Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength Low-Alloy with Improved Formability, Solution Hardened, and Bake Hardenable

ASTM A167 (2011) Standard Specification for Stainless and Heat-Resisting Chromium-Nickel Steel Plate, Sheet, and Strip

ASTM A325 (2014) Standard Specification for Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum Tensile Strength

ASTM F594 (2009; E 2015) Standard Specification for Stainless Steel Nuts

1.2 RELATED WORK SPECIFIED IN OTHER SECTIONS

11 53 43 Laboratory Service Fittings and Fixtures Plumbing Sections for pipied utilities mounted on the carrier

Electrical Sections for the wiremold component for electrical and data.

All electrical devices, wiring, electrical and ground connections are to be provided and installed under Electrical Division and data raceway products shown mounted in the overhead service carrier is to be provided by laboratory casework manufacturer, Electrical and Data Divisions will provide and install all electrical devices, wiring, electrical and ground connections within this unit.

1.3 LEED COMPLIANCE AND DOCUMENTATION

Text

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

SECTION 11 53 23.16 Page 1

Submit fabrication drawings for overhead service carriers. Submit Installation Drawings in accordance with the paragraph entitled, "Installation," of this section.

SD-03 Product Data

Descriptive literature, technical sheets and diagrams for Corrosion-Resistant Steel, Filler Material, Accessories.

SD-04 Samples

Submit Manufacturer's Standard Color Charts in accordance with paragraph entitled, "General," of this section.

SD-06 Test Reports

Include independent laboratory certification that applied finishes comply with specified chemical and physical resistance requirements

SD-07 Certificates

Submit certificates for the following items showing conformance with the referenced standards contained in this section.

Corrosion-Resistant Steel

Service Fixtures

SD-08 Manufacturer's Instructions

Submit Manufacturer's Instructions for in accordance with paragraph entitled, "General," of this section

1.5 SUBMITTAL REQUIREMENTS

1.5.1 Drawing Requirements

Indicate on shop drawing the location of equipment and rough-in of steam, water, waste, electrical power and other services to which connections are to be made. Show entire assembly including wiring, piping and ductwork service requirements. Prepare shop drawings to show all units at locations in which multiple units are directly adjacent to each other.

Show location of overhead service carrier field joints and all typical details for connections, typical joints and fixtures.

In preparing shop drawings, fabricator shall verify that component parts and assembly of each item will support superimposed loads, without deflection detrimental to function, appearance and safety.

1.5.2 Mock-Up

One (1) 36-inch section of overhead service carrier, which can be incorporated into the construction once approved.

1.6 DELIVERY, STORAGE AND HANDLING

Deliver, store, and handle metal casework in a manner that prevents damage

SECTION 11 53 23.16 Page 2 or disfigurement. Provide temporary skids under units

Provide and install the overhead service carrier tie rods, overhead service carrier structure, metal closure items, perorated metal, plumbing outlets, raceway without devices and conduit.

PART 2 PRODUCTS

2.1 GENERAL

Submit Manufacturer's Standard Color Charts for metal cabinets showing the manufacturer's recommended color and finish selections. Submit Manufacturer's Instructions for overhead service carrier including special provisions required to install carrier components.

Provide the manufacturer's standard size and type of components conforming with the contract documents.

2.2 MATERIALS

2.2.1 Corrosion-Resistant Steel

Provide Corrosion-Resistant Steel conforming to ASTM A1008/A1008M and ASTM A167, Type (302) (304) (316) Finish 4.

2.2.2 Fasteners

Fasteners conforming to the following:

Screws: Complying with ANSI Standards, Group, Type and Class as applicable

Nuts: ASTM F594, corrosion-resistant steel

Bolts: ASTM A325, Heavy, hexagon head bolts corrosion-resistant steel

2.3 SERVICE CARRIER METAL FINISH

2.3.1 Preparation

Spray clean metal with a heated cleaner/phosphate solution, pre-treat with iron phosphate spray, water rinse, and neutral final seal. Immediately dry in heated ovens, gradually cooled, prior to application of finish.

2.3.2 Application

Electrostatically apply urethane powder coat of selected color and bake in controlled high temperature oven to assure a smooth, hard satin finish.

Surfaces shall have a chemical resistant, high grade laboratory furniture quality finish of the following thickness: Liquid, dipped, solvent based finishes are not and will not be acceptable.

a. Exterior and interior exposed surfaces: 1.5 mil average and 1.2 mil min.

b. Surfaces not exposed to view: 1.2 mil average.

SECTION 11 53 23.16 Page 3

2.4 SERVICE CARRIER CONSTRUCTION

2.4.1 Design per Drawings

Coordinate with requirements of Division 15 & 16 for installation of electrical, data, plumbing and telephone devices.

2.4.2 Structure

Provide structure per linear foot to support 400 pounds per assembly.

Provide diagonal bracing above ceiling plane to resist a 100 plf (1460 N/m) applied horizontally at the base of the assembly in any direction.

2.4.3 Unistrut Structure

Provide Unistrut structure as shown on drawings. Rods shall be bolted to the slab with steel angles or appropriate support.

a. Unistrut P1026 angle fitting.

b. Unistrut P2458-24 Tubular knee brace.

PART 3 EXECUTION

3.1 INSTALLATION

Install overhead service carrier as described in manufacturers installation drawings in accordance with design intent.

Prior to commencement of installation, ensure mounting devices, members and surfaces are satisfactory for fitting, and adequate for securing of work.

Take site measurements of construction to which work of the section must conform, and through which access must be made, before Overhead Service

Carriers are delivered to site, to ensure that adaptation is not required which would result in construction delay

Provide anchorage information, roughing-in dimensions, templates and service requirements for installation of work of this section, and assist or supervise, or both, the setting of anchorage devices, and construction of other work incorporated with Overhead Service Carriers specified in this section in order that they function as intended.

Install Service Carriers to meet manufacturer's recommended specifications, true, tightly fitted, and level or flush to adjacent surfaces, as suitable for installation.

Work shall include rough hardware, fastenings and other items necessary for secure installation.

Install Service Carriers straight, plumb, level, and secured to prevent distortion or displacement. Shim as necessary with concealed shims.

Where required, use grout on which iron oxide deposits will not form.

Secure fixed Service Carriers to building structure or construction as required to maintain it permanently in place, and so that it functions properly.

SECTION 11 53 23.16 Page 4

Install Service Carriers with connections provided as required for plumbing and electrical services.

3.2 COORDINATION

Verify location and size of mechanical and electrical services as required.

Verify reinforcement of walls and partitions for support and anchorage of casework.

Provide reinforcing and anchorage for built-in products.

Insulate between dissimilar metals, and metal and concrete or masonry to prevent electrolysis.

Overhead Service Carriers shall include all electrical components, UL approved, required by jurisdictional authorities, and to protect the equipment for damage during operation.

3.3 CLEANING

Remove crating and packing materials from premises. Wipe down surfaces to remove fingerprints and markings and leave in clean condition.

3.4 INSPECTION

Examine casework grounds and supports for adequate anchorage, foreign material, moisture, and unevenness that could prevent quality casework installation. Ensure that electrical and plumbing rough-ins for casework are complete. Do not proceed with installation until defects are corrected.

SECTION 11 53 23.16 Page 5

SECTION 12 31 00

MANUFACTURED METAL LABORATORY CASEWORK

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN WELDING SOCIETY (AWS)

AWS D1.1/D1.1M (2015; Errata 1 2015; Errata 2 2016) Structural Welding Code - Steel

AWS D1.3/D1.3M (2018) Structural Welding Code - Sheet Steel

ASTM INTERNATIONAL (ASTM)

ASTM A1008/A1008M (2016) Standard Specification for Steel, Sheet, Cold-Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength Low-Alloy with Improved Formability, Solution Hardened, and Bake Hardenable

ASTM A167 (2011) Standard Specification for Stainless and Heat-Resisting Chromium-Nickel Steel Plate, Sheet, and Strip

ASTM A325 (2014) Standard Specification for Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum Tensile Strength

ASTM A325M (2014) Standard Specification for Structural Bolts, Steel, Heat Treated, 830 MPa Minimum Tensile Strength (Metric)

ASTM C1036 (2016) Standard Specification for Flat Glass

ASTM F594 (2009; E 2015) Standard Specification for Stainless Steel Nuts

ASTM F836M (2016, E 2018) Standard Specification for Style 1 Stainless Steel Metric Nuts (Metric)

BUILDERS HARDWARE MANUFACTURERS ASSOCIATION (BHMA)

ANSI/BHMA A156.11 (2014) Cabinet Locks

ANSI/BHMA A156.5 (2014) Cylinder and Input Devices for Locks

SECTION 12 31 00 Page 1

ANSI/BHMA A156.9 (2015) Cabinet Hardware

KITCHEN CABINET MANUFACTURERS ASSOCIATION (KCMA)

KCMA A161.1 (2017) Performance & Construction Standards for Kitchen and Vanity Cabinets

U.S. GENERAL SERVICES ADMINISTRATION (GSA)

FS FF-B-588 (Rev E; Notice 1) Bolt, Toggle: and Expansion Sleeve, Screw

FS FF-S-325 (Basic; Int Amd 3; Notices 3, 4) Shield, Expansion; Nail, Expansion; and Nail, Drive Screw (Devices, Anchoring, Masonry)

FS TT-E-489 (Rev J; Notice 2) Enamel, Alkyd, Glass, Low VOC Content

FS TT-F-336 (Rev E; Notice 1) Filler, Wood, Paste

1.2 ADMINISTRATIVE REQUIREMENTS

1.2.1 Pre-Installation Meeting

Within 30 calendar days after date of award, submit for the approval of the Contracting Officer six (6) copies of outline drawings of all casework to be furnished under this contract, together with weights and overall dimensions, and required samples. Ensure drawings show the general arrangement and overall dimensions of the casework, details of any casework supports, and provisions for electrical outlets, special provisions for external cables and cords. Submit the following for review and approval:

a. Fabrication Drawings

b. Installation Drawings

Submit installation drawings for metal cabinets. Include in drawings the location of cabinets, details of cabinet relationship and dimensional positions, and locations for roughing in plumbing, including sinks, faucets, strainers and cocks, special electrical lines or conduits cables.

Submit manufacturer's catalog data and certificates for the following items showing conformance with the referenced standards contained in this section:

a. Cabinets

b. Steel Gauges and Types

c. Glass

d. Adhesives

e. Filler Material

f. Fasteners

g. Accessories and Hardware

SECTION 12 31 00 Page 2

Submit manufacturer's instructions for metal cabinet systems including special provisions required to install equipment components and system packages. Include special notices detailing impedances, hazards and safety precautions.

Submit manufacturer's standard color charts for metal cabinets showing the manufacturer's recommended color and finish selections.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-02 Shop Drawings

Fabrication Drawings; G

Installation Drawings; G

SD-03 Product Data

Cabinets; G

Steel Panels and Components; G

Glass; G

Adhesives; G

Filler Material; G

Fasteners; G

Accessories and Hardware; G

SD-04 Samples

Manufacturer's Standard Color Charts; G

SD-06 Test Reports

Include independent laboratory certification that applied finishes comply with specified chemical and physical resistance requirements.

SD-07 Certificates

Corrosion-Resistant Steel

Glass

Adhesives

Filler Material

SECTION 12 31 00 Page 3

Fasteners

Accessories and Hardware

SD-08 Manufacturer's Instructions

Manufacturer's Instructions; G

1.4 SUBMITTAL REQUIREMENTS

1.4.1 Drawing Requirement

Submit full scale joinery and all fully dimensioned typical details showing sizes, materials, substrates and finish for all metal casework components, support strut sizes and locations. All details to be keyed to a furniture schedule showing plans, elevations and sections of each cabinet type at 3/4"=1'-0" and referencing architect's numbers for cabinet types.

Show location of laboratory casework countertops field joints and all typical details for all types of surfaces including but not limited to:

edge and drip details, connections, typical joints, cut-outs for sinks, cup sinks and fixtures.

1.4.2 Samples

Material and Finish Samples: Submit 6" x 6" samples of each specified finish material. Samples will be reviewed by Architect for color, texture, and pattern only.

1.5 DELIVERY, STORAGE, AND HANDLING

Deliver, store, and handle metal casework in a manner that prevents damage or disfigurement.

Provide temporary skids under units.

PART 2 PRODUCTS

2.1 SYSTEM DESCRIPTION

2.1.1 Design Requirements

Provide metal casework meeting SOFA 8 standards, factory-fabricated and finished in the manufacturer's standard sizes and finishes of the type, design, and configuration indicated. Construct casework as specified.

Provide wall and base cabinet assemblies consisting of individual units joined into continuous sections. Accomplish fastenings to permit removal and replacement of individual units without affecting the remainder of the installation. Provide counters with watertight sink rim. Provide removable doors equipped with position stops to avoid accidental complete withdrawals. Fix or adjust shelves as indicated. Flush overlay square edge cabinet construction typical; BOD, Kewaunee Research Collection (or provide equal).

2.1.2 General

Submit Manufacturer's Standard Color Charts for metal cabinets showing the full line of all manufacturer's standard and custom color and finish selections.

SECTION 12 31 00 Page 4

Submit Manufacturer's Instructions for metal cabinet systems including special provisions required to install equipment components and system packages. Include special notices detailing impedances, hazards and safety precautions.

Provide the manufacturer's standard size and type of casework conforming with the design indicated. type and design indicated. Provide both wall and base cabinet assemblies consisting of individual units joined into continuous sections as indicated. Accomplish fastenings to permit removal and replacement of individual units without affecting the remainder of the installation.

2.2 MATERIALS

Provide corrosion-resistant steel conforming to ASTM A1008/A1008M, and ASTM A167, Type 316 Finish 4.

Provide glass conforming to ASTM C1036, Type I, Class 1, Quality q3, 1/4 inch thick, for unframed sliding glass doors; other glass is to conform to ASTM C1036, Type II, Class 1, Quality q8, 7/32 inch thick. All glass to be tempered.

Provide filler material conforming to FS TT-F-336.

Provide accessories and hardware conforming to the following requirements, as applicable:

Extension drawer slides: ANSI/BHMA A156.9, Type B85071

Concealed hinges: ANSI/BHMA A156.9, overlay concealed

Bar type pulls: ANSI/BHMA A156.9, 4-inch overall length, Type B12012 refer Part 2.6.

Locks, keying, and keys: As directed

Catches: Positive Catch.

All base and wall cabinet doors, hinged.

All base and wall cabinets with 2 adjustable shelves; tall floor cabinets, 5 adjustable shelves.

Provide Fasteners conforming to the following:

Screws: Complying with ANSI Standards, Group, Type and Class as applicable

Anchoring Devices: FS FF-S-325, Group, Type, and Class as applicable

Toggle bolts: FS FF-B-588, Type I, Class A, Style 2

Nuts: ASTM F594, corrosion-resistant steel

Bolts: ASTM A325, heavy, hexagon head bolts corrosion-resistant steel

Nuts: ASTM F836M, corrosion-resistant steel

Bolts: ASTM A325M, heavy, hexagon head bolts corrosion-resistant steel

SECTION 12 31 00 Page 5

2.3 CASEWORK METAL FINISH

2.3.1 Preparation

Spray clean metal with a heated cleaner/phosphate solution, pre-treat with iron phosphate spray, water rinse, and neutral final seal.

Immediately dry in heated ovens, gradually cooled, prior to application of finish.

2.3.2 Application

Electrostatically apply urethane powder coat of selected color and bake in controlled high temperature oven to assure a smooth, hard satin finish.

Surfaces shall have a chemical resistant, high grade laboratory furniture quality finish of the following thickness: Liquid, dipped, solvent based finishes are not and will not be acceptable.

a. Exterior and interior exposed surfaces: 1.5 mil average and 1.2 mil min.

b. Surfaces not exposed to view: 1.2 mil average.

2.4 STEEL CASEWORK FABRICATION

2.4.1 General

Provide wall and base cabinets fabricated from 18-gauge, cold-rolled furniture steel, except for backs of cabinets and backs of doors provide manufacturer's standard. Construct cabinets with no raw edges or exposed flanges, with welds being flush and ground smooth on all exposed surfaces.

Provide concealed fasteners at all exposed exterior surfaces. Provide doors and drawer fronts with panelized double-wall construction, not less than 1/2-inch thick, with a sound-absorbing material adhered between the walls. Equip doors and drawers with rubber or plastic silencers and bumpers. Provide drawers with removable fronts, mounted on metal guides and equipped with position stops for complete drawer withdrawal. Provide adjustable shelving as indicated.

2.4.2 Workmanship

Align end panels, top rails, bottoms and vertical posts at intersections in same plane, without overlap. Grind exposed welds flush and smooth.

Welding is to conform to AWS D1.1/D1.1M and AWS D1.3/D1.3M.

Additional casework construction requirements:

a. Welded assembly.

b. Fabricate with enclosed uprights or posts full height or width at front, include sides, backs, bottoms, soffits, ceilings under sloping tops, headers and rail, assembled to form an integral unit.

c. Form sides to make rabbeted stile 3/4 to 1-1/8 inch wide, closed by channel containing shelf adjustment slots.

d. Make bottom of wall units flush, double panel construction.

e. Make top and cross rails of "U" shaped channel.

SECTION 12 31 00 Page 6

f. Enclose all backs and bottoms in cabinets, including drawer units.

g. Provide finish panel on exposed cabinet backs.

h. Do not use screws and bolts in construction or assembly of casework, except to secure hardware, applied door stops, accessories, removable panels and where casework is required to fastened end to end or back to back.

i. Fabricate casework, except benches, and desks with finished end panels.

j. Close flush exposed soffits of wall hung shelving, knee spaces in counters, and toe spaces at bases.

k. In base units with sinks provide on piece, lowered backs.

l. In base units with doors provide removable backs.

m. Provide built-in raceways or tubular or channel shaped members of casework for installation of wiring and electric work. Mount junction boxes on rear of cabinets. Electric work is specified in electrical sections of specifications.

n. Provide reinforcing for hardware.

o. Size Dimensions:

(1) Used dimensions shown or specified within tolerances specified.

(2) Tolerance:

(a) Depth: 13-inches in lieu of 12 -inches, 18 inches in lieu of 16 -inches, except wall hung units above counter 21 inches to 24 inches in lieu of 22-inches.

(b) Width: Minus one inch.

(c) Height: 1-inch plus or minus for wall hung cabinets and counter mounted cabinets, excluding sloping tops. 1-inch plus for floor standing cabinets,excluding base and sloping tops. Full height cabinets shown back to back same height.

(d) Manufacturer's tolerance for the length, depth or height: Not to exceed 0.0625-inches

SECTION 12 31 00 Page 7

2.4.3 Minimum Thickness of Steel

U. S. Standard Thickness

GAUGE

(INCH)

Drawer fronts, backs, bodies, closure plates or scribe and filler strips less than 75 mm wide,filler strips less than 75 mm wide, sloping top, shelf reinforcement channel and shelves. Toe space or casework soffits and ceilings and ceilings under sloping tops.

20 0.035

Base pedestals, casework top sides, back, and bottom panels, closure scribe and filler strips 75 mm or more.

Reinforcement for drawers with locks. Table legs, spreaders and stretchers, when fabricated of cold rolled tubing. Metal for desks;

except legs and aprons. Door exterior and…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.